WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Housing and Communities Committee: 25 February 2026
___________________________________________________________________ 
Subject:  Housing Revenue Account (HRA) Capital   
Budgetary Control Report to 31 October 2025 (Period 7) 
1. Purpose 
1.1 This report provides an update on the HRA capital programme to 31 October
2025. 
2. Recommendations 
2.1 Committee is asked to: 
i) Note the position of the 2025/26 HRA capital budget and the HRA capital plan
as 31 October 2025. 
ii)  Note project life performance is monitored against a £345.311m project life
expenditure estimate, a £80.378m project life income estimate and a
£264.933m five-year borrowing requirement. 
iii)  Note all projects are currently on track to achieve their planned completion
dates and that eleven projects are forecast to deliver a total underspend of
£7.999m against their five-year project life budgets. 
iv) Note in year financial performance is monitored against a 2025/26 capital
expenditure budget of £55.547m, 2025/26 capital income budget of £6.290m
and a one-year borrowing requirement of £49.257m. 
v) Note there is an anticipated under spend of £9.475m against 2025/26 budgets
reducing the forecast one-year borrowing requirement to £39.782m. 
3. Background 
3.1 The Council approved the HRA Capital Plan for 2025/26 to 2029/30 on 5
March 2025. The HRA capital plan approved £70.590m of capital expenditure
and £15.324m of capital income in 2025/26, creating a borrowing requirement
of £55.266m. 
3.2  At its meeting on the 27 August 2025, the Housing and Communities
Committee agreed budget adjustments that revised the 2025/26 capital
expenditure budget to £55.547m and the capital income budget to £6.290m,
an updated one-year borrowing requirement of £49.257m. Committee also
approved a revised project life budget of £264.933. A summary of the revised
capital budgets is set out in Exhibit 1. 
ITEM 13

Page 2

Exhibit 1: HRA Capital Estimates 2025/26 – 2029/30 
2025/26
Forecast
BCR07
(£m)
2025/26 
Budget
(£m)
Variance 
(£m) 
Project Life
Forecast
BCR07 
(£m)
Project
Life
Budget
(£m)
Other Capital   6.690 7.433 -0.743  26.052 26.267
Component Replacement   14.778 20.881 -6.103  87.908 93.567
Void  5.775 5.258 0.517  19.873 19.873
Structural & Environmental   1.905 3.762 -1.857  16.653 17.320
Support Costs  3.100 3.100 -  17.155 17.155
More Homes   17.972 15.113 2.859  171.129 171.129
Total Expenditure  50.220 55.547 -5.327  338.770 345.311
Total Income   -10.438 -6.290 -4.148  -81.836 -80.378
Prudential Borrowing  39.782 49.257 -9.475  256.934 264.933 
4. Main Issues 
4.1 Progress against the 2025/26 capital plan is detailed in: 
Appendix 1 – HRA Capital Summary BCR07  
Appendix 2 – HRA Capital Detail BCR07 
4.2  The HRA capital summary report at Appendix 1 reports that: 
• project life expenditure is forecast to be less than budget by £6.541m over
the 5-year period of the capital plan. 
• one project has forecast project life income of £1.458m more than the
project budget
• consequently, prudential borrowing will be £7.999m less than the approved
project life budget over the 5-year period of the capital plan. 
4.3  Appendix 2 reports all projects with their approved in year and project life
estimates as well as their 2025/2026 expenditure and income forecasts. The
appendix reports: 
• 2025/26 forecast spend of £50.220m, a £5.327m underspend against the
2025/26 budget.
• 2025/26 forecast income of £10.438m, a £4.148m over-recovery against
the 2025/26 budget.
• 2025/26 prudential borrowing forecast of £39.782m, £9.475m less than the
approved budget for 2025/26. 
4.4 Commentary on the 2025/26 variances above £50,000 are set out in Exhibit 2
below. 
Exhibit 2: Project Over / Underspends 2025/2026 as at BCR07 
Project 25/26
Forecast 
(£m) 
25/26
Budget
(£m) 
25/26
Variance
(£m)  Commentary
1 Capitalised
Minor Works
3.500 3.715 -0.215 Reduced contractors spend.

Page 3

Project 25/26
Forecast 
(£m) 
25/26
Budget
(£m) 
25/26
Variance
(£m)  Commentary
2 Environmental
Sensors
1.500 2.000 -0.500 Underspend due to
challenges getting access to
properties 
3 Targeted
SHQS
/EESSH
compliance
works
5.000 6.628 -1.628 Underspend reflects the
changing mix of the capital
programme with an
increased number of mixed
tenure blocks that require
owner consent before work
can start. This necessary
process delays project start. 
4 External
Component
Renewal -
Roofs
1.360 2.550 -1.190 Underspend reflects the
changing mix of the capital
programme with an
increased number of mixed
tenure blocks that require
owner consent before work
can start. This necessary
process delays project start.  
5 Doors/Window
Component
Renewals
3.800 4.985 -1.185 Underspend due to
challenges getting access to
properties. Install team to
continue programmed
addresses and revisit no
accesses to use materials
already supplied. 
Underspend will reduce
borrowing requirement. 
6 External
Stores /
Garages / Bin
Stores
0.000 0.048 -0.048 Works are being funded from
the capitalised minor works
budget. 
7 Secure entry
component
renewals
0.000 0.100 -0.100 Works are being funded from
the capitalised minor works
budget. 
8 Statutory /
Compliance
Works
0.150 0.594 -0.444 Health and safety works are
now being delivered across
two years. 
9 Energy
Improvements
/ Efficiency
Works
0.000 0.058 -0.058 Works are being funded from
the capitalised minor works
budget. 
10 Kitchen
Upgrade
1.600 2.850 -1.250 Underspend projected as
team re-assess and pre-
inspect to ensure a focus on
necessary renewals led by
condition.

