WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing
Housing and Communities Committee: 25 February 2026
__________________________________________________________________
Subject: Housing Capital Investment Programme
1. Purpose
This purpose of this report is to provide the Housing and Communities
Committee (the Committee) with an overview of Housing Revenue Account
(HRA) proposed capital investment and spending plans and assess options
for future investment.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Notes the content of this report and the financial pressures on the
Council’s Housing Revenue Account and the actions that have
been taken to improve the wider health of the HRA and ensure
tenant and service investment priorities are delivered, including
the reduction in the borrowing requirement in 2025/2026 by £6m
as outlined in 4.10 of this report;
(ii) Approves that the Council’s Better Homes Investment Programme
proceeds as detailed in sections 4.14 - 4.20 through Option 2
which will see a proposed 50% reduction in capital spend on
environmental works form part of the tenant rent consultative
exercise for 2027/28 which will commence in October 2026,
subject to discussion with tenant representatives.
(iii) Approves the delivery of the Council’s More Homes Affordable
Housing Supply Programme set out in the Strategic Housing
Investment Plan (SHIP) and proceeds as detailed at 4.37-4.47 of
this report, and with Option 2 to target the delivery of 25 new
council homes every year from 2028/29-2031/32, subject to
ongoing review in terms of deliverability and affordability and
discussion with tenant representatives. 
(iv) Note the remedial actions led by the Chief Officer, Housing to
address the financial challenges by progressing a plan to
replenish and maintain HRA reserves to above prudential levels
and work towards a CFCR (Capital Financed from Current
Revenue) strategy.  The aim of this approach is to reduce future
borrowing as seen with the £6m borrowing reduction in 2025/26
and mitigate future borrowing cost risks, while still delivering
tenant and service investment priorities and
(v) Invites the Chief Officer, Housing to fully refresh the HRA 30-year
business plan and develop a future rental and investment strategy
ITEM 10

Page 2

and report back to the Housing and Communities Committee later
this year.
3. Background
3.1 On 5 March 2025 the Council approved an 8% rent increase for 2025/26 to
deliver tenant priorities and the Housing Capital Investment Plan for the 5-
year period until 2029/30.
3.2 The capital investment plan estimated expenditure over the five-year period of
£291m with capital grant / other income of £50m resulting in a net borrowing
requirement of £241m. This estimated borrowing was split between £175m
(73%) for investment in current homes and £66m (27%) to deliver the More
Homes West Dunbartonshire programme inclusive of the Council’s buyback
programme. This is illustrated in Table 1.
Table 1 – Housing Capital Investment Plan 2025-2030 agreed March 2025
HRA Financial Position
3.3 The HRA, consistent with many other HRAs across Scotland, is under
financial pressure. Whilst the HRA revenue budgetary control report (BCR)
presented to the Committee today projects a 2025/26 in-year surplus of
£1.087 million this has been driven by lower HRA debt servicing costs
including a non-recurring in year benefit through debt restructuring.  The BCR
also confirms there remain high cost and demand pressures in areas such as:
 Responsive/void repairs
 Bad debt provisions
 Void loss and council tax
Furthermore, staff costs have increased in particular due to the increase in
employer national insurance contributions. This has proved a challenge to a 
25/26
£m
26/27
£m
27/28
£m
28/29
£m
29/30
£m
Total
£m
1 More Homes Expenditure 30.2 33.7 16.5 12.7 23.3 116.4
2 More Homes Grant Income -15.3 -11.9 -4.8 -5.8 -12.6 -50.4
3 Net More Homes
Expenditure / Borrowing
Requirement (1-2)
14.9 21.8 11.7 6.9 10.7 66.0
4 Better Homes Expenditure /
Borrowing Requirement
40.4 36.8 35.9 31.7 30.0 174.8
5 Total Borrowing
Requirement (3 + 4)
55.3 58.6 47.6 38.6 40.7 240.8
6 % of Borrowing that relates
to More Homes (including
buyback programme)
26.9% 37.2% 24.6% 17.9% 26.3% 27.4%
7 % of Borrowing that relates
to Better Homes
73.1% 63.8% 75.4% 83.1% 73.7% 72.6%

Page 3

number of housing providers across Scotland and is one of the causes of
above inflation rent increases in 2026/27 and beyond.
3.4 Table 2 provides a HRA financial analysis, alongside the proposed HRA
capital investment detailed in the rent consultation exercise. It confirms the
Council has:
 higher rents than most other Scottish councils (though below the national
social rented average)
 a lower proposed rent increase in 2026/27 than most Scottish councils
 the second highest housing debt level per home of all Scottish Local
Authorities
Consequently, as with public sector finances in general, HRA finances will
remain challenged for the near future with revenue and capital plans requiring
rent increases in the region of 7% over the next few years to provide sufficient
income to meet increasing operating and debt financing costs. Table 2 also
advises of expected HRA capital debt levels in March 2030 based on existing
borrowing plans.
Table 2 – HRA Financial Analysis 
HRA Rent - Rent was increased by 8% from April 2025. The average
council house rent in 2025/26 was £102.28. (52-week basis)
Scottish Housing Network HRA statistics for the 2024/25 financial year
reported West Dunbartonshire had the fifth highest council house rents in
Scotland behind Edinburgh City Council, Aberdeenshire, Renfrewshire, and
Orkney Councils. Wheatley Homes the largest housing association
operating in Scotland (Loretto Housing in West Dunbartonshire) also have a
higher average rental charge. 
Housing Rent Analysis 24/25

Page 4

2026/27 Rent Increase - The 2026/27 tenant rent consultation has a base
option of a 6.7% rent increase and three additional options. The options are:
Rent Increase Includes
1 6.7%
(average weekly
increase of £6.84)
 Maintaining all services tenants receive
 Delivering New Build housing programme
 Delivering Capital Investment programme to
improve existing Council homes
 Tenant Priority Budget of £200k for tenant-
led improvements
2 6.95%
(average weekly
increase of £7.09)
Option 1 plus:
 Additional expenditure of £140k to re-instate
open space maintenance to 2024/25 funding
levels.
3 7.2% 
(average weekly
increase of £7.35)
Option 1 plus:
 Additional £3.6m of Capital Investment
during 2026/27 expanding the Buy Back
Scheme to deliver 24 additional Council
homes for rent.
4 7.45%
(average weekly
increase of £7.60)
Option 1 plus:
 Additional expenditure of £140k to re-instate
open space maintenance to 2024/25 funding
levels.
 Additional £3.6m of Capital Investment
during 2026/27 expanding the Buy Back
Scheme to deliver 24 additional Council
homes for rent.
There are a range of cost pressures contributing to the rent increase, the
key pressures being increased employee costs (pay award, national
insurance changes, employer pension costs) and increased debt servicing
costs as capital debt increases.
HRA financial modelling for the next five years takes account of additional
income from new build and buyback properties, and significant revenue cost
pressures that require to be addressed including the impact of current
capital investment plans on HRA borrowing and associated debt financing
costs.  This modelling indicates that annual rent increases of around 7% per
annum over the period 2027/28 – 2030/31 are needed to provide the
sufficient income to meet increasing operating and debt financing costs.
The housing service will as part of future planning look at ways to reduce
operating costs without impacting negatively on the quality of life of our
current and future tenants.
The information below highlights the average rent increases across Scottish
local authorities in 2025/26.

