WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 24 August 2022
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme 
1. Purpose
1.1 This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach
including the forthcoming practical completion and handover of the latest
development project at Queens Quay (Site B) scheduled for early
September subject to meeting all planning conditions; and
(ii) Approves the commitment that all future new homes programmed within
our More Homes delivery programme building are consistent with our Net
zero ambitions outlined within 4.4 of this report;
(iii) Approves the undertaking to conduct procurement exercises for identified
sites within the Future New Build – West Dunbartonshire Affordable
Housing Supply Programme. Refer to Table 2: Identified Additional Future
Sites
(iv) Approves the undertaking to conduct procurement exercises for the
maintenance contracts required for Net Zero technologies including Solar
Panels and MVHR (Mechanical Ventilation with Heat Recovery) units as
referenced in 4.19 of this report, and approves the revenue spend
included in this report including approval to explore and secure multi-year
contracts, contracts utilising framework agreements (FA) or contracts
utilising dynamic purchasing systems (DPS) beyond the term of approved
budgets where efficiencies and savings can be achieved;
(v) Approve the transfer of the site at Old Bonhill referenced at 4.18 of this
report from the General Fund to the Housing Revenue Account for the
delivery of new Council homes for £160k subject to clear title.
ITEM 8

Page 2

3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which was initially tasked and has successfully delivered over 1000 new
affordable homes in West Dunbartonshire by 2022 and includes the Council’s
own ambitious New House Building Programme.
3.2 The Council’s latest practical completion will take place at the Queens Quay
development in September this year delivering 29 new Council homes in a
key regeneration area as part of a wider development which has delivered
146 new social rented homes.  This, is in addition to the completion of the
Council’s first fully dementia designed development at Creveul Court,
Alexandria and other exemplar developments in Haldane, Aitkenbar,
Bellmsyre, Dumbarton Harbour and St Andrews, Clydebank.  The Council
have now completed 12 new build developments since 2013 and are the
largest developer of social homes in West Dunbartonshire delivering 496 new
homes to date as outlined in Table 1 below:
Table 1:  Completed Council New Build
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank 126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank* 29 August 2022
Totals 496
*Scheduled to complete on 19th August 2022
3.3 The Strategic Housing Investment Plan (SHIP) 2022-2026, outlining West
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2021. A new SHIP is being prepared
and will be presented to the November meeting of the Housing and
Communities Committee.
4. Main Issues
Net Zero Homes
4.1 Scotland has committed to net zero emissions by 2045, five years ahead of
the other UK nations. If this target is to be met it is essential that major
changes to carbon emissions take place with a 75% reduction by 2030.

Page 3

4.2 The first major milestone is the Scottish Government’s New Build Heat
Standard, where no gas boilers or oil heating systems will be permitted in new
build homes from 2024.
4.3 To help West Dunbartonshire Council’s wider sustainable transition to Net
Zero it is essential that we reconsider how best to heat our homes whilst
simultaneously minimising fuel poverty and creating employment opportunities
within the emerging technologies sector to maximise opportunities for our
communities.
4.4 In terms of our affordable housing delivery programme it is proposed that all
future new homes programmed within our More Homes delivery programme
building on our pathfinder development projects at Pappert and Clydebank
East are optimised for operational net zero, by incorporating renewable
technologies within our new build program, with immediate effect by:
• Incorporating Renewable Technology
• Adopting a Fabric First approach
• Investing in Carbon Sequestration
• Creation of a Green workforce
Incorporating Renewable Technology
4.5 Solar Panels should be considered when orientation and positioning allow.
Solar panels harness energy from the sun to power items within the home.
The solar panels will be “zero-export” to grid.  When incorporated within a
house or cottage flat the tenant will receive direct benefit from the energy
generated. Where solar panels are fitted to blocks of flats the tenants and
landlord will benefit from the supply.
4.6 Heat Pumps are a low carbon source of heating. Heat is absorbed from a
source (water, air or ground) and transferred to a fluid. The fluid is
compressed further to increase the temperature. The heat is transferred form
the fluid into water which circulates around the home to provide heating and
hot water.
Adopting a Fabric First approach
4.7 It is proposed that a strengthened continuation to our fabric first approach to
create highly insulated and airtight homes that will ultimately require less
energy to heat and result in lower utility bills for tenants. The thermal
performance of the building will be enhanced by applying the principles of:
• Passivhaus featuring a mechanical ventilation system with highly
efficient heat recovery; or
• Platinum Aspect Level 1 (Carbon Dioxide Emissions) under Section
7 (Sustainability) of the current building standards. The relevant
standard is noted below:

Page 4

4.8 Carbon dioxide emissions under the guidance to Standard 6.1, carbon dioxide
emissions CO2 Dwelling Emission Rate (DER) is to be 100% lower than the
Target Emission Rate (TER) set by the 2010 Standards. To establish this, the
DER should not exceed zero. (This net zero carbon equivalent is a 100%
improvement on the 2007 Standards).
4.9 A typical sustainability label for properties meeting Platinum 1 Carbon Dioxide
Emissions is illustrated below:
Investing in Carbon Sequestration
4.10 We plan to optimise investment in projects to capture and store atmospheric
carbon dioxide, such as supporting the expansion of West Dunbartonshire
Council’s carbon sequestration tree planting program within all future housing
developments, resulting in communities that are rich in biodiversity.  The
Housing Development are already working closely with the Council’s
Biodiversity Officer in maximising opportunities within all planned
developments.

Page 5

Creation of a Green Workforce
4.11 It is the aim of the Council to create a Green Workforce within West
Dunbartonshire. Working with Working4U we will engage with stakeholders,
including Skills Development Scotland, to identify upskilling and modern
apprenticeship opportunities within the emerging technology sector. 
4.12 By developing a workforce to address labour shortages within the renewable
sector, such as Solar Panel Maintenance Operatives, it is anticipated that
residents will benefit from increased employment prospects and the Council
will simultaneously make cost savings by delivering future maintenance
contracts in house.
4.13 It is West Dunbartonshire Council’s ambition to deliver new build homes
optimised for a decarbonised grid with a focus on health and wellbeing. A
reduction in energy will result in homes that are more efficient and affordable
to run, with the elimination of fuel poverty. An investment in the creation of a
Green Workforce will ensure that the journey to Net Zero will benefit the wider
community and contribute to West Dunbartonshire Council’s economic
sustainability. By enhancing the biodiversity of our greenspaces and reducing
carbon emissions, our communities will provide a life enhancing environment
for many years to come.
4.14  While the above signifies a strong commitment from West Dunbartonshire
Council to deliver net zero ambitions around our current house building
programme, we will also engage with our Strategic Housing Partners, it is our
ambition to encourage West Dunbartonshire’s Registered Social Landlords to
share our commitment that all new build homes within our future Affordable
Housing Supply Program will comply with Net Zero standards, ensuring that
our communities will provide a life enhancing environment for many years to
come.
More Homes West Dunbartonshire - Delivery Programme
4.15 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic recovery plans.  It is also
clear that the need for affordable homes has and will increase. Our More
Homes West Dunbartonshire approach is an ambitious plan that aims to
continue the positive momentum of the delivery of much needed Council
homes in West Dunbartonshire.
4.16 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified a number of future development sites for new council
homes to address existing and new housing need. The design of these homes
will further develop, improve and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low
carbon ambitions including passivhaus and other net zero carbon
opportunities.

Page 6

4.17 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  Some of the
initial plans were and continue to be impacted as a result of global issues
revised new build targets for the Council are outlined below:
Table 2: Council New Build Programme
4.18 Updates for each site are noted below:
Queens Quay
We anticipate handover of 29 new Council homes on 9 September 2022, the
developer Wheatley Group are required to ensure full compliance with all
planning conditions to achieve the completion certification.  At the time of
writing there are two notable planning conditions that require to be achieved
around the provision of a car and bike club within the development.  We are
working with Wheatley to ensure that these are achieved and that the final
handovers take place as planned on the 9th September. 
Clydebank East: 
The demolition of 339 properties completed in October 2019.  Design of 88
new build council properties has been underway with CCG and architects
Anderson, Bell and Christie.  The project and was heard at the October 2021
Planning Committee. however, Planning was continued as committee were
concerned at the parking provision provided.
The Planning was approved in June 2022, with an extended parking scheme,
125%, and the inclusion of electric charging points and future proofing of all
parking spaces for the provision of EVs.
This delay has caused considerable financial increases estimated to be in
region of 25%, caused by global construction inflation and the Ukraine
invasion in February, which has resulted in additional pressures on the supply
chain.
Site/Developer Number of Units Est Completion Date
Queens Quay Site B 29 August 2022
Clydebank East,
Clydebank 88 August  2024
Pappert, Bonhill
Alexandria 27 September 2024
Willox Park 17 May 2024
Gap Site Strategy 29 September 2024
Mount Pleasant 25 March 2024
Bank Street 20 January 2025
Queens Quay Site C 20 March 2024
Buyback Scheme 100 Ongoing at 20 per year
Dennystoun Forge 20 March 2024
375 units

