Appendix 1 - Housing Emergency Declaration action plan Icon Name 1 - Deliver and maintain More Homes - West Dunbartonshire approach to the delivery of affordable housing. Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Issue letter to the housing minister highlight the Housing Emergency declaration and requesting that the full AHSP is restored. 30-Aug- 2024 Yes Highlight within SHIP and Programming Process the impacts of cuts to the AHSP 31-Oct- 2024 Yes Participate in a number of Member and Officer groups and influence agenda to maximise AHSP budget settlement 31-Mar- 2025 Yes Continue to lobby SG for increase in AHSP funding in partnership with COSLA/SOLACE/ALA CHO 31-Mar- 2025 While we await the final outturn report West Dunbartonshire Council has been allocated around £2m additional funding through our 2024/25 RPA through the Affordable Housing Supply Programme in recognition of our ability to deliver, the additional funding is from the existing funding within the wider AHSP. For 2025/26 we now know our RPA to be £11.053m. Review impact of discussions with Scottish Government 31-Mar- 2025 Yes John Kerr Presentation to West Dunbartonshire Strategic Housing Providers Forum 30-Aug- 2024 Yes Carry out prioritisation exercise 21-Oct- 2024 Yes Refresh Strategic Housing Investment Plan to ensure the delivery of new homes to meet acute housing need in West Dunbartonshire 29-Nov- 2024 Draft SHIP approved by More Homes Project 31-Oct- 2024 Yes John Kerr ITEM 8 - APPENDIX 1
Page 2
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Board Deliver new Strategic Housing Investment Plan 31-Oct- 2024 SHIP approved at Housing and Communities Committee of 20th November Jamie Dockery Deliver the Council's approved new build programme for 24/25 helping meet the identified housing need. 01-Mar- 2025 Development delivered. action will be repeated in new year, report to MHPB Dawn Conner SHIP to be prepared and draft submitted to the Scottish Government by October 31 31-Oct- 2024 Yes Develop and acquire More Homes Project Board approval for proposal to ensure the acceleration and prioritisation of new home delivery. 31-Dec- 2024 Yes Examine ways to accelerate new build delivery considering housing emergency declaration 31-Dec- 2024 While the initial action is complete, ongoing progress in this will be reported and monitored within the governance of the More Homes Board. There does continue to be internal challenges in the delivery of new housing. Develop revised Strategic Local Programme in partnership with Scottish Government 31-Dec- 2024 Yes John Kerr Scale up and extend the Buy Back Scheme to meet the key housing demand factors including the provision of temporary accommodation 31-Mar- 2025 The buyback scheme has been scaled up through £10m of additional funding over the next 5 years in addition for 2024/25 we have been awarded an additional £309k in 24/25 to secure buyback acquisitions that directly take households out of temporary accommodation, our stated priority is families with children. We have a similar allocation of £296k for 25/26. 31-Mar- 2025 Yes Laura Hanna Participate in Housing Investment task force 25-Sep- 2024 YesExplore innovative housing investment 30-Sept- 2025 Action on track paper being developed for the September meeting of the More John Kerr
Page 3
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To discussions Continue to develop own proposals in partnership with external agencies and potential investors 31-Mar- 2025 Yes and partnership models to maximise housing investment approaches Homes Project Board. Proposal paper to More Homes Project Board to define policy 31-Sep- 2025 No In partnership with the Scottish Government review the planning and consenting system considering the national housing emergency to increase the scale and pace of development across all tenures 28-Feb- 2025 Updated to 50% as work is ongoing, a lot is however out of our local control and actions will be taken forward as part of the SG response to the national housing emergency. actions from the meeting - attended by chief planning officer 28-Feb- 2025 Yes Michael Mulgrew Detail development priorities within SHIP 31-Oct- 2024 YesReview HRA resource allocation across the Council to help facilitate/deliver new build programme 30-Sept- 2025 More Homes Co=Ordinator currently being recruited as part of Housing Development Service Redesign Housing Development service design to be