Page 5

As part of our rent consultation exercise, we have benchmarked our
proposed rent increase for 2026/2027 with comparable councils. Current
available contextual information is provided below. Around 60% of Council
tenants receive assistance with rent through housing benefit or universal
credit.
Council Proposed 2026/27 Rent Increase
Aberdeenshire 12%
Angus 8%
Dundee 8%
Falkirk 8%
Highland 8%
Renfrewshire 7.5%
Shetland 7.5%
East Ayrshire 7%
East Lothian 7%
Edinburgh 7%
West Dunbartonshire 6.7%
Perth and Kinross 6.5%
Clackmannanshire 6%
Moray 6%
Stirling 5.8%
Aberdeen 5%
Orkney 4%
West Lothian 3.5%
Rent Affordability - An affordability analysis undertaken prior to the
commencement of the Council’s 2026/27 rent consultation determined
Council WDC rents are on average £77 (42%) less than Market Rents with
all properties comfortably below the equivalent average market rent.  In
addition, all households on minimum income can afford Council rents
assuming the 35% rent to income ratio. Using equivalised income
measures, all tenant household types spend under 35% of their income on

Page 6

housing, in some cases as little as 14%. Single adults on Universal Credit
are the only group exceeding the 30% mark.
Reserves - HRA reserves are forecast to be circa £1.70m in March 2026,
which exceeds the prudential HRA reserve target of £1.16m. The current
rent increase assumption of around 7% per annum over the period 2027/28
– 2030/31 is predicted to maintain reserves at March 2026 levels over the
next 5 years.
Interest Rates - HRA financial modelling for the next five years assumes a
4.25% interest rate on debt. Interest rates have been volatile over the last 3
years with the interest payable on council debt sharply increasing placing
strain on HRA finances.
An increase in the interest rate is considered the most significant financial
risk to HRA finances. To illustrate, HRA capital debt is forecast to be £414m
in March 2027. An increase of 0.25% to 4.50% in 2026/27 would add
around £1m annually to HRA costs placing considerable pressure on HRA
finances.  The current modelled rent increase would need to be increased
by circa 1.5%.
Similarly, a reduction of 0.25% to 4.00% would reduce HRA costs by £1m
annually, this could be utilised by decreasing the modelled rent increase by
1.5% or strengthening reserves.
Currently most financial institutions are projecting interest rates will continue
to fall, however there is no clear consensus around the speed or depth of
the projected reductions.
Capital Debt - The HRA had £348m of HRA capital debt in March 2025,
circa £33,500 of capital debt per lettable unit (excluding surplus stock). For
2024/25 West Dunbartonshire had the second highest HRA debt level per
lettable unit in Scotland.
Current HRA capital investment plans will increase debt servicing costs to
circa £40m by 2029/30 and contribute to the 7% projected rent strategy
needed over the next three years.
The Housing Investment Taskforce, established by the Scottish
Government, reported in Summer 2025, and set out a series of actions to
support investment in new and existing business models. This included an
action to seek to write-off of historic HRA debt to provide immediate
capacity for new supply. If this were to be achieved, it would require
agreement with the UK Government and would have a significant positive
impact on the Council’s HRA financial position.
3.5 As a housing provider with landlord responsibilities for over 10,500 properties,
the housing service must be agile to continue to deliver tenant priorities in a
challenging strategic and financial landscape. A balance needs to be struck
between meeting tenant needs, maintaining and improving existing assets,
building new homes to meet identified need, and keeping rent levels as
affordable as possible. This balance is achieved in West Dunbartonshire
through strong tenant participation mechanisms. These have highlighted

Page 7

continued tenant support for the Council’s housing investment plans as
highlighted below.
3.6 In November 2024, the Housing Service conducted an independent Tenant
Satisfaction Survey. The survey highlighted HRA cost pressures to tenants
and asked tenants to outline their two most important spending priorities
within this context. Feedback overwhelmingly showed that the two top
spending priorities for tenants to be a responsive and high-quality housing
repairs service and building new Council homes:
3.7 The survey findings were reported to the Housing and Communities
Committee on 26 February 2025, which approved the recommendation for the
Chief Officer, Housing to ensure tenant spending priorities were reflected in
the delivery of investment plans over the next three-year period.
3.8 The tenant satisfaction survey highlighted 86% of tenants felt their rent
represents good value for money. Only 2.6% of tenants felt the rent is poor
value for money, a reduction from 15% in the previous survey in 2022. Table
3, taken from the Scottish Housing Regulator Charter Return, highlights the
Scottish local authority average for this measure is 80%.
Table 3 - % of tenants who feel rent represents good value for money.
Housing Emergency
Council % of tenants
Stirling Council 93%
Loretto Housing Association
(Wheatley)
93%
West Dunbartonshire Council 86%
River Clyde Homes 85%
All RSLs (Scotland) 82%
All Social Landlords 82%
All Local Authorities 80%
East Dunbartonshire Council 76%
Renfrewshire Council 70%

Page 8

3.9 In May 2024, informed by extreme pressures facing housing and
homelessness services in meeting statutory duties, the Council declared a
Housing Emergency. This prompted the development of the Housing
Emergency Declaration Action Plan which had four strategic themes.
 Deliver and maintain More Homes - West Dunbartonshire approach to the
delivery of affordable housing.
 Make Best Use of Existing Stock.
 Enhancing Housing Access and the prevention of homelessness.
 Strengthen the Financial viability and capacity of the Housing Revenue
Account and associated Housing and Homelessness budgets.
3.10 The Scottish Government’s Housing Emergency Action Plan, published in
September 2025, sets out a range of enhanced and accelerated actions to
tackle the national housing emergency.  The plan is structured through the
following three pillars:
 Ending children living in unsuitable accommodation as a vital part of the
Scottish Government’s determination to end child poverty.
 Supporting the needs of vulnerable communities.
 Building our future – maximising investment in Scotland’s housing sector.
The plan includes a commitment of funding of £4.9billion over the next four
years to support the delivery of over 25,000 new social rented homes in
Scotland.
3.11 This national intervention provides both an opportunity and a challenge. While
the enhanced resources will support the expansion of the Council’s Affordable
Housing Supply Programme and enable delivery of much-needed new
homes, the Council must also ensure alignment with evolving national
priorities and demonstrate capacity to secure and deploy any additional
funding effectively. Once the Scottish Government makes formal
announcements on the aspects of the Action Plan, such as distribution of
funding, the Council will review the current programme with a focus on
maximising investment opportunities and ensuring the delivery of affordable
housing continues to meet the needs of West Dunbartonshire’s communities.
4. Main Issues
4.1 In response to the financial challenges facing the Council’s HRA, the Chief
Officer, Housing chairs a weekly HRA Value for Money (VFM) Group. It
consists of senior staff across housing and finance and has overseen
interventions that have positively impacted on HRA finances, including
preventing the HRA from fully exhausting its reserves in 2024/25, and the
improved financial position reported to Council. This group is progressing a
plan to maintain HRA reserves to above prudential levels and to develop a
future CFCR (Capital Funded from Current Revenue) strategy to enable the
Council to deliver tenant investment priorities with a reduced need to borrow
to deliver those investment plans.
4.2 The HRA VFM Group also targeted efficiencies across HRA income and
expenditure in advance of the rent consultation, targeting reduced spend

