WEST DUNBARTONSHIRE COUNCIL 
Report by the Chief Officer, Housing 
Housing and Communities Committee: 12 August 2026 
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme 
1. Purpose 
1.1 The purpose of this report is to provide the Housing and Communities
Committee with an update on progress with West Dunbartonshire’s More
Homes Programme, which oversees delivery of the Council’s new build
housing programme. 
2. Recommendations 
2.1 It is recommended that the Housing and Communities Committee: 
(i) Notes the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach 
(ii) Notes the nomination of Mount Pleasant and the award win of the Willox
Court development in the Excellence in Accessibility and Inclusion
category at the 2026 Scottish Home Awards; 
(iii) Notes the commendation award of Mount Pleasant and the award win for
Willox Court in the 2026 Homes for Scotland ‘Affordable Development of
the Year – Small’ category; 
(iv) Notes the successful completion and forthcoming completion of the Bonhill
Gap Sites at Braehead and Campbell Street; 
(v) Approve that the Chief Officer, Housing, in collaboration with the
Procurement Manager, explores the potential for, and where appropriate
undertakes, a procurement exercise for a design and build contract for the
Queen’s Quay Site C development, subject to costs returned being
deemed acceptable by the service and compliant with procurement
requirements 
(vi) Notes the mainly positive feedback of the West Dunbartonshire Council
Strategic Housing Investment Programme (SHIP) from the Scottish
Government; and 
(vii) Approve and invite the Chief Officer, Housing, in collaboration with the
Chief Officer, Regulatory and Regeneration and the Chief Officer,
Resources, to conclude a short-term leasing arrangement for the vacant
site at Vale of Leven Industrial Estate to support the temporary decant of
ITEM 10

Page 2

Dennystoun Forge tenants while the wider regeneration works are
completed. 
3. Background 
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over one thousand new affordable homes in
West Dunbartonshire and includes the Council’s own new home building
programme. 
3.2 The Strategic Housing Investment Plan (SHIP) 2026-2031, outlining West
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach, was approved by the Housing and
Communities Committee in November 2025. The SHIP outlines plans to
contribute to the Council Administration’s aim of delivering 2,500 new
affordable and social rented homes over the 10-year period 2022-2032. 
4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic and economic recovery
plans, negating the impacts of the current cost of living crisis and combatting
poverty principally child and fuel poverty.  It is also clear that the need for
affordable homes has and will increase in the current ongoing economic
environment and declaration of a housing emergency. 
4.2 In July 2025, Shelter published its study The Social Value of New Social
Housing in Scotland  The research report’s key conclusion is that it has shown
that new social housing is driving improvements in social, economic and
health outcomes for its residents, and where this impact is achieved, there is
huge capacity for significant preventative savings to wider society. 
4.3 The Council’s More Homes West Dunbartonshire approach is an ambitious
plan that aims to continue the positive momentum of the delivery of much
needed Council homes in West Dunbartonshire and will significantly assist the
Council’s aim to deliver 2500 new social and affordable homes by 2032. 
4.4 As the largest affordable housing developer in West Dunbartonshire, the
Council has identified a number of development sites for new council homes
to address existing and new housing need. The design of these homes
provides sustainable homes using innovative technology and delivering on our
low carbon ambitions including Passivhaus and other net zero carbon
opportunities.  We anticipate the new homes delivered by the Council will
have a minimum lifespan of beyond 100 years.