completed 31-Sep- 2025 No John Kerr Approval for Gilmour Avenue modular development 25-Sep- 2024 Yes Develop revised approach based on review and share with development partners 31-Dec- 2024 Yes Explore an approach to develop modular and other forms of innovative housing by working in partnership with other housing providers 31-Oct- 2025 This action has been delayed due to the administration of Connect Modular and the subsequent delay to the Gilmour Avenue development. Review Gilmour Avenue development 31-Oct- 2025 No John Kerr Examine the capacity of the HRA to deliver agreed 29-Aug- 2025 The ability of the HRA to deliver all identified tenant priorities including the delivery of new housing within the HRA review for 2024/25 31-Mar- 2025 Yes Peter Barry
Page 4
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To housing ambitions/tenant priorities Capital Investment plan will continue to be discussed with tenant representatives primarily within future rent consultations although not exclusive to these. We will ensure housing ambitions and service spend continues to reflect tenant priorities. Participation in Scottish Government trawl process 30-Sep- 2024 Yes Special More Homes Board scheduled for November to look at the opportunities with other service departments (now Housing Summitt). 28-Feb- 2025 Yes Engage with public and private sector landowners to increase the HRA landbank and support development in line with the refreshed Strategic Housing Investment Plan 31-Oct- 2025 Discussions ongoing with one housing developer re potential for them to landbank housing opportunities, model to be explored further. Plan agreed at More Homes Board to inform delivery plans from 2025/26 31-Oct- 2025 No John Kerr Review Affordable Housing Design Standard 31-Mar- 2026 Full review to be undertaken in 2025, but the design standard was examined as part of the SHIP development process and it was found not to be limiting in terms of new build ambitions, many developing associations citing it as a benefit in the design process and providing clear guidance. John Kerr Increase provision of Mid-Market Rent properties as a viable housing option for homeless and housing applicants 30-Apr- 2026 Proposal is being taken forward following May 2024 committee approval; however, we now await clarity in terms of Scottish Government funding arrangements and the identification of a suitable site and associated business plan John Kerr Refresh Housing Needs and Demand Assessment (HNDA) within a local WDC perspective 31-Mar- 2026 Action on track following support at the Housing Summit in February 2025 John Kerr; Claire McKay
Page 5
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Carry out a review of design standards (Housing development and planning) 31-Mar- 2026 Action commenced looking at the planning requirements in relation to the delivery of new homes. Jamie Dockery; Michael Mulgrew Icon Name 2 - Make Best Use of Existing Stock Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Continue to Improve our approach to empty council homes with a strengthened focus on reducing void time and letting longer term empty homes and negating any use of unsuitable accommodation. 31-Dec- 2024 Although the action has been completed work continues on the Void Improvement Action Plan working alongside Housing Operations to improve performance across the Council. Building Services continue to set targets to improve productivity and reduce the average cost to bring a property back to the Councils' relet standard. At end of quarter 3 to end of December Building Services had received 665 and returned 706 ready for let properties. The average time to bring back to relet standard in quarter 3 was 13 days (target 12 days) compared with 27 days in 2023/2024 (discounted days). Actual days in quarter 3 was 55 days compared to 79 days in quarter 2. Up to the 27/01/2025 major and extensive voids have been reduced by 15. The average cost to bring a property back to the Councils' relet standard has reduced in 2024/2025 compared to 2023/2024. Less void properties have been subcontracted and a significant reduction in void overtime costs has been achieved. Costs may increase in quarter 4 as efforts to achieve the target of 150 by year end continue. Martin Feeney Consider a fixed 20-Dec- Action on track for completion by target Martin Feeney
Page 6
