Item 13 Appendix 3-6 - Housing Revenue Account Budgetary Control Report to 30 September 2022 (Period 6)

West Dunbartonshire Council · 23 November 2022
Back to Housing & Communities Committee — 23 November 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

APPENDIX 3
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
OVERALL PROGRAMME SUMMARY
MONTH END DATE
PERIOD 6
Spend to
Date Spend to Date
£000 £000
Red
5 18.5% 4,754 41.0% 5 18.5% 4,754 41.0%
Amber
0 0.0% 0 0.0% 0 0.0% 0 0.0%
Green
22 81.5% 6,850            59.0% 22 81.5% 6,850                59.0%
27 100% 11,604 100% 27 100% 11,604 100%
Budget Spend to
Date
Forecast
Spend Forecast Variance Budget Spend to Date Forecast
Spend
Forecast
Variance Reprofiled Over/
(Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
131,888 4,754 132,654 766 45,222 4,754 18,172 (27,050) (27,816) 766
0 0 0 0 0 0 0 0 0 0
84,232 6,850 84,051 (181) 20,382 6,850 20,201 (181) 0 (181)
216,120 11,604 216,706 585 65,604 11,604 38,373 (27,230) (27,816) 585
216,120 11,604 216,706 (585) 65,604 11,604 38,373 27,230
0 0 0 0 0 0 0 0
TOTAL RESOURCES
NET EXPENDITURE
Projects are forecast to be overspent and/or significant delay to
completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
TOTAL EXPENDITURE
Project Status Analysis
Project Life Financials Current Year Financials
Red
Projects are on target both in relation to overall budget and the forecast
stages in the project life cycle and no issues are anticipated at this time
30 September 2022
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project Spend at
RAG Status
Number of
Projects at
RAG Status
% Projects at
RAG Status
% Project
Spend at RAG
Status
Red
Projects are forecast to be overspent and/or experience material delay
to completion
Amber
Projects are either at risk of being overspent and/or delay in completion
(although this is unquantifiable at present) or the project has any issues
that require to be reported at this time
Green

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 6
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 10,963 398 4% 10,963 0 0%
Current Year Financials 2,500 398 16% 1,500 (1,000) -40%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials 566 123 22% 658 92 16%
Current Year Financials 108 123 115% 200 92 86%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
3
Project Life Financials 5,092 1,467 29% 5,092 0 0%
Current Year Financials 969 1,467 151% 1,500 531 55%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Mitigating Action
None available since essential spend.
Anticipated Outcome
Budget to overspend.
Heating improvement works
Carry out works to renew inefficient boilers/full systems as identified from the stock condition
survey and renewal of obsolete/damaged boilers. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Anticipated to meet full spend and targets and likely to overspend. This budget has overspent in recent years as demand has
exceeded expectations. Current progress continues this trend. Due to the nature of this project (ensuring heating and hot water
availability) there is no option for a conscious reduction of installs.
Main Issues / Reason for Variance
Projected to exceed budget, this is necessary work to meet demand and comply with legislation.
Mitigating Action
None available.
Anticipated Outcome
Budget to overspend.
Statutory/regulatory compliance works (lifts/electrical/legionnella/fire etc)
This budget will be used to upgrade / replace components / installations in order to comply with
the relevant standards / legislation / health and safety in relation to housing stock. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Officers working to meet revised targets.  Additional external support has been programmed in from August onwards to assist with
window installs, feedback from officers have highlighted challenges with resource levels from back-up contractor. This will be
monitored closely, however approximately £1m will need to reprofiled into 23/24.
Mitigating Action
Building Services actively redeploying internal resurces to assist with installs and working with external support to maximise
contribution.
Anticipated Outcome
Anticipated to meet reduced forecast spend
Doors/window component renewals
Doors/Windows Component Renewals 
Planned End Date  Forecast End Date
30 September 2022
Budget Details Project Life Financials
Spend to Date Variance