Page 7

We are now working through the revised planning conditions.  Following
additional and more detailed site investigations we are now also looking at
very significant additional costs to deliver the ground remediation strategy. 
These additional costs place the development at risk due to affordability
issues.  We expect to be in receipt of full information to make an assessment
in early September and we will provide an update to the Housing and
Communities Committee when this has been achieved. This is intended to be
the Council’s first fully zero carbon housing development and marks a
significant milestone in our transition to net zero outlined in paragraphs 4.1-
4.14 of this report.
Pappert, Bonhill
The development of 27 new homes comprises 7 Passivhaus homes and 20
homes meeting the net zero ready standard. 
House Type Sustainability Standard Number of New
Homes
House 3bed/4 person Passivhaus 4
House 3bed/5 person Passivhaus 3
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6
Employer’s Requirements and tender documents have been issued to legal
for review. Due to the specialist nature of construction (Net Zero & Passive
House) tender period will be 6-8 weeks. 
Willox Park, Doveholm, Dumbarton
All demolition works are now complete with Practical Completion Certificate
issued to contractor. The site has been secured in anticipation of the
construction phase of the development.
Our specialist contractor commenced site investigation works on 20th June
with drilling completed on 24th June. Groundwater testing and chemical
testing are currently underway. So far no gross contamination has been
encountered and ground conditions are as expected. Final factual report due
in late August. 
The initial design proposals following community consultation will be
presented to the Council’s planning service in advance of any formal planning
submission and this is planned to take place before the end of August.

Page 8

Gap Site Strategy
An exercise is currently underway to assess the viability of a number of gap
sites for future housing development within the ownership of HRA. A number
of sites within Bonhill have been identified and approval has been obtained
from the Scottish Government to batch these sites together to form one
project to allow WDC to secure grant funding.  To further support our
ambitions we are in discussions with our Corporate Assets colleagues
regarding the purchase of an area of land located within Old Bonhill.  The
particular site comprises of a rectangular shaped parcel of land that is
generally level and extends to extends to 2,437.46 square metres (0.60 acres)
or thereby.  Approval is sought within this report to transfer the site from
General Fund to the Housing Revenue Account at its gross valuation of
£160k.  A copy of the District Valuer valuation is available as a background
paper to this report.
A similar exercise is underway at Clydebank with the intention of combining
gap sites within Lilac Avenue and Melbourne Avenue. 
In response to families facing overcrowding, it is the intention to deliver a
proportion of larger homes within the gap site developments.
Mount Pleasant, Old Kilpatrick
A number of surveys have been instructed prior to the planned demolition of
the existing building.  While planning in terms of this development is at an
early stage we would seek to deliver a similar development to the recent
Creveul Court development this is supported by a housing needs assessment.
Bank Street, Alexandria
The council is currently developing a proposal for 20 sheltered housing units.
There are a number of infrastructure constraints within the site including a
main sewer which may affect the viability of the site. We are currently working
on pre-planning drawings for submission in August. Requirements from WDC
Roads will be included in these drawings. This project will be required to
present to the Planning and Design Panel due to the town centre location
To facilitate Smollet Fountain resurfacing works, WDC Roads Department are
using the site for their compound until November 2022.
Queens Quay, Site C, Clydebank
The Council is currently developing a design to deliver a projected 20 units on
this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network
.
Pre-planning response was received on the 25th February highlighting
concern of the WDC development proceeding in isolation. We have adopted
a, proactive response to this issue and have developed Masterplan diagrams