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Implement and monitor measures to improve the control and generation of non- essential repairs. 30-Aug- 2024 Yes Based on performance and progress made on reducing the number of empty homes agree to continue to monitor and postpone any decision on a fixed term moratorium. 27-Sep- 2024 Yes Continue to implement improvement actions in the void management improvement plan including increasing productivity and reducing the average cost to bring an empty home back to the Councils' relet standard. 29-Nov- 2024 Yes term moratorium on non-essential housing repairs to focus activity around bring empty homes back into use 2024 date with 3 of the 4 sub actions completed. Actions in the void management improvement plan and building services action plan 2024/2025 are progressing well. Increased productivity in void operations and reduction in the average cost to bring a void back to the Councils' relet standard are evident and further improvement are progressing and being monitored. The reduction in costs is in addition to reduced costs for decorations which is no longer routinely completed. Due to increased void properties year to date compared to 2023/2024 the use of sub-contractors will increase December - March. Review evidence to make final decision on a 3-month (last quarter of 2024/2025) moratorium on non- essential housing repairs to focus resources on the repair of the Councils' housing properties. 13-Dec- 2024 Yes Complete review of referral/communication processes between void team and Helptomove 30-Sep- 2024 Yes Engage with Consumer 30-Sep- Yes Develop a process including exploring potential partnering arrangements to address lengthy delays by energy 31-Dec- 2025 Nicola Pettigrew
Page 7
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Scotland to discuss problems encountered and provide case studies to support national focus on holding energy companies accountable to resolve meter issues more efficiently 2024 Introduce new report from help the move to identify move ins with no end date meter readings to enable more accurate billing information 30-Sep- 2024 Yes Introduce weekly monitoring report for support worker to track progress of complex meter issues and update to teams 30-Sep- 2024 Yes Review liaison arrangements with Helpthemove ensuring appropriate representation to input to operational challenges 30-Sep- 2024 Yes Develop escalation process with helpthemove on more problematic meter problems 31-Oct- 2024 Yes suppliers in the reletting process. Explore other providers to establish if can provide additional support to helpthemove arrangements Yes Accelerate the 31-Mar- A significant milestone was achieved Karen Rae
Page 8
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Seek HACC approval of new strategy - aim to bring 25 properties per year back into use 30-Nov- 2024 Yes reduction of private sector empty homes by delivering a new Long Term Empty Homes Strategy 2025 which seen the approval of the new Empty Homes Strategy by committee on the 20th of November Review numbers of empty homes brough back into use at end of current financial year 31-Mar- 2025 Yes Carry put early consultation with tenants to inform revised Repairs Policy and ensure tenant priorities are delivered. 30-Jun- 2024 Yes HRA Value for Money Group to develop revised Repairs Policy which will meets tenant priorities and reflects input from key stakeholders. 31-Aug- 2024 Yes Deliver with tenant representatives a new repairs policy 30-Nov- 2024 Seek approval for revised Repairs Policy from Housing and Communities Committee November 2024. 20-Nov- 2024 Yes Stefan Kristmanns Ensure new repairs policy achieves key objectives 30-Nov- 2024 New repairs policy was approved by the HACC Committee in November 2024. The policy will achieve objectives to improve the reactive repair service, making this more efficient whilst meeting tenants’ expectations. Work is progressing to get the new policy live by 1 April 2025. Martin Feeney Review and agree the new 70% allocation to transfer applicants for all new builds 30-Aug- 2024 Yes new media/drive for 16-Feb- Yes Review and promote Allocations Policy flexibilities and enhanced Transfer Incentive Scheme 31-Mar- 2025 Claire McKay
Page 9