Page 9

across budgets not aligned with tenant and service priorities. These targeted
reductions helped reduce the rent increase in the options developed for the
tenant consultation exercise which was launched on 30 October 2025 and are
outlined in Table 2. This efficiency work will also be one of the building blocks
to progress to deliver on a future CFCR strategy that will help reduce future
borrowing risks.  The consultation closed on the 23 January 2026, and the
outcome will inform the rent setting report to West Dunbartonshire Council on
4 March 2026.
4.3 The proposed rent increase of 6.7% - 7.45% will help support the ongoing
financial viability of the HRA and provide financial headroom for the capital
investment needed to deliver agreed tenant priorities. However, further
actions are required to reduce the impact of borrowing commitments over the
next period. This will include a full refresh of the HRA 30-year business plan,
this essential piece of work will report to the Housing and Communities
Committee in Autumn 2026 and inform a future rental and investment strategy
from 2027/28 and beyond.
4.4 As highlighted in Table 1, the Housing Capital Investment Plan approved
March 2025, assumed borrowing levels of circa £241m, as illustrated below:
Year Estimated Borrowing (£m)
2025/26 55.3
2026/27 58.6
2027/28 47.6
2028/29 38.6
2029/30 40.8
Total 240.9
4.5 These borrowing requirements include expenditure to support the decision
taken by the Council meeting on 1 March 2023 to approve a 5% rent increase
for 2023/24. The 5% rent increase levered borrowing for an additional £50m
of capital expenditure over a five-year period (2023/24-2027/28). This
investment decision was taken at a time when borrowing costs were at
historically low levels. Since that decision was made, global events have
contributed to a significant increase in council borrowing costs.
4.6 The decision to borrow an additional £50m and agree the tenant priorities with
tenant representatives has led to the following positive outcomes:
 Scaling up of the Council’s buyback scheme, supported by Scottish
Government funding, strengthening the financial viability of the HRA and
helping meet housing need particularly in relation to family homes.
 An agreed approach to eradicating damp and mould issues in council
properties through a multi-year investment in environmental sensors. The
Council is the sector leader in this area, and this will prove to be prudent
expenditure as we prepare for the introduction of Awaab’s law as part of
the Housing (Scotland) Act 2025 in March 2026. Awaab’s law is designed
to protect social and private tenants from unsafe housing conditions,
specifically requiring landlords to investigate and fix damp and mould
within mandatory timeframes, it was introduced following the tragic death
of 2-year-old Awaab Ishak caused by prolonged exposure to mould in his
family’s housing association home in Rochdale, England in 2020.

Page 10

 Tenant-initiated upgrades to CCTV provision within our multi storey homes
to improve the quality of life for the tenants and help minimise vandalism,
wider anti-social behaviour and criminality, and reduce future repair costs. 
4.7 These three priorities contributed £20.8m of the additional £50m included as
part of the Enhanced Housing Capital Programme. The remaining £29.2m has
been earmarked to support existing investment programmes including
external wall insulation and heating system replacements. Approximately
£12.8m has been added to the HRA borrowing since 2023/24 to support these
investment programmes.
4.8 As referenced within paragraph 4.3 there requires an element of service
intervention to reduce borrowing levels in the short term to help maintain the
ongoing financial viability of the HRA and rent affordability for our current and
future tenants. These interventions have been led by the Chief Officer,
Housing supported by senior colleagues in housing and finance, and they
have reprofiled housing investment plans which were reported to the October
2025 meeting of the Council. This reprofiling has ensured tenant investment
priorities will continue to be delivered in parallel with the planned reduction in
HRA borrowing requirements.
4.9 On 27 August 2025, the Housing and Communities Committee agreed budget
adjustments that revised the 2025/26 capital expenditure budget to £55.6m
and the capital income budget to £6.3m, resulting in an updated one-year
borrowing requirement of £49.3m from £55.3m as illustrated in Table 4 below.
4.10 The Chief Officer, Housing will continue to lead the HRA VFM Group to
identify areas where capital and revenue spend can be minimised without
significantly impacting on tenant and service priorities and will progress a plan
which will reduce borrowing requirements as outlined in Table 4.
Table 4: HRA Borrowing Projections
Year Approved
Borrowing
Commitment
£m
Refreshed
Borrowing
Commitment
£m
Proposed
Change to
Borrowing
Commitment
£m
2025/26 55.3* 49.3** - 6.
2026/27 58.6* 50.0*** - 8.6
2027/28 47.6* 50.5*** +2.9
2028/29 38.6* 37.9*** -0.7
2029/30 40.7* 37.1*** -3.6
Total 240.8 224.8 -16
*Approved 5th March 2025
** Approved 27th August 2025
***Projected
4.11 The impact of reduced borrowing has been included as part of the preparation
of the rent consultation exercise with tenant representatives through the Joint
Rent Group, which is the established tenant consultative and engagement
forum for issues directed related to the financial health of the HRA and is
chaired by the Housing and Communities Committee Convener.

Page 11

4.12 The Housing Capital Investment Programme is underpinned by a strategic
framework aligned to the Council’s housing objectives, statutory duties, and
tenant priorities.  Those evidenced tenant priorities are highlighted in
paragraph 3.6 and confirm the building of new homes to be the top capital
spending priority with the lowest being environmental improvements and
tackling damp and mould.  While the Council continues to explore further
options for reduced capital investment, these decisions need to be considered
alongside the Council’s legal and regulatory frameworks. 
4.13 Specifically, the Council holds a statutory duty to ensure housing stock meets
the Scottish Housing Quality Standard (SHQS).  This effectively sets a guide
for necessary capital expenditure informed by our housing asset management
data. Any reduction in investment that compromises these standards would
result in a breach of regulations.  It would also be counter productive as
insufficient planned investment in viable housing stock would lead to the
Council incurring significantly higher reactive repair costs in the future.
4.14 Better Homes Option Analysis
As a result, three assessed options to reduce spend in these areas from
2027/28 to 2030/31 are as follows:
 Option 1 – Maintain planned housing investment programme.
 Option 2 – 50% reduction in spend on environmental works.
 Option 3 – 50% reduction in spend on environmental sensor programme
(tackling damp and mould)
Table 5a: Option 1 – Maintain planned housing investment programme.
27/28
£m
28/29
£m
29/30
£m
30/31
£m
Total
Borrowing
Requirement
Current Environmental
Works
1.2 1.2 1.2 1.2 4.8
Current Environmental
Sensor Programme 
1.5 1.5 1.5 0.0 4.5
Table 5b: Option 2 – 50% Reduction in Environmental Works
27/28
£m
28/29
£m
29/30
£m
30/31
£m
Total
Borrowing
Requirement
Current Environmental
Works
1.2 1.2 1.2 1.2 4.8
Option 2 – Revised
Environmental Works
0.6 0.6 0.6 0.6 2.4
Table 5c:  Option 3 - Environmental Sensor Programme Reduction
27/28
£m
28/29
£m
29/30
£m
30/31
£m
Total
Borrowing
Requirement
Current Environmental
Sensor Programme 
1.5 1.5 1.5 0.0 4.5

