Page 1

1
West Dunbartonshire Council
Report by Chief Officer, Housing
Housing and Communities Committee:  19 November 2025
Subject:  More Homes West Dunbartonshire Strategic Housing Investment
Plan 2026/27 – 2030/31
1. Purpose
1.1 This report seeks approval and summarises the key points set out in West
Dunbartonshire’s Strategic Housing Investment Plan (SHIP) 2026/27 –
2030/31, which details the priorities for investment in new affordable housing
in West Dunbartonshire.
2.        Recommendation
2.1      It is recommended that the Council:
i) Agree the draft SHIP 2026/27 - 2030/31 as appended to this report,
designed to continue the delivery of an ambitious programme of new
affordable homes in compliance with the West Dunbartonshire Local
Housing Strategy 2022 -2027;
ii) Note the SHIP is wider in scope than in recent years, with a
requirement by the Scottish Government to demonstrate more clearly
its contribution towards addressing local and national priorities such as
homelessness, child poverty and the housing emergency; and 
iii) Invite the Chief Officer, Housing to implement the investment plan
inclusive of the Council’s new home delivery in partnership with
relevant stakeholders. 
3. Background
3.1 The Scottish Government requires local authorities to submit a Strategic
Housing Investment Plan (SHIP) each year.  The core purpose of the SHIP is
to set out the strategic investment priorities for new affordable housing over a
five-year period to achieve the outcomes contained in the Local Housing
Strategy. 
3.2     The SHIP focuses on the delivery of affordable housing by location, type and
tenure and indicates how the programme will be resourced, particularly
through the Scottish Government’s Affordable Housing Supply Programme
(AHSP) funding and its Council House Building Programme component.
ITEM 10

Page 2

2
3.3      The SHIP sets out the funding priorities for new affordable housing in West
Dunbartonshire for the next five years, 2026/27 – 2030/31.   It complements
the West Dunbartonshire Local Housing Strategy 2022 - 2027 approved by
Council and submitted to the Scottish Government in November 2021 and
contributes to the delivery of national priorities particularly in relation to
homelessness, child poverty and the housing emergency.  
3.4   While the previous SHIP (2025/26 – 2029/30) was presented in the context of
a significant cut in funding to the Scottish Government’s Affordable Housing
Supply Programme (AHSP), the funding has this year been largely restored to
levels more in keeping with previous awards.  
3.5     The Scottish Government advises local authorities annually of their minimum
Resource Planning Assumptions (RPA) indicating what AHSP grant total will
be made available.  The current RPA for 2025/26 shows a slight increase in
resources from last year’s figure and stands at £11.363m.   This includes the
sum of £0.406m specifically allocated to acquire homes to help address
homelessness pressures.
3.6     This SHIP sets out proposals for a continuation of the high levels of new
affordable housing delivery achieved in West Dunbartonshire over recent
years.    
3.7 Where details are not yet known, the project grant levels have been estimated
based on current guidance with an estimated £120K per unit being projected
for both Council and Housing Association schemes.  There remains a
discrepancy between Council and Housing Association benchmark grant
levels, but it is anticipated that a higher proportion of larger family homes in
the Council programme attracting a higher level of grant will even out average
grant levels across the developing housing providers identified within the plan.
3.8     The Scottish Government grant funding required to deliver the priority projects
listed in the 5- year programme amounts to around £48.3m.   The programme
beyond the current financial year shows an over commitment of spend and
will need to be the subject of a smoothing exercise.  Despite this we remain
confident that the programme outlined can be delivered, even if some projects
may subject to delay.   Ongoing discussion will take place with the Scottish
Government’s More Homes Division over resourcing this SHIP programme.
3.9      In September 2025, the Scottish Government published its Housing
Emergency Action Plan which committed to a £4.9bn investment over the next
four years for the delivery of new homes, this will see an increased RPA
allocation for all Scottish local authorities and the welcome introduction of
multiyear funding allocations to strengthen the delivery of strategic housing
investment plans. Once the Scottish Government makes formal
announcements on this aspect of the Action Plan, such as the increased
funding and how this will be distributed to local authorities, the Council will
review the SHIP with a focus on maximising investment opportunities and
ensuring the delivery of affordable housing continues to meet the needs of