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To downsizing etc 2025linked to the review of the Housing Allocations approach Review current transfer incentive scheme 28-Feb- 2025 Yes Introduce notification to Repair and Maintenance Manager on voids properties due for return on back of transfer move in advance of sign-up 30-Sep- 2024 Yes Introduce robust pre- allocation house assessments process which embeds ongoing discussions with Building Services to highlight condition of voids and recharges as required 30-Sep- 2024 Yes Introduced homeless liaison meetings in advance handover dates to identify existing WDC tenants with open homeless case 30-Sep- 2024 Yes Prepare lettings initiative action plan 30-Sep- 2024 Yes Identify properties for each quota and engage with relevant teams to finalise 31-Oct- 2024 Yes Actively introduce a pre letting process initially linked to the transfer led allocation process for new build social housing 31-Aug- 2025 Action on track and final milestone will be achieved with the target time of August 2025. Review house assessment form to ensure capturing relevant information via HO mobile app 31-Aug- 2025 No Nicola Pettigrew Project board to agree options for HACC 31-Mar- 2025 YesDeliver the recommendations 31-Mar- 2026 Action on track and deliverables programmed from November 2024 Claire McKay
Page 10
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To following all feasibility studies and financial reviews Linked to action H/RRTP/19-24/064 HACC approval on options 30-Nov- 2025 Nofrom the Supported Housing Review Carry out procurement exercise to meet new needs and options agreed 30-Jan- 2026 No Establish project plan and resource requirement 30-Nov- 2024 Yes Initial Report findings to be presented and recommendations agreed at Better Homes Project Board 30-Sep- 2025 No Stock assessment to be undertaken against key technical and operational indicators to assess performance 30-Sep- 2025 No Finding to inform refreshed Housing Asset Management Strategy which will be presented to August Housing and Communities Committee 30-Sep- 2025 No Carry out a comprehensive assessment of our housing stock to ensure it can deliver the key priorities within the Local Housing Strategy 30-Oct- 2025 Action on track and will inform the development of the refreshed housing asset management strategy. Implementation Plan including the focused regeneration initiatives to be led by Housing Development Co- ordinator (Better Homes) 30-Oct- 2025 No Jackie McRory Continue to roll out 31-Mar- Environmental sensors now installed at Emily Dorrian
Page 11
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To 1000 Homes 31-Oct- 2024 Yesour approach to address condensation, dampness and mould within our homes through the use of smart technology that strengthens housing management 2025 over 2000 homes 2000 homes 31-Mar- 2025 Yes Initial Proposal developed 18-Oct- 2024 Yes The initial introduction of 2 new compliance roles to be managed within the housing service and dedicated to HRA properties (phase 1) 28-Feb- 2025 Yes Implementation of Phase 1 31-Oct- 2025 No Deliver new proactive approach to ensure our housing stock continues to meet all statutory compliance requirements 31-Oct- 2025 Delayed in terms of the recruitment aspect, will progress before the end of September. Review of planned approach with tenant representatives and paper to be submitted to Better Homes Board in September regarding a potential Phase 2 to ensure compliance requirements are met 31-Oct- 2025 No John Kerr Obtain baseline data to support VFM in promoting mutual exchange options with applicants 30-Sep- 2024 Yes Review functionality and best practice with HomeSwapper 30-Sep- 2024 Yes Maximise use of Home Swapper to meet rehousing need of transfer applicants 31-Oct- 2025 Nicola Pettigrew
Page 12
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Introduce quarterly marketing information via social media, tenants’ news to maximise awareness 28-Feb- 2025 Yes Complete marketing awareness campaign to increase use of homeswapper 31-Mar- 2025 Yes Add link to online housing application form to direct to home swapper and increase uptake 30-Apr- 2025 Yes targeted campaign - news article highlighting how easy text transfer applicants with no housing need access Facebook groups to link with homeswapper 31-May- 2025 Yes Identify additional resource required to support home swapper back admin functions required 31-Oct- 2025 No Review VFM annual costing of home swapper and consider if in-house platform could be developed (similar to rent insights approach) 31-Oct- 2025 No Gather all information on all leases for an overview 30-Nov- 2024 Yes Begin consultation/actions to 31-Sep- 2025 No Review of all current lease agreements within context of housing emergency (e.g., Safe as 31-Oct- 2025 Action on track will help ensure best use of housing stock. John Kerr
