Appendix 1 H&E  22-23 Delivery Plan Interim Progress Report
1. Our communities
Objective 1. Our neighbourhoods are safe, resilient and inclusive
Action Status Progress Due Date Note Owner
Build community resilience and
advance community
empowerment including the
development of a training
programme to support the
Community empowerment agenda
31-Mar-
2023
The actions from the approved Community Engagement Strategy
(2019) are being delivered with oversight from the Community
Empowerment Project Board. Year 1 priority projects that are all well
underway. Projects include corporate mainstreaming approach to
Participatory Budgeting; Communication Plan; Review of Community
Asset Transfer and a programme of awareness raising and training to
Support the Community Empowerment Agenda. The projects ensure
community based work to continue to raise awareness of the
empowerment agenda and of the opportunities open to communities.
It should be noted that additional projects have been added to the
delivery plan incorporating the UKSPF investment, including the
development of the CCTV network. The Board have considered and
agreed Year 2 priority projects ensuring a focus on the Cost of Living
Crisis. In doing so the Delivery Plan will be up-dated regularly
highlighting progression. It is anticipated this action will be completed
by year end.
Clare
English
Continue to improve and develop
the Councils CCTV processes and
infrastructure
31-Mar-
2023
The Communities Team are included within the proposals for the
United Kingdom Shared Prosperity Fund (UKSPF) programme that will
deliver a series of actions from 2022 to March 2025. The primary goal
Clare
English
ITEM 9

Page 2

Action Status Progress Due Date Note Owner
of the UKSPF is to build pride in place and increase life chances across
the UK. With a key theme being Communities and Place the investment
will allow for Improving Community Safety by upgrading of the current
CCTV system for public space surveillance to provide support in the
protection of the public, the deterrence of and the detection of crime
and to provide support in the investigation of such crimes.
Improvements will seek to link enhanced public space, social housing
and Council establishment cameras to one network with access from
one control centre. This action will go beyond the due date of March
2023 in line with the UKSPF allocation to 2025.Procurement route will
include a procured CCTV survey leading to a transmission strategy in
order to inform a tender. The CCTV Delivery group has been re-
established and will be directed by the Community Empowerment
Project Board.
Explore alternative forms of
funding to encourage less reliance
on mainstream council funding
31-Mar-
2023
The Communities Team are a key part of the proposals for the United
Kingdom Shared Prosperity Fund (UKSPF) programme that will deliver a
series of actions from 2022 to March 2025. The primary goal of the
UKSPF is to build pride in place and increase life chances across the UK.
These focus on: communities and place; capital projects; people and
skills and multiply (functional numeracy).
Within the communities and place category the West Dunbartonshire
plan will focus on: Improving Community Safety by upgrading of the
current CCTV  system for public space surveillance; Pride in Place
Project will focus on building on pride in place centred round a
Community Garden supporting neighbourhood and partnerships
working to reduce anti-social behaviour (Housing/ Fire Scotland/
Communities/ Police Scotland/ Greenspace; Participatory Budgeting -
Awareness /training resource;  West Dunbartonshire Pantry Network -
Clare
English

Page 3

Action Status Progress Due Date Note Owner
community pantries offer a dignified and sustainable approach to
addressing food insecurity and food poverty; Community Soup
Engagement to develop small community-based projects that will
improve the quality of life in local areas. Equating to additional funding
of £744,222 for 2023 - 2025 and a commercial viable CCTV network.
Deliver the objectives set out in
the Community Empowerment
Strategy and Action Plan through
identified priority projects
31-Mar-
2023
The actions from the approved Community Engagement Strategy
(2019) are being delivered with direction from the Community
Empowerment Project Board. The Board agreed Year 1 and Year 2
priority projects that are progressing well including the completion of
the Participatory Budgeting Mainstreaming Pilot. It should be noted
that with the allocation of UKSPF, additional projects have been
included within the delivery plan; Pride in Place; Food Pantry network;
PB awareness; Community Soup and development of a CCTV network
upgrade by March 2025.The projects ensure community based work to
continue to raise awareness of the empowerment agenda and of the
opportunities open to communities.
The board agreed that priority projects ensure a focus on the Cost of
Living Crisis. In doing so the Delivery Plan will be up-dated regularly
highlighting progression. It is anticipated this action will be completed
by year end.
Clare
English
Lead on the Council’s approach to
Participatory Budgeting
Mainstreaming across the
organisation
31-Mar-
2023
The PB Mainstreaming pilot and evaluation have been successfully
completed. The team continue to encourage and embed a culture of
participation across the authority, with a PB ilearn module developed
for WDC staff use; Community Budgeting Six roll out; and establishing
PB spend and service champions across all WD service areas. HSCP PB
Clare
English