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 6
Budget Forecast Spend
£000 £000 % £000 £000 %
30 September 2022
Budget Details Project Life Financials
Spend to Date Variance
4
Project Life Financials 8,384 1,794 21% 9,384 1,000 12%
Current Year Financials 2,000 1,794 90% 3,000 1,000 50%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
5
Project Life Financials 106,883 972 1% 106,556 (326) 0%
Current Year Financials 39,645 972 2% 11,972 (27,673) -70%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Sites to be reprofiled £m
Aitkenbar Primary School (374)
Clydebank East (13,754)
Queens Quay Site B (629)
Queens Quay Site C (878)
Pappert (4,481)
Bank Street (575)
Willow Park Phase  1 (1,989)
Mount Pleasant (2,420)
Future New build sites (2,246)
TOTAL OF ALL PROJECTS (27,346)
Aitkenbar. Fully complete. Project spend now requires to be reprofiled. Retention figure of £0.374m budgeted to be paid out in
2022/23 will now be reprofiled to be paid in 2023/24 to allow time to finalise account.
Main Issues / Reason for Variance
Progress will continue to be monitored as the year progresses.  The £27.673 variance is made up of £0.326m underspend and a
reprofiling of £27.346m into 2023/24 onwards . Summary of reprofiled sites together with site specific updates as follows:-
Clydebank East - 88 units to be completed on the site. Project spend now requires to be reprofiled. Anticipated site start of June
2022 has been delayed as a result of assessing remediation strategy options, while the exercise has proved to be a lengthy
process the options have identified an affordable method which is estimated to be around £9m less costly than the original
proposed method.  We expect revised tender costs early in November and anticipate a site start before the end of the year.  The
remediation methods will take longer and will be the first phase of the development and the construction of the new homes will
likely commence in April 2023. £13.754m of the £18.754m current year budget will be required to be reprofiled into 23/24.
Queens Quay Site B - 29 units now completed on the site. Project spend now requires to be reprofiled. Retention figure of
£0.629m budgeted to be paid out in 2022/23 will now be reprofiled to be paid in 2023/24 to allow time to finalise account.
Queens Quay Site C  – 20 units to be completed on site. Project spend now requires to be reprofiled. The budget provision is to
acquire additional land within Queens Quay to enhance the Site C proposals, the discussions with CRL/Rydens have been
protracted but we intend to make an offer shortly subject to the DV valuation being received. This will be reprofiled into 2022/23
(£1.878m).
Affordable Supply Programme
Affordable Housing Supply Programme 
Planned End Date  Forecast End Date
Anticipated Outcome
Void properties to be brought up to lettable standard
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Void works to continue into 22/23 to bring void properties up to a lettable standard.  The high number of voids has led to a higher
than expected demand for this budget, resulting in a projected overspend in 22/23. 
Mitigating Action
None available at this time
Void house strategy programme
Spend on Void Properties to bring them up to letting standard

Page 4

WEST DUNBARTONSHIRE COUNCIL APPENDIX 4
HRA CAPITAL PROGRAMME
ANALYSIS OF RED PROJECTS
MONTH END DATE
PERIOD 6
Budget Forecast Spend
£000 £000 % £000 £000 %
30 September 2022
Budget Details Project Life Financials
Spend to Date Variance
TOTAL OF ALL PROJECTS
Project Life Financials 131,888 4,754 4% 132,654 766 1%
Current Year Financials 45,222 4,754 11% 18,172 (27,050) -60%
Future New Build gap sites  – Project spend now requires to be reprofiled. Ongoing work to acquire private and Council owned
sites to finalise wider strategy . Expected that there will be  spend of £0.500m this during 2022/23 so £2.246m will be reprofiled
into 2023/24.
Anticipated Outcome
Project will still complete and will meet revised spend profiles .
Bank Street - 20 units to be completed on the site. Project spend needs reprofiled due to wider strategic reasons and potential
reprovisioning of sheltered accommodation which will require consultative exercise . Revised estimated start date July 2023,
estimated completion January 2025.  Project is currently at feasibility stage.  Likely outturn for 22/23 for the Bank Street site is
expected to be circa. £0.420m with £0.575m therefore required to be reprofiled to 23/24.
Willox Park Phase1 - 17 units to be completed on site. Project spend now requires to be reprofiled  . Pre planning discussions
were more involved than anticipated and required some re designing which has resulted in delay to estimated start date from
January 2023 to June 2023 with estimated completion May 2024. Demolition complete, and site investigation under way.  Officers
ready to submit to for full planning.  Tender application expected to go out April 23.  At this stage spend in the current year is
expected to be £0.400m against budget of £2.390m resulting in reprofiling rquirement of £1.989m.
Mount Pleasant - 25 units to be completed on site. Project spend now requires to be reprofiled. Unanticipated longer time frame
for demolition (9 months) has delayed this project by 6 months, now estimating a March 2023 site start, although demolitions are
planned for next month. £0.100m expected costs in 22/23, resulting in reprofiling requirement of £2.420m to 23/24.
Bonhill Gap Site - 32 units to be completed on site.  Estimated start date July 2023 and estimated completion September 2024. 
The project is currently  at design stage with spend of £0.420m expected in 22/23 . No reprofilng required .
Mitigating Action
Staff will work closely with all stakeholders to try and ensure timely resolutions of issues as they arise.
Pappert - 27 units to be completed on site . Projects spend now requires to be reprofiled.  The anticipated site start of October
2022 will not be realised due to a number of factors that have caused the project to miss a number of milestones, notably a longer
than anticipated procurement process and the subsequent delay in developing a contract/tender preparation forced us to miss a
pricing window from the contractor, we anticipate a new cost price in November with a site start of March 23.  It is expected
£0.500m will be paid out in 2022/23 withthe remaining £4.481m to be reprofiled into 2023/24

