WEST DUNBARTONSHIRE COUNCIL 
Report by the Chief Officer, Housing 
Housing and Communities Committee: 13th May 2026 
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme 
1. Purpose 
1.1      This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme. 
2. Recommendations 
2.1 It is recommended that the Housing and Communities Committee: 
(i) Notes the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach
include the successful award nominations for the Willox Court and Mount
Pleasant developments; 
(ii) Notes the successful completion of the new Willox Court development in
February 2026;  
(iii) Invite the Chief Officer, Housing, to carry out the procurement of, and to
subsequently award, the contract up to the budgeted costs for the projects
at Gray Street and 28 Bridge Street, Alexandria; 
(iv) Note the lifting of the temporary letting suspension at Young Street
sheltered housing complex. And 
(v) Notes the new resource planning allocations for West Dunbartonshire for
the next four years 
3. Background 
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over one thousand new affordable homes in
West Dunbartonshire and includes the Council’s own new home building
programme. 
3.2 The Strategic Housing Investment Plan (SHIP) 2026-2031, outlining West   
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
ITEM 10

Page 2

Communities Committee in November 2025. The SHIP outline plans to
contribute to meet the Council Administration’s aim of delivering 2500 new
affordable and social rented homes over the 10-year period 2022-2032. 
4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic and economic recovery
plans, negating the impacts of the current cost of living crisis and combatting
poverty principally child and fuel poverty.  It is also clear that the need for
affordable homes has and will increase in the current ongoing economic
environment. 
4.2 In July 2025, Shelter published its study The Social Value of New Social
Housing in Scotland  The research report’s key conclusion is that it has shown
that new social housing is driving improvements in social, economic and
health outcomes for its residents, and where this impact is achieved, there is
huge capacity for significant preventative savings to wider society. 
4.3 The Council’s More Homes West Dunbartonshire approach is an ambitious
plan that aims to continue the positive momentum of the delivery of much
needed Council homes in West Dunbartonshire and will significantly assist the
Council’s aim to deliver 2500 new social and affordable homes by 2032. 
4.4 As the largest affordable housing developer in West Dunbartonshire, the
Council has identified a number of development sites for new council homes
to address existing and new housing need. The design of these homes
provides sustainable homes using innovative technology and delivering on our
low carbon ambitions including Passivhaus and other net zero carbon
opportunities.  We anticipate the new homes delivered by the Council will
have a minimum lifespan of beyond 100 years. 
4.5 The Council’s More Homes West Dunbartonshire approach has evidenced
strong support from council tenants and is highlighted as one of the top two
key future spending priority areas for tenants through the comprehensive
tenant satisfaction survey reported to the Housing and Communities
Committee in February 2025. 
4.6 The Council’s recent completed developments at Mount Pleasant and Willox
Court have both been shortlisted for the Affordable Housing Development of
the Year Award in the Scottish Housing Awards which will be announced in
late May 2026, both have also been shortlisted in the Scottish Home Awards
and the winners will be announced in June 2026.  This follows the Clydebank
East development being awarded the prestigious Herald Property Awards -
Affordable Housing Development of the Year Award late last year. 
4.7 As part of our ongoing monitoring of the impact of the completed housing
developments, the three most recent mainstream completions (Clydebank