Page 12

Option 3 – Revised
Environmental Sensor
Programme
0.75 0.75 0.75 0.75 3
4.15 Tables 5b and 5c illustrate:
 Option 2 - annual reduction in borrowing of £0.600m and total reduction of
£2.4m over 4 years
 Option 3 – annual reduction in borrowing of £0.750m and total reduction of
£1.5m over 4 years
4.16 Table 5d summarised the changes to the overall borrowing requirements for
the three options.
Table 5d: Revised HRA Borrowing Projections from 2027/28-2030/31.
Option 1
Borrowing
£m
Option 2
Borrowing
£m
Option 3
Borrowing
£m
2027/28 50.5 49.9 49.75
2028/29 37.9 37.3 37.15
2029/30 37.1 36.5 36.35
2030/31 38.6 38 39.35
Totals 164.1 161.7 162.6
4.17 The reduction in borrowing requirement for the three options would reduce
debt servicing costs which would support lower rent increases. This is
summarised in Table 5e.
Table 5e: Indicative impact on rent of options 2 and 3
Option 2 -
Reduced Cost
of Borrowing
£,000
Option 2 -
Impact on
Rent
%
Option 3 -
Reduced Cost
of Borrowing
£,000
Option 3 -
Impact on
Rent
%
2027/28 26 -0.04% 32 -0.05%
2028/29 70 -0.10% 88 -0.12%
2029/30 114 -0.15% 146 -0.19%
2030/31 157 -0.20% -69 0.09%
Table 5e highlights option 2 would reduce future rent increases by 0.04% in
2027/28 up to 0.2% in 2030/31. Option 3 would reduce future rent increases
by 0.05% in 2027/28 up to 0.19% in 2029/30 but require a 0.09% increase in
2030/31 unless the environmental sensor programme was ceased without
being inclusive of the Council’s total housing stock. This is because the
programme would require to be extended.
4.18 Following approval of the Housing Act 2025, the Scottish Government on 21st
January 2026 introduced legislation for Awaab’s Law (detailed in paragraph
4.6 of this report) to come into force across the social rented sector from

Page 13

March 2026, starting with tackling damp and mould to ensure cases are
swiftly investigated and acted upon as appropriate. 
4.19 The Council’s agreed approach to eradicating damp and mould issues in
council homes is supported by a strong preventative strategic response
through the investment in environmental sensors to prevent future damp and
mould issues within our homes and improve tenant’s health and wellbeing.
Option 3 as detailed above would dilute this strategic intention. Maintaining
the current proposed expenditure would lead to wider revenue savings
through the spend to save preventative approach supporting the financial
health of the HRA together with the health of tenants. Therefore, the officer
view is that the Council should not pursue Option 3. For the same rationale a
fourth option which would have seen options 2 and 3 combined was not
considered.
4.20 Option 2 is recommended. It provides a £2.4m borrowing reduction consistent
with the wider financial strategy for the HRA over a 4-year period with minimal
impact on statutory standards, evidenced tenant priorities and also maintains
compliance with the introduction of Awaab’s Law through the Housing
Scotland Act 2025 and the Council’s wider approach to tenant safety, unlike
Option 3 and the potential combined option of 2 and 3. It is therefore
proposed that Option 2 will form part of the rent consultation exercise in
2027/28 which will commence in October 2026. 
Affordable Housing Supply Programme
4.21 A key element of the Housing Capital Investment Plan is the Council’s
Affordable Housing Supply Programme. Financing the new build programme,
as with every element of expenditure incurs additional costs that adds to
financial challenges and requires a strategic approach to ensure the service
can deliver on evidenced tenant priorities.  In terms of the cost of new build
homes this is partially mitigated by a 15% premium applied to new build home
rents.   The refreshed Strategic Housing Investment Plan approved by the
Housing and Communities Committee in November 2025 reprofiled our
development plans, which has positively impacted on our projected borrowing
requirements in the short term.
4.22 The delivery of new social homes, including new council homes, plays a key
role in:
 tackling the housing emergency
 combatting poverty, principally child and fuel poverty
 revitalising local economies and assisting with wider economic recovery
 negating the impacts of the current cost of living crisis
 improving social, economic and health outcomes for tenants
 providing a huge capacity for significant preventative savings to wider
society and public finance and
 delivering net zero ambitions.
4.23 It is also clear the need for new social homes will continue to increase in the
economic and social environment the Council is operating in, including
demographic challenges such as an ageing population. West

Page 14

Dunbartonshire’s Strategic Housing Investment Plan 2026-2031 addresses
these challenges.
4.24 Furthermore, the addition of new homes has a significant longer term positive
impact on the financial health of the HRA although, as with any expenditure, it
does place pressure on rent levels in the short and medium terms. All
projects, before commencement, are subject to a robust viability assessment
as part of the Affordable Housing Supply Programme grant funding eligibility
rules
4.25 The long-term positive impact on the financial sustainability of the HRA from
the development of new homes is outlined using the modelling from the
currently on-site development at Bonhill. This development delivers 28 new
homes including a number of large homes as set out in Table 6.
Table 6: Bonhill Gap Site Housing Mix
4.26 Key Financial Assumptions and Model – Bonhill (28 homes)
Rental Income – The site is projected to generate £213,552 of rental income
in year 1. For future years it has been assumed rent will increase by 3% per
annum (general assumption of 2% CPI plus 1%)
Capital Costs and Loan Charges - The site has a development capital cost
of £6.983m (£249,375 per unit) of which £3.360m was assumed to be funded
through Scottish Government Affordable Housing Supply Grant. This
therefore requires net borrowing of £3.622m.  Based on borrowing £3.622m
over 60 years, and assuming a loan interest rate of 4.25%, the Council would
repay £10.011m over the life of the loan, including repayment of the principal
and the interest. This equates to £166,850 per annum.
Operating Costs – Operating costs are assumed to be £2,750 per unit so 28
homes at £2,750 per annum = £77,000.  For future years highlighted in Table
7 it has been assumed operating costs will increase by 2% per annum
(general assumption of 2% CPI). Operating costs includes all management
and maintenance costs including staff, responsive repair and maintenance
costs and includes provision for void periods and bad debt provision.
Replacement Costs – Assumption there will be no replacement costs in
years 1-15 then fixed costs of £1,500 per unit per annum so a total of £42,000
per annum.
House Size Sustainability Standard New Homes
1bed wheelchair Net Zero 4
1 bed general needs Net Zero 10
2 bed wheelchair Net Zero 3
3 bed general needs Net Zero 3
4 bed general needs Net Zero 2
5 bed general needs Net Zero 4
7 bed general needs Net Zero 2

