WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Resources 
Housing and Communities Committee: 13 May 2026
___________________________________________________________________
Subject: Housing Revenue Account (HRA) Capital 
Budgetary Control Report to 31 January 2026 (Period 10)
1. Purpose
1.1 This report provides an update on the HRA capital programme to 31 January
2026.
2. Recommendations
2.1 Members are asked to:
i) Note the position of the 2025/26 HRA capital budget and the HRA capital plan
on 31 January 2026.
ii) Note project life performance is monitored against a £345.311m project life
expenditure estimate, an £80.378m project life income estimate and a
£264.933m five-year borrowing requirement.
iii) Note that eleven projects are forecast to deliver a total underspend of
£9.249m against their five-year project life budgets.
iv) Note in year financial performance is monitored against a 2025/26 capital
expenditure budget of £55.547m, 2025/26 capital income budget of £6.290m
and a one-year borrowing requirement of £49.257m.
v) Note there is an anticipated under spend of £10.477m against 2025/26
budgets reducing the forecast one-year borrowing requirement to £38.780m.
3. Background
3.1 The Council approved the HRA Capital Plan for 2025/26 to 2029/30 on 5
March 2025. The HRA capital plan approved £70.590m of capital expenditure
and £15.324m of capital income in 2025/26, creating a borrowing requirement
of £55.266m.
3.2 At its meeting on the 27 August 2025, this committee agreed budget
adjustments that revised the 2025/26 capital expenditure budget to £55.547m
and the capital income budget to £6.290m, an updated one-year borrowing
requirement of £49.257m. Committee also approved a revised project life
budget of £264.933m. A summary of the revised capital budgets is set out in
Exhibit 1.
ITEM 14

Page 2

Exhibit 1: HRA Capital Estimates 2025/26 – 2029/30
Forecast
BCR10
(£m)
2025/26
Budget
(£m)
Variance
(£m)
Project Life
Forecast
BCR10
(£m)
Project
Life
Budget
(£m)
Other Capital 6.338 7.433 (1.095) 25.982 26.267
Component Replacement 13.450 20.881 (7.431) 86.762 93.567
Void 5.777 5.258 0.519 19.873 19.873
Structural & Environmental 1.942 3.762 (1.820) 16.689 17.320
Support Costs 3.100 3.100 - 17.155 17.155
More Homes 19.452 15.113 4.339 170.877 171.129
Total Expenditure 50.059 55.547 (5.488) 337.388 345.311
Total Income (11.279) (6.290) (4.989) (81.654) (80.378)
Prudential Borrowing 38.780 49.257 (10.477) 255.684 264.933
4. Main Issues
4.1 Progress against the 2025/26 capital plan is detailed in:
Appendix 1 – HRA Capital Summary BCR10
Appendix 2 – HRA Capital Detail BCR10
4.2 The HRA capital summary report at Appendix 1 reports that:
 project life expenditure is forecast to be less than budget by £7.973m over
the 5-year period of the capital plan.
 one project has forecast project life income of £1.276m more than the
project budget
 consequently, prudential borrowing will be £9.249m less than the approved
project life budget over the 5-year period of the capital plan.
4.3 Appendix 2 reports all projects with their approved in year and project life
estimates as well as their 2025/2026 expenditure and income forecasts. The
appendix reports:
 2025/26 forecast spend of £50.059m, a £5.488m underspend against the
revised 2025/26 budget.
 2025/26 forecast income of £11.279m, a £4.989m over recovery against
the revised 2025/26 budget.
 2025/26 prudential borrowing forecast of £38.780m, £10.477m less than
the revised budget for 2025/26.
4.4 Commentary on the 2025/26 variances above £50,000 are set out in Exhibit 2
below.

Page 3

Exhibit 2: Project Over / Underspends 2025/2026 as at BCR10
Ref Project BCR10
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
1 Capitalised Minor
Works
3.430 3.715 (0.285) Reduced contractors spend.
2 Environmental
Sensors
1.200 2.000 (0.800) Underspend due to challenges
getting access to properties
3 Targeted SHQS
/EESSH compliance
works
4.000 6.628 (2.628) Underspend reflects the
changing mix of the capital
programme with an increased
number of mixed tenure
blocks that require owner
consent before work can start.
This necessary process
delays project start.
4 External Component
Renewal - Roofs
0.850 2.550 (1.700) Underspend reflects the
changing mix of the capital
programme with an increased
number of mixed tenure
blocks that require owner
consent before work can start.
This necessary process
delays project start.
5 Doors/Window
Component
Renewals
3.914 4.985 (1.071) Underspend due to challenges
getting access to properties.
Install team to continue
programmed addresses and
revisit no accesses to use
materials already supplied.
6 External Stores /
Garages / Bin Stores
0.000 0.048 (0.048) Works are being funded from
the capitalised minor works
budget.
7 Secure entry
component renewals
0.000 0.100 (0.100) Works are being funded from
the capitalised minor works
budget.
8 Statutory /
Compliance Works
0.100 0.594 (0.494) Health and safety works are
being funded from the
capitalised minor works
budget.
9 Energy Improvements
/ Efficiency Works
0.000 0.058 (0.058) Works are being funded from
the capitalised minor works
budget.
10 Kitchen Upgrade 1.700 2.850 (1.150) Underspend projected as
team re-assess and pre-
inspect to ensure a focus on
necessary renewals led by
condition.

