West Dunbartonshire Council Annual Assurance Statement 
As Convenor of the Housing and Communities Committee I confirm that we have seen
appropriate evidence to give us assurance that: 
• We comply with all the relevant regulatory requirements set out in Chapter 3
of the Scottish Housing Regulator's Regulatory Framework.
• We are achieving all the relevant standards and outcomes outlined in the
Scottish Social Housing Charter, and
• We are compliant with all relevant legislative duties associated with housing
and homelessness services, tenant and resident safety and equality and
human rights. 
We comply with all the above requirements except for the areas set out below: 
Tenant and resident safety 
Tenant safety within the Councils’ housing stock is one of our main priorities and a key
concern remains in terms of our rate of compliance with the Scottish Housing Quality
Standard. The key driver for this is the number of properties without a valid Electrical
Installation Condition Report (EICR). 
Our current assessment is that the primary constraint to achieving compliance is access
to properties, rather than contractor capacity or resource availability. Properties without
gas appliances present a greater challenge, as tenants are less accustomed to cyclical
servicing visits and our engagement levels are lower. To address this, we are
strengthening our approach to tenant engagement and access. This includes enhanced
communication with tenants, alongside the use of formal legal access procedures where
all reasonable attempts to gain access have been exhausted. These measures are
applied proportionately and as a last resort, and we are increasing the level of activity in
this area where appropriate to support continued progress. The formal legal access
approach has had a positive impact in ensuring tenant engagement and we will continue
to monitor this as it may accelerate our full compliance projection. As agreed, we will
continue to provide monthly updates on our EICR position after each Better Homes
Board. 
In our 2025/26 ARC submission, we also reported that we had 27 properties without
satisfactory equipment for detecting fire and giving warning in the event of fire or
suspected fire. A targeted programme of persistent engagement is underway, including
direct contact and cold calling, to secure access to complete installations. 
Lack of compliance with homelessness duties 
Pressures around the homelessness system was one of the key contributing factors to us
declaring a Housing Emergency within West Dunbartonshire in May 2024. Challenges 
ITEM 11 -
APPENDIX 1

Page 2

Official
remain in terms of the time being taken to move households experiencing homelessness
into settled accommodation and the subsequent pressures which exist in terms of
providing suitable temporary accommodation. 
Whilst we continue to meet most of our homelessness duties including our statutory
responsibility of offering temporary accommodation to those that need it, we reported 43
breaches of the Unsuitable Accommodation Order (UAO), during 2025/26. 
This remains a key area of focus, and we have a number of actions in both our Housing
Emergency Action Plan and Housing Solutions Strategy which aim to ensure that we are
doing all that we can to minimise any future breaches of the UAO. 
Specific assurance on areas requested by the SHR. 
A letter from the SHR dated 19 March 2026 outlined that in our AAS to be submitted
this year we should provide specific assurance on the following areas: 
Data on homes: 
West Dunbartonshire Council holds good quality information on the components and
condition of all its housing stock, maintained within the Council's Housing Quality
database. This data actively informs our SHQS compliance programme, five-year
investment planning and tenant and resident safety obligations. 
In 2025/26, over 2,150 major component renewals were completed, each informed
by and recorded within our housing quality database. Component condition data is
updated continuously through routine stock condition survey updates, planned
maintenance inspections, wider responsive repairs assessments and tenant home
visits.   
Our homes with major component elements approaching end of life are identified
through regular data analysis and incorporated into our rolling five-year housing
capital investment programme, with acceleration applied where required to manage
risk within available resources. 
We recognise, however, that data information on the stock condition is limited to a
small number of Housing Officers and we are in the process of incorporating our
stock data fully within our integrated housing management system, and we anticipate
that our programme to deliver this will be complete in December 2026. 
This will further enhance our approach to stock data/information; however, we are
satisfied that our data on homes is of sufficient quality and completeness to underpin
our asset management decisions, support financial planning within the Housing
Revenue Account, and provide assurance on tenant and resident safety. 
Compliance with the Scottish Government’s minimum site standards for
Gypsy/Traveller sites: 
We have a rolling programme of 6-monthly site inspections which continuously
assesses compliance with the Scottish Government’s minimum site standards. A site
inspection report is completed and any actions identified to maintain compliance are
actioned to ensure compliance is maintained. We are therefore assured that we have

Page 3

Official
an approach in place which ensures our site maintains compliance with the minimum
site standards. 
We have active engagement with the residents of our Gypsy Traveller site via our
Tenant Participation Team, and we have a dedicated Gypsy Traveller Support Co-
ordinator based at the site to more effectively engage with residents on a day-to-day
basis in the most appropriate way. Meetings are held monthly to keep the residents
updated on issues of interest to them and a newsletter styled minute is produced and
then printed and shared. The style and format of this newsletter was developed in
conjunction with site residents. 
Our Annual Assurance Statement was considered at a meeting of the Housing and
Communities Committee on 12th August 2026 and was formally approved and
subsequently signed by me as Convenor. 
Councillor Gurpreet Singh Johal,
Convenor, Housing and Communities Committee 