Page 3

4.5 The Council’s More Homes West Dunbartonshire approach has evidenced
strong support from council tenants and is highlighted as one of the top two
key future spending priority areas for tenants through the comprehensive
tenant satisfaction survey reported to the Housing and Communities
Committee previously. 
4.6 The Council’s recent completed developments at Mount Pleasant and Willox
Park have both been shortlisted for the Affordable Housing Development of
the Year Award in the Homes for Scotland Awards, for which Mount Pleasant
was commended and Willox Park won. Both were also shortlisted for the 2026
Scottish Home Awards Excellence in Accessibility and Inclusion category of
which Willox Park also won. This follows the Clydebank East development
being awarded the prestigious Herald Property Awards - Affordable Housing
Development of the Year Award late last year, for which the Mount Pleasant
development has also been shortlisted this year. 
4.7 As part of our ongoing monitoring of the impact of the completed housing
developments, the three most recent mainstream completions (Clydebank
East/Mount Pleasant and Pappert) have significantly contributed to meeting
housing need within West Dunbartonshire communities and combined have
contributed to lifting 131 children out of homelessness and into a secure
tenancy through initial and secondary allocations through the transfer led
approach.  The reduction in children experiencing homelessness is a key
strategic objective of the Housing Emergency Declaration Action Plan.   
4.8 The approved Strategic Housing Investment Plan and HRA Capital
Investment Plan outlined the plans the Council have for meeting their new
build ambitions.  An update on each development site is provided below: - 
Willox Park Phase 1, Doveholm, Dumbarton 
Housing Mix 
This development was completed on the 9th February 2026. 
The development has won two awards recently:
• The 2026 Homes for Scotland ‘Affordable Development of the Year –
Small’ award and;
• The 2026 Scottish Home Awards ‘Excellence in Accessibility and
Inclusion’. 
Willox Park Phase 2 
Phase 2 is part of the wider housing regeneration plans for the Willox Park
area. 
House Type Sustainability Standard Number of New
Homes
Flat 2bed/3person  Net Zero 2
Flat 1 bed/2person Net Zero 15

Page 4

Planning was submitted for 22 new amenity homes on the 23rd June 2026.
The housing mix can be viewed in the table below: 
McTaggart Construction have been awarded the design and build contract
which will also include the demolition of the existing homes following
completion of Phase 1. All homes are being designed to housing for varying
needs standards and dementia friendly principles to encourage ageing in
place and inclusive living.   
The design team are currently working towards the demolition of the existing
Willox Park stock. This is estimated to begin in October to enable a site start
in the new year. One resident remains in the complex.   
Bonhill Gap Site Strategy 
The 28 units of housing at Braehead (17 homes) and Campbell Street (11
homes) went on site in August 2025 and were scheduled to complete within a
56-week period. 
Handovers for Braehead were completed in July. The full handover for the
properties in Campbell Street are expected to be completed in August 2026. 
The JR Group were successful in the tender for the 6x 1 bedroom cottage
flats at the O’Hare site and are currently developing the technical design and
programme. All going well with approvals there is an estimated site start for
early Autumn 2026. 
The housing mix of the full Bonhill Gap Site development programme is
highlighted in the table below and will include 8 large family homes and 16x 1-
bedroom flats to meet the key identified need: - 
Bank Street, Alexandria
House Type Sustainability
Standard
Number of New
Homes
Bungalow 1bed/2person Net Zero 14
Bungalow 1bed/2person w/c Net Zero 2
Cottage Flat 1bed/2person UF Net Zero 3
Cottage Flat 1bed/2person LF Net Zero 3
House Size Sustainability Standard Number of New
Homes
1bed wheelchair Net Zero 4
1 bed general needs Net Zero 16
2 bed wheelchair Net Zero 3
3 bed general needs Net Zero 3
4 bed general needs Net Zero 2
5 bed general needs Net Zero 4
7 bed general needs Net Zero 2

