WEST DUNBARTONSHIRE COUNCIL 
Report by the Chief Officer, Housing 
Housing and Communities Committee: 25th February 2026 
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme 
1. Purpose 
1.1      This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme. 
2. Recommendations 
2.1 It is recommended that the Housing and Communities Committee: 
(i) Notes the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach: 
(ii) Notes the completion of the Gilmour Avenue development in January
2026; and 
(iii) Invite the Chief Officer, Housing, to carry out the procurement of, and to
subsequently award, the contract up to budgeted costs for the new build
development at Ottawa Crescent, Dalmuir, Clydebank. 
3. Background 
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over one thousand new affordable homes in
West Dunbartonshire and includes the Council’s own new home building
programme. 
3.2 The Strategic Housing Investment Plan (SHIP) 2026-2031, outlining West   
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2025. The SHIP outline plans to
contribute to meet the Council Administration’s aim of delivering 2500 new
affordable and social rented homes over the 10-year period 2022-2032. 
ITEM 8

Page 2

4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 The delivery of new affordable homes has a key role to play in revitalising
local economies and assisting with wider economic recovery plans, negating
the impacts of the current cost of living crisis and combatting poverty,
principally child and fuel poverty. It is also clear that the need for affordable
homes has and will increase in the current ongoing economic environment
both in a local and national context. 
4.2 In July 2025, Shelter published its study The Social Value of New Social
Housing in Scotland which calculated that each new social home in Scotland
can generate on average £11,639 in social value within just six months of a
tenant moving in. This figure includes a £990.44 saving to the public purse
and £10,648 in wellbeing value to the tenant, who benefits from improved
opportunities such as securing employment, better health, transport
connections, and reduced housing costs, thanks to a new social home.  The
research report’s key conclusion is that it has shown that new social housing
is driving improvements in social, economic and health outcomes for its
residents, and where this impact is achieved, there is huge capacity for
significant preventative savings to wider society. 
4.3 The Council’s More Homes West Dunbartonshire approach is an ambitious
plan that aims to continue the positive momentum of the delivery of much
needed Council homes in West Dunbartonshire and will significantly assist the
Council’s aim to deliver 2500 new social and affordable homes by 2032. 
4.4 As the largest affordable housing developer in West Dunbartonshire, the
Council has identified a number of development sites for new council homes
to address existing and new housing need. The design of these homes
provides sustainable homes using innovative technology and delivering on our
low carbon ambitions including Passivhaus and other net zero carbon
opportunities.  We anticipate the new homes delivered by the Council will
have a minimum lifespan of beyond 100 years. 
4.5 The Council’s More Homes West Dunbartonshire approach has evidenced
strong support from council tenants and was recently highlighted as one of the
top two key future spending priority areas for tenants through the
comprehensive tenant satisfaction survey reported to the Housing and
Communities Committee in February 2025. 
4.6 In September 2025, the Council’s major housing led regeneration project
which overseen the development of 88 new council homes at Clydebank East
was awarded the prestigious Herald Property Awards - Affordable Housing
Development of the Year Award recognising this high-quality housing
development.  This development was also the runner up in the Scottish
Housing Awards 2025 in the Excellence in Regeneration and Sustainability
category.

Page 3

4.7 The three most recent new home developments completed In West
Dunbartonshire (Pappert, Clydebank East, and Mount Pleasant) have
significantly contributed to meeting housing need and combined have
contributed to lifting 121 children out of homelessness and into a secure
tenancy.   
4.8 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  An update on
each current development site is provided below: - 
Willox Park Phase 1, Doveholm, Dumbarton 
The Phase 1 development of seventeen new homes for the elderly at a former
care home site will comprise of the housing mix below. 
This will be our first project using a ground source heat network to deliver heat
and hot water. 
Current tenants at Willox Park have been consulted throughout the design
process and this has continued with the contractor holding Q&A sessions. 
We are currently working to make sure the process of moving into the new
facility is as easy and streamlined as possible. The units have all been
allocated. 
The original move to the new facility was planned for 30th November 2025.
Unfortunately, there was a delay in the programme due to issues with the
fabrication of the steel balconies for the new homes. The new completion date
was achieved on 9th February 2026, and phased handovers will take place
over a full two-week period. The tenants have been supported on their moving
arrangements which the Council has facilitated in full. 
Willox Park Phase 2 
Feasibility studies for the site are now showing an increased site capacity of
22 new homes from 21 homes The current proposed housing mix is
highlighted below: - 
House Type Sustainability Standard Number of New
Homes
Flat 2bed/3person  Net Zero 2
Flat 1 bed/2person Net Zero 15
House Type Sustainability
Standard
Number of
New Homes
Bungalow 1bed/2person Net Zero 14
Bungalow 1bed/2person
w/c
Net Zero 2
Cottage Flat 1bed/2person
UF
Net Zero 3