Page 5

APPENDIX 5
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 6
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials 2,487 253 10% 2,487 0 0%
Current Year Financials 474 253 53% 474 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials 2,266 406 18% 2,266 0 0%
Current Year Financials 431 406 94% 431 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
3
Project Life Financials 1,557 28 2% 1,557 0 0%
Current Year Financials 664 28 4% 664 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
4
Project Life Financials 271 0 0% 271 0 0%
Current Year Financials 185 0 0% 185 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No issues. Development of QL system to carry on through 22/23.
Mitigating Action
None required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
QL Development
This budget relates to the costs associated with the development of the Integrated Housing
Management System
Better Homes Priority Budget
Priority projects as prioritised by the Better Homes Group 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
A number of priority initiatives, supported by the Better Homes Project Board,  are being investigated and are envisaged to have a
positive impact on the current council housing stock and budget, with works expected to progress in 22/23.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Capitalised minor works
Gypsy/ Traveller Site improvements 
Planned End Date  Forecast End Date 
Adaptations to Housing for Special Needs 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets. Possibility of overspend due to price increases and demand levels rising.
Mitigating Action
30 September 2022
Budget Details Project Life Financials
Spend to Date Variance
Special needs adaptations
None required at this time
Anticipated Outcome
Full budget spend, possibility of overspend.

Page 6

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 6
Budget Forecast Spend
£000 £000 % £000 £000 %
30 September 2022
Budget Details Project Life Financials
Spend to Date Variance
5
Project Life Financials 170 0 0% 170 0 0%
Current Year Financials 40 0 0% 40 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
6
Project Life Financials 17 0 0% 17 0 0%
Current Year Financials 17 0 0% 17 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
7
Project Life Financials 36 0 0% 36 0 0%
Current Year Financials 36 0 0% 36 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
8
Project Life Financials 192 0 0% 192 0 0%
Current Year Financials 192 0 0% 192 0 0%
Project Description
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Awaiting receipt of the airport scheme outline from Glasgow Airport before works can planned.  Project expected to make
progression in 22/23.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Anticipated Outcome
Full budget spend
Airport Noise
Noise Insulation Project 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
5 redeployable cameras to be purchased as planned.  No issues anticipated.
Mitigating Action
None required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Redployable CCTV Cameras
Purchase of 5 redeployable CCTV cameras for Housing use
Community Safety Projects
Community Safety Projects 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Gypsy Travellers Site
Gypsy/ Traveller Site improvements 
Planned End Date  Forecast End Date