Page 15

Number of Tenants – 10,500
Table 7: - Bonhill Gap Site Housing Development Financial Modelling
Year Rent Revenue
(£)
Operating
Costs (£)
Capital
Replacement
(£)
Net
Revenue
(£)
Loan
Repayment
(£)
Surplus
/Deficit
(£)
Cumulative
Surplus (£)
Per Tenant
Impact (£)
1 213,552 77,000 0 136,552 166,850 -30,298 -30,298 -2.89
5 240,355 83,347 0 157,008 166,850 -9,842 -101,184 -9.64
7 254,992 86,714 0 168,278 166,850 1,428 -104,055 -9.91
10 278,637 92,022 0 186,615 166,850 19,765 -63,492 -6.05
13 304,474 97,654 0 206,820 166,850 39,970 35,779 3.41
15 323,016 101,599 0 221,417 166,850 54,567 137,497 13.10
16 332,707  103,631 42,000 187,076 166,850 20,226 157,723 15.02
20 374,465 112,200 42,000 220,265 166,850 53,415 320,281 30.50
22 397,270 116,733 42,000 238,537 166,850 71,687 454,373 43.27
30 503,250 136,772 42,000 324,478 166,850 157,628 1,400,255 133.36 
4.27 Table 7 shows, over the 60-year borrowing life, the cost and benefit to HRA.
The Bonhill Development, based on this modelling, achieves:
 Cash-flow positive from Year 7
 Cumulative Surplus from Year 13
 A 30-year surplus of £1.4m to support the wider HRA.
This evidences that the site is financially viable over its life.  Furthermore the
48% grant ratio and £249,375 per unit cost maintain the project within
affordability thresholds. The 28 new homes will also generate additional
council tax revenue. However, the financial modelling highlights a continued
need for rent increases to be higher than the CPI rate.
4.28 It should be noted that council tenants in new build council homes are subject
to a 15% rental premium and as a result will contribute more to the cost of
new home developments through this. Those tenants benefit with lower fuel
bills because of the superior energy efficiency performance of the new build
homes compared with existing stock.
4.29 The modelling summarised within this report conservatively includes a 60-
year lifetime of the new asset (council home). However, in reality our new
build homes will be a longer-term asset to the HRA of over 100 years.
4.30 The Bonhill development is one of the Council’s current developments within
our wider new home build programme More Homes West Dunbartonshire
which has approval to deliver 212 new homes before the end of 2027/28: -
Table 8: Current More Homes Delivery Programme
Willox Park, Dumbarton Ph1 17
Bank St, Alexandria 22

Page 16

4.31 Key Financial Assumptions and Model- More Homes Committed Programme
(212 homes)
The same modelling scenarios are applied as in Table 7 to this wider
programme, (for illustrative purposes it is assumed that all complete in year
1).
Rental Income – The More Homes Committed Programme is projected to
generate £1,618,752 of rental income in year 1.  For future years it has been
assumed rent will increase by 3% per annum (general assumption of 2% CPI
plus 1%)
Capital Costs and Loan Charges - The combined next phase developments
has a total development capital cost of £54.06m (£255k per unit) of which
£25.44m (£120k per home) is projected to be funded through Scottish
Government Affordable Housing Supply Grant. This therefore requires net
borrowing of £28.62m.  Based on borrowing £28.62m over 60 years, and
assuming a loan interest rate of 4.25%, the Council would repay £79.53m
over the life of the loan, including repayment of the principal and the interest.
This equates to £1.33m per annum.
Operating Costs – Operating costs are assumed to be £2,750 per unit so
212 homes at £2,750 per annum = £583k.  For future years highlighted in
Table 9 it has been assumed operating costs will increase by 2% per annum
(general assumption of 2% CPI). Operating costs includes all management
and maintenance costs including staff, responsive repair and maintenance
costs and includes provision for void period and bad debt provision.
Replacement Costs – Assumption there will be no major component
replacement costs in years 1-15 then fixed costs of £1,500 per unit per annum
so a total of £318k per annum.
Number of Tenants – 10,500
Table 9: - More Homes committed new build programme financial
modelling.
Bonhill Gap Sites, Alexandria 28
Dennystoun Forge, Dumbarton 20
West Thomson St, Clydebank 42
Willox Park Dumbarton Ph 2 22
Ottawa Crescent, Dalmuir 21
28 Bridge St, Alexandria 8
Silverton, Dumbarton 9
O’Hare, Alexandria 6
Queen Mary Avenue, Clydebank 17
Total 212

Page 17

Year Rent
Revenue (£)
Operating
Costs (£)
Capital
Replacement
(£)
Net
Revenue
(£)
Loan
Repayment
(£)
Surplus/
Deficit (£)
Cumulative
Surplus (£)
Per
Tenant
Impact
(£)
1 1,618,752 583,000 0 1,035,752 1,325,443 -289,691 -289,691 -27.54
9 2,050,587 679,969 0 1,371,618 1,325,443 46,175 -1,156,316 -110.12
10 2,112,105 693,348 0 1,420,757 1,325,443 95,314 -1,061,002 -101.05
15 2,448,509 761,347 0 1,694,162 1,325,443 368,719 216,694 20.64
16  2,521,964 775,174 318,000 1,428,790 1,325,443 103,347 320,041 30.48
20 2,838,493 831,262 318,000 1,689,231 1,325,443 363,788 1,373,238 130.78
25 3,290,591 903,251 318,000 2,069,340 1,325,443 743,897 4,306,661 410.16
30 3,814,697 977,528 318,000 2,519,169 1,325,443 1,193,726 9,345,623 890.06 
4.32 Table 9 shows, over the 60-year borrowing life, and the cost and benefit to the
HRA. The More Homes Committed New Build Programme based on this
modelling, achieves:
 Cash-flow positive from Year 9
 Cumulative Surplus from Year 15
 A 30-year surplus of £9.3m to support and strengthen the wider HRA.
This evidences that the sites are financially viable over its life.  Furthermore,
the projected 47% grant ratio and £255k per unit cost maintain the project
within the affordability thresholds. The 212 new homes will also generate
additional council tax revenue.
4.33 The financial assessment modelled in Table 9 has been scenario tested
looking at the following sensitivity scenarios: -
 Scenario 1 – 4% per annum rent increases (CPI (2%) + 2%) and 2% cost
inflation.
 Scenario 2 – 5% per annum rent increases (CPI (2%) +3 %) and 2% cost
inflation.
 Scenario 3 – 6% per annum rent increases (CPI (2%) + 4%) and 2% cost
inflation.
 Scenario 4 – 5% per annum rent increases (CPI (3%) = 2%) and 3% cost
inflation (CPI uprated)
Table 10 - More Homes committed new build programme Sensitivity
Testing
Scenario First Positive
Annual Surplus
Cumulative Surplus
Achieved
Year 30 Surplus/Deficit
(£)
Baseline case (Rent CPI at 2%
plus 1% = 3% Operating Costs
CPI at 2%)
Year 9 Year 15 +£1,193,726
Scenario 1 (Rent CPI at 2% plus
2% = 4% Operating Costs CPI at
2%)
Year 8 Year 14 +£1,750,000
Scenario 2 (Rent CPI at 2% plus
3% = 5% Operating Costs CPI at
2%)
Year 7 Year 12 +£2,500,000
Scenario 3 (Rent CPI at 2% plus
4% = 6% Operating Costs CPI at
2%)
Year 6 Year 10 +£3,500,000
Scenario 4 ( (Rent CPI at 2%
plus 3% = 5% Operating Costs
CPI at 2% plus 1% = 3%)
Year 8 Year 13 +£2,100,000