Page 4

McTaggart Construction have been awarded the design and build contract
which will also include the demolition of the existing homes following
completion of Phase 1. All homes are being designed to housing for varying
needs standards and dementia friendly principles to encourage ageing in
place and inclusive living. 
Phase 2 is part of the wider housing regeneration plans for the Willox Park
area and priority to the new homes in Phase 2 will be given to the tenants
within Phase 1 in the first instance. 
Gilmour Avenue, Hardgate 
This 2x 3-bedroom development was completed and handed over in January
2026. 
The Health and Social Care Partnership have identified occupants for one of
the houses and a tenant household on the transfer list have been allocated for
the other. 
Bonhill Gap Site Strategy 
The 28 units of housing at Braehead (17 homes) and Campbell Street (11
homes) went on site in August 2025 and are scheduled to complete within a
56-week period.   
The Council have been successful in achieving above benchmark Affordable
Housing Supply Programme funding from the Scottish Government amount to
over £131k per home. 
The sites are currently facilitating work experience for West Dunbartonshire
residents who have presented from the Working4U Project Search team. 
The tender for the O’Hare project (6 units) was returned on 30th October. The
evaluation process has now been complete, and JR Group have been
successful with a tender price of £1.5m We anticipate grant levels to be
consistent with the award for the wider Bonhill Gap site development. 
The housing mix of the full Bonhill Gap Site development programme is
highlighted in the table below and will include 8 new large family homes to
meet the key identified need: -
Cottage Flat 1bed/2person
LF
Net Zero 3
House Size Sustainability Standard Number of New
Homes
1bed wheelchair Net Zero 4
1 bed general needs Net Zero 16
2 bed wheelchair Net Zero 3
3 bed general needs Net Zero 3
4 bed general needs Net Zero 2

Page 5

Bank Street, Alexandria 
The development will consist of twenty-two sheltered/amenity housing units in
partnership with the HSCP. A site start was achieved in October 2025 and is
scheduled for completion in late January 2027. 
House Type Sustainability Standard Number of New
Homes
Flat 1bed/2person w/c Net Zero 22
Communal Room Net Zero 1
Staff Office Net Zero 1 
As reported to the August Housing and Communities Committee the tender
return was some £2.4m below the initial estimated cost.  This development as
with the development at Willox Park, involved the tenants at Gray Street who
have been consulted throughout the design process and will be assisted to
make the transition as smooth as possible. 
The Council is currently undertaking feasibility studies in terms of future
options for Gray Street, Alexandria. Following work on the feasibility the
optimum house type and number of homes (mix of cottage flats and family
houses) would be circa 15 new homes to meet housing need. 
West Thomson Street (former Clydebank Health Centre) 
Demolition of the former Clydebank health centre building was completed in
late 2024. 
The proposed development will provide 42 new homes - 15 units of family
housing and 27, fully accessible, sheltered/amenity homes for the elderly. The
proposed housing mix is noted below: - 
5 bed general needs Net Zero 4
7 bed general needs Net Zero 2
House Type Bed Number WCH
Sheltered/Amenity
Flat
1 27 27
Cottage Flat 1 2 2
Duplex Cottage Flat 3 2 
House 5 2 
House 4 5 
House 3 4 
Total 77 42 29

