WEST DUNBARTONSHIRE COUNCIL 
Report by the Chief Officer, Housing and Employability 
Housing and Communities Committee: 23 November 2022
__________________________________________________________________ 
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme 
1. Purpose 
1.1 This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme. 
2. Recommendations 
2.1 It is recommended that the Housing and Communities Committee: 
(i) Note the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach
including the practical completion and handover of the latest development
project at Queens Quay (Site B); and 
(ii) Approves the undertaking to conduct all necessary procurement exercises
for the new identified sites within the Future New Build – West
Dunbartonshire Affordable Housing Supply Programme identified in
section 4.3 of this report to deliver new council homes: and 
(iii) Approve the acquisition of the former Clydebank Health Centre site at the
cost of £707,400 from NHS Greater Glasgow and Clyde for the delivery of
new Council homes. 
3. Background 
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which was initially tasked and has successfully delivered over 1000 new
affordable homes in West Dunbartonshire by 2022 and includes the Council’s
own ambitious New House Building Programme. 
3.2 The Council’s latest practical completion took place at the Queens Quay
development in September this year delivering 29 new Council homes in a
key regeneration area as part of a wider development which has delivered

Page 2

146 new social rented homes.  These are first residential properties to be
heated from the Council’s Queens Quay District Heating Network.   
3.3 These 29 new homes, are in addition to the completion of the Council’s first
fully dementia designed development at Creveul Court, Alexandria and other
exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton
Harbour and St Andrews, Clydebank.  The Council have now completed 12
new build developments since 2013 and are the largest developer of social
homes in West Dunbartonshire delivering 496 new homes to date as outlined
in Table 1 below: 
Table 1:  Completed Council New Build
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank  126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank 29 August 2022
Totals 496   
3.4 The Strategic Housing Investment Plan (SHIP) 2022-2026, outlining West
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2021. A new SHIP is being prepared
and will be presented to the November 2022 meeting of the Housing and
Communities Committee covering the period 2023-2027.  The new SHIP will
outline plans to meet the new Council Administration’s aim of delivering 2500
new affordable and social rented homes over the next 10 years. 
4. Main Issues 
More Homes West Dunbartonshire - Delivery Programme 
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic recovery plans.  It is also
clear that the need for affordable homes has and will increase in the current
economic environment. Our More Homes West Dunbartonshire approach is
an ambitious plan that aims to continue the positive momentum of the delivery
of much needed Council homes in West Dunbartonshire and will significantly
assist the Council’s aim to deliver 2500 new social and affordable homes by
2032. 
4.2 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified a number of future development sites for new council

Page 3

homes to address existing and new housing need. The design of these homes
will further develop, improve and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low
carbon ambitions including passivhaus and other net zero carbon
opportunities. 
4.3 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  Some of the
initial plans were and continue to be impacted as a result of global issues
revised new build targets for the Council are outlined below:   
Table 2: Council New Build Programme 
*Current Planning figures 
4.4 Updates for each site are noted below: 
Clydebank East: 
Following the Housing and Communities Committee decision in November
2015 to fully demolish the 336 homes in Clydebank East and regenerate the
area, the demolitions were completed in October 2019.  Design of 88 new
build council properties has been underway with architects Anderson, Bell and
Christie.  The project was heard at the October 2021 Planning Committee.
However, Planning was continued as committee were concerned at the
parking provision provided.
Site/Developer Number of
Units
Number of
Specialist
Provision 
Est Site
Start
Est Completion
Date
Clydebank East,
Clydebank 88  9 
January
2023
Spring 2025
Pappert, Bonhill
Alexandria 27  3
March
2023
Summer 2024 
Mount Pleasant 25 25 March
2023
Summer 2024
Dennystoun
Forge
20 20 April 2024 Summer 2024
Willox Park 17 17 June 2023 Summer 2024
Bonhill Gap Sites* 35 4 July 2023 Winter 2024/25
Bank Street,
Alexandria
20 20 Autumn
2023
Winter 2024/25
Queens Quay
Site C
100 10 Autumn
2023
Spring 2025
Clydebank Health
Centre*
38 5 Autumn
2023
Spring 2025
Clydebank Gap
Sites*
50 10 Spring
2024
Summer 2025
Buyback Scheme
(50 per year)
250 25 2023/24 2027/28
670 units 148 units