Page 5

The development will consist of twenty-two sheltered/amenity housing units in
partnership with the HSCP. A site start was achieved in October 2025 and is
scheduled for completion in April 2027 
House Type Sustainability Standard Number of New
Homes
Flat 1bed/2person w/c Net Zero 22
Communal Room Net Zero 1
Staff Office Net Zero 1 
As reported to the August Housing and Communities Committee the tender
return was some £2.4m below the initial estimated cost.  This development as
with the development at Willox Park, involved the tenants at Gray Street who
have been consulted throughout the design process and will be assisted to
make the transition as smooth as possible. 
The estimated completion date is 1st April 2027 
Gray Street Regeneration 
As the development at Bank Street will replace the current sheltered housing
accommodation at Gray Street, we have carried out both feasibility and
viability assessments for the future Gray Street regeneration site.  The
optimum housing mix aligns with the Council’s strategic housing objectives of
providing family housing and housing for the elderly, the project will also have
provision for 2 family sized wheelchair homes and is outlined below which will
see the delivery of 15 new council homes below: 
A viability assessment based on the optimum housing mix has been
undertaken using the following planning assumptions and was approved at
the May meeting of the Housing and Communities Committee. 
West Thomson Street (former Clydebank Health Centre) 
The proposed development will provide 42 new homes - 15 units of family
housing and 27, fully accessible, sheltered/amenity homes for the elderly. The
proposed housing mix is noted below: - 
House Type Sustainability
Standard
Number of new
Homes
House 4 bed/6 person  Net Zero 2
House 3 bed/6 person Net Zero 2
House 3bed/6-person w/c Net Zero 1
Cottage Flat 1bed/2 person Net Zero  8
Cottage Flat 3bed/5-person w/c Net Zero 1
Cottage Flat 2bed/4person Net Zero 1

Page 6

CCG were awarded the contract for the design and build of the development.
They are currently working on the technical design. The programme indicates
a site start of winter 2026 with completion 56 weeks later.   
The current plan is to introduce twenty-seven additional sheltered/amenity
homes through this West Thomson Street development. The current energy
strategy allows for a communal ground source heating system. This may offer
future opportunity to tie into the wider district heat network and the end of the
system’s life cycle. We are applying for funding from the Scottish Heat
Network Fund to try and mitigate the costs of this but have yet to receive a
decision. Councillors should be aware that this system will be subject to
reporting as a requirement of the new Ofgem regulations for heat networks
which will have resource implications and will be highlighted to a future
meeting of the Housing and Communities Committee. Other sites including
Clydebank East, Queen’s Quay and Willox Court will also be subject to this
new regulatory obligation. We are continuing to monitor these factors and
costs as we move forward with the design.   
Dennystoun Forge Gypsy/Traveller Site 
To enable the works to proceed safely, residents will require to be decanted
during the contract period. Officers from across relevant service areas,
together with residents, carried out an assessment of Council decant site
options. The assessment found that a vacant site within the Vale of Leven
Industrial Estate was the favoured location, with the old pavilion area at Havoc
being considered as the standby should the preferred option not be possible. 
Committee approval is sought to proceed to agree terms for a short-term
lease of this site for a period of approximately 6-9 months while the main
regeneration works at Dennystoun Forge take place. A planning application
will require to be lodged for temporary consent. If consent is granted, works
will proceed as soon as practicable to enable residents to move from the main
site. Timescales will be finalised, but it is hoped that works will commence
before the end of 2026. 
Queen Mary Avenue, Clydebank (Clydebank Gap Sites) 
The Housing Mix can be seen below:
House Type Bed Number WCH
Sheltered/Amenity
Flat
1 27 27
Cottage Flat 1 2 2
Duplex Cottage Flat 3 2 
House 5 2 
House 4 5 
House 3 4 
Total  42 29