Page 13
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To end any leases we no longer think appropriate - report to HIB Houses scatter flats and impact on generating homelessness) Review all leases and decide whether best use of housing stock 31-Sep- 2025 Yes Deliver housing Capital Investment Programme to ensure all homes meet the Scottish Housing Quality Standard 31-Mar- 2025 Housing Capital Investment projects competed for 24-25 contributing to improving SHQS compliance. % compliance numbers are being collated for year-end reporting and SHR ARC Alan Young Maximise the use of existing housing systems to support effective stock management 31-Mar- 2026 action being taken forward as part of IHMS Improvement Plan, IHMS team working with a nominated Senior Housing Development Officer to ensure the system meets wider housing service needs before involving key managers Graham Watters Explore options for a common mutual exchange WDC wide scheme 31-Mar- 2026 No Explore options of a common downsizing scheme for social landlords in west Dunbartonshire 31-Mar- 2026 NoExplore establishing a common downsizing WDC wide scheme and a mutual exchange site 31-Mar- 2026 Initial progress has been made through discussion with RSL representatives. Explore requirements of a dedicated resource to facilitate increased numbers if downsizers and mutual exchanges 31-Mar- 2026 No Claire McKay Icon Name 3: Enhancing housing access & prevention of homelessness
Page 14
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Review current information on different platforms 31-Aug- 2025 No explore option of stock and turnover tool being added to the public 31-Oct- 2025 No Carry out a communications audit to ensure tenants and services fully informed on housing availability in WDC 31-Mar- 2026 Action newly commenced and will be delivered within timeframe. create a briefing and offer to attend services team meetings to discuss housing in WDC 31-Mar- 2026 No Claire McKay Develop and implement transfer led approach to new build housing allocations 31-Aug- 2024 Action has been achieved but will be monitored and a report will follow initially to the More Homes Project Board recommending any refinements following a review of Clydebank East detailing we are making allocations based on housing need and there is visibility that it is tackling homelessness. Committee Approval in place and ensure ongoing tenant support 30-Aug- 2024 Yes John Kerr Set up meeting with all senior management from both HSCP and Housing/Homeless to take forward discussions 29-Nov- 2024 Yes Strengthen strategic leadership approach with HSCP regarding housing emergency 30-Jun- 2025 Follow up actions from joint meeting 25-Apr- 2025 Yes Peter Barry; Margaret- Jane Cardno set up new meeting of the housing bill group now Bill is through stage 1 30-Oct- 2024 Yes Discuss options for task force - link to timeline for the bill 29-Nov- 2024 Yes Establish a Task Force approach to engage public bodies to promote prevention measures linked to the Housing (Scotland) Bill 31-Dec- 2025 Task force established and expectation is Stage 2 of the BILL will make its way through Parliament in 2025. Develop West Dunbartonshire approach 01-Sep- 2025 No John Kerr Develop a new 01-Apr- Claire McKay
Page 15
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Finalise draft of strategy following consultation (Aug until Dec) 31-Dec- 2024 Yes Seek HACC approval of new strategy 28-Feb- 2025 Yes refreshed strategic approach to the prevention of homelessness through the delivery of a Housing Solutions Strategy 2025 Embed and deliver new strategy 01-Apr- 2025 Yes VAWG partnership supportive of action H/HEDAP/2024/038 but will be carrying out a self-assessment of the group where Prevention will be a key element 30-Nov- 2024 Yes In partnership with Violence Against Women Partnership deliver a refreshed focus on preventing negative housing situations as a result of domestic abuse. 