Page 1

Period 10 - 31 January 2026
Summary
HRA Capital Expenditure Project Life
Budget
Project Life
Forecast Spend
Project Life
Variance
Rolling
Programmes
Projects Projects
On Track / Complete
Projects
Off Track
£000 £000 £000
Other Capital Expenditure 26,267                25,982                (285) 8                    -                -                              -                             
Major Component Replacement 93,567                86,762                (6,805) 11                  -                -                              -                             
Void Capital 19,873                19,873                0 1                    -                -                              -                             
Structural & Environmental 17,320                16,689                (631) 4                    -                -                              -                             
Support Costs 17,155                17,155                0 1                    -                -                              -                             
Affordable Housing Supply Programme 171,129              170,877              (252) 5                    12                  12                                -                             
Total Expenditure 345,311              337,338              (7,973) 30                  12                  12                                -                             
Total Income (80,378) (81,654) (1,276) 4                    12                  12                                -                             
Total 264,933 255,684 (9,249)