Page 4

Ref Project BCR10
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
11 Bathroom & Shower
Replacement
0.750 0.800 (0.050) Underspend projected as
team re-assess and pre-
inspect to ensure a focus on
necessary renewals led by
condition.
12 Void House
Programme
5.777 5.258 0.519 Overspend due to mix of work
requiring contactors in addition
to in-house team.
13 Defective structures
/component renewals
0.169 0.800 (0.631) Underspend projected as
future blocks are pre-
inspected for condition and re-
prioritisation for completion if
necessary.
14 Environmental
Renewal - Paths &
Environment
1.131 1.000 0.131 Overspend due to mix of work
requiring contactors in addition
to in-house team.
Overspend will be re-profiled
across future years.
15 Multi Storey Flat
Strategy
0.400 1.720 (1.320) Revised projection based on
timing of programme.
16 Demolition
Programme
0.213 0.140 0.073 Revised projection based on
timing of programme.
17 Clydebank East 0.300 0.250 0.050 Revised projection based on
development project plan.
18 Pappert 0.875 0.730 0.145 Revised projection based on
development project plan.
19 Gilmour Avenue 0.336 0.264 0.072 Revised projection based on
development project plan
20 Willox Park Phase1 3.400 2.980 0.420 Revised projection based on
development project plan.
21 Bank Street 1.300 1.500 (0.200) Revised projection based on
development project plan.
22 Bonhill Gap Sites 5.145 1.600 3.545 Revised projection based on
development project plan.
23 West Thomson Street 0.460 0.375 0.085 Revised projection based on
development project plan.
24 Silverton 0.050 0.100 (0.050) Revised projection based on
development project plan.
25 Queen Mary Avenue 2.000 0.800 1.200 Revised projection based on
development project plan.

Page 5

Ref Project BCR10
Forecast
(£m)
25/26
Budget
(£m)
25/26
Variance
(£m) Commentary
26 Dennystoun Forge 0.030 0.400 0.370 Revised projection based on
development project plan.
27 Ottawa Crescent 0.400 0.250 0.150 Revised projection based on
development project plan.
28 Future New Build &
Related Regeneration
Projects
0.000 0.550 (0.550) Revised projection based on
development project plan.
29 Fees, Contingency 0.000 0.150 (0.150) Contingency released
30 Scottish Govt
Buyback
Grant Income
(2.700) (0.550) (2.150) Revised projection based on
the distribution of Scottish
Government acquisition
funding.
31 Bank Street
Grant Income
(0.950) (1.500) 0.550 Revised projection based on
the application of the Strategic
Local Programme
32 Bonhill Gap Sites
Grant Income
(3.360) (1.600) (1.760) Revised projection based on
the application of the Strategic
Local Programme
33 West Thomson Street
Grant Income
(0.450) (0.375) (0.075) Revised projection based on
the application of the Strategic
Local Programme
34 Ottawa Crescent
Grant Income
(0.400) 0.000 (0.400) Revised projection based on
the application of the Strategic
Local Programme
35 Future new build sites
& regeneration
projects
Grant Income
0.000 (0.060) 0.060 Funding released to support
accelerated projects
36 Other Grant Income (1.620) (0.406) (1.214) Additional Scottish
Government Net Zero Funding
awarded to fabric first energy
efficiency works and additional
Scottish Government grant to
support capital works on
properties allocated to the
resettlement service
4.5 Budget assumptions are required to forecast costs / income, especially where
projects span multi-year and project finances have yet to be finalised. It is
therefore likely that the projected year end position will change during the
year.
5. Option Appraisal
5.1 No option appraisal was required for this report.

Page 6

6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital estimates.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
several variable factors which could arise between now and 31 March
which could affect the year end results for capital budgets.
(b) To forecast for the full year costs budget assumptions have been
required. These assumptions continue to change regularly and therefore
it is likely the projected year end position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital estimates have been consulted
during the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
________________
Laurence Slavin
Chief Officer – Resources
Date: 13 May 2026

Page 7

Person to Contact: Jim McCarron
Business Partner, Finance 07772 322055
E-mail: james.mccarron@west-dunbarton.gov.uk
Appendices: Appendix 1 - HRA Capital Summary BCR10
Appendix 2- HRA Capital Details BCR10
Background Papers:
Housing Revenue Account (HRA) Capital Investment Programme, Revenue
Budget, and Rent Levels for 2025/26 - Council 5 March 2025.
Wards Affected           All Wards