31-Dec- 2024 deliver action H/HEDAP/2024/038 31-Dec- 2024 Yes Claire McKay Job evaluation 01-Aug- 2025 No Direct Matches & Matching Pools and Expressions of Interest 29-Aug- 2025 No Full implement the introduction of the Housing Solutions Service following on from the Homelessness Service redesign 31-Dec- 2025 The implementation of the new service delivery model has been amened due to the job evaluation timescales. Service Rebranding Action List 31-Dec- 2025 No Joanne Sutherland Agree in principle online form and tweak to ensure all aspects covered 30-Sep- 2024 Yes RSL to seek Committee approval on form before being finalised 30-Nov- 2024 Yes Agree data sharing agreement and Information to be used on the website for all involved and link 13-Jun- 2025 Yes In partnership with local RSLs develop and implement a common application form for all social housing providers in West Dunbartonshire as part of the development of a Common Housing Register 17-Oct- 2025 Claire McKay
Page 16
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Agree Launch online form 01-Oct- 2025 No this is linked to Action 48 being achieved first 31-Oct- 2024 Yes Delivery of stock sheet training and Team Leader Support/shadowing in interviews. 28-Feb- 2025 Yes Development and trial of Housing Solutions paperwork and personal housing plan. 28-Feb- 2025 Yes Review process once new structure in place 30-Sep- 2025 No Completion to module 6 housing options toolkit for all casework staff 30-Sep- 2025 Yes Introduce a comprehensive housing options interviews at application stage to manage demand and options 31 Dec- 2025 Will be delivered within the new service redesign within the Housing Solutions service Housing Options Survey and presentation to all casework staff 30-Sep- 2025 Yes Joanne Sutherland Decision paper for Housing Improvement Board to agree the extent of the review 31-Aug- 2024 Yes meeting of Co- ordinators to agree the remit 30-Sep- 2024 Yes new paper to HIB agreeing new proposals of the remit 31-Dec- 2024 Yes update guidance and relevant policies on agreed remit 31-Dec- 2024 Yes Review remit of Housing Allocations Panel to reflect a homelessness prevention perspective (domestic, at risk, others that would otherwise present) 31-Jan- 2025 communicate and 31-Jan- Yes Claire McKay
Page 17
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To update new remit to all staff 2025 Review current open Homeless cases with children 06-Dec- 2024 Yes Joint meeting between Homelessness and Housing operations focusing cases who do not have an offer 20-Dec- 2024 Yes following on identify any new processes to be implemented and rolled out to help continually reduce times children spend in temporary accommodation 31-Jan- 2025 Yes Using additional Temporary accommodation funds to focus on acquisitions for those households in temp with children waiting on offers 06-Apr- 2025 Yes Deliver a refreshed process which will ensure that time in minimised for children in all forms of temporary accommodation 31-Aug- 2025 ongoing monthly monitoring of numbers to review and maximise offers 31-Augl- 2025 Yes Claire McKay Carry out recent research around stigma and homeless with view to creating further actions to take forward 20-Dec- 2024 Yes Liaise with WDC comms team on appropriate campaign actions 31-Jan- 2025 Yes Design and deliver a dynamic public awareness campaign focused on the realities of homelessness and housing need 31-Aug- 2025 Donna Kirkwood; Mayra Nunes
Page 18
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Review WDC homeless webpage content to ensure appropriate language/images used around homelessness. 03-Feb- 2025 Yes Identify positive case studies detailing household circumstances and support provided by WDC to resolve homelessness to highlight help available and realities of homelessness. 31-Jul- 2025 Yes Prepare article for Housing News, include positive case study and advice around homelessness 31-Aug- 2025 Yes Review of Pathway 1 cases (i.e., those homeless but not in temporary accommodation) over 6 months to assess if in stable accommodation (and close if this is confirmed) 30-Apr- 2025 295 homeless applications where temporary accommodation wasn’t required, 198 cases closed when applicants given a housing outcome. 86 cases closed no housing outcome. Most common; asked to leave, fleeing domestic violence and relationship breakdowns. Yes Joanne Sutherland Linked to action 48 being achieved first 31-Oct- 2024 YesIntroduce a consistent assessment of housing and support needs regardless of 01-Sep- 2025 review support process once new housing 04-Aug- 2025 No Claire McKay; Joanne Sutherland
Page 19