Page 9

incorporating the surrounding sites and early discussions have taken place to
explore acquiring adjacent land for development by ourselves to deliver more
affordable housing in the Queens Quay regeneration site.  We are also
examining the opportunities for a mixed tenure approach to any expanded
development site.
Buy Back Scheme:
In the financial year ending April 2022, we purchased 14 homes at a cost of
£980,000.
We have a budget of £2.4 million to purchase homes to the financial year
ending 2023 having secured additional grant funding.
To date we have purchased 2 homes, with 3 under offer and we have
targeted to deliver an additional 20 homes each year through our buyback
scheme.
As part of a pilot project, we are refurbishing a semi-detached house at 87
O’Hare, bringing it up to a higher standard than our ready to let standard and
improving energy efficiency of the property.  This will inform our future retrofit
strategy.
Dennystoun Forge Gypsy/Traveller Site
A submission has been made to the Scottish Government for support funding
from their Gypsy/Traveller Accommodation Fund for significant improvements
to the Dennystoun Forge site, including new energy efficient chalets and utility
blocks.  Our proposal has made it to the second round of the bidding process
and we are scheduled to make a presentation to the Scottish Government in
October 2022, following a consultation exercise with site residents.  
4.19 To continue to ensure our new homes meet the needs of our tenants we
require to put in place a maintenance and monitoring contract for solar panel
and MVHR systems.  It is intended that this will be an externally sourced for a
period of 12 months, with an option to extend by an additional year. It is the
Council’s intention to upskill their Building Services workforce during this
period with a view to carrying out the maintenance of West Dunbartonshire
Council’s green technology thereafter. Following committee approval Housing
Development will liaise with procurement partners to carry out a procurement
exercise to secure suitable contractors.
4.20 The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper.
4.21 Our dementia friendly development at Creveul Court received the Association
Public Sector Excellence (APSE) Margo Blair Innovation Award, celebrating
outstanding local councils that use innovative ideas and solutions to tackle the
current challenges facing their frontline services.

Page 10

5. People Implications
5.1 There are no people implications from this report.
6. Financial and Procurement Implications
Financial
6.1 In March 2021 Council approved the Housing Capital Programme 2021-2026
which saw significant resources committed to the delivery of new council
homes in West Dunbartonshire.  An expenditure budget of £83.393m for the
affordable housing supply programme is factored into the HRA Capital
Programme.  The additionality in the costs highlighted for the Pappert
development can be met from this existing budget; however we would
anticipate additional grant funding would be made. As it currently stands, it is
anticipated that this programme will complete on project life budget.
6.2 Influenced by Brexit, the current Covid-19 pandemic and other issues, the
emergence of supply issues and subsequent cost increases has begun to be
felt within not only our existing and future sites, but sites across Scotland and
the UK.  Whilst the impact of these is still being examined, it is prudent to
mention this as early as possible in order to provide more detailed information
at a future Committee when new tender prices are known.
6.3 We are likely to see this impact on our future development sites including
Clydebank East. Housing Development Officers and Finance will continue to
assess the impacts in the context of affordability of developments.
Procurement
6.3 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted with 4.17 of this report will
continue to be prioritised.
6.4 Where the contract award is less than £50,000, authority is delegated to
the Chief Officer in consultation with the Procurement Manager to instruct the
award of contracts for the planned revenue and capital spend detailed in this
report to suppliers providing the most economically advantageous offer to the
Council.
6.5 Where the value of the contract is over £50,000, remittance for
approval will be submitted to the Tendering Committee.
Community Benefits
6.6 As part of each project, the contract has incorporated an element of
Community Benefits that can support a wide range of social, economic and
environmental benefits for communities including jobs, apprenticeships and
local charity and community initiatives. A summary of the community benefits

Page 11

achieved through the first phase of the More Homes West Dunbartonshire
approach is outlined in the table below:-
Community Benefit Value Total
Work placement opportunities (16 plus years) – no.
individuals
30
Construction Curriculum support activities – no. individuals 16
Graduates - no. individuals 1
Apprenticeship starts  - no. individuals 17
Existing Apprenticeships - no. individuals 17
Apprenticeships completed - no. individuals 22
New jobs created on construction project - no. individuals 16
Community Engagement/Investment £83k
7. Risk Analysis
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis.
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel.
8. Equalities Impact Assessment (EIA)
8.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
9. Consultation
9.1 As part of our recent rent consultation exercise, 92% of respondents indicated
their support for the Council’s ambitious plans to deliver the Housing Revenue
Account (HRA) new council house build programme.  Regular updates on
new build development are provided to the West Dunbartonshire Tenants and
Residents Organisation at the bi-monthly liaison meetings. As detailed at 6.6
above, each project will have their own element of Community Benefits.  This
will provide opportunities for the community to become involved and
participate whether this is pupils at the local school or interested community
members.
10. Strategic Assessment
10.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future

Page 12

investment in housing and related services across West Dunbartonshire.
Having considered all the Council’s strategic priorities, this report and the
provision of new supply social housing for rent contributes greatly to all
strategic priorities. 
Peter Barry
Chief Officer, Housing and Employability
Date: 11 August 2022
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, telephone: 07793717981, email: john.kerr@west-
dunbarton.gov.uk
Appendices: None
Background Papers: West Dunbartonshire Council’s Local Housing Strategy
Local Housing Strategy, Health Inequalities Impact
Assessment
DVS Valuation Report Development Site:WDC Amenity
Land Main Street Bonhill West Dunbartonshire G83 9HS
Wards Affected: All