Page 3

East/Mount Pleasant and Pappert) have significantly contributed to meeting
housing need within West Dunbartonshire communities and combined have
contributed to lifting 129 children out of homelessness and into a secure
tenancy through initial and secondary allocations through the transfer led
approach.  The reduction in children experiencing homelessness is a key
strategic objective of the Housing Emergency Declaration Action Plan.   
4.8 The approved Strategic Housing Investment Plan and HRA Capital
Investment Plan outlined the plans the Council have for meeting their new
build ambitions.  An update on each development site is provided below: - 
Willox Park Phase 1, Doveholm, Dumbarton 
Housing Mix 
This development was completed on the 9th February 2026. Housing have
been assisting in helping the tenants to settle into their new homes. 
Willox Park Phase 2 
Feasibility studies for the site are showing an increased site capacity of 22
new homes from 21 homes The current proposed housing mix is highlighted
below: - 
McTaggart Construction have been awarded the design and build contract
which will also include the demolition of the existing homes following
completion of Phase 1. All homes are being designed to housing for varying
needs standards and dementia friendly principles to encourage ageing in
place and inclusive living. 
Phase 2 is part of the wider housing regeneration plans for the Willox Park
area and priority to the new homes in Phase 2 will be given to the tenants
within Phase 1 in the first instance. 
There was a consultation exercise with tenants which took place in April 2026.
Following on from this, the design team are currently working towards the
House Type Sustainability Standard Number of New
Homes
Flat 2bed/3person  Net Zero 2
Flat 1 bed/2person Net Zero 15
House Type Sustainability
Standard
Number of New
Homes
Bungalow 1bed/2person Net Zero 14
Bungalow 1bed/2person w/c Net Zero 2
Cottage Flat 1bed/2person UF Net Zero 3
Cottage Flat 1bed/2person LF Net Zero 3

Page 4

demolition of the Willox Park stock, the building warrant and planning
submission for phase 2 of the project. 
Bonhill Gap Site Strategy 
The 28 units of housing at Braehead (17 homes) and Campbell Street (11
homes) went on site in August 2025 and are scheduled to complete within a
56-week period. 
Work has progressed well and we are anticipating completions in June for the
Braehead site and July for the Campbell Street site. 
The pre-start meeting between The Council and JR Group (contractor) for the
O’Hare gap site was held on 10th March. JR Group are developing the
technical design and programme. 
The housing mix of the full Bonhill Gap Site development programme is
highlighted in the table below and will include 8 large family homes and 16x 1-
bedroom flats to meet the key identified need: - 
Bank Street, Alexandria 
The development will consist of twenty-two sheltered/amenity housing units in
partnership with the HSCP. A site start was achieved in October 2025 and is
scheduled for completion in late January 2027. 
House Type Sustainability Standard Number of New
Homes
Flat 1bed/2person w/c Net Zero 22
Communal Room Net Zero 1
Staff Office Net Zero 1 
As reported to the August Housing and Communities Committee the tender
return was some £2.4m below the initial estimated cost.  This development as
with the development at Willox Park, involved the tenants at Gray Street who
have been consulted throughout the design process and will be assisted to
make the transition as smooth as possible. 
The estimated completion date is 1st April 2027
House Size Sustainability Standard Number of New
Homes
1bed wheelchair Net Zero 4
1 bed general needs Net Zero 16
2 bed wheelchair Net Zero 3
3 bed general needs Net Zero 3
4 bed general needs Net Zero 2
5 bed general needs Net Zero 4
7 bed general needs Net Zero 2