Page 7

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 6
Budget Forecast Spend
£000 £000 % £000 £000 %
30 September 2022
Budget Details Project Life Financials
Spend to Date Variance
9
Project Life Financials 19,841 0 0% 19,841 0 0%
Current Year Financials 4,455 0 0% 4,455 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
10
Project Life Financials 17,607 3,646 21% 17,607 0 0%
Current Year Financials 4,955 3,646 74% 4,955 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
11
Project Life Financials 257 22 9% 257 0 0%
Current Year Financials 75 22 30% 75 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Mitigating Action
None required
Anticipated Outcome
Full budget spend
External stores/garages/bin stores/drainage component renewals
This budget is to focus on external stores/garages/bin stores etc. component renewals as
identified and recommended from the housing stock condition survey. 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Anticipated Outcome
Full budget spend
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Currently behind monthly targets, however tentatively anticipated to meet full spend and targets. Current tiled roof progress is
behind cumulative monthly targets but overall output is anticipated to increase with the new metal and flat roof framework contract
coming on board contributing to a wider range of roof types being completed.
Mitigating Action
None required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Roof Coverings
Building external component renewals, roofs/chimneys/flashings/fascias/gutters/svp
Targeted SHQS /EESSH compliance works
This budget is to focus on work required to maintain the SHQS compliance and energy
efficiency  with WDC housing stock.   
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets. Current progress is slightly behind cumulative monthly targets, work is
progressing and additional resources will be coming on board shortly with new framework contractor.

Page 8

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 6
Budget Forecast Spend
£000 £000 % £000 £000 %
30 September 2022
Budget Details Project Life Financials
Spend to Date Variance
12
Project Life Financials 273 50 18% 273 0 0%
Current Year Financials 91 50 55% 91 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
13
Project Life Financials 280 0 0% 280 0 0%
Current Year Financials 54 0 0% 54 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
14
Project Life Financials 5,293 325 6% 5,293 0 0%
Current Year Financials 1,036 325 31% 1,036 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
15
Project Life Financials 103 0 0% 103 0 0%
Current Year Financials 103 0 0% 103 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Improvement works (Risk St)
Risk Street Over clad 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Anticipated Outcome
Full budget spend
Modern facilities and services
New Kitchens, Bathrooms and Showers 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Energy improvements/energy efficiency works
Energy improvements/ efficiency works (e.g. loft insulation, pipe/tank insulation, draught
exclusion)
Anticipated Outcome
Anticipated not to meet full spend despite best efforts.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
This programme always presents challenges with owner liaison and reaching agreements to install door entry where none exists,
this contributes directly to achieving SHQS compliance for this element and reducing abeyances. The budget reflects the demand
and number of installs required but it is acknowledged that full uptake is unlikely.
Mitigating Action
Officers continue to liaise with owners to encourage agreement for install.
Secure entry component renewals
This budget is to focus on secure door entry component renewals as identified and
recommended from the housing stock condition survey and appropriate council officer referrals.

Page 9

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 6
Budget Forecast Spend
£000 £000 % £000 £000 %
30 September 2022
Budget Details Project Life Financials
Spend to Date Variance
16
Project Life Financials 581 0 0% 400 (181) -31%
Current Year Financials 181 0 0% 0 (181) -100%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
17
Project Life Financials 3,637 184 5% 3,637 0 0%
Current Year Financials 887 184 21% 887 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
18
Project Life Financials 5,092 717 14% 5,092 0 0%
Current Year Financials 969 717 74% 969 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
19
Project Life Financials 1,135 63 6% 1,135 0 0%
Current Year Financials 215 63 29% 215 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Anticipated Outcome
Full budget spend
Asbestos management works
This budget is to fund work associated with the management of current asbestos legislation and 
Planned End Date  Forecast End Date 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Mitigating Action
None required
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Environmental renewal works, paths/fences/walls/parking area's
Environmental renewal works, paths/fences/walls/parking areas
Defective structures/component renewals
Defective structures 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet full spend and targets.
Main Issues / Reason for Variance
No Issues, contingent budget for unplanned spend
Mitigating Action
none at this time
Anticipated Outcome
Spend as required
Contingencies
This is a contingent budget for unforeseen matters which may arise during the year. 
Planned End Date  Forecast End Date