Page 4

Action Status Progress Due Date Note Owner
budget for 2023/24 has been identified. It is anticipated this action will
be completed by year end.
Develop an Employee Volunteering
Policy to support the ambitions of
the Community Empowerment
(Scotland) Act 2015
31-Mar-
2023
An Employee Volunteering framework approach has been adapted as
the pilot progresses. The framework will link with the TU learning
agreement and offer employee volunteering as a learning opportunity,
work is ongoing lead by the Communities and Organisational
Development teams. A Pilot scheme will be developed by year end with
a launch date to be agreed by the Community Empowerment Board. It
is anticipated this action will be completed by year end.
Identify and implement
improvements in partnership
working between the CCTV team
and key partners to promote
feelings of safety in the area
31-Mar-
2023
Partnership working is well established with Police Scotland to promote
feelings of safety across the area, with the CCTV team being highly
commended for outstanding partnership working at the Police Scotland
-Argyll and West Dunbartonshire, Partner of the Year Awards in
December 2022. Work will continue to incorporate CCTV information
on the Twenty Minute Neighbourhood mapping system to support safe
routes for residents. The reestablishment of the CCTV working group in
line with the UKSPF will support progression of the action as the new
CCTV network develops. It is anticipated this action will be completed
by year end.
Clare
English
Development and implementation
of revised Anti-Social Behaviour
strategy
31-Mar-
2023
The development of the ASB strategy has been delayed due to
requirement for SAFE DIG partnership outcome document to be
produced by same group of members, however information from
partner services is being collated to prepare document meantime and
commitment agreed via Safe DIG that partners will contribute to
development of strategy.  Expected timescale for ASB Strategy will be
impacted due to this and requirement to conduct consultation period
once document collated. This action will therefore not be completed by
year end and will be carried forward to the 2023/24 action plan.
Nicola
Pettigrew

Page 5

Risk & Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to secure community and partner buy-in for
the emerging Community Empowerment Strategy
and Action Plan.
In order to deliver on the ambitions of the
Community Empowerment Strategy and associated
action plan, it is vital that a partnership approach is
promoted to ensure best use of resources, skills and
expertise.
30-Nov-
2022
The risk profile will remain the same despite
significant progress being made with a number
of priority projects.
Clare
English;
Elaine
Troup
Failure to deliver on the capacity building of the
Community Empowerment (Scotland) Act.
As communities continue to recover from the
impact of Covid-19 there is an ever greater need to
support and develop communities. Community
capacity building and community development work
continues within existing resources.
30-Nov-
2022
The risk levels remain the same despite
significant progress being made to support
communities across the authority through
increased levels of capacity building.
Clare
English;
Elaine
Troup
Failure to deliver sufficient community capacity
building / community development support to
groups impacted by COVID-19.
COVID-19 has had a huge impact on communities
across the authority. A focused approach is needed
to understand the impact on community groups and
to support them to re-start and re-build. Failure to
do this would impact on the individual and
community resilience of citizens.
30-Nov-
2022
The Communities Team continues to support a
range of community organisations to re-start or
develop on the back of the pandemic. The team
have a dedicated capacity building resource
available to support.
Clare
English;
Elaine
Troup

Page 6

Risk & Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Engaging positively with Residents, Communities &
Partnerships.
The risk that the Council fails to adequately engage,
establish and maintain positive relationships with
local residents and communities in addition to
partnership bodies.
30-Nov-
2022
Whilst the Community Planning Partnership is
currently being managed under a shared service
agreement, it is well established with strong
partnership working arrangements in place
reducing likelihood of this risk being realised.
We continue to promote and ensure strong
communications and engagement through the
Engaging Communities Framework. As well as
gathering resident feedback, we ensure that key
information is communicated through a variety
of media channels including online, social media
and publications such as Housing News.
Clare
English;
Elaine
Troup
Objective 3. Our residents are supported to increase life and learning skills
Action Status Progress Due Date Note Owner
Digital inclusion – progress the
opportunities for provision of wi-fi
infrastructure into new build
properties and priority areas of
deprivation
31-Mar-
2023
This action is progressing well. Digital inclusion capabilities are
incorporated into our new build design standard and all new housing
will benefit from this infrastructure.  We have connected with two
telecommunications companies in terms of the provision of social
tariffs for broadband connectivity and plans are in place to install
infrastructure across our housing estate. It is anticipated this action
will be completed by year end.
John Kerr