Page 18

Table 10 illustrates that in all the modelled scenarios the project will
breakeven significantly within the 60-year borrowing period meaning the
project is viable overall. However, it again highlights a need for rent increases
to be higher than the CPI rate in the coming period to protect the financial
health of the HRA. 
4.35 Notwithstanding the positive long-term benefit to the HRA the Council’s  
home building programme also has a short to medium term negative impact
on rent levels with the examples above in Table 7 and Table 9 highlighting
this.
4.36 As part of the Housing Capital Investment Programme approved by Council in
March 2025 it was assumed there would be a £42.5m allocation in
uncommitted new build projects up until 2030/31, of which £7m has been
allocated against new approved projects included in the Table 8 of this report
leaving £35.5m budget provision exclusive of affordable housing supply
programme grant funding.  A number of future sites are identified in the West
Dunbartonshire Strategic Housing Investment Plan which was approved by
the Housing and Communities Committee in November 2025, these include
the following future development opportunities. These future development
opportunities will be subject to a robust financial and viability assessment prior
to any formal approval.  It should also be noted that other future development
opportunities could be identified through the Local Development Plan for the
delivery of social housing and the sites identified below are therefore not
exhaustive:
More Homes Option Analysis
4.37 While the delivery of new homes is a high-confidence strategy for
strengthening the long-term health of the HRA and is the main route to tackle
our housing and homelessness emergency, it adds to HRA costs until such
time as the project returns an in-year surplus.  To assess the optimum short
term delivery model for the development of new Council Homes the following
options have been assessed:
Option 1 – 45 homes a year - Current Delivery Model = 45 new homes per
year (180 new homes) for the 4 years 2028/29-2031/32 (The additional cost of
borrowing is £292k in year 1, £584k in year 2, £876k in Year 3 and £1.168m
from Year 4-Year 60)
Option 2 – 25 homes a year - Revised Delivery Model = 25 new homes per
year (100 homes) for the 4 years 2028/29-2031/32 (The additional cost of
borrowing is £163k in year 1, £325k in year 2, £488k in Year 3 and £650k
from Year 4-Year 60)
Artizan Centre, Dumbarton
North Mountblow, Clydebank
Gray Street, Alexandria
Queens Quay Site C, Clydebank
Edinbarnet, Faifley
Skypoint, Faifley
Central Radnor Park, Clydebank
Sheltered Housing Regeneration, Various

Page 19

Option 3 – No investment in new homes over the four-year period 2028/29-
2031/32. (while no additional borrowing costs will be required it will lead to
reduced projected income to the HRA and increased expenditure to the
Council’s General Fund through higher homelessness and lower council tax
income than would otherwise be the case).
4.38 West Dunbartonshire continues to be in midst of a housing emergency with
5,688 households on the Council waiting list as of 30 September 2025.
Furthermore, there are 424 homeless households and 257 children
experiencing homelessness. In the last quarter of 2025 over 90 households
required to be placed in bed and breakfast accommodation.  This emphasises
that the need for more Council housing is acute, and therefore the risks
associated with Option 3, with no further investment in new homes, will
increase homelessness and not contribute to the longer-term financial health
of the HRA.  On that basis the officer recommendation is not to progress
Option 3.
4.39 Research undertaken by Policy Scotland/Cyrenians estimates the cost of an
incidence of homelessness to a local authority at £23k.  It would also mean
the Council would lose over a 4-year period £32m of available grant funding.
4.40 The delivery of these new homes within Option 1 and Option 2 in as yet
unknown development sites, has been modelled in Tables 11 and 13 below
and demonstrates consistent outcomes as the current development
appraisals modelled above for Bonhill and the Committed More Homes
Programme.
Option 1 – (45 homes a year)
Rental Income – The proposal is projected to generate £351k of rental
income in year 1. For future years it has been assumed rent will increase by
3% per annum (general assumption of 2% CPI plus 1%).
Capital Costs and Loan Charges – Option 1 would have a development
capital cost of £46.8m (£260k per home) of which £21.6m (£120k per home)
is projected to be funded through Scottish Government Affordable Housing
Supply Grant. This therefore requires net borrowing of £25.2m.  Based on
borrowing £25.2m over 60 years, and assuming a loan interest rate of 4.25%,
the Council would repay £68.33m over the life of the loan, including
repayment of the principal and the interest. This equates to £1.17m per
annum.
Operating Costs – Operating costs are assumed to be £2,750 per unit for the
45 homes in year 1 this would be £123,750.  For future years it has been
assumed and illustrated within Table 11 operating costs will increase by 2%
per annum (general assumption of 2% CPI). Operating costs includes all
management and maintenance costs including staff, responsive repair and
maintenance costs and includes provision for void period and bad debt
provision.

Page 20

Replacement Costs – Assumption there will be no replacement costs in
years 1-15 then fixed costs of £1,500 per unit per annum so a total of £318k
per annum.
Number of Tenants – 10,500
Table 11 – Option 1 – 45 new homes a year
Year Rent
Revenue
(£)
Operating
Costs (£)
Capital
Replacement
(£)
Net Revenue
(£)
Loan
Repayme
nt (£)
Surplus/
Deficit (£)
Cumulative
Surplus (£)
Per
Tenant
Impact
(£)
1 351,000 123,750 0 227,250 292,000 -64,750 -64,750 -6.17
2 722,060 252,225 0 469,835 584,000 -114,165 -178,915 -17.04
3 1,114,904 388,000 0 726,904 876,000 -149,096 -328,011 -31.24
4 1,468,453 527,000 0 941,453 1,168,000 -226,547 -554,558 -52.82
5 1,512,506 537,540 0 974,966 1,168,000 -193,034 -747,592 -71.20
10 1,753,408 593,488 0 1,159,920 1,168,000 -8,080 -1,169,922 -111.42
11 1,806,010 605,358 0 1,200,652 1,168,000 32,652 -1,137,270 -108.31
15 2,032,680 655,258 0 1,377,422 1,168,000 209,422 -571,875 -54.46
20 2,356,433 723,457 270,000 1,362,976 1,168,000 194,976 -124,536 -11.86
21 2,427,126 737,926 270,000 1,419,200 1,168,000 251,200 126,664 76.68
25 2,731,752 798,755 270,000 1,663,997 1,168,000 495,997 1,732,209 165.00
30 3,166,848 877,789 270,000 2,036,059 1,168,000 868,059 5,295,797 504.36 
4.41 Table 11 shows, over the 60-year borrowing life, the cost and benefit to the
HRA. Option 1 based on this modelling, achieves:
 Cash-flow positive from Year 11
 Cumulative Surplus achieved at Year 21
 A 30-year surplus of £5.3m to support and strengthen the wider HRA.
This evidences that the site is financially viable over its life.  Furthermore, the
projected 46% grant ratio and £260k per unit cost maintain the project within
the affordability thresholds. The 180 new homes will also generate additional
council tax revenue.
4.42 The financial assessment modelled in Table 11 has been scenario tested
looking at the same sensitivity scenarios highlighted in 4.33 of this report but
have been stress tested further through the introduction of scenarios 5 and 6 -
o Scenario 5 – Borrowing rate increased to 5%
o Scenario 6 – Borrowing rate increased to 10%