Page 4

Project 25/26
Forecast 
(£m) 
25/26
Budget
(£m) 
25/26
Variance
(£m)  Commentary
11 Bathroom &
Shower
Replacement
0.600 0.800 -0.200 Underspend projected as
team re-assess and pre-
inspect to ensure a focus on
necessary renewals led by
condition. 
12 Void House
Programme
5.775 5.258 0.517 Overspend due to mix of
work requiring contactors in
addition to in-house team. 
13 Defective
structures
/component
renewals
0.175 0.800 -0.625 Underspend projected as
future blocks are pre-
inspected for condition and
re-prioritisation for
completion if necessary. 
14 Environmental
Renewal -
Paths &
Environment
1.130 1.000 0.130 Overspend due to mix of
work requiring contactors in
addition to in-house team. 
Overspend will be re-profiled
across future years. 
15 Asbestos
Management
Works
0.200 0.242 -0.042 Demand lower than
anticipated. 
Underspend will reduce
borrowing requirement 
16 Multi Storey
Flat Strategy
0.400 1.720 -1.320 Revised projection based on
timing of programme. 
17 Buy Backs 4.000 4.380 -0.380 Revised projection based on
the anticipated programme of
thirty-five acquisitions to be
completed in 25/26. 
18 Demolition
Programme
0.213 0.140 0.073 Revised projection based on
timing of programme. 
19 Clydebank
East
0.365 0.250 0.115 Revised projection based on
development project plan. 
20 Pappert 0.875 0.730 0.145 Revised projection based on
development project plan. 
21 Willox Park
Phase1
3.398 2.980 0.418 Revised projection based on
development project plan. 
22 Bank Street 0.839 1.500 -0.661 Revised projection based on
development project plan.  
23 Bonhill Gap
Sites
5.145 1.600 3.545 Revised projection based on
development project plan.

Page 5

Project 25/26
Forecast 
(£m) 
25/26
Budget
(£m) 
25/26
Variance
(£m)  Commentary
24 Silverton 0.050 0.100 -0.050 Revised projection based on
development project plan. 
25 Queen Mary
Avenue
1.000 0.800 0.200 Revised projection based on
development project plan. 
26 Future New
Build &
Related
Regeneration
Projects 
0.000 0.550 -0.550 Revised projection based on
development project plan. 
27 Scottish Govt
Buyback
Grant
-2.378 -0.550 -1.828 Revised projection based on
the distribution of Scottish
Government acquisition
funding. 
28 Bank Street -0.839 -1.500 0.661 Revised projection based on
the application of the
Strategic Local Programme 
29 Bonhill Gap
Sites 
-3.360 -1.600 -1.760 Revised projection based on
the application of the
Strategic Local Programme
30 West
Thomson
Street 
-0.350 -0.375 0.025 Revised projection based on
the application of the
Strategic Local Programme
31 Other Grant -1.712 -0.406 -1.206 Additional Scottish
Government Net Zero
Funding awarded to fabric
first energy efficiency works. 
Additional Scottish
Government grant to support
capital works on properties
allocated to the resettlement
service 
4.5 Budget assumptions are required to forecast costs / income, especially where
projects span multi-year and project finances have yet to be finalised. It is
therefore likely that the projected year end position will change during the
year. 
5. Option Appraisal 
5.1 No option appraisal was required for this report. 
6. People Implications 
6.1 There are no people implications.

Page 6

7. Financial and Procurement Implications 
7.1 The report notes the projected in-year financial position for capital estimates. 
8. Risk Analysis 
8.1 The main risks are as follows: 
(a) The reported variances should be viewed in the knowledge that there
are several variable factors which could arise between now and 31
March which could affect the year end results for capital budgets. 
(b) To forecast for the full year costs budget assumptions have been
required. These assumptions continue to change regularly and therefore
it is likely the projected year end position will change from that reported. 
9. Equalities Impact Assessment (EIA) 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability 
10.1 No assessment of environmental sustainability was required in relation to this
report. 
11. Consultation 
11.1 All services involved in delivering the capital estimates have been consulted
during the compilation of this report. 
12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
________________
Laurence Slavin
Chief Officer – Resources
Date: 25 February 2026 
Person to Contact: Jim McCarron 
Business Partner, Finance 07772 322055  
E-mail: james.mccarron@west-dunbarton.gov.uk 
Appendices: Appendix 1 -  HRA Capital Summary BCR07 
Appendix 2-  HRA Capital Details BCR07 
Background Papers: 
Housing Revenue Account (HRA) Capital Investment Programme, Revenue
Budget, and Rent Levels for 2025/26 - Council 5 March 2025. 
Wards Affected           All Wards