Page 7

2. Our Environment
Objective 6. Our neighbourhoods are sustainable and attractive
Action Status Progress Due Date Note Owner
Develop and implement Housing
regeneration approaches to
improve our communities
31-Mar-
2023
This action is progressing as planned. Priority areas referenced in the
new local housing strategy, and an area based approach has been
launched from this which will cover the 5 year period of the strategy.
Some key initiatives that are underway include Clydebank East,
Pappert, Alexandria and Bellsmyre, Dumbarton. It is anticipated this
action will be completed by year end.
John Kerr
Develop our Housing Asset
Management to ensure
sustainability and deliver new
Housing Capital Investment
Programme
31-Mar-
2023
This action is progressing as planned. New Asset Management
Strategy in development, a draft will be available within the target
date and following detailed consultation will be submitted to a
Housing and Communities Committee in 2023. It is anticipated this
action will be completed by year end.
John Kerr
Implement  new Local Housing
Strategy & council wide response
to 2040
31-Mar-
2023
This has been successfully completed.  High level steering group
tasked with ensuring delivery continues to meet and prioritise key
objectives.  Scottish Government has now fed back views on the
strategy in a positive manner. The Annual progress action plan update
will be provided to the HAC.
John Kerr
Implement year 4 of rapid
rehousing plan (Home at the
Heart)
31-Mar-
2023
This action is progressing as planned. While we continue to roll out
the plan in a positive manner in respect of the key actions, delivery on
some of the key performance measures are not being realised as a
result of slower than anticipated housing access system and notably
John Kerr

Page 8

Action Status Progress Due Date Note Owner
around void turnaround times. It is anticipated this action will be
completed by year end.
Deliver New build Housing
programme 31-Mar-
2023
This action is progressing as planned. Positive progress continues to
be made, with the completion of the Queens Quay development in
22/23, and anticipated site starts at Clydebank East and Pappert. It is
anticipated this action will be completed by year end.
John Kerr
Deliver high rise accommodation
strategy 31-Mar-
2023
This action has made significant progress. We have consulted with
tenants and residents and will incorporate the outcome of the
consultation into the new strategy to promote high rise living across
West Dunbartonshire, the Strategy will be presented to HAC in May
and therefore will not be completed within year. The Strategy will still
remain a priority.
John Kerr
Risk & Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
The public space CCTV infrastructure covers the three main
townships of Alexandria, Dumbarton and Clydebank with a
mix of fixed space and redeployable cameras. Until
resources can be secured and improvements made the
Council does remain at risk from reputational damage,
should the system fail.
30-Nov-
2022
CCTV investment to upgrade the
current network is a key element of the
UK Shared Prosperity Funding applied
for through the Theme - Communities
and Place. A decision on the
Investment Plan focus is due in October
2022.
Clare
English;
Elaine
Troup
Failure to achieve the outcomes of the Scottish Social
Housing Charter.
The Scottish Social Housing Charter sets out the standards
and outcomes that tenants and customers should expect
30-Nov-
2022
Areas of non-compliance (SHQS) will be
highlighted within Annual Assurance
process.
John Kerr

Page 9

Risk & Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
from social landlords, in terms of the quality and value for
money of the services they receive. Failure to continue to
meet these could place the Council at risk of the
intervention powers of the Scottish Housing Regulator
3. Our Economy
Objective 7. Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish
Action Status Progress Due Date Note Owner
Develop investment plan for
shared prosperity fund
31-Mar-
2023
This action is progressing as planned. The UK Shared Prosperity Fund
(UKSPF) is the UK Government’s main method replacing for EU
Structural Funds and has a potential value to West Dunbartonshire of
£3.8m. The fund has three core investment priorities that will be
funded on the basis of an Investment Plan.  West Dunbartonshire
worked in partnership with Glasgow City Region Partners to develop
and submit a Regional Investment Plan in September.  The final
decision on the funds allocated to West Dunbartonshire will depend on
the outcome of the UK Government assessment of the Regional
Investment Plan.  A committee report has been endorsed at the IRED
Committee and the Housing and Communities Committee; an
accompanying Equality Impact Assessment has also been prepared.
The next stage, following, award notice will be the preparation for
delivery. This will include the development of grant fund opportunities
Stephen
Brooks