Page 10

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
MONTH END DATE
PERIOD 6
Budget Forecast Spend
£000 £000 % £000 £000 %
30 September 2022
Budget Details Project Life Financials
Spend to Date Variance
20
Project Life Financials 2,378 0 0% 2,378 0 0%
Current Year Financials 800 0 0% 800 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
21
Project Life Financials 7,729 321 4% 7,729 0 0%
Current Year Financials 2,019 321 16% 2,019 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
22
Project Life Financials 13,031 835 6% 13,031 0 0%
Current Year Financials 2,504 835 33% 2,504 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
TOTAL OF ALL PROJECTS
Project Life Financials 84,232 6,850 8% 84,051 (181) 0%
Current Year Financials 20,382 6,850 34% 20,201 (181) -1%
Main Issues / Reason for Variance
No Issues, budget for salaries and support
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Salaries/central support/offices
Allocation of costs from other WDC services who support the HRA capital programme 
Planned End Date  Forecast End Date
Anticipated Outcome
Budget spend anticipated, should criteria be met.
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
The main objective of the Buy Back Scheme is to bring former council properties that were sold through the RTB scheme, back
into council use.  These properties must assist the council with reducing housing need on the waiting list and where appropriate
assist with external capital works.  For these reasons, any purchase is subject to stringent criteria to ensure accountability and
value for money for existing tenants.  Spend in 22/23 will therefore be dependent on these factors.  So far this year, 8 homes have
been purchased, with a further 4 under offer. The target is to deliver an additional 20 homes each year through the buyback
scheme.
Mitigating Action
None required.
Mitigating Action
None required
Anticipated Outcome
Full budget spend
Buy Backs
This is a budget to undertake specific projects that will deliver housing policies/strategies,
example: Ex local authority and mortgage to rent buy-back scheme
Multi Story Flats  ( including Fire Risk Assessment Works)
High Rise Fire Safety Measures 
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
No Issues, anticipated to meet spend and revised targets.

Page 11

APPENDIX 6
WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
MONTH END DATE
PERIOD 6
Budget Forecast Spend
£000 £000 % £000 £000 %
1
Project Life Financials (48,826) 0 0% (48,826) 0 0%
Current Year Financials (30,006) 0 0% (10,480) 19,526 -65%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials (42,531) 0 0% (41,168) 1,363 -3%
Current Year Financials (9,215) 0 0% (7,852) 1,363 -15%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
3
Project Life Financials (123,078) (11,550) 9% (123,078) 0 0%
Current Year Financials (26,286) (11,550) 44% (19,945) 6,341 -24%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
Prudential borrowing is impacted by programme delivery therefore due to reprofiling, the requirement in 2022/23 will be less.
Mitigating Action
None available at this time.
Anticipated Outcome
While prudential borrowing requirement is likely to be less than budgeted in the current financial year this is anticipated to catch
up over the programme life.
Prudential Borrowing
Prudential borrowing is long term borrowing from financial institutions that has been approved
for the purposes of funding capital expenditure
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Income from Revenue reduced to offset adverse varainces in HRA revenue
Mitigating Action
Non required
Anticipated Outcome
Reduced CFCR
CFCR
This is capital spend which is funded by revenue budgets
Planned End Date  Forecast End Date
Main Issues / Reason for Variance
Main Issues / Reason for Variance
30 September 2022
Budget Details Project Life Financials
Spend to Date Variance
New Build Grant 
Grant to facilitate new build housing 
Planned End Date  Forecast End Date
Due to spend being later than anticiapted , receipt of grant will also be later than budgeted.
Mitigating Action
Income budget wil be reprofiled to match reprofiled spend
Anticipated Outcome
Income will be received in 2023/24

Page 12

WEST DUNBARTONSHIRE COUNCIL
HRA CAPITAL PROGRAMME
ANALYSIS OF RESOURCES
MONTH END DATE
PERIOD 6
Budget Forecast Spend
£000 £000 % £000 £000 %
30 September 2022
Budget Details Project Life Financials
Spend to Date Variance
New Build Grant 4
Project Life Financials (96) (54) 56% (96) 0 0%
Current Year Financials (96) (54) 56% (96) 0 0%
Project Description
Project Lifecycle 31-Mar-27 31-Mar-27
TOTAL RESOURCES
Project Life Financials (214,531) (11,604) 5% (213,168) (1,363) 1%
Current Year Financials (65,604) (11,604) 18% (38,373) (27,230) 42%
No variance
Mitigating Action
Non required
Anticipated Outcome
Income will be received
Other Capital Income
Other Income to capital
Planned End Date  Forecast End Date
Main Issues / Reason for Variance