Page 5

Gray Street Regeneration 
As the development at Bank Street will replace the current sheltered housing
accommodation at Gray Street, we have carried out both feasibility and
viability assessments for the future Gray Street regeneration site.  The
optimum housing mix aligns with the Council’s strategic housing objectives of
providing family housing and housing for the elderly, the project will also have
provision for 2 family sized wheelchair homes and is outlined below which will
see the delivery of 15 new council homes below: 
A viability assessment based on the optimum housing mix has been
undertaken using the following planning assumptions 
Rental Income – The site is projected to generate £117k of rental income in
the first year following completion (Year 1). For future years it has been
assumed rent will increase by 3% per annum (general assumption of 2% CPI
plus 1%) 
Capital Costs and Loan Charges – The development is assumed to have a
development capital cost of £4.5m (£300k per home) of which £2.04m (£136k
per home) is projected to be funded through Scottish Government Affordable
Housing Supply Grant. This therefore requires net borrowing of £2.46m. 
Based on borrowing £2.46m over 60 years, and assuming a loan interest rate
of 4.25%, the Council would repay £6.84m over the life of the loan, including
repayment of the principal and the interest. This equates to £114k per annum. 
Operating Costs – Operating costs are assumed to be £2,750 per unit
(£41,250 in year 1).  For future years it has been assumed operating costs will
increase by 2% per annum (general assumption of 2% CPI). Operating costs
includes all management and maintenance costs including staff, responsive
repair and maintenance costs and includes provision for void periods and bad
debt provision. 
Replacement Costs – Assumption there will be no replacement costs in
years 1-15 then fixed costs of £1,500 per unit per annum so a total of £22.5k
per annum from year 16 onwards. 
House Type Sustainability
Standard
Number of new
Homes
House 4 bed/6 person  Net Zero 2
House 3 bed/6 person Net Zero 2
House 3bed/6-person w/c Net Zero 1
Cottage Flat 1bed/2 person Net Zero  8
Cottage Flat 3bed/5-person w/c Net Zero 1
Cottage Flat 2bed/4person Net Zero 1

Page 6

The above table illustrates over the 60-year borrowing life, the cost and
benefit to the Housing Revenue Account and based on this modelling,
achieves: 
• Cash-flow positive from Year 13
• Cumulative Surplus achieved from Year 28
• A 60-year surplus of £6.5m to support and strengthen the wider HRA. 
This evidences that the site is financially viable over its life.  Furthermore, the
projected 45% grant ratio maintains the project within the HRA affordability
thresholds. The 15 new homes will also generate additional council tax
revenue per annum.  Therefore, it is recommended for inclusion within the
current More Homes Delivery Programme.  It is estimated that demolition
works will commence in Autumn 2027 before a site start on the new homes
could be achieved in the first quarter of 2028.  It is the preferred route that the
demolition and the delivery of the new homes will be within the one contract
award and seek to carry out the procurement of, and to subsequently award,
a design and build contract up to budgeted costs for the demolition of current
Gray Street homes and the delivery of the 15 new council homes.   
West Thomson Street (former Clydebank Health Centre) 
The proposed development will provide 42 new homes - 15 units of family
housing and 27, fully accessible, sheltered/amenity homes for the elderly. The
proposed housing mix is noted below: - 
Gray Street Regeneration Viability Assessment - (15 homes)
Year Rent
Revenue
(£)
Operating
Costs (£)
Capital
Replacement
(£)
Net
Revenue
(£)
Loan
Repayment
(£)
Surplus/
Deficit (£)
Cumulative
Surplus (£)
Per Tenant
Impact (£)
1 117,000 41,250 0 75,750 113,927 -38,177 -38,177 -3.64
2 120,510 42,075 0 78,435 113,927 -35,492 -73,669 -7.02
3 124,125 42,916 0 81,209 113,927 -32,718 -106,387 -10.13
4 127,849 43,775 0 84,074 113,927 -29,853 -136,240 -12.98
5 131,685 44,650 0 87,035 113,927 -26,892 -163,132 -15.54
10 152,658 49,298 0 103,360 113,927 -10,567 -249,672 -23.78
15 176,973 54,428 0 122,545 113,927 8,618 -246,186 -23.45
16 182,282 55,517 22,500 104,265 113,927 -9,662 -255,848 -24.37
20 205,160 60,093 22,500 122,567 113,927 8,640 -249,472 -23.76
25 237,837 66,348 22,500 148,989 113,927 35,062 -128,690 -12.26
28 259,891 70,409 22,500 166,982 113,927 53,055 12,101 1.15
30 275,718 73,254 22,500 179,964 113,927 66,037 137,582 13.10
40 370,543 89,297 22,500 258,746 113,927 144,819 1,210,784 115.31
50 497,979 108,853 22,500 366,626 113,927 252,699 3,224,476 307.09
60 669,242 132,691 22,500 514,051 113,927 400,124 6,524,496 621.38 
House Type Bed Number WCH
Sheltered/Amenity
Flat
1 27 27
Cottage Flat 1 2 2
Duplex Cottage Flat 3 2 
House 5 2 
House 4 5 
House 3 4