Page 10

Action Status Progress Due Date Note Owner
and processes for acquiring/procuring the services we require to meet
the SPF aims.
Objective 8. We will support our residents to access employment and training opportunities
Action Status Progress Due Date Note Owner
Ensure no one left behind by
supporting skills and learning
for work, life and learning
31-Mar-
2023
This action has been successfully completed. We have established a
three year CLD plan with associated actions and activities that are
designed to support skills for life, learning and work. This includes: the
delivery of community based vocational courses that are accredited by
SQA; supporting digital skills; and assisting the delivery of ESOL (English
for Speakers of Other languages). In addition we are developing a
proposal for Multiply activities (Adult numeracy) to include in our plans
for the use of UK Shared Prosperity Funds.
Stephen
Brooks
Promote inclusive growth
through access to training and
apprenticeship opportunities
31-Mar-
2023
This action is progressing as planned. There are 122 MA's supported
through the W4U SDS MA programme over this period. They are
actively being supported through their Apprenticeship by W4U who
commenced their MA in previous years - some MA's can take up to 4
years to complete - for example construction related apprenticeships.
The apprentices are combination of MA's within the Council and Private
Sector, as well as upskilling opportunities offered to existing council
employees in Childcare, Business Admin, Digital Analytics and Social
care sectors.
Stephen
Brooks

Page 11

Risk & Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to prepare for changes associated with No One Left
Behind.
No One Left Behind represents a transformational change in
employability service provision, failing to prepare and reaching
a state of readiness will lead to lost opportunities for
investment in employability services.
30-Nov-
2022
We have complied with the
relevant guidance in relation to
the delivery of No One Left
Behind; a new approach to
employability service provision.
As such, the impact and
likelihood remain low.
Stephen
Brooks
Objective 9. We will work with partners to support economic development to deliver increased prosperity for our area
Action Status Progress Due Date Note Owner
Support and implement CLD,
Employability and Welfare
benefit three year plans to
promote  quality frameworks
and partnership working to
enhance work, learn, money
service provision
31-Mar-
2023
This action has been successfully completed. We have completed the
three year plans for CLD, Information and Advice Services and
Employability Services. Each plan has a set of actions that focus on
continuous improvement that we will monitor on an ongoing basis.
Allied to this are a set of service activities with associated performance
indicators. These reports will be used to gauge progress and provide
evidence for the various quality standard assessments.
Our three year employability plan has been endorsed by the Scottish
Government and will serve as a guide for the use of No One Left
Behind resources. This plan will also inform the development of our
proposals for UK Shared Prosperity Funds 'People and Skills' priority.
Meanwhile the CLD Plan will inform our approach to UK Shared
Prosperity 'Multiply' objectives.
Stephen
Brooks

Page 12

Action Status Progress Due Date Note Owner
These plans were used to inform the local child poverty annual report
which was circulated to the key stakeholders (Council, Community
planning, NHS Greater Glasgow and Clyde) in September.
Maximise income from
employment
13-Mar-
2023
This action is progressing as planned. We are delivering support
through the use of European Social Funds, No One Left Behind and
Parental Employability Support. These funds are intended to improve
people's prospects by developing confidence, self-esteem, skills and
understanding of the labour market. As such progression towards the
labour market is a key indicator. Nevertheless we have supported
approximately 200 people to secure employment in the first half of
the current financial year (22/23). This is consistent with our overall
aim of supporting 390 people to secure employment over the course
of the year.
Stephen
Brooks
Maximise income from benefits 13-Mar-
2023
This action is progressing as planned. We continued to deliver services
through the period of health restrictions. We are now developing a
hybrid service, face to face/home visits and remote on-line support,
that draws on the experience and lessons learned during covid. We
have established a target of supporting people to secure £7.9m of
additional income and this takes into account our approach, our
resources and the likely level of demand.  Nevertheless, in the first half
of the current year we are on track to meet our annual target.
Stephen
Brooks
Ensure no one left behind by
addressing life challenges and
reducing costs
13-Mar-
2023
This action has been successfully completed. We are reviewing our
activity and associated targets in the light of our experience of service
delivery during and beyond COVID-19 restrictions. In addition, we are
also reviewing how we gather information to demonstrate how we
support people to reduce costs by managing debt. We have set an
interim target while we review the approach and in the first half of the
Stephen
Brooks