Page 21

Table 12 Option 1 Sensitivity Testing
Scenario First Positive Annual
Surplus
Cummulative Surplus
Achieved 
Year 30
Surplus/Deficit
(£)
Baseline case (Rent CPI at 2% plus
1% = 3% Operating Costs CPI at 2%)
Year 11 Year 21 +£868k
Scenario 1 (Rent CPI at 2% plus 2% =
4% Operating Costs CPI at 2%)
Year 10 Year 20 +£1,650,000
Scenario 2 (Rent CPI at 2% plus 3% =
5% Operating Costs CPI at 2%)
Year 9 Year 19 +£2,300,000
Scenario 3 (Rent CPI at 2% plus 4% =
6% Operating Costs CPI at 2%)
Year 8 Year 17 +£3,200,000
Scenario 4 ( (Rent CPI at 2% plus 3%
= 5% Operating Costs CPI at 2% plus
1% = 3%)
Year 10 Year 20  +£1,950,000
Scenario 5 (as with baseline), but
with 5% capital borrowing rate
Year 13 Year 27 +£756k
Scenario 6 (as with baseline), but
with 10% capital borrowing rate
Year 35 Year 57 -£444k 
4.43 Option 2 (25 homes a year)
Rental Income – The site is projected to generate £195k of rental income in
year 1. For future years it has been assumed rent will increase by 3% per
annum (general assumption of 2% CPI plus 1%)
Capital Costs and Loan Charges – Option 2 would have a development
capital cost of £26m (£260k per home) of which £12m (£120k per home) is
projected to be funded through Scottish Government Affordable Housing
Supply Grant. This therefore requires net borrowing of £14m.  Based on
borrowing £14m over 60 years, and assuming a loan interest rate of 4.25%,
the Council would repay £38.03m over the life of the loan, including
repayment of the principal and the interest. This equates to £650k per annum.
Operating Costs – Operating costs are assumed to be £2,750 per unit
(£68,750 in year 1).  For future years it has been assumed and illustrated in
Table 13 operating costs will increase by 2% per annum (general assumption
of 2% CPI). Operating costs includes all management and maintenance costs
including staff, responsive repair and maintenance costs and includes
provision for void period and bad debt provision.
Replacement Costs – Assumption there will be no replacement costs in
years 1-15 then fixed costs of £1,500 per unit per annum so a total of £150k
per annum.
Number of Tenants – 10,500

Page 22

Table 13 – Option 2 - 25 homes per year
Year Rent
Revenue (£)
Operating
Costs (£)
Capital
Replacement
(£)
Net
Revenue
(£)
Loan
Repayment
(£)
Surplus/D
eficit (£)
Cumulative
Surplus (£)
Per Tenant
Impact (£)
1 195,000 68,750 0 126,250 162,500 -36,250 -36,250 -3.45
2 401,700 140,250 0 261,450 325,000 -63,550 -99,800 -9.50
3 619,200 215,625 0 403,575 487,500 -83,925 -183,725 -17.50
4 815,808 293,250 0 522,558 650,000 -127,442 -311,167 -29.63
5 840,282 299,115 0 541,167 650,000 -108,833 -420,000 -40.00
10 974,117 330,247 0 643,870 650,000 -6,130 -662,731 -63.12
11 1,003,340 336,852 0 666,488 650,000 16,488 -646,243 -61.55
15 1,129,267 364,619 0 764,648 650,000 114,648 -338,856 -32.27
19 1,270,999 394,675 150,000 726,324 650,000 76,324 19,436 1.85
20 1,309,129 402,568 150,000 756,561 650,000 106,561 125,997 12.00
21 1,348,403 410,620 150,000 787,783 650,000 137,783 263,780 25.12
25 1,517,639 444,468 150,000 923,171 650,000 273,171 1,147,969 109.33
30 1,759,360 490,728 150,000 1,118,632 650,000 468,632 3,087,753 294.07 
4.44 Table 13 shows again, over the 60-year borrowing life, the cost and benefit to
the HRA. Option 2 based on this modelling, achieves:
 Cash-flow positive from Year 11
 Cumulative Surplus achieved from Year 19
 A 30-year surplus of £3m to support and strengthen the wider HRA.
This evidences that the site is financially viable over its life.  Furthermore, the
projected 46% grant ratio and £260k per unit cost maintain the project within
the affordability thresholds. The 100 new homes will also generate additional
council tax revenue per annum.
4.45 The financial assessment modelled in Table 12 has been scenario tested
looking at the same sensitivity scenarios highlighted in the previous modelling
example and this is shown at Table 14:
Table 14 – Option 2 – Sensitivity Analysis
Scenario First Positive Annual
Surplus
Cummulative
Surplus
Achieved
Year 30
Surplus/Deficit
(£)
Baseline case (Rent CPI at 2% plus 1% =
3% Operating Costs CPI at 2%)
Year 11 Year 19 +£468k
Scenario 1 (Rent CPI at 2% plus 2% = 4%
Operating Costs CPI at 2%)
Year 10 Year 18 +£1,050,000
Scenario 2 (Rent CPI at 2% plus 3% = 5%
Operating Costs CPI at 2%)
Year 10 Year 18 +£1,500,000
Scenario 3 (Rent CPI at 2% plus 4% = 6%
Operating Costs CPI at 2%)
Year 9 Year 17 +£2,200,000
Scenario 4 (Rent CPI at 2% plus 3% = 5%
Operating Costs CPI at 2% plus 1% =
3%)
Year 10 Year 18 +£1,250,000
Scenario 5 (as with baseline), but with
5% capital borrowing rate
Year 14 Year 27 +357k
Scenario 6 (as with baseline), but with
10% capital borrowing rate
Year 41 Not within 60
years
-£552k

Page 23

4.46 A further detailed comparison of Option 1 and 2 is outlined in Table 15 below.
Option 1, in terms of a projected 80% higher borrowing requirement to deliver
the 45 homes a year places added risk to the shorter-term health of the
Housing Revenue Account with the required additional annual capital spend. 
4.47 Option 2 balances tackling ongoing housing and homelessness pressures in
the midst of a housing emergency with maintaining shorter term financial
sustainability of the HRA and the need to avoid overstretching borrowing
capacity.  It may be more prudent at this time to plan forward with Option 2
and review that on an ongoing basis to see if additional financial capacity
could deliver much needed more homes without adding financial risk to the
HRA the financial capacity will be investigated through the planned HRA
Business Plan refresh exercise. It is therefore the officer recommendation to
plan ahead with Option 2.    
Table 15 Option 1 and 2 comparison
Metric Option 1
45 homes/year programme
(180 homes)
Option 2 
25 homes/year programme
(100 homes)
Difference 
(45 vs 25)
Notes / Reason for Difference
Total homes 180 100 +80 homes  Scale difference 
Total Borrowing
Requirement
£25.2m £14m +£11.2m 80% additional borrowing
requirement with Option 1
proportional to number of
homes.
Cumulative Surplus
Achieved
21 years 19 years +2 years Option 1 longer as larger
programme includes higher
absolute borrowing. 
First Positive Annual
Surplus 
Year 11 (£33k) Year 11 (£16k) +£17k Both achieve first positive
annual surplus in Year 11
positively impacting on the
financial health of the HRA
Year 1 Surplus/Deficit -£64,750 -£36,250 -£28,500  Only 45/25 of the 180/100
delivered.  Proportional to
number of new homes.
Year 2 Surplus/Deficit -£114,165 -£63,550 -£50,615  Only 90/50 of the 180/100
delivered.  Proportional to
number of new homes
Year 3 Surplus/Deficit -£149,096 -£83,925 -£65,171  Only 135/75 of the 180/100
delivered.  Proportional to
number of new homes
Year 4 Surplus/Deficit -£226,547 -£127,442 -£99,105  Full capacity reached; Annual
deficits increase to highest point
in the modelling.
Year 5 Surplus/Deficit -£193,034 -£108,833 -£84,201  Deficits begin to lessen from
this point in both scenarios. 
Year 10 Cumulative
Surplus
-£1,169m -£662,731 -£507,191  Both negative at Year 10; larger
programme has bigger absolute
deficit
Year 20
Cumulative 
Surplus 
-£124,536 +£125,997 -£250,533 Option 2 has a positive
cumulative surplus at this point,
it is a further year before Option
1 (Year 21)achieves this. 
Year 30 Cumulative
Surplus
£5.3m £3.1m +£2.2m Larger scale eventually
produces higher surplus despite
higher borrowing costs 
4.48 The Scottish Government have committed to providing additional resource to
the delivery of new housing. It is recommended that, in addition to existing
new build plans will deliver 212 homes, the Council commits to the delivery of
an additional 25 new homes a year from 2028/29 to 2031/2032 (Option 2, 100
additional homes). This resource can be met within the existing housing