Page 7

CCG were awarded the contract for the design and build of the development.
They are currently working on the technical design. The programme indicates
a site start of winter 2026/7 with completion 56 weeks later.   
The Young Street tenants had the opportunity to visit the Willox Park Phase 1
homes to give more informed feedback of a potential new homes within this
development. Six of the 22 residents attended this arranged visit.  The
consultive exercise with the Young Street residents didn’t provide a clear
consensus that the new homes at West Thomson Street should be a
replacement for the existing sheltered housing at Young Street. 
This combined with an updated analysis of the waiting list and stock lists
indicate that the demand for sheltered/amenity housing in Clydebank is
significant. As committed within the local housing strategy we must
strategically plan for an increasing ageing demographic taking these factors
into consideration the plan is to introduce twenty-seven new
sheltered/amenity homes in the West Thomson Street development and
recommence general letting activity within the Young Street complex
immediately.  Housing and HSCP will work in partnership to develop the new
homes to meet identified need.   
Dennystoun Forge Gypsy/Traveller Site 
The project has been scored and assessed as a priority in the new Strategic
Housing Investment Plan, with a proposed site start late financial year
2026/27. Our in-house design team and procurement colleagues are
proceeding to detail our plans, and discussions are ongoing with other council
service areas in terms of assessing potential decant location options to allow
the works to the existing site to commence.    
We have carried out further detailed consultations individually with all
residents on their detailed decant needs, including what support is required
for older members of the community, and now have good information on their
preferred final design solution. We are following this up with consideration of
the chalet options available which meet our criteria.   As of 1st April 2026,
projects of this nature are eligible for AHSP grant support. 
Queen Mary Avenue, Clydebank (Clydebank Gap Sites) 
The Housing Mix can be seen below: 
House Type Sustainability Standard Number of New
Homes
1 bed/2 person  Cottage Flat Net Zero 10
2 bed/3 person WCH Cottage Flat Net Zero 1
3 bed/4 person Cottage Flat Net Zero 1
3 bedroom terraced house Net Zero 3
4 bedroom semi-detached Net Zero 2
Total  42 29

Page 8

The main contractor is CCG. Site start was the 20th October 2025 with a
planned programme of 61 weeks. 
Dumbuie Avenue and Smollett Road (Silverton Regeneration) 
The council have been assembling this site for over 10 years, following
structural issues with the previous properties located within the sites which
were demolished in November 2024. 
Following approval from the Housing and Communities Committee to direct
award a design and build contract to deliver the Silverton regeneration project
up to the budgeted costs for project (Dumbuie Avenue and Smollett Road),
the project is now included within the Council’s Strategic Housing Investment
Plan 2026/27-2031/32 which was approved at the Housing and Communities
Committee of 19th November 2025. 
A Planning application for the Dumbuie element is planned to be submitted
May 2026. 
The refreshed housing mix includes:
• 1x 3-bedroom wheelchair bungalow; 
• 2x 3-bedroom semi-detached houses; and 
• 3x 3-bedroom terraced houses. 
Bridge Street, Alexandria 
Following the purchase of the former Prep4Life building at Bridge Street,
Alexandria; The Council is seeking approval to conduct a mini competition on
the Scottish Procurement Alliance RM3 framework for a contractor to convert
the building into 8 units of self-contained accommodation. The aim of these
works is to enable accommodation for young care leavers to transition out of
residential care, with a level of support, prior to taking on their own
independent tenancy. 
Ottawa Crescent 
The Council are seeking to deliver 21 amenity homes, similar to the
successful developments at Creveul Court, Alexandria and Mount Pleasant,
Old Kilpatrick. This was assessed as a strategic housing priority in the
Strategic Housing Investment Plan approved in November and permission to
undertake the procurement exercise was established at the February 26
HACC. 
We were able to secure additional Scottish Government acquisition funding of
£379,000 for the 2025/6 financial year from the Scottish Government’s
Affordable Housing Supply Programme.