Page 13

Action Status Progress Due Date Note Owner
current financial year we have supported our service users to manage
approximately £906,377 of debt.
In addition, we are developing approaches as part of the aim to
address the cost of living crisis. This includes supporting local food
banks to develop their services and address food insecurity. We are
also supporting activity to address fuel poverty through our Improving
the Cancer Journey project, family opportunity hub and information
and advice partnership.
Risk & Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to respond to child poverty legislation.
Failure to respond will have a significant impact on the
Council’s reputation, more importantly an opportunity to
raise issues and respond more effectively to child poverty
issues will be lost
30-Nov-2022
We have complied with the
guidance for the production of
local child poverty reports. We
have also reviewed the new
national plan and we are in a
good position to compile the
2022 plan as required. 
Stephen
Brooks
Universal Credit Full Service changes breadth and depth of
demand for services.
Migration of all claims to Universal Credit may lead to
increased service demand from people who would not have
used Working 4U service otherwise. Including those requiring
assistance to meet the digital by default requirement; those
seeking to maintain their claim through increased
30-Nov-2022
The risks associated with the
migration to Universal Credit
were mitigated as part of the
response to Covid-19. During
the pandemic, access was made
easier overcoming some of the
challenges associated with the
Stephen
Brooks

Page 14

Risk & Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
employability service requirement; and the need to improve
IT skills.
The process has been intensified as a direct result of covid-19
and the associated relaxation of the rules has reduced the
risk of increased demand from this source. 
waiting period for U claimant
first payments.
Failure to secure alternative funds to replace European
funding.
Failure to identify alternative funds to replace European
Structural funds will increase uncertainty and loss of staff to
other services
30-Nov-2022 An investment plan has been
submitted to the UK
Government and is being
assessed. We will receive
notification of the review at the
end of October.
Stephen
Brooks
The cost of living crisis will lead to a substantial demand for
access to welfare/debt support services.
We will monitor the changing levels of demand and target
our resources to individuals and areas that are most in need.
We will seek to work with partners to ensure we receive
appropriate referrals who can benefit from our support.
30-Nov-2022 We are working to ensure we
focus our efforts on those most
affected by the cost of living
crisis. This includes managing
food insecurity and fuel debt
funds.
Stephen
Brooks
4. Our Council
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents

Page 15

Action Status Progress Due
Date Note Owner
Develop and implement
wellbeing, employee
engagement, equality and
training plans to enable
capabilities, improved resilience
and promotion of a diverse
workforce.
31-
Mar-
2023
Progress has been made across the H&E strategic team. Be the Best
conversations are in place. Staff are encouraged to engage with the
Trickle platform and discussions are underway for a wider rollout
across the full Housing Operations service with HR and seeking
Champions to help roll out within service area. W4U have carried out a
training needs assessment across the teams and are liaising with the
relevant training providers.
Be the Best conversations continue to be progressed with all staff and
reoccurrence dates set up to ensure ongoing process.  Focus incudes
wellbeing, support, and discussions around workload and is being
supported with training matrix completed by staff, any training
requirements needed will be arranged from this as needed. Housing
Operations employee survey completed November 2022, in addition
service.  Housing Operations staff newsletter issued Jan 2023, provides
overview of key areas of performance, developments and information
for staff within service, part of which seeks ideas/suggestions from
staff on developments to service.  Housing Operations improvement
plan shared with teams following from staff survey Nov 22 and staff
encouraged to input to items included for development
Communities Staff will be encouraged to continue their professional
development with all opportunities being logged in line with HMIe -
How Good is our CLD? Practice. Staff have completed EQIA training in
2022 and relevant teams are developing skills to support the inclusion
of UNCRC actions within their work plans. Forthcoming UKSPF
investment in the CCTV network will require training and development
for teams involved. The Housing Development and Homelessness
Team include training needs assessment as part of the be the Best
Peter Barry