Page 6

The planning application for this site was submitted 8th October 2025. We are
continuing to temporarily suspend lettings within the Young Street sheltered
housing complex unless in emergency circumstances as we complete the
consultative exercise which will see the sheltered/amenity new housing
provision potentially as replacement housing for the existing Young Street
tenants. As planned, The Young Street tenants will have the opportunity to
visit the Willox Park Phase 1 homes to give more informed feedback of a
potential new homes within this development. 
Following a competitive procurement exercise, CCG have been awarded the
contract for the design and build of the development. 
Dennystoun Forge Gypsy/Traveller Site 
The project has been scored and assessed as a priority in the new Strategic
Housing Investment Plan, with a proposed site start next financial year
2026/27. Our in-house design team and procurement colleagues are
proceeding to detail our plans, and discussions are taking place with other
council service areas in terms of assessing potential decant location options
to allow the works to the existing site to commence. 
Regular engagement continues with the Dennystoun Forge community
through monthly engagement meetings. The community are supported by
Minority Ethnic Carers of People Project (MECOPP) including representation
by the charity at these engagement sessions. The regular engagement has
been welcomed by the community and has with dedicated staff resource led
to a strong collaborative focus on the delivery of the new accommodation. 
Our focus remains on identifying suitable decant options and on what type of
chalet will be chosen for the final design. We are consulting on to what extent
home design can be customised to meet individual needs. 
The Scottish Government has now issued guidance on how these projects will
be funded through the Affordable Housing Supply Programme for 2026/27,
and this will influence our discussions going forward. 
Queen Mary Avenue, Clydebank (Clydebank Gap Sites) 
This development consists of 17 new units on the now demolished Queen
Mary Day Centres in Drumry which was acquired from the Council’s General
Fund at market value. 
House Type Sustainability Standard Number of New
Homes
1 bed/2 person  Cottage Flat Net Zero 10
2 bed/3 person WCH Cottage Flat Net Zero 1
3 bed/4 person Cottage Flat Net Zero 1
3 bedroom terraced house Net Zero 3
4 bedroom semi-detached Net Zero 2

Page 7

The Council’s appointed main contractor, CCG, has undertaken the design
stage for this site and successfully initiated a site start on the 20th October
with a planned programme of 61 weeks. This start date achieved is only one
year and one month after the demolition highlighting the success of the
procurement and design strategy for this project and the ability to deliver at
pace within the context of the current housing emergency. 
Dumbuie Avenue and Smollett Road (Silverton Regeneration) 
The council have been assembling this site for over 10 years, following
structural issues with the previous properties located within the sites which
were demolished in November 2024. 
Following approval from the Housing and Communities Committee to direct
award a design and build contract to deliver the Silverton regeneration project
up to the budgeted costs for project (Dumbuie Avenue and Smollett Road),
the project is now included within the Council’s Strategic Housing Investment
Plan 2026/27-2031/32 which was approved at the Housing and Communities
Committee of 19th November 2025. 
The contractor will be undertaking more detailed site investigation to
determine what is possible in terms of future housing mix. 
Ottawa Crescent 
The Council are working to enter into a design and build contract with the
current site owner to deliver 21 amenity homes, similar to the successful
developments at Creveul Court, Alexandria and Mount Pleasant, Old
Kilpatrick. This was assessed as a strategic housing priority in the Strategic
Housing Investment Plan approved in November. This is a flat site which
would lend itself well to this type of housing as we strategically prepare for an
ageing population. 
The proposed housing mix is provided below: 
House/Flat Type Bedrooms Number
Flat GF WCH 1 3
Flat with lift 2 9
GF Cottage Flat 1 2
FF Cottage Flat 1 2
Bungalow 1 5 
It is now planned to carry out a procurement exercise to award the design and
build construction contract to deliver the new homes at Ottawa Crescent,
Dalmuir, which would see the site acquired by the Council in advance of the
works commencement, within the approved capital budget.  As the site has
been granted planning permission, it could be on site as early as late Summer
2026.