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To if a tenant or presenting as homeless solutions services are rolled out Recruitment of new co- ordinator required to take forward 31-Dec- 2025 No Develop and implement a new approach to resettlement and humanitarian schemes 31-Mar- 2026 Recruitment of new post is scheduled to commence in August 2025 once restructure and recruitment in place new co-ordinator to review current approach 31-Mar- 2026 No Claire McKay Minimise and eradicate the use of unsuitable accommodation for homeless households 31-Mar- 2025 Continue with monthly analysis of placements in unsuitable accommodation and breaches of UAO. 31-Mar- 2025 Yes Joanne Sutherland Objective 1 - whole system approach 27-Apr- 2025 Yes Objective 2 - rapid rehousing (16 weeks) 27-Apr- 2025 Yes Objective 3 - interim housing options 27-Apr- 2025 Yes Deliver the outcomes of the Rapid Rehousing Transition Plan 30-Apr- 2025 Objective 4 - housing first 27-Apr- 2025 Yes Claire McKay Linked to action =one Door being achieved first 31-Oct- 2025 Yes Explore expanding a homelessness prevention approach and better managed demand for temporary accommodation 31-Mar- 2026 Analysis has been carried out, the changes indicate prevention work has been successful, where previous cases who did not require temporary accommodation are receiving successful outcomes without the need to make a homeless application which has meant those who have been presenting as homeless have also required temporary accommodation rather than being able to stay with friends or have a temporary option available. Prevention workshops will be held in the Autumn which will complete this action. review in line with decrease of pathway 1 and increased need to for temp 13-Mar- 2026 No Joanne Sutherland Introduce a 30-Nov- Joanne Sutherland
Page 20
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Action 48 needs achieved first 31-Oct- 2024 Yes"Mediation First" approach to housing applications for 16–19-year-olds (as a homelessness prevention approach) 2025 Restructure - once in place and introduction of youth specialist team put process in place 30-Nov- 2025 No actions 37, 42, 46 and 47 can then follow on from this action if achieved 31-Oct- 2024 Yes Paper on the possible vision to be taken to Access to Housing Group in Sep 2025) 30-Sep- 2025 No Agree principles relating to new one door housing access system aligned to the new Housing Solutions service 30-Sep- 2025 No Implement a ‘One Door’ preventative housing access system under one service to prepare for new prevention duties. 31-Dec- 2025 Proposal being developed and will be introduced for discussion at the next Access to Housing Board (September) Develop implementation plan 31-Oct- 2025 No John Kerr review current provision 31-Mar- 2025 Yes Upscale the Housing First programme through collaborative commissioning 30-Sep- 2025 linked to wider discussions with HSCP Take forward actions agreed following HSCP meeting 30-Sep- 2025 No Claire McKay Deliver and implement in partnership with RSL a Common Housing Register for West Dunbartonshire 31-Mar- 2026 The launch of the Common application form in October 2025 signifies the beginning of the development of an operating CHR in West Dunbartonshire. Claire McKay Review current information available to the public 31-Aug- 2025 No create a project plan 01-Sep- No Carry out communication audit to help manage current and future 01-Apr- 2026 Action newly commenced and will deliver within timeframe. Donna Kirkwood; Claire McKay
Page 21
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To following the review of information on our webpages 2025 tenants’ and partners expectations better on housing availability Make contact with other partners to provide better understood housing information 31-Dec- 2025 No Include exploring use of supported lodging whilst reviewing different temporary accommodation for young people 01-Apr- 2026 Action commenced following introduction at Housing Summit in February 2025 Contact other LAs with supported lodgings 01-Oct- 2025 No Claire McKay; Mayra Nunes Carry out modelling reviewing backlog, expected demand and turnover with a view to reducing current letting ask 30-Apr- 2025 Yes Review housing allocation % to households who experience homelessness 01-May- 2025 Seek HIB approval and ask RSL to match 01-May- 2025 Yes Claire McKay Icon Name 4: Strengthen the Financial viability and capacity of the Housing Revenue Account and associated Housing and Homelessness budgets Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Building services action plan created 31-Oct- 2024 YesComplete the review of Building Services Repairs and Maintenance service costs to deliver immediate efficiencies to the HRA 31-Mar- 2025 Building Services - Service Costs Recovery and Management of the HRA Maintenance and Repairs Budgets 2024/2025 is progressing well with all high priority actions 90% or more complete at 23/01/2025. These action include improving service efficiency, effective financial management and improve people management practice Deliver action plan - include service efficacies 31-Mar- 2025 Yes Martin Feeney
