Page 1

WEST DUNBARTONSHIRE COUNCIL 
Report by Chief Officer – Resources   
Housing and Communities Committee: 25 February 2026
___________________________________________________________________ 
Subject:  General Fund Housing and Communities Financial Report 2025/26
as at Period 7 (31 October 2025) 
1. Purpose 
1.1 The purpose of the report is to provide the Committee with an update on the
financial performance to 31 October 2025 (Period 7) of General Fund
Revenue services under the remit of the Housing and Communities
Committee. 
2. Recommendations 
2.1 Members are asked to 
i) note the account currently shows a projected annual favourable variance
of £0.244m. 
ii) note the progress on efficiencies incorporated into 2025/2026 budgets. 
3. Background 
3.1      Revenue Budget
Members agreed the 2025/2026 revenue estimates at the Council meeting on
5th March 2025.   
The Financial Update report to Council on 29 October 2025 advised that two
further areas of service activity that were previous managed within council
suspense accounts, the Resettlement Service and the Energy Efficiency
Scotland Area Based Scheme project, would have their income and
expenditure recorded in the General Fund this financial year. 
The Council Budgetary Control report on 17 December 2025 incorporated
these two services within the General Fund with the revised portfolio of
service areas for this committee detailed below. 
Service Area 
Budgeted
Expenditure
£m
Budgeted 
Income
£m 
Budgeted 
Net Expenditure
£m 
Homelessness Services 5.069 -4.241 0.828
Resettlement Service  0.668 -0.668 -
Private Sector Housing 0.016 - 0.016
Private Sector Housing Grant 0.425 -0.382 0.043
Energy Efficiency Scotland Area Based Scheme 0.583 -0.583 -
Anti-Social Behaviour & CCTV 0.535 -0.230 0.305
Housing Maintenance Trading Organisation  20.581 -20.872 -0.293
Total   27.875 -26.976 0.899
ITEM 14

Page 2

4. Main Issues 
4.1 Appendix 1 reports the forecast outturn for the services at £0.655m, a
projected favourable variance of £0.244m. 
Service Area 
Forecast
Outturn
£m
Budgeted 
Net Expenditure
£m
Variance
£m
Homelessness Services 0.854 0.828 0.026
Resettlement Service  -0.262 - -0.262
Private Sector Housing 0.016 0.016 
Private Sector Housing Grant 0.043 0.043 
Energy Efficiency Scotland Area Based
Scheme - - 
Anti-Social Behaviour & CCTV 0.297 0.305 -0.008
Housing Maintenance Trading Organisation  -0.293 -0.293 -
Total   0.655 0.899 -0.244 
4.2     The Homelessness Service is the only service forecasting an adverse
variance. The current forecast is for a small overspend of £0.026m compared
to the previous forecast to November committee of a £0.017m overspend. The
service has put in place a series of actions that will improve financial
performance and service managers will continue to target further efficiencies
that can eliminate the remaining overspend. 
The Resettlement Service is forecasting a positive variance of £0.262m. The
UK and the Scottish Government provide grant income to help the council to
meet the cost of supporting refugees within local communities. It is forecast
that the grant income that the council will receive this year will exceed the
direct cost of providing resettlement support. Other council service areas also
provide support to refugees and this surplus income will be reallocated at the
end of the financial year. 
Appendix 2 provides a detailed analysis by service area. 
Appendix 3 provides commentary of projected net annual variances greater
than £0.050m. 
Appendix 4 shows progress on the delivering 2025/2026 saving options. 
5. People Implications 
5.1 There are no people implications. 
6. Financial Implications 
6.1 Other than the financial position noted above, there are no financial
implications of the budgetary control report. 
6.2      Agreed efficiencies for 2025/2026 are monitored with current indications being
that all the budgeted savings of £0.049m will be achieved. (see Appendix 4)

Page 3

7. Risk Analysis 
7.1 The present variances should be viewed in the knowledge that there are
several variable factors which could arise between now and 31 March and
which could affect the year end results for both the revenue and capital
budgets.  
8. Equalities Impact Assessment (EIA) 
8.1 The report is for noting and therefore no Equalities Impact Assessment was
completed for this report. 
9. Consultation 
9.1 All services involved in delivering the budgets have been consulted in the
compilation of this report. 
10. Strategic Assessment 
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. This report is for noting and, therefore, does not
directly affect any of the strategic priorities. 
Laurence Slavin
Chief Officer, Resources                       
Date: 25 February 2026
___________________________________________________________________ 
Person to Contact:  Jim McCarron - Finance Business Partner, 
16 Church Street, Dumbarton, G82 1QL  
Telephone: 07772 322055  
e-mail james.mccarron@west-dunbarton.gov.uk 
Appendices:  Appendix 1 - Summary Budgetary Position (Revenue)    
Appendix 2 - Detailed Budgetary Position (Revenue)    
Appendix 3 - Variance Analysis (Revenue)
Appendix 4 - Monitoring of Efficiencies/Savings Options
(Revenue)     
Background Papers: None 
Wards Affected:  All