Page 4

The Planning was approved in June 2022, with an extended parking scheme,
125%, and the inclusion of electric charging points and future proofing of all
parking spaces for the provision of EVs. 
This delay has caused considerable financial increases estimated to be in
region of 25%, caused by global construction inflation and the Ukraine
invasion in February, which has resulted in additional pressures on the supply
chain and increased costs. 
We are now working through the revised planning conditions.  Following
additional and more detailed site investigations we were also looking at very
significant additional costs of an estimated £11m to deliver the ground
remediation strategy.   
These additional costs placed the development at risk due to affordability
issues.  However, we have over the last couple of months carried out a value
engineering exercise to deliver the most cost effective method of delivering
the required remediation strategy.  This has resulted in an extension of the
construction period but has reduced the costs from the projected £11m to a
cost of £4.796m.  It should be noted that in discussions with the Council’s
Land Contamination Team that remediation works would be necessary
regardless of the intention to build new Council homes on the site.     
The value engineering exercise undertaken has resulted in a significant cash
saving of £6.204m to the project and having been assessed within the HRA
Business Plan is within the affordability threshold and we plan to commence
the remediation works in January 2023.  This will avoid the requirement to
return £1.511m to the Scottish Government in Affordable Housing Supply
Funding that has been drawn down on the project to date. 
While the current Affordable Housing Supply Grant benchmarks are not due
to be reviewed and uprated based on inflation until April, it is our intention to
seek grant above current benchmark levels and have already opened
dialogue with the Scottish Government on this in advance of submission of
our grant application before the end of this calendar year.   
The development at Clydebank East will see the completion of a major
housing led regeneration of a key priority area identified in the Local Housing
Strategy and will be the Council’s first fully zero carbon housing development
and marks a significant milestone in our transition to net zero approved at the
August 2022 meeting of the Housing and Communities Committee. 
Pappert, Bonhill 
The development of 27 new homes comprises 7 Passivhaus homes and 20
homes meeting the net zero ready standard.

Page 5

House Type Sustainability Standard Number of New
Homes
House 3bed/4 person Passivhaus 4
House 3bed/5 person Passivhaus 3
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6 
We have commenced preplanning consultation in advance of submitting a
formal planning application within the next few weeks.  This development is
also subject to a funding application to the Scottish Government’s Vacant and
Derelict Land Fund. 
Mount Pleasant, Old Kilpatrick 
The demolition of the former care home at the site commenced on Monday
31st October with a completion date of 2 February 2023. 
We have had an initial consultation with the Old Kilpatrick Community Council
where we presented our concept of providing between 25 units of housing in a
similar style to Creveul Court, one and 2 bedroom flats and terraced 1 / 2
bedroom terraced cottages with private gardens. 
Dennystoun Forge Gypsy/Traveller Site 
A submission has been made to the Scottish Government for support funding
from their Gypsy/Traveller Accommodation Fund for significant improvements
to the Dennystoun Forge site, including new energy efficient chalet type
accommodation following a consultation exercise with site residents. This
proposal has made it to the final round of the bidding process and following a
positive presentation to the Scottish Government in October 2022 we await a
decision if funding will be granted before the end of this calendar year. 
Willox Park, Doveholm, Dumbarton 
As we prepare tom submit a formal planning application before the end of this
year, we have appointed a Landscaping consultant to design a scheme for the
planning application.  In addition we are in the process of appointing a civil
engineer to prepare a flood plain analysis, which will form part of the planning
permission. 
During the consultation, tenants and adjacent owners have highlighted
parking and vehicle movement as a concern, we instructed a parking survey,
which concluded that the existing car parking provision, had a maximum
capacity of 30% at different times of the day during the survey period.

Page 6

All demolition works are now complete with Practical Completion Certificate
issued to contractor. The site has been secured in anticipation of the
construction phase of the development. 
Bonhill Gap Site Strategy 
We are currently progressing design drawings for each of the gap sites and
await an estimated cost for the projects by end of November following the
acquisition of the additional site from the Council’s General Fund. 
In response to families facing overcrowding, it is the intention to deliver a
proportion of larger homes within the gap site developments. 
Bank Street, Alexandria 
The council is currently developing a proposal for 20 sheltered/amenity
housing units in partnership with the HSCP. This will include an options
appraisal in terms of the existing provision within the local area. 
There are a number of infrastructure constraints within the site including a
main sewer which may affect the viability of the site. We are currently working
on pre-planning drawings for submission in early 2023 based on the
conclusion of the discussions with HSCP. 
Queens Quay, Site C, Clydebank 
The Council is currently developing a design to deliver a projected 20 units on
this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network
.
Pre-planning response was received on the 25th February highlighting
concern of the WDC development proceeding in isolation. We have adopted
a, proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have instructed the District Valuer to
value these adjacent site to Queens Quay C with a view to purchasing
additional land to deliver more affordable housing in the Queens Quay
regeneration site.  If this is achieved we would seek to develop a mixed tenure
approach to any expanded development site. 
Clydebank Health Centre 
The Council are continuously looking for opportunities to provide additional
new build council homes and this includes through the Scottish Government’s
trawl process which seeks to utilise public sector land sales for the delivery of
key national ambitions which includes the delivery of new homes. The former
Clydebank Health Centre in Kilbowie Road, Clydebank was identified through