Page 22
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To within the service. Explore innovative housing investment and partnership models to maximise housing investment approaches 30-Nov- 2025 Action on track but completion date pushed back to November. Good progress made through the More Homes Board and the establishment of an LLP John Kerr Agreement made in 24/25 CFO agreed to full whole system review of HRA payments that will begin once Year end work completed in 2025. 31-Mar- 2025 Yes Carry out review of HRA contributions to other non-housing Council service areas 31-Mar- 2026 take forward actions following whole system review of all HRA payments by Chief Finance Officer 31-Mar- 2026 No Peter Barry Examine the capacity of the HRA and the Council's General Fund to deliver agreed housing ambitions 30-Jun- 2025 further review this action has been closed as linked to action 53 31-Mar- 2025 Yes Peter Barry; Laurence Slavin Develop a 3-year rental strategy in partnership with tenants to ensure tenant priorities and strategic housing ambitions can be delivered 30-Nov- 2026 Discussions around the viability of a 3- year rental strategy from the period 2026-29 will be taken forward via the HRA Value for Money Group. work has begun via HRA value for money subgroup - paper will be taken to the Aug 25 HACC for agreement 30-Aug- 2025 No Stefan Kristmanns several actions part of the review already taken place saving money 31-Mar- 2025 YesReview Building Services structures and external contractors to 31-Dec- 2025 Significant work completed to review BS structures and external contracts to reduce cost and improve efficiency Peter Barry
Page 23
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To Review Building Services structures and external contractors to ensure best value Significant work completed to review BS structures and external contracts to reduce cost and improve efficiency Last actions as part of the review to be taken forward 30-Nov- 2025 No Working with other local authority partner re-examine housing finance position in Scotland to promote the delivery of new social housing including the treatment of historic HRA Capital Debt 31-Mar- 2025 Council Officers participated in the Housing Investment Taskforce through ALACHO. Joint work with COSLA 01-Mar- 2025 Yes Claire McKay Review homelessness services funding with aim of being able to reduce level of temporary accommodation and free up staff resource 31-Mar- 2026 Ongoing action and alignment with the Housing Solutions service redesign John Kerr Develop a refreshed funding delivery model for the delivery of new housing in light of increased borrowing levels exploring increased grant benchmark levels 09-May- 2025 Work ongoing in terms of this action to ensure we can continue to deliver the required new housing at sustainable scale take paper to more homes board for approval on the viability of new agreed benchmarking (£120K) 30-Apr- 2025 Yes John Kerr Directly lobby the Scottish Government to ensure the cost of achieving net zero in social housing is met with national funding to ensure rental 30-Apr- 2025 Link in via SIG this has fed into both COSLA and ALACHO being clear tenants should pay, and all measures should be fully funded by Scottish 30-Apr- 2025 Yes Claire McKay
Page 24
Action Status Progress Due Date Comment Milestone Due Date Done Assigned To income can be utilised for improving current and developing new social housing. government - awaiting SG publication Action Status Cancelled Overdue; Neglected Unassigned; Check Progress Not Started; In Progress; Assigned Completed PI Status Alert Warning OK Unknown Data Only Long Term Trends Improving No Change Getting Worse Short Term Trends Improving No Change Getting Worse Risk Status Alert High Risk Warning
Page 25