Page 9

Housing Development are now working with partners in Legal and
Procurement to procure the main contractor for the project and work towards
a site start date in Summer 2026.   
The proposed housing Mix is provided below: 
House/Flat Type Bedrooms Number
Flat GF WCH 1 3
Flat with lift 2 9
GF Cottage Flat 1 2
FF Cottage Flat 1 2
Bungalow 1 5 
Buyback Programme 
Total number of properties purchased in 2025/26 financial year   35
Total Purchase Value                                                                    £3,460,850 
6 of these properties were long term Empty Homes and we worked alongside
our Empty Homes Officer to purchase these properties and bring them back
into use in West Dunbartonshire. 
In 2026/27 we have already purchased one four-bedroom property, in addition
a further six properties are under offer. 
Below is an update breakdown of acquisitions by electoral ward for the full
financial year 25/26: 
4.9 The Housing Service are continuously looking for opportunities to provide
additional new build council homes and will bring any potential site to the
Housing and Communities Committee with as much information as possible
as part of the regular More Homes update paper. 
PROPERTY SIZE PURCHASED
5 apt 7
4 apt 12
3 apt 6
2 apt 10
Buyback Acquisitions 2025/26 No of Acquisitions (as at
31/03/26)
Ward 1 - Lomond 5
Ward 2 – Leven 10
Ward 3 – Dumbarton 3
Ward 4 – Kilpatrick 4
Ward 5 – Clydebank Central  6
Ward 6 – Clydebank Waterfront 7
Total  35

Page 10

4.10 In March, the Scottish Government published the four-year resource planning
allocations to deliver new housing within the Affordable Housing Supply
Programme.  West Dunbartonshire receives 1.7% of the total overall funding
and £51m over the four-year period. 
5. People Implications 
5.1 The delivery of the More Homes delivery programme is managed through
existing resource within the Housing Development & Homelessness team
funded from the Housing Capital Investment Programme.   
6. Financial and Procurement Implications 
Financial 
6.1 The Council has to date delivered 586 new homes for social rent; these
additional homes bring council tax revenue of around £815k per year to West
Local Authority Area
2026-27
£m
2027-28
£m
2028-29
£m
2029-30
£m
Total
£m
Aberdeen City 16.298 16.787 17.290 17.809 68.184
Aberdeenshire 27.779 28.612 29.470 30.355 116.216
Angus 10.118 10.422 10.735 11.057 42.332
Argyll & Bute 20.189 20.795 21.419 22.062 84.465
Clackmannanshire 6.984 7.193 7.409 7.631 29.216
Dumfries & Galloway 22.597 23.275 23.973 24.692 94.537
Dundee City 18.616 19.174 19.749 20.342 77.881
East Ayrshire 13.598 14.006 14.426 14.859 56.890
East Dunbartonshire 7.738 7.970 8.209 8.455 32.372
East Lothian 12.554 12.931 13.319 13.718 52.521
East Renfrewshire 7.696 7.926 8.164 8.409 32.196
Edinburgh, City of 66.383 68.375 70.426 72.539 277.723
Falkirk 14.982 15.431 15.894 16.371 62.679
Fife 39.963 41.162 42.396 43.668 167.189
Glasgow, City of 123.283 126.982 130.791 134.715 515.772
Highland 50.132 51.636 53.185 54.781 209.733
Inverclyde 10.476 10.791 11.114 11.448 43.830
Midlothian 10.586 10.904 11.231 11.568 44.288
Moray 9.571 9.858 10.153 10.458 40.040
Na h-Eileanan Siar 9.088 9.361 9.642 9.931 38.021
North Ayrshire 16.889 17.396 17.918 18.455 70.659
North Lanarkshire 36.014 37.095 38.208 39.354 150.671
Orkney Islands 3.933 4.051 4.172 4.297 16.453
Perth & Kinross 16.998 17.508 18.033 18.574 71.112
Renfrewshire 19.171 19.747 20.339 20.949 80.206
Scottish Borders 17.743 18.275 18.823 19.388 74.230
Shetland Islands 5.609 5.777 5.950 6.129 23.465
South Ayrshire 13.225 13.622 14.031 14.451 55.329
South Lanarkshire 32.384 33.356 34.357 35.387 135.484
Stirling 11.738 12.090 12.453 12.826 49.106
West Dunbartonshire 12.201 12.567 12.944 13.333 51.046
West Lothian 17.933 18.471 19.025 19.596 75.026
Total 702.470 723.544 745.250 767.608 2938.872