Page 7

The main contractor is CCG. Site start was the 20th October 2025 with a
planned programme of 61 weeks. 
The contractor is optimistic of a handover at the beginning of September
2026. 
Dumbuie Avenue and Smollett Road (Silverton Regeneration) 
The council have been assembling this site for over 10 years, following
structural issues with the previous properties located within the sites which
were demolished in November 2024. 
Following approval from the Housing and Communities Committee to direct
award a design and build contract to deliver the Silverton regeneration project
up to the budgeted costs for project (Dumbuie Avenue and Smollett Road),
the project is now included within the Council’s Strategic Housing Investment
Plan 2026/27-2031/32 which was approved at the Housing and Communities
Committee of 19th November 2025. 
A Planning application for Dumbuie was submitted in May 26 however we
now have design information which has increased the cost of delivery
summarised below: 
1, A piled foundation solution is required due to ground conditions.
2. Scottish Water have notified that connection can’t be made to the adjacent
combined sewar and this needs to be taken to a connection at the A82
3. Flood mitigation to the threshold is required. 
The three components above now make the development unaffordable within
the current approved budget. Officers have approached the Scottish
Government for additional funding and further grant funding would be required
for this project to meet the Council’s viability assessment. Officers are also
exploring other potential grant funding streams to support delivery of the site. 
The housing mix includes:
• 1x 3-bedroom wheelchair bungalow; 
• 2x 3-bedroom semi-detached houses; and 
• 3x 3-bedroom terraced houses. 
House Type Sustainability Standard Number of New
Homes
1 bed/2 person  Cottage Flat Net Zero 10
2 bed/3 person WCH Cottage Flat Net Zero 1
3 bed/4 person Cottage Flat Net Zero 1
3 bedroom terraced house Net Zero 3
4 bedroom semi-detached Net Zero 2

Page 8

28 Bridge Street, Alexandria 
This project relates to the purchase of the former Prep4Life building at Bridge
Street, Alexandria. A mini competition was published on 23rd June 2026 with a
closing date of 21st July 2026, through the Scottish Procurement Alliance RM3
framework, for a contractor to convert the building into 8 units of self-
contained accommodation – including 2 ground floor wheelchair accessible
units. 
The aim of these works is to enable accommodation for young care leavers to
transition out of residential care, with a level of support, prior to taking on their
own independent tenancy. Housing have worked closely with West
Dunbartonshire’s Health and Social Care Partnership on this project. 
Ottawa Crescent 
This project is for 21 amenity homes, similar to the successful developments
at Creveul Court, Alexandria and Mount Pleasant, Old Kilpatrick. 
CCG are the build contractor. They started on site at the start of June and
have a completion date estimate of July 2027 
The proposed housing Mix is provided below: 
House/Flat Type Bedrooms Number
Flat GF WCH 1 3
Flat with lift 2 9
GF Cottage Flat 1 2
FF Cottage Flat 1 2
Bungalow 1 5 
Queen’s Quay Site C 
The current development proposals from Barratt for 227 new homes on the
adjacent land next to site C has enhanced the viability of being able to
develop the council owned land on Queen’s Quay Site C. 
Previously, Queen’s Quay Site C has not been an affordable site to develop
due to the costs associated with infrastructure such as extensive road and
utilities provision. However, the Barratts development offers a unique
opportunity which could potentially mitigate these costs and open up the Site
C land to develop for affordable social housing. There are also other factors
which may help to keep development costs down for the Council if we enter
into a deal with the contractor. For example, there will be a mitigated/shared
cost for programming, site mobilisation, site investigation, required piling work,
and connection to district heat network and roads infrastructures. It is
anticipated that this would result in value for money for the council due to

Page 9

economies of scale for Barratt, which would not be achievable if this was
developed as a stand-alone site. 
Barratt are not currently on a framework which can be utilised for local
authority council housing. We are therefore seeking permission to explore the
potential to enter into a design and build contract, depending on price and
design, with Barratt for the development of affordable social housing for West
Dunbartonshire Council. 
The Council has received grant funding to acquire the site, if the site is not
able to be developed the funding would be clawed back by the Scottish
Government. No current legal agreement or commitment has been made as
we are only exploring this as an avenue to develop the site. 
Buyback Programme 
Total number of properties purchased in 2026/27 financial year   10
Total Purchase Value                                                                    £1,300,550 
We have a further 7 properties under offer awaiting completion dates. 
Below is an update breakdown of acquisitions by electoral ward for the
financial year so far 26/27: 
Mortgage to Rent 
We have also completed the purchase of a property in O’Hare through the
Scottish Governments mortgage to rent scheme.   
4.9 In May 2026 the Scottish Government issued its feedback on the West
Dunbartonshire Council Strategic Housing Investment Plan (SHIP) 2026 –
2031 which was approved by Housing and Communities Committee in
PROPERTY SIZE PURCHASED
5 apt 2
4 apt 4
3 apt 2
2 apt 2
Buyback Acquisitions 2025/26 No of Acquisitions (as at
09/07/26)
Ward 1 - Lomond 2
Ward 2 – Leven 2
Ward 3 – Dumbarton 1
Ward 4 – Kilpatrick 0
Ward 5 – Clydebank Central  5
Ward 6 – Clydebank Waterfront 0
Total  10