Page 24

capital investment programme from the future new build and regeneration
budget line. 
4.49 The additional resource committed by the Scottish Government is up to
£4.9bn investment over the next four years for the delivery of new homes, an
increase of around 20% on the current affordable housing supply programme
budget,  the additional funding will see an increased Resource Planning
Allocation (RPA) allocation for all Scottish local authorities and the
introduction of multiyear funding allocations to strengthen the delivery of
strategic housing investment plans. Once the Scottish Government makes
formal announcements on this aspect of the Action Plan, such as the
increased funding and how this will be distributed to local authorities, the
Council will review the programme with a focus on maximising investment
opportunities and ensuring the delivery of affordable housing continues to
meet the needs of West Dunbartonshire’s communities.
4.50    As indicated previously he Council’s More Homes West Dunbartonshire
approach has evidenced strong support from council tenants. The transfer led
approach to the allocation of new build housing has also strengthened support
for the new build programme with tenants, as this approach prioritises existing
council tenants with a housing need on the allocation of the new homes, and
fosters additional lets required to support the wider housing access system.
4.51 An example of this has seen the three most recently completed new home
developments (Clydebank East/Mount Pleasant/Pappert) significantly
contributing to meeting wider housing need within West Dunbartonshire
communities and combined have contributed to lifting 124 children out of
homelessness and into a secure tenancy. 
4.52   The plans and actions highlighted within this report, including the partnership
approach with tenant representatives, has laid the foundations for the annual
rent consultation exercise which completed in January 2026 and will inform
the Rent Setting and Capital Investment report to West Dunbartonshire
Council in March 2026.
5. People Implications
5.1 The delivery of the Housing Capital Investment Programme is managed
through existing resources.
6. Financial and Procurement Implications
Financial
6.1 Housing and Finance officers will continue to assess the ongoing affordability
of future investment and spending plans within the context of the Housing
Revenue Account Business Plan. Current plans are assessed as being within
the affordability thresholds.
6.2 The viability assessments of new home development opportunities factor in
assumed grant benchmark levels, if any assessment highlights viability
concerns housing officers will initially engage with the Scottish Government
More Homes Team to assess additional grant funding requirements to

Page 25

ensure project viability.  West Dunbartonshire Council has a long-standing
positive relationship with the Scottish Government team in this regard and
have successfully worked collaboratively to ensure above benchmark grant
levels on a number of new home projects.
Procurement
6.3 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within the report will continue to
be prioritised.
6.4 All procurement activity conducted by the Council, more than £2m is
subject to a contract strategy. The contract strategy for new housing
development within the HRA capital programme will be developed by the
Corporate Procurement Unit in consultation with housing development
officers. The contract strategy will include but is not limited to; contract scope,
service forward plan, the market, procurement model, and routes – including
existing delivery vehicles, roles and responsibilities, risks, issues and
opportunities and on-going contract management. Opportunities to maximise
the positive social, economic, and environmental impact for the Council
through the relevant procurement processes will be developed in line with
procurement policy.
7. Risk Analysis
7.1 Interest rate increases are the key risk to HRA finances with regards all
investment programmes.  If interest rates rise there will be a proportionate
increased impact on rent levels without action to reduce other costs. The
interest rate assumptions for outstanding capital debt are based on advice
received from the Council’s external treasury advisors. Borrowing rates are
influenced by a range of macro-economic factors and there is a high likelihood
that the interest rate charged on outstanding council debt will be different from
the figure used in financial planning. The current risk approach is to tolerate
this financial risk given the scope to revise future HRA revenue and HRA
capital plans to reduce cost and minimise the impact on future rent levels
which is highlighted within this report.
7.2 The risk from higher interest rates is further mitigated by having more
fixed/long term borrowings as opposed to shorter term borrowing. HRA total
capital debt is expected to be circa £414m in 2027. If the pooled interest rate
was 2% higher on March 27 (6.25% as opposed to 4.25%) then the HRA debt
servicing costs would be around £8m higher, placing upward pressure on
rents to meet the increased costs. However, this scenario is unlikely.   
7.3 The other financial risks to the ongoing challenging financial position of the
HRA are included within this report.  This includes that without the proposed
remedial actions in terms of spending and investment commitments that
impact on borrowing levels, rent increases will be required in future years
which could risk the affordability of council housing. .
7.4 A further risk identified is if spending decisions are not aligned to service and
tenant priorities there is a risk of heightened regulatory engagement and
decreasing levels of tenant satisfaction which are currently at a record high

Page 26

level, however this will be mitigated through the approved processes including
the HRA VFM Group and the Joint Rent Group. This risk is compounded if
planned investment is not delivered in terms of current and future Council
homes the Council will fail to meet identified housing need, which will lead to
increased homelessness, time in temporary accommodation, and will result in
increased pressure to other Council and HSCP budgets.
7.5 West Dunbartonshire continues to be in midst of a local and national housing
emergency with the second highest homelessness rate in Scotland the need
to maintain and increase housing supply is acute, if this strategic aim was
compromised an exponential risk would be placed on the Council’s ability to
meet its statutory requirements without detrimentally impacting on the wider
financial health of the Council.
8 Environmental Sustainability
8.1 Our current and future approach to strategic housing asset management will
continue to prioritise a ‘zero carbon’ approach to decision making and
deliverability and this will be done the aims of the Housing Asset Management
Strategy and the Council’s Climate Change Strategy.
9. Equalities Impact Assessment (EIA)
9.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
10. Consultation
10.1 Consultation has taken place with all housing services with a collective
responsibility in delivering services to council tenants and finance and legal,
the paper also supports the ongoing consultation and involvement in the
implementation of actions with tenant representatives.
11. Strategic Assessment
11.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
11.2 Having considered all the Council’s strategic priorities, this report, and the
provision of new supply social housing for rent contributes to all the council’s
strategic priorities.
Peter Barry
Chief Officer, Housing
Date: 11th February 2026
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk

Page 27

Appendices: None
Background Papers: Strategic Housing Investment Plan 2026-2031
60 new build viability assessment tables
Wards Affected: All