Page 7

this process and approval is sought to acquire the site from NHS Greater
Glasgow and Clyde to West Dunbartonshire Council. 
The transfer will be carried out using the process set out in the Scottish Public
Finance Manual - Guidelines for the Transfer of Property within the Scottish
Public Sector. 
A plan of the area is included as Appendix 1 to this report and has a gross site
area which extends to 0.98 ha (2.43 acres).  A valuation carried out by the
District Valuer in October 2022 placed a valuation of £1.6m for the site.
Tripartite discussions involving the Scottish Government, NHS Greater
Glasgow and Clyde have reached agreement on a financial assessment on
the levels of abnormal costs within the site resulting in an offer of £707,400
subject to Committee approval. 
Therefore approval is sought within this report for West Dunbartonshire
Council’s Housing Revenue Account to acquire the Clydebank Health Centre
site for the sum of £707,400. 
The acquisition costs will be met in full from acquisition grant from the Scottish
Government’s Affordable housing Supply Programme budget.   On the
successful completion of the acquisition it would be the Council’s intention to
demolish the existing property as a matter of urgency. 
4.5 The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper. 
5. People Implications 
5.1 There are no people implications from this report. 
6. Financial and Procurement Implications 
Financial 
6.1 In March 2022 Council approved the Housing Capital Programme 2022-2027
which saw significant resources committed to the delivery of new council
homes in West Dunbartonshire.  An expenditure budget of £83.393m for the
affordable housing supply programme is factored into the HRA Capital
Programme.  The additionality in the costs highlighted for the Clydebank East
development can be met from this existing budget; however we would
anticipate additional grant funding would be made. As it currently stands, it is
anticipated that this programme will complete on project life budget. 
6.2 Influenced by Brexit, the current Covid-19 pandemic, Ukraine and other global
issues, the emergence of supply issues and subsequent cost increases has
begun to be felt across Scotland and the UK.  Whilst the impact of these is still

Page 8

being examined, it is prudent to mention this as early as possible in order to
provide more detailed information at a future Committee when new tender
prices are known. 
6.3 We are likely to see this impact on all our future development sites. Housing
Development Officers and Finance will continue to assess the impacts in the
context of affordability of developments. 
Procurement 
6.3 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted with 4.4 of this report will continue
to be prioritised. 
6.4 Where the contract award is less than £50,000, authority is delegated to
the Chief Officer in consultation with the Procurement Manager to instruct the
award of contracts for the planned revenue and capital spend detailed in this
report to suppliers providing the most economically advantageous offer to the
Council. 
7. Risk Analysis 
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis. 
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel. 
8. Equalities Impact Assessment (EIA) 
8.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment. 
9. Consultation 
9.1 As part of our previous rent consultation exercise, 92% of respondents
indicated their support for the Council’s ambitious plans to deliver the Housing
Revenue Account (HRA) new council house build programme. In addition,
there was positive support for the wider delivery of new build housing as part
of the recent Local Housing Strategy.  Regular updates on new build
development are provided to the West Dunbartonshire Tenants and Residents
Organisation at the bi-monthly liaison meetings. 
10. Strategic Assessment

Page 9

10.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
Having considered all the Council’s strategic priorities, this report and the
provision of new supply social housing for rent contributes greatly to all
strategic priorities. 
Peter Barry
Chief Officer, Housing and Employability
Date: 8 November 2022 
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, telephone: 07793717981, email: john.kerr@west-
dunbarton.gov.uk   
Appendices: 1. Clydebank Health Centre site plan 
Background Papers: West Dunbartonshire Council’s Local Housing Strategy     
Local Housing Strategy, Health Inequalities Impact
Assessment 
DVS Valuation Report Development Site: Clydebank
Health Centre   
Wards Affected: All