Page 10

November 2025.   The feedback re-emphasises the importance of the SHIP
as the expression of the Council’s strategic housing investment priorities. 
4.10 The feedback provided a positive summary of Scottish Government feedback
on West Dunbartonshire Council’s Strategic Housing Investment Plan 2026–
2031, highlighting strong alignment with Local Housing Strategy outcomes
and clear recognition of the Council’s delivery performance, prioritisation and
partnership approach. The feedback particularly acknowledges the SHIP’s
contribution to increasing the supply of new build social rented homes,
including larger family homes, wheelchair accessible properties and specialist
provision, supporting wider objectives around homelessness prevention, child
poverty reduction and equalities. It also recognises the Council’s strong
collaborative approach with partners and communities. Two areas for further
consideration are identified: exploring the use of income from empty and
second homes to support affordable housing delivery, and ensuring that all
new developments, including those delivered by RSL partners, contribute to
Housing Solutions/Rapid Rehousing Transition Plan and Housing First
objectives. 
4.11 In July, the Scottish Government officially published the four-year resource
planning allocations to deliver new housing within the Affordable Housing
Supply Programme.  West Dunbartonshire receives 1.7% of the total overall
funding and £51m over the four-year period. 
Local Authority Area
2026-27
£m
2027-28
£m
2028-29
£m
2029-30
£m
Total
£m
Aberdeen City 16.298 16.787 17.290 17.809 68.184
Aberdeenshire 27.779 28.612 29.470 30.355 116.216
Angus 10.118 10.422 10.735 11.057 42.332
Argyll & Bute 20.189 20.795 21.419 22.062 84.465
Clackmannanshire 6.984 7.193 7.409 7.631 29.216
Dumfries & Galloway 22.597 23.275 23.973 24.692 94.537
Dundee City 18.616 19.174 19.749 20.342 77.881
East Ayrshire 13.598 14.006 14.426 14.859 56.890
East Dunbartonshire 7.738 7.970 8.209 8.455 32.372
East Lothian 12.554 12.931 13.319 13.718 52.521
East Renfrewshire 7.696 7.926 8.164 8.409 32.196
Edinburgh, City of 66.383 68.375 70.426 72.539 277.723
Falkirk 14.982 15.431 15.894 16.371 62.679
Fife 39.963 41.162 42.396 43.668 167.189
Glasgow, City of 123.283 126.982 130.791 134.715 515.772
Highland 50.132 51.636 53.185 54.781 209.733
Inverclyde 10.476 10.791 11.114 11.448 43.830
Midlothian 10.586 10.904 11.231 11.568 44.288
Moray 9.571 9.858 10.153 10.458 40.040
Na h-Eileanan Siar 9.088 9.361 9.642 9.931 38.021
North Ayrshire 16.889 17.396 17.918 18.455 70.659
North Lanarkshire 36.014 37.095 38.208 39.354 150.671
Orkney Islands 3.933 4.051 4.172 4.297 16.453
Perth & Kinross 16.998 17.508 18.033 18.574 71.112
Renfrewshire 19.171 19.747 20.339 20.949 80.206
Scottish Borders 17.743 18.275 18.823 19.388 74.230
Shetland Islands 5.609 5.777 5.950 6.129 23.465
South Ayrshire 13.225 13.622 14.031 14.451 55.329
South Lanarkshire 32.384 33.356 34.357 35.387 135.484
Stirling 11.738 12.090 12.453 12.826 49.106
West Dunbartonshire 12.201 12.567 12.944 13.333 51.046
West Lothian 17.933 18.471 19.025 19.596 75.026
Total 702.470 723.544 745.250 767.608 2938.872