Page 3

3
West Dunbartonshire’s communities.
4. Main Issues 
4.1     The purpose of the SHIP is to set out the strategic investment priorities for
increasing provision of affordable housing through new build and buyback
programmes in support of outcomes contained in the Local Housing Strategy.
This SHIP sets out the planned housing investment programme for 5 years,
covering the period 2026/27 – 2030/31.
4.2    The funding for the projects will be from two principal sources:
 the allocation from the Scottish Government’s Affordable Housing
Supply Programme
 borrowing from the developing organisation’s own lending resources.         
4.3    The SHIP contains tables detailing the projects included in the proposed
programme.  It should be stressed that inclusion in the SHIP does not
guarantee scheme approval, as each proposal will require to go through a
further detailed project and financial appraisal before funding is committed.
4.4    All new homes built through the SHIP will require to meet high quality
requirements including the Council’s Design Standard for Affordable Housing,
which was updated in November 2023, and which applies to all projects
commencing after April 2024. 
4.5     This SHIP provides more information than previously on how it will help in the
delivery of key priorities including those featuring in:
 Housing to 2040
 Housing Emergency Action Plan
 Child Poverty Action Report
 WD HSCP Strategic Plan
 Rapid Rehousing Transition Plan.
4.6    SHIP 2026/27 – 2030/31 Priority Projects
The priority projects for this period including those currently on site, are as   
shown in table 3 below.  All units are social rented unless otherwise stated
and unit numbers are draft in some cases.
Table 3: SHIP 2026/27- 2030/31: Priority Projects by Developer
Site/Developer Number of
Units
WDC
Willox Park,
Dumbarton Ph1
17
Bank St, Alexandria 22

Page 4

4
Bonhill Gap Sites,
Alexandria
28
Dennystoun Forge,
Dumbarton
20
West Thomson St,
Clydebank
42
Willox Park
Dumbarton Ph 2
21
Ottawa Crescent,
Dalmuir
21
28 Bridge St,
Alexandria
8
Silverton, Dumbarton 9
O’Hare, Alexandria 6
Queen Mary Avenue,
Clydebank
17
Buybacks/ROTS 181
392 units
Wheatley Group/
(Loretto HA)
Dumbain Road,
Haldane  
23
23 units
Knowes HA
Abbeylands Road,
Faifley
27
Buybacks/ROTS 32
59 units
Dunbritton HA
Golfhill Drive,
Dalmonach
7
Cottage Hospital,
Dumbarton
10
17 units
Bellsmyre
Regeneration Phase
2
33                     
Bellsmyre
Regeneration Phase
3
34
Bellsmyre
Regeneration Phase
4
16
Bellsmyre
Regeneration Phase
5
28       
111 units
Dalmuir Park HA
Auld St, Dalmuir       32

Page 5

5
Buybacks/ROTS       15
47 units
4.7   In total, the SHIP shows the delivery of around 649 affordable homes over the
5-year plan period. This level of development continues the ambitious new
affordable house building programme in West Dunbartonshire. The delivery
the plan will depend upon the support of our developing housing association
partners, an increase in funding from the Scottish Government and continued
Housing Revenue Account capital investment.
4.8    The SHIP is supported by funding from the Affordable Housing Supply
Programme to assist the popular Rental Off the Shelf (ROTS) / Buyback
programme of ex- local authority and Registered Social Landlord housing
stock, as well as acquisitions from the private sector including of-the-shelf
homes from house builders. It is proposed that over 200 units are acquired in
this way by the Council and participating RSLs over the five years of the plan.
4.9   The grant funding required to deliver this programme is estimated to be
around £51m.  While this figure is higher than our current confirmed Resource
Planning Target, an announcement is expected early in 2026 from the
Scottish Government on new levels of funding and a new multi-year funding
arrangement which will help in programme planning. 
4.10 Due to uncertainties over details of some of the proposed projects in the SHIP
and the availability of funding, the SHIP will require to demonstrate flexibility
and will be subject to continual monitoring and evaluation.  The SHIP lists a
series of reserve/shadow projects which we hope will feature in the
programme as it progresses.   Monitoring of progress will be carried out
through the Council’s performance management system and through key
structures such as the Strategic Housing Providers Forum, More Homes
Project Board and programme review meetings with the Scottish Government.
4.11 The Council has carried out an analysis of potential projects against an
objective Prioritisation Scoring Matrix and scored them accordingly.  A
number of factors are taken into account including type of housing being
proposed, deliverability, value for money, and compliance with key local and
national housing objectives.   Where a project proposes an element of
particular needs /specialist provision, engagement takes place with the West
Dunbartonshire Health and Social Care Partnership.   
5. People Implications
5.1 While there are no direct people implications.
6. Financial and Procurement Implications     
6.1 The ability to deliver the SHIP relies on continuing to receive appropriate
levels of grant from the Scottish Government. West Dunbartonshire’s
Resource Planning Assumption (RPA) from the Scottish Government for
2025/26 is £11.3863m. For the SHIP to be delivered in full, RPA levels would
require to increase above current levels, however we expect to see this this