Page 11

Dunbartonshire Council. 
6.2 On 4 March 2026 supported by tenant representatives the Council approved
the Housing Capital Programme 2025-2030 which saw appropriate resources
committed to the delivery of new council homes in West Dunbartonshire.  An
expenditure budget of £99.675m for the affordable housing supply programme
inclusive of acquisitions is factored into the 5-year HRA Capital Programme. 
As it currently stands, it is anticipated that this programme will complete within
project life budget. 
6.3 Housing and Finance Officers will continue to assess the ongoing affordability
of future developments within the context of the Housing Revenue Account
Business Plan. 
Procurement 
6.4      All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within 4.8 of this report will
continue to be prioritised. Where the contract award for services is less than
£213,477 (inc VAT), authority is delegated to the Chief Officer in consultation
with the Procurement Manager to instruct the award of contracts for the
planned revenue and capital spend detailed in this report to suppliers
providing the most economically advantageous offer to the Council. 
6.5      All procurement activity conducted by the Council more than £2m for works is
subject to a contract strategy.  The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include but is not limited to; contract scope,
service forward plan, the market, procurement model, and routes – including
existing delivery vehicles, roles and responsibilities, risks, issues and
opportunities and on-going contract management. Opportunities to maximise
the positive social, economic, and environmental impact for the Council
through the relevant procurement processes will be developed in line with
procurement policy. 
7. Risk Analysis 
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis. 
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel.

Page 12

7.3 Housing supply continues to be the key factor in terms of the national and
local housing emergencies and if not increased and/or demand reduced it will
lead to continued pressures on other Council and Health and Social Care
Partnership service areas such as Homelessness which will have negative
financial implications for the wider Council’s general fund.   
8 Environmental Sustainability 
8.1  The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy. 
9. Equalities Impact Assessment (EIA) 
9.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment. 
10. Consultation 
10.1 As part of a rent consultation exercise in 2025, 92% of respondents indicated
their support for the Council’s ambitious plans to deliver the Housing Revenue
Account (HRA) new council house build programme. In addition, there was
positive support for the wider delivery of new build housing as part of the
current Local Housing Strategy.  Regular updates on new build development
are provided to the West Dunbartonshire Tenants and Residents Organisation
at the bi-monthly liaison meetings. 
11. Strategic Assessment 
11.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire. 
11.2 Having considered all the Council’s strategic priorities, this report, and the
provision of new supply social housing for rent contributes greatly to all the
Council’s strategic priorities. 
Peter Barry
Chief Officer, Housing 
Date: 29 April 2026 
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk

Page 13

Mikayla Deeley, Senior Housing Development Officer,
Housing Development and Homelessness Team,
Housing and Employability: email mikayla.deeley@west-
dunbarton.gov.uk 
Appendices: None 
Background Papers: West Dunbartonshire Council’s Local Housing Strategy 
West Dunbartonshire Council’s Strategic Housing
Investment Plan     
Local Housing Strategy, Health Inequalities Impact
Assessment 
Wards Affected: All