Page 11

4.12 The Housing Service are continuously looking for opportunities to provide
additional new build council homes and will bring any potential site to the
Housing and Communities Committee with as much information as possible
as part of the regular More Homes update paper. 
5. People Implications 
5.1 The delivery of the More Homes delivery programme is managed through
existing resource within the Housing Development & Homelessness team
funded from the Housing Capital Investment Programme.   
6. Financial and Procurement Implications 
Financial 
6.1 The Council has to date delivered 586 new homes for social rent; these
additional homes bring council tax revenue of around £815k per year to West
Dunbartonshire Council. 
6.2 On 4 March 2026 supported by tenant representatives the Council approved
the Housing Capital Programme 2025-2030 which saw appropriate resources
committed to the delivery of new council homes in West Dunbartonshire.  An
expenditure budget of £99.675m for the affordable housing supply programme
inclusive of acquisitions is factored into the 5-year HRA Capital Programme. 
As it currently stands, it is anticipated that this programme will complete within
project life budget. 
6.3 Housing and Finance Officers will continue to assess the ongoing affordability
of future developments within the context of the Housing Revenue Account
Business Plan. 
Procurement 
6.4 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within 4.8 of this report will
continue to be prioritised. Where the contract award is less than £213,000,
authority is delegated to the Chief Officer in consultation with the Procurement
Manager to instruct the award of contracts for the planned revenue and
capital spend detailed in this report to suppliers providing the most
economically advantageous offer to the Council. 
6.5 All procurement activity conducted by the Council more than £2m is.
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include but is not limited to; contract scope,
service forward plan, the market, procurement model, and routes – including
existing delivery vehicles, roles and responsibilities, risks, issues and
opportunities and on-going contract management. Opportunities to maximise

Page 12

the positive social, economic, and environmental impact for the Council
through the relevant procurement processes will be developed in line with
procurement policy. 
7. Risk Analysis 
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis. 
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel. 
7.3 Housing supply continues to be the key factor in terms of the national and
local housing emergencies and if not increased and/or demand reduced it will
lead to continued pressures on other Council and Health and Social Care
Partnership service areas such as Homelessness which will have negative
financial implications for the wider Council’s general fund.   
8 Environmental Sustainability 
8.1  The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy. 
9. Equalities Impact Assessment (EIA) 
9.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment. 
10. Consultation 
10.1 As part of a rent consultation exercise in 2025, 92% of respondents indicated
their support for the Council’s ambitious plans to deliver the Housing Revenue
Account (HRA) new council house build programme. In addition, there was
positive support for the wider delivery of new build housing as part of the
current Local Housing Strategy.  Regular updates on new build development
are provided to the West Dunbartonshire Tenants and Residents Organisation
at the bi-monthly liaison meetings. 
11. Strategic Assessment

Page 13

11.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire. 
11.2 Having considered all the Council’s strategic priorities, this report, and the
provision of new supply social housing for rent contributes greatly to all the
Council’s strategic priorities. 
Peter Barry
Chief Officer, Housing 
Date: 30 July 2026 
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk 
Mikayla Deeley, Senior Housing Development Officer,
Housing Development and Homelessness Team,
Housing and Employability: email mikayla.deeley@west-
dunbarton.gov.uk 
Appendices: None 
Background Papers: West Dunbartonshire Council’s Local Housing Strategy 
West Dunbartonshire Council’s Strategic Housing
Investment Plan 
West Dunbartonshire Council’s Strategic Housing
Investment Plan, Feedback Report, Scottish Government,
May 2026     
Local Housing Strategy, Health Inequalities Impact
Assessment 
Wards Affected: All