Appendix 1: SD&P HA&I Delivery Plan 2021/22 Year-end Progress
2. Supported individuals, families and carers living independently and with dignity
More affordable and suitable housing options
Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
% of council dwellings that meet the
Scottish Housing Quality Standard 79.18% 18.17% 86.15%
Target Not Met
An increase in SHQS failures due to the
Electrical Installation Condition Reports
(EICRs) programme not being completed as
planned by the end of March 2022. The
programme has been delayed due to COVID
impact on internal and external resource
availability to deliver the programme as
planned. We have since secured additional
resource to deliver the programme as early
as possible. To ensure the programme
continues to accelerate all our housing stock
to full compliance in terms of EICRs we are
undertaking proactive communications with
tenants to minimise any access issues.
Alan Young
Percentage of council houses that are
energy efficient 82.84% 83.7% 100%
Target Not Met
Work continues incrementally each year to
increase the number of homes meeting the
energy efficiency standard for social housing
EESSH. Compliance continues a positive
trend and 22-23 capital programme will
continue to improve those homes not meeting
the standard.
Alan Young

Page 2

Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
Action Status Progress Due Date Note Owner
Ensure the Council’s Housing stock progresses towards
the achievement of the energy efficiency standard for
social housing.
31-Mar-2022
Whilst work has progressed well and monthly completions
increasing towards targets. Programme has been impacted by
effects of COVID on access, labour and materials availability.
Alan Young
Deliver the HRA Capital Investment programme for
2021/22 31-Mar-2022 Main work streams for 21/22 progressed well considering impact
and restrictions of COVID. Alan Young
Ensure the Council’s Housing stock maintains
compliance with the Scottish Housing Quality Standard
and reduce the number of properties held in abeyance.
31-Mar-2022
Main work streams progressed well, however, issues with
adequate resources in UPVC, Kitchens, Bathrooms and SNA
although this has been improving throughout the year. Building
Services are the main delivery team and have procured additional
contractor support to help delivery of programmes noted above.
It is recognised that compliance level is not where we want it to
be, in the main due to low level of EICR compliance (see SHQS PI
above) compliance level will increase as EICR’s are completed and
progress continues with EESSH work. Officers continue to engage
with owners to encourage participation in door entry projects to
incrementally reduce those properties in abeyance.
Alan Young
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Failure to meet citizen
expectation and service
standards
Risk of citizen dissatisfaction due to us
not doing what we say we will when
we say we will or not completing
required works first time.
31-Mar-2022
Customer service improvement plan
actions have been completed. Customer
satisfaction increased in 2021 / 2022 to
87.7% from 3162 surveys completed.
No change to risk matrix at year end
Martin Feeney
Failure to deliver medical
adaptations in agreed target
timescales
This is monitored to ensure target
timescale of 60 days average for
housing medical adaptations is
adhered to ensure satisfaction with the
service and support those in need of
this service.
31-Mar-2022
Good in-year progress and cleared many
legacy applications, however overall
average days number will still be high
due to older jobs completing.
No change to risk matrix.
Alan Young

Page 3

5. Efficient and effective frontline services that improve the everyday lives of residents
A continuously improving Council delivering best value
Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of repairs appointments
kept 94.87% 89.72% 93%
Marginally missed target. During 2021-22
28,730 appointments were made with
25,807 within their appointment slot.
Resource shortages due to Covid contributed
to appointment failures.
Martin Feeney
% of properties that require a gas
safety record which had a gas check
and record completed by the
anniversary date
97.7% 100% 100% Target achieved. Martin Feeney
Percentage of reactive repairs carried
out completed right first time 89.76% 86.49% 90%
Marginally missed target Right First Time
target due to ongoing issues from covid
restrictions, backlog of repairs and
resourcing issues.
Martin Feeney
Average length of time taken to
complete emergency repairs 6.14 5.81 4
Despite missing target an improvement has
been made compared to the previous year.
There were 5959 emergency repairs
completed in 2021-22.  Performance
impacted by resource issues including high
levels of absence particularly due to covid
and isolation requirements. We continually
work with services to ensure all emergency
repairs are correctly categorised and
resources directed correctly.
Martin Feeney

