All Approved HRA Capital Projects at Period 10
Project Category Project Life
Budget
Expenditure
to 31 /3/25
Expenditure
to Date
Projected
Future Spend
Project Life
Forecast Spend
Project
Variance
Approved
Budget
2025/26
Expenditure
to Date
2025/26
Projected
Spend
2025/26
In Year
Variance
2025/26
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
OCE1 Special Needs Adaptations Rolling 3,661                    -                             572                       3,089                    3,661                    -                             668                       572                       668                       -                       
OCE2 Capitalised Minor Works Rolling 12,623                  -                             2,491                    9,847                    12,338                  (285) 3,715                    2,491                    3,430                    (285)
OCE3 Better Homes Priority Budget Rolling 1,175                    -                             33                          1,142                    1,175                    -                             275                       33                          275                       -                       
OCE4 Environmental Sensors Programme Rolling 7,897                    -                             974                       6,923                    7,897                    -                             2,000                    974                       1,200                    (800)
OCE5 Housing CCTV Installation Programme Rolling 750                       -                             692                       58                          750                       -                             750                       692                       750                       -                       
OCE6 QL Development Rolling 50                          -                             13                          37                          50                          -                             10                          13                          15                          5                           
OCE7 Gypsy Travellers Site Rolling 15                          -                             -                             15 15                          -                             15                          -                             -                             (15)
OCE8 Airport Noise Rolling 96                          -                             -                             96                          96                          -                             -                             -                             -                             -                       
Other Capital Expenditure 26,267                  -                        4,775                    21,207                  25,982                  (285) 7,433                    4,775                    6,338                    (1,095)
MCR1 Targeted SHQS /EESSH compliance works Rolling 30,163                  -                             2,895                    24,640                  27,535                  (2,628) 6,628                    2,895                    4,000                    (2,628)
MCR2 External Component Renewal - Roofs Rolling 13,204                  -                             844                       10,660                  11,504                  (1,700) 2,550                    844                       850                       (1,700)
MCR3 Doors/Windows Component Renewals Rolling 23,190                  -                             3,272                    18,847                  22,119                  (1,071) 4,985                    3,272                    3,914                    (1,071)
MCR4 External Stores / Garages / Bin Stores Rolling 247                       -                             -                             199                       199                       (48) 48                          -                             -                             (48)
MCR5 Secure entry component renewals Rolling 500                       -                             -                             400                       400                       (100) 100                       -                             -                             (100)
MCR6 Statutory / Regulatory Compliance Works Rolling 1,106                    -                             28                          1,078                    1,106                    -                        594                       28                          100                       (494)
MCR7 Heating Improvement Works Rolling 11,771                  -                             1,376                    10,395                  11,771                  -                        2,268                    1,376                    2,136                    (132)
MCR8 Energy Improvements / Energy Efficiency Works Rolling 297                       -                             -                             239                       239                       (58) 58                          -                             -                             (58)
MCR9 Kitchen Upgrade Rolling 10,089                  -                             1,471                    7,468                    8,939                    (1,150) 2,850                    1,471                    1,700                    (1,150)
MCR10 Bathroom & Shower Replacement Rolling 3,000                    -                             607                       2,343                    2,950                    (50) 800                       607                       750                       (50)
Major Component Replacement 93,567                  -                        10,493                  76,269                  86,762                  (6,805) 20,881                  10,493                  13,450                  (7,431)
VOC1 Void House Strategy Programme Rolling 19,873                  -                             -                             19,873                                     19,873                            -   5,258                    -                             5,777                    519                      
-                       
Void Capital 19,873                  -                        -                        19,873                  19,873                  -                        5,258                    -                             5,777                    519                      
STE1 Defective structures/component renewals Rolling 4,389                                                 - 169                       3,589                    3,758                    (631) 800                       169                       169                       (631)
STE2 Environmental Renewal - Paths & Environment Rolling 5,436                                                 - 881                       4,555                    5,436                    -                        1,000                    881                       1,131                    131                      
STE3 Asbestos Management Works Rolling 1,239                                                 - 183                       1,056                    1,239                    0 242                       183                       242                       -                       
STE4 Multi Storey Flat Strategy Rolling 6,256                    -                             159                       6,097                    6,256                                               -   1,720                    159                       400                       (1,320)
Structural & Environmental 17,320                  -                             1,392                    15,297                  16,689                  (631) 3,762                    1,392                    1,942                    (1,820)
SUP1 Salaries / Central Support / Overhead Rolling 17,155                  -                             2,583                    14,572                                     17,155                            -   3,100                    2,583                    3,100                    -                       
Support Costs 17,155                  -                        2,583                    14,572                  17,155                  -                        3,100                    2,583                    3,100                    -                            
AHP1 Buy Backs Rolling 21,387                  -                             2,796                    18,591                                     21,387                            -   4,380                    2,796                    4,380                    -                       
AHP2 Demolition Programme Rolling 1,140                    -                             213                       927                                            1,140                            -   140                       213                       213                       73                         
AHP3 Contingency Rolling 530                       -                             -                             428                                               428 (102) 102                       -                             -                             (102)
AHP4 Clydebank East Project 33,643                  32,953                  33,102                  541                                          33,643                            -   250                       149                       300                       50                         