Page 8

Buyback Programme 
Total number of properties purchased in 2025/26 financial year   29
Total Purchase Value                                                                    £2,733,500 
There are currently 6 properties under offer, 1 of which is a 5 apt bungalow
which will assist in meeting medical housing need in West Dunbartonshire. 
Below is a breakdown of purchases, into electoral wards for this financial
year: 
4.9 The Housing Service are continuously looking for opportunities to provide
additional new build council homes and will bring any potential site to the
Housing and Communities Committee with as much information as possible
as part of the regular More Homes update paper. 
5. People Implications 
5.1 The delivery of the More Homes delivery programme is managed through
existing resource within the Housing Development & Homelessness team
funded from the Housing Capital Investment Programme.   
6. Financial and Procurement Implications 
Financial 
6.1 The Council has to date delivered 586 new homes for social rent; these
additional homes bring council tax revenue of around £815k per year to West
Dunbartonshire Council. 
6.2 On 5 March 2025 supported by tenant representatives the Council approved
the Housing Capital Programme 2025-2030 which saw appropriate resources
committed to the delivery of new council homes in West Dunbartonshire.  A
PROPERTY SIZE PURCHASED
5 apt 6
4 apt 11
3 apt 3
2 apt 9
Buyback Acquisitions 2025/26 No of Acquisitions (as at 15/01)
Ward 1 - Lomond 3
Ward 2 – Leven 10
Ward 3 – Dumbarton 3
Ward 4 – Kilpatrick 4
Ward 5 – Clydebank Central  5
Ward 6 – Clydebank Waterfront 4
Total  29

Page 9

net expenditure budget of £69m for the affordable housing supply programme
inclusive of acquisitions is factored into the 5-year HRA Capital Programme. 
As it currently stands, it is anticipated that this programme will complete within
project life budget. 
6.3 Housing and Finance Officers will continue to assess the ongoing affordability
of future developments within the context of the Housing Revenue Account
Business Plan. 
Procurement 
6.4 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within 4.8 of this report will
continue to be prioritised. Where the contract award is less than £213,000,
authority is delegated to the Chief Officer in consultation with the Procurement
Manager to instruct the award of contracts for the planned revenue and
capital spend detailed in this report to suppliers providing the most
economically advantageous offer to the Council. 
6.5 All procurement activity conducted by the Council more than £2m is.
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include but is not limited to; contract scope,
service forward plan, the market, procurement model, and routes – including
existing delivery vehicles, roles and responsibilities, risks, issues and
opportunities and on-going contract management. Opportunities to maximise
the positive social, economic, and environmental impact for the Council
through the relevant procurement processes will be developed in line with
procurement policy. 
7. Risk Analysis 
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis. 
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel. 
7.3 Housing supply continues to be the key factor in terms of the national and
local housing emergencies and if not increased and/or demand reduced it will
lead to continued pressures on other Council and Health and Social Care
Partnership service areas such as Homelessness which will have negative
financial implications for the wider Council’s general fund.

Page 10

8 Environmental Sustainability 
8.1  The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy. 
9. Equalities Impact Assessment (EIA) 
9.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment. 
10. Consultation 
10.1 As part of a rent consultation exercise in 2025, 92% of respondents indicated
their support for the Council’s ambitious plans to deliver the Housing Revenue
Account (HRA) new council house build programme. In addition, there was
positive support for the wider delivery of new build housing as part of the
current Local Housing Strategy.  Regular updates on new build development
are provided to the West Dunbartonshire Tenants and Residents Organisation
at the bi-monthly liaison meetings. 
11. Strategic Assessment 
11.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire. 
11.2 Having considered all the Council’s strategic priorities, this report, and the
provision of new supply social housing for social rent contributes greatly to all
the Council’s strategic priorities. 
Peter Barry
Chief Officer, Housing 
Date: 11th February 2026 
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk 
Mikayla Deeley, Senior Housing Development Officer,
Housing Development and Homelessness Team,

Page 11

Housing and Employability: email mikayla.deeley@west-
dunbarton.gov.uk 
Appendices: None 
Background Papers: West Dunbartonshire Council’s Local Housing Strategy 
West Dunbartonshire Council’s Strategic Housing
Investment Plan     
Local Housing Strategy, Health Inequalities Impact
Assessment 
Wards Affected: All