Page 4

Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
Average time taken to complete non-
emergency repairs 6.76 10.16 7
As expected, target not met due to the
volume of non-essential repairs reported
which could not be complete whilst Covid
restrictions were in place between March
2020 and 26 April 2021. When restrictions
lifted we prioritised those backlog over new
non urgent repairs reported in 2021-22.  This
resulted in average days to complete repairs
increasing compared to previous years.
Martin Feeney
Action Status Progress Due Date Note Owner
Successfully implement the IHMS into service delivery
across all building services teams 31-Mar-2022
Building Services full IHMS support team in place with IHMS
Change Officer, Senior Job Scheduling Planner and all Job
Scheduling Planner posts now filled. This is providing the resource
and support to deliver improvements in the use of the QL system.
Improvement initiatives have been successfully implemented as
planned in 2021/22, a new action will be included in the 2022/23
delivery plan to monitor the improvements already in place and
those still required to be delivered in 2022/23.
Martin Feeney
Introduce project management approach to ensure
continued implementation of the building services
improvement plan (Phase 1)
31-Mar-2022
Phase 1 of the revised structure is being implemented and
satisfactory progress is being made. The overall action will run
into 2022/23 to allow for recruitment of all posts included in
phase 1 and a new action will be introduced to monitor progress
and deliver associated actions in the 2022/23 plan.
Martin Feeney
Review, develop and test new financial costing /
charging model for Building Services work 31-Mar-2022
The new recharge model has been introduced from April.
Development, performance and progress will continue to be
monitored and reviewed on a monthly basis. 
Martin Feeney
Develop the plan to address the outstanding council
house repairs (due to COVID-19), Inform tenants and
undertake repairs within agreed timescales.
31-Mar-2022
Action completed for outstanding repairs reported during in
lockdown periods. Additional system functionality “Locator plus”
application is now live. The level of repair orders closed due to no
access reduced in quarter 4 compared to quarter 3 and the right
first time repair performance also improved although target was
not achieved. Additional resource have been assigned to ensure
timescales are improved on enquiries and complaints and the
number of outstanding complaints did reduce significantly.
Martin Feeney

Page 5

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Failure to implement
improvement plan to ensure
Building Services are fit for
purpose
The implementation of the
improvement plan will enhance the
effectiveness, efficiency and best value
of Building Services
31-Mar-2022
Good progress made in 2021/2022 with
a number of key actions within the
improvement plan completed.
No change to risk matrix at year end.
Martin Feeney
Failure to implement IHMS
system across building
services
The effective implementation of the
IHMS system will delivery efficiency,
improve case tracking, capture
customer satisfaction and improve
service delivery.
31-Mar-2022
All vacancies have been filled including
IHMS and Change Officer, Senior
Planner and vacant Job Scheduling
Planner posts. A comprehensive
improvement action plan has been
developed with various workgroups set-
up to implement improvement required.
No change to risk matrix for year end.
Martin Feeney
Failure to demonstrate robust
financial and productivity
systems within building
services
The development of new costing model
will mitigate against this financial risk.
Process change and review will
improve the system for charging of
works
31-Mar-2022
Regular finance meetings including Chief
Officers from SD&P, H&E and Resources
(Chief Finance Officer) supporting the
service to achieve robust financial
management is in place. Regular
focused meetings in place to discuss and
monitor improvements in data, systems,
processes, workforce and productivity.
A new financial charging model aims to
provide increased visibility and
streamline processes.
Current risk matrix amended with
likelihood reducing from 3 to 2 and no
change to impact.
Martin Feeney
Action Status
Overdue
Completed

Page 6

PI Status
Significantly Missed Target
Narrowly Missed Target
Met or Exceeded Target
Long Term Trends
Improving
No Change
Getting Worse
Short Term Trends
Improving
No Change
Getting Worse
Risk Status
Alert
High Risk
Warning
OK
Appendix 2: Quality Standards - Year-end Progress
SD&P HA&I Quality Standards
Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
Annual review and assessment of
ISO 9001:2015 successfully
completed ensuring continuing
suitability and conformance with no
major non-conformance issues
identified.
100% 0% 100%
We were unable to maintain the ISO
accreditation in 2021/2022 due to covid.  We
will reapply for the accreditation at
appropriate date to be confirmed.
Martin Feeney

Page 7

Performance Indicator
2020/21 2021/22
Owner
Value Status Value Target Short Trend Long Trend Note
Average time taken to complete
medical adaptations
75.7
123.25
87.4
107.84 60
Target not met. 
Performance in 2021/22 continued to be
affected by the previous restrictions in
activity due to Covid-19 and the backlog that
this created.
Activity in terms of carrying out medical
adaptations has now resumed. The number
of medical adaptations completed increased
from 119 in 2020/21, to 313 in 2021/22,
with the number of households waiting for
adaptations to be completed reducing from
134 at the end of 2020/21, to 49 at the end
of 2021/22.
However, completing a large number of
legacy applications which had been on the
list for some time, affected the overall
average days taken to complete medical
adaptations which was 107.84 days. This
remains above our target but was an
improvement from 123.25 days in 2020/21.
Both internal and external resources are
being utilised to increase completions and
further improve performance during
2022/23.
Alan Young
PI Status Long Term Trends Short Term Trends

Page 8

Significantly Missed Target
Narrowly Missed Target
Met or Exceeded Target
Improving
No Change
Getting Worse
Improving
No Change
Getting Worse