AHP5 Pappert Project 9,034                    8,169                    9,044                    10-                                               9,034                            -   730                       875                       875                       145                      
AHP6 Mount Pleasant Project 5,357                    4,900                    5,283                    74                                               5,357                            -   382                       383                       383                       1                           
AHP7 7-9 Gilmour Avenue Project 733                       459                       785                       52-                                                  733                            -   264                       326                       326                       62                         
AHP8 Willox Park Phase1 Project 5,531                    1,951                    4,910                    621                                            5,531                            -   2,980                    2,959                    3,400                    420                      
AHP9 Willox Park Phase2 Project 5,355                    -                             4                            5,351                                         5,355                            -   100                       4                            130                       30                         
AHP10 Bank Street Project 5,797                    297                       1,247                    4,550                                         5,797                            -   1,500                    950                       1,300                    (200)
AHP11 Bonhill Gap Sites Project 9,521                    241                       3,637                    5,884                                         9,521                            -   1,600                    3,396                    5,145                    3,545                   
AHP12 West Thomson Street Project 15,642                  1,017                    1,390                    14,252                                     15,642                            -   375                       373                       460                       85                         
AHP13 Silverton Project 2,889                    29                          29                          2,860                                         2,889                            -   100                       -                             50                          (50)
AHP14 Queen Mary Avenue Project 4,540                    40                          1,505                    3,035                                         4,540                            -   800                       1,465                    2,000                    1,200                   
AHP15 Queens Quay Site C Project 7,231                    31                          31                          7,200                                         7,231                            -   -                             -                             -                             -                       
AHP16 Dennystoun Forge – New Build Project 4,129                    59                          59                          4,070                                         4,129                            -   400                       -                             30                          (370)
AHP17 28 Bridge Street Project 810                       -                             14                          796                                               810                            -   60                          14                          60                          -                       
AHP18 Ottawa Crescent Project 6,000                    -                             -                             6,000                                         6,000                            -   250                       -                             400                       150
AHP19 Future New Build & Related Regeneration Projects Rolling 31,030                  -                             31,030                                     31,030                            -   550                       -                             -                             (550)
AHP20 Fees, Staffing Costs, contingency Rolling 830                       -                             -                             680                                               680 -                       150 150                       -                             -                             (150)
Affordable Housing Supply Programme 171,129                50,146                  64,049                  106,828                170,877                (252) 15,113                  13,903                  19,452                  4,339                   
Total Expenditure 345,311                50,146                  83,292                  254,046                337,338                (7,973) 55,547                  33,146                  50,059                  (5,488)
Full Project Life
ITEM 14 - APPENDIX 2

Page 2

All Approved HRA Capital Projects at Period 10 Appendix 2
Full Project Life
Project Category Project Life
Budget
Income
to 31/3/25
Income
to Date
Projected
Future Income
Project Life
Forecast Income
Project
Variance
Approved
Budget
2025/26
Income
to Date
2025/26
Projected
Income
2025/26
In Year
Variance
2025/26
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
CAPI1 Scottish Govt Buyback Grant Rolling (10,550) 0 (100) (10,450) (10,550) -                             (550) (100) (2,700) (2,150)
CAPI2 Clydebank East Project (12,605) (12,605) (12,605) -                             (12,605) -                             -                             -                             -                             -                            
CAPI3 Pappert Site Project (3,725) (3,475) (3,725) -                             (3,725) -                             (250) (250) (250) -                            
CAPI4 Mount Pleasant Project (1,838) (1,838) (1,838) -                             (1,838) -                             -                             -                             -                             -                            
CAPI5 7-9 Gilmour Avenue Project (311) (191) (191) (120) (311) -                             (120) -                             (120) -                            
CAPI6 Willox Park Phase1 Project (1,644) (1,644) (1,644) -                             (1,644) -                             -                             -                             -                             -                            
CAPI7 Willox Park Phase2 Project -                             -                             -                             -                            
CAPI8 Bank Street Project (2,220) (258) (258) (1,962) (2,220) -                             (1,500) -                             (950) 550                      
CAPI9 Bonhill Gap Sites Project (3,748) (378) (378) (3,370) (3,748) -                             (1,600) -                             (3,360) (1,760)
CAPI10 West Thomson Street Project (4,781) (966) (1,313) (3,468) (4,781) -                             (375) (347) (450) (75)
CAPI11 Silverton Project (1,080) -                             -                             (1,080) (1,080) -                             -                             -                             -                             -                            
CAPI12 Queen Mary Avenue Project (2,040) (140) (140) 1,900-                    (2,040) -                             -                             -                             -                             -                            
CAPI13 Queens Quay Site C Project (4,814) (2,086) (2,014) (2,800) (4,814) -                             72 72                          72 -                            
CAPI14 Dennystoun Forge – New Build Project (2,400) -                             -                             (2,400) (2,400) -                             -                             -                             0 -                            
CAPI15 28 Bridge Street Project -                             -                             0 -                            
CAPI16 Ottawa Crescent Project -                             -                             (400) (400)
CAPI17 Future new build sites & related regeneration projects Rolling (24,711) -                             -                             (24,711) (24,711) -                             (60) -                             0 60                         
CAPI18 Owners Recoveries Rolling (3,500) -                             (1,463) (2,037) (3,500) -                             (1,500) (1,463) (1,500) -                            
CAPI19 Other Grant Rolling (406) -                             (841) (841) (1,682) (1,276) (406) (841) (1,620) (1,214)
CAPI20 HRA Loan Repayments Rolling (5) -                             (1) (4) (5) -                             (1) (1) (1) -                            
Total Income (80,378) (23,581) (26,511) (55,143) (81,654) (1,276) (6,290) (2,930) (11,279) (4,989)
Prudential Borrowing Requirement 264,933                26,565                  56,781                  198,903                255,684                (9,249) 49,257                  30,216                  38,780                  (10,477)
Full Project Life In Year