Page 16

Action Status Progress Due
Date Note Owner
conversations and these outputs have led to the development of the
proposed Housing Academy to further boost housing professionalism
within the service area.
Develop and implement
employee life cycle plans in line
with the People First Strategy to
attract and retain the workforce
31-
Mar-
2023
This action is progressing well. A Training matrix with staff for
completion and will be linked to scheduled Be the Best conversations
to identify required training and job shadowing needs for individual
staff, discussions with staff and Team Leaders.  W4U have reviewed
accreditation needs of teams to ensure continuing professional
development in in place. Training plans are developed for all Housing
development and homelessness team members, the identification of
professional qualifications for all staff is also supported.
Peter Barry
Implement service review
process including role design, use
of new technology and new ways
of working to add resilience,
address gaps, and establish
opportunities for efficiencies
31-
Mar-
2023
This action is progressing well. The Void working group continues to
meet 6 weekly and has implemented improved processes to aid void
management, including new KPIs, enhanced void phases and finalising
void performance dashboard to support staff operationally.
Digital opportunities are in progression for wider development of self-
serve portal for allocations in New Year with IHMS team.  Housing
Operations and IHMS Officer working group met January 2023 28 day
processes identified as first area for development and work is
underway to pilot before year end.  Once initial pilot undertaken wider
rollout of this area will across all Housing Officers/Assistant Housing
Officers and further areas of service will follow in conjunction with
staff/IHMS team to commence work on mobile app.
Communities’ team are adopting the Scottish Approach to Service
design in key areas of their work. This will simplify their work streams
Peter Barry

Page 17

Action Status Progress Due
Date Note Owner
allow for collaboration with partners and establish opportunities for
efficiencies. Advice Pro Management Information system continues to
be developed in line with CLD/HMIE audit requirements. W4U have
begun review of services in line with successful funding awards.
Housing Development & Homelessness continue to assess the
strength of service delivery and review practices.  The further
development of our QL system is leading to improvements in other
service areas and we will follow that pathway to further improve
housing asset management and homelessness.  Elements of the
service are also governed by regulatory bodies and we regularly assess
compliance with a number of governance standards.
Develop and implement training
plans and development
opportunities to improve
capabilities and resilience within
the workforce.
31-
Mar-
2023
This action is progressing well, and is a key element of 1-2-1 and be
the best conversations, the introduction of our housing academy will
also deliver positive outcomes in terms of this action. Caretaking
working group has agreed online training for Caretaking staff which is
progressing within team.  The Communities’ team and W4U will be
involved in a review of the CLD competencies. Registration of CLD
standards council will be promoted. Working practice continues to be
developed to ensure compliance with CLD/HMIE audit requirements.
Peter Barry
Objective 11. Our Council is adaptable and focused on delivering best value for our residents
Action Status Progress Due Date Note Owner
Carry out review of housing
policies and processes across
31-Mar-
2023
This action has been successfully completed. The void working group
has been established and meets 6 weekly, range of processes have
Nicola
Pettigrew

Page 18

Action Status Progress Due Date Note Owner
housing management areas
including void management and
re-let standards
been reviewed in line with Fit For Future recommendations.  Options
paper presented to HIB with recommendations for revised re-let
standards will be further discussed at WDTROA Range of short term
working groups established across Housing Operations service areas
and undertaken review of existing operational processes with staff.
Objective 12. Our residents are engaged and empowered
Action Status Progress Due Date Note Owner
Explore digital opportunities to
develop housing management
customer service and experience
(such as mobile app and Near Me
technology)
31-Mar-
2023
This action is progressing as planned. Housing Officers have
now returned to generic model, with some retained centrally
to focus on voids.  Digital opportunities are in progression for
wider development of self-serve portal for allocations in New
Year with IHMS team.  Housing Operations and IHMS Officer
working group met January 2023 28 day processes identified
as first area for development and work is underway to pilot
before year end.  Once initial pilot undertaken wider rollout
of this area will across all Housing Officers/Assistant Housing
Officers and further areas of service will follow in conjunction
with staff/IHMS team to commence work on mobile app. 
Nicola
Pettigrew
Action Status
Cancelled
Overdue

Page 19

Not on track
In Progress and on track
Completed
Risk Status
Alert
High risk
Warning
OK