WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Resources 
Housing and Communities Committee: 20 August 2025
___________________________________________________________________
Subject: Housing Revenue Account (HRA) Capital 
Budgetary Control Report to 30 June 25 (Period 3)
1. Purpose
1.1 This report provides an update on the HRA capital programme to 30 June
2025.
2. Recommendations
2.1 Members are asked to:
i) note the current position of the 2025/26 HRA capital estimates and the
HRA capital plan.
ii) note that in year financial performance will be monitored against a
2025/26 capital expenditure estimate of £55.547m and a 2025/26
capital income estimate of £6.290m, a forecast borrowing requirement
of £49.257m.
iii) note that project life performance will be monitored against a project life
expenditure estimate of £345.311m and a project life income estimate
of £80.378m, a five-year borrowing requirement of £264.933m.
iv) note that at this early stage all projects are on track regarding achieving
their planned completion dates and delivering within the updated
capital estimate.
3. Background
3.1 The Council approved the HRA Capital Plan for 2025/2026 to 2029/2030 on 5
March 2025. The HRA capital plan estimated £70.590m of capital expenditure
and £15.324m of capital income in 25/26, a forecast borrowing requirement of
£55.266m.
3.2 Since then, budget adjustments have taken place to reflect up to date
information on progress delivering the plan and any need for budget
acceleration and budget deceleration from / to future years, and to update the
expenditure and income budgets for Affordable Housing Supply projects to
reflect the 2024/2025 outturn and to reflect that the most recent cost and
income forecasts.  The budget adjustments result in revised capital budgets
as set out in Exhibit 1. The updated borrowing requirement for 25/26 of
£49.257m is £6.009m less than the estimate that Council agreed in March
2025. 
ITEM 13

Page 2

Exhibit 1: Revised HRA Capital Estimates 2025/2026 – 2029/2030
2025/26
BCR03
(£m)
Project Life
BCR03
(£m)
2025/26
March 25
(£m)
Project Life
March 25
(£m)
Other Capital Expenditure 7.433 26.267 7.433 26.267
Component Replacement 20.881 93.567 20.881 93.567
Void Capital 5.258 19.873 5.258 19.873
Structural & Environmental 3.762 17.320 3.762 17.320
Support Costs 3.100 17.155 3.100 17.155
More Homes Programme  15.113 171.129 30.156 166.469
Total Expenditure 55.547 345.311 70.590 340.651
Total Income -6.290 -80.379 -15.324 -73.009
Prudential Borrowing 49.257 264.932 55.266 267.642
4. Main Issues
4.1 Progress against the 2025/26 capital plan is detailed in:
Appendix 1 – HRA Capital Summary BCR03
Appendix 2 – HRA Capital Detail BCR03
4.2 The HRA capital summary report at Appendix 1 reports that planned
expenditure and planned income are both in line with the overall project
estimates. Appendix 1 reports that there are fifteen capital projects where
expenditure is tracked over the multi-year life of the project and twenty-nine
projects classified as rolling programme projects / contingency / fees, that is
programmes of work where an annual estimate is set each year that takes
account of demand, cost, and affordability.
4.3 Appendix 2 shows all projects with approved in year and project life estimates
as well as forecast expenditure / income. The appendix highlights a
2025/2026 expenditure budget of £55.447m and a forecast spend of
£55.447m. The 2025/2026 capital income budget is £6.290m, with a forecast
income of £6.290m.
4.5 Budget assumptions are required to forecast costs / income, especially where
projects span multi-year and project finances have yet to be finalised. It is
therefore likely that the projected year end position will change during the
year.
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital estimates.

Page 3

8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
several variable factors which could arise between now and 31 March
which could affect the year end results for capital budgets.
(b) To forecast for the full year costs budget assumptions have been
required. These assumptions continue to change regularly and therefore
it is likely the projected year end position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital estimates have been consulted
during the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
________________
Laurence Slavin
Chief Officer – Resources
Date: 20 August 2025
Person to Contact: Jim McCarron
Business Partner, Finance 07772 322055
E-mail: james.mccarron@west-dunbarton.gov.uk
Appendices: Appendix 1 - HRA Capital Summary BCR03
Appendix 2- HRA Capital Details BCR03
Background Papers:
Housing Revenue Account (HRA) Capital Investment Programme, Revenue
Budget, and Rent Levels for 2025/26 - Council 5 March 2025.
Wards Affected           All Wards