Page 6

6
following the Scottish Government commitment to £4.9bn of investment over
the next four years in the delivery of new homes, this will see the introduction
of multiyear funding allocation to strengthen the delivery of strategic housing
investment plans.
6.2 The programme of projects shown in the SHIP can only take place if both its
two principal funding streams, namely the developing landlord using
reserves/borrowing and Scottish Government Affordable Housing Supply
Programme grant, are able to provide the required ongoing financial support. 
It is estimated that the total grant ask of the Affordable Housing Supply
Programme would be around £48m. 
6.3      West Dunbartonshire’s New Build Programme has been closely aligned with
Housing Revenue Account affordability, through the ongoing rent consultative
exercise for 2026/27. In respect of the Council House Build element, financial
modelling demonstrates that the new council house building programme is
beneficial to the long-term health of the Housing Revenue Account.  However,
care requires to be taken to ensure that the prudential borrowing required is
financially sustainable.
6.4      There is a danger that future resource allocation could suffer if the SHIP fails
to deliver on the programme contained in this SHIP.  In most recent years we
have not only been able to meet our spend targets but have attracted
additional funding from underspend elsewhere within the national programme.
6.5      The Council is continuing to lobby for increased grant levels from the Scottish
Government and where appropriate will apply for above benchmark awards
on a project-by-project basis.
6.6 There are no procurement implications to note.
7. Risk Analysis
7.1 Inevitably, with such a varied programme of projects there are risks that the
ambitious outputs set out in the SHIP will not be met.  A number of the
projects are at an early stage with site investigations not having been carried
out or infrastructural constraints fully known.
7.2      There is a risk that Affordable Housing Supply Programme funding will be
reallocated to other Council areas if the Council is unable to spend within any
financial year.  Housing Development staff will liaise regularly with Scottish
Government More Homes colleagues to address any concerns of this nature,
to maximise spend within West Dunbartonshire.
7.3 If the development of new affordable housing, the level of housing need will
increase with negative consequences for West Dunbartonshire’s communities
and wider Council finances. Monitoring of progress will be carried out through
key structures such as the Strategic Housing Providers Forum, the Housing
Improvement Board, the More Homes Project Board and programme review
meetings with the Scottish Government.   A new SHIP will be submitted

Page 7

7
annually to the Scottish Government each October and will be the subject of a
report to the Housing and Communities Committee.
8 Environmental Sustainability
8.1 The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy.
9.       Equalities Impact Assessment
9.1 Equality is central to all housing and housing services delivery. An Equalities
Impact Assessment (EIA) has been undertaken on the Local Housing
Strategy 2022-27 to ensure that the needs of local communities have been
fully considered. The SHIP reflects identified needs and draws on findings
from the EIA when considering the implications flowing from the translation of
strategic aims into housing policies.
9.2      All new housing supported through the programme will be compliant with the
West Dunbartonshire Design Standard and will meet the Housing for Varying
Needs requirements.  The West Dunbartonshire Design Standard requires
developers in the programme to provide higher standards than those required
by statute and are of particular benefit to those with mobility issues.  The
SHIP supports the delivery of specialist housing provision and generally
allows for a 10% element in each project.  We place an emphasis in the SHIP
on increasing the supply of larger family homes, to help address child poverty.
10.      Consultation
10.1   The SHIP was drawn up in consultation with potential housing association
partners and the Scottish Government More Homes Division.    Where an
interest has been shown, detailed discussions have taken place with the
prospective developer on how the project could be accommodated in the
programme.  
10.2 The West Dunbartonshire Tenants and Residents Organisation received a   
presentation on the proposed SHIP in October 2025 and are supportive of its
aims in particular the council new build developments.  
10.3   The preparation of the SHIP has been a corporate task, involving all relevant
departments of the Council and has been carried out in collaboration with
colleagues in the Scottish Government More Homes Division.  The Health and
Social Care Partnership was an active partner in preparing the plans where
there was a significant element of specialist accommodation involved, and a
number of projects were significantly amended as a result
11. Strategic Assessment

Page 8

8
11.1   This Strategic Housing Investment Plan presents the priorities for affordable
and deliverable housing development for the next five years as set out in the
Local Housing Strategy.             
It also supports the Council’s key strategic priorities to:
 Improve local housing and environmentally sustainable
infrastructure
 Improve economic growth and employability
 Improve the well-being of communities and protect the welfare of
vulnerable people
 Improve care for and promote independence with older people
 Improve life chances for children and young people. 
Peter Barry, Chief Officer, Housing
Date:   5 November 2025
Person to Contact: John Kerr, Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, 16 Church Street,
Dumbarton John Kerr@west-dunbarton.gov.uk
Jamie Dockery, Senior Housing Development Officer,
Housing Development and Homelessness Team,
Jamie.dockery@west-dunbarton.gov.uk
Appendices:                      Appendix 1: Strategic Housing Investment Plan             
2026/27 - 2030/31
Background Papers: West Dunbartonshire Council’s Local Housing Strategy
2022-2027
West Dunbartonshire Council’s Local Housing Strategy
2022-2027 EIA
Wards Affected: All Wards