WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 7 May 2025
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme
1. Purpose
1.1      This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Notes the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach,
including the final handovers of 88 new Council homes at the zero carbon
Clydebank East development which completes a significant housing led
regeneration project;
(ii) Invite the Chief Officer, Housing and Employability to carry out a
procurement exercise and to subsequently award the contract up to
budgeted costs for the new build developments at West Thomson Street,
Clydebank and the next phase at Willox Park, Dumbarton. and; 
(iii) Notes the resource planning allocation of an initial £10.757m to West
Dunbartonshire Council to deliver the Affordable Housing Supply
Programme in 2025/26.
3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over one thousand new affordable homes in
West Dunbartonshire to date and includes the Council’s own ambitious New
House Building Programme.
3.2     The Strategic Housing Investment Plan (SHIP) 2025-2030, outlining West   
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2024. The SHIP outline plans to
ITEM 10

Page 2

contribute to meet the Council Administration’s aim of delivering 2500 new
affordable and social rented homes over the 10-year period 2022-2032.
4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic and economic recovery
plans, negating the impacts of the current cost of living crisis and combatting
poverty principally child and fuel poverty.  It is also clear that the need for
affordable homes has and will increase in the current ongoing economic
environment.
4.2 The Council’s More Homes West Dunbartonshire approach is an ambitious
plan that aims to continue the positive momentum of the delivery of much
needed Council homes in West Dunbartonshire and will significantly assist the
Council’s aim to deliver 2500 new social and affordable homes by 2032.
4.3 As the biggest social housing developer in West Dunbartonshire, the Council
has identified several development sites for new council homes to address
existing and new housing need. The design of these homes will further
develop, improve, and exceed current best practice, providing sustainable
homes using innovative technology and delivering on our low carbon
ambitions including Passivhaus and other net zero carbon opportunities.
4.4 The Council’s More Homes West Dunbartonshire approach has evidenced
strong support from council tenants and was recently highlighted as one of the
two key future spending priority areas for tenants through the comprehensive
tenant satisfaction survey undertaken in late 2024. 
4.5 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  An update on
each development site is provide below: -
Clydebank East:
This development has now completed and has delivered eighty-eight new
homes designed to meet the urgent housing need within the wider West
Dunbartonshire area. The table below shows the housing mix:
House Type Sustainability Standard Number of New
Homes
Wheelchair Bungalow
3bed/4person
Net Zero 3
House 3bed/5person Net Zero 15
House 4 bed/7person Net Zero 12
House 5 bed/8 person Net Zero 8
Wheelchair Cottage Flat
1bed/2 person
Net Zero 4

Page 3

Cottage Flat 2 bed/4 person Net Zero 4
Flat 1 bed/2person Net Zero 16
Flat 2 bed/4 person Net Zero 24
Wheelchair Flat 1 bed/2person Net Zero 2
The development at Clydebank East sees the completion of a major housing
led regeneration of a key priority regeneration area identified in the Local
Housing Strategy and will be the first fully zero carbon housing development
in West Dunbartonshire and marks a significant milestone in our transition to
net zero new homes approved at the August 2022 meeting of the Housing
and Communities Committee.
The Practical completion was completed on time and handed over on 11th
April 2025 with the project delivering within project budget.
Pappert, Bonhill
This construction element of this development commenced in early March
2025, delivering the housing mix as follows: -
House Type Sustainability Standard Number of New
Homes
House 3bed/5 person Passivhaus 6
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6
The development is currently meeting all delivery targets and will be
completed in Summer 2025 with the first handovers planned for 28th April
2025.
Mount Pleasant, Old Kilpatrick
The site started on 15th April 2024 and construction was planned to last
approximately eighteen months.
This is a 19-unit complex which is designed for elderly residents and will
deliver exemplar high quality amenity housing, the housing mix is outlined
below for information. The site completion is scheduled for the 8th May 2025.
House Type Sustainability Standard Number of New
Homes
Bungalow 1bed/2person Net Zero 3
Flat 1bed/2person w/c Net Zero 4
Flat 1bed/2person Net Zero 4
Flat 2bed/4person Net Zero 8

Page 4

Willox Park, Doveholm, Dumbarton
The development of seventeen new homes for the elderly at a former care
home site is Phase 1 of the wider regeneration programme for Willow Park
and will comprise of the housing mix below.
House Type Sustainability Standard Number of New
Homes
Flat 2bed/3person Net Zero 2
Flat 1 bed/2person Net Zero 15
McTaggart Construction have been onsite since November 2024 with a 52
week build program, with the first handovers of Phase 1 due in December this
year.
The net zero heat strategy will be delivered via a ground source heat pump,
as it was felt that this solution to be preferable than an air source heat pump
for each individual home. 
Current tenants at Willox Park have been consulted throughout the design
process and this has continued with the contractor holding Q&A sessions. 
We are currently working with the existing tenants to ensure they have an up-
to-date housing application live to make sure the process of moving into the
new facility as easy and streamlined as possible.
The further phases of the regeneration works are a phased demolition
programme of the existing homes within the Willox Park sheltered housing
complex and the development of a minimum 20 new one-bedroom cottages to
replace the demolished homes.  To achieve this outcome, we require to
undertake a procurement exercise and award of the contracts up to the
budgeted value within the future new build and related regeneration project
line in the approved Housing Revenue Account Capital Investment
Programme.
Bonhill Gap Site Strategy
House Size Sustainability Standard Number of New
Homes
1bed wheelchair Net Zero 4
1 bed general needs Net Zero 16
2 bed wheelchair Net Zero 3
3 bed general needs Net Zero 3
4 bed general needs Net Zero 2
5 bed general needs Net Zero 4
7 bed general needs Net Zero 2
Planning has been granted for all sites.  CCG have been successful in
winning the tender for the Campbell St and Braehead development sites. The
tender cost was returned far below the estimated cost of the development. It

Page 5

was estimated that the construction of these two sites would be in the region
of £9.7million. The tender return was £6.98 million.
We are currently assessing the returned tenders for the remaining 6 units
proposed for O’Hare as part of this wider development.
Bank Street, Alexandria
The development will consist of twenty-two sheltered/amenity housing units in
partnership with the HSCP. Planning has been submitted and approved.
House Type Sustainability Standard Number of New
Homes
Flat 1bed/2person w/c Net Zero 22
Communal Room Net Zero 1
Staff Office Net Zero 1
The contract for this project has been awarded to the JR Group. This tender
return has returned a development price of £5.375m against an estimated
cost of £7.79million.
Similar to the development at Willox Park, existing tenants at Gray Street
have been consulted throughout the design process and will be assisted to
make the transition to the new facility as smooth as possible.
West Thomson Street (former Clydebank Health Centre site)
Demolitions of the former health centre building was completed in late 2024.
Having received the feasibility report for the site, the Council plans to develop
20+ units of sheltered/amenity housing to potentially reprovision or expand
existing sheltered housing provided at Young Street, therefore strategically
improving the provision of older persons accommodation within Clydebank.
We also aim to build additional family housing as part of the wider
development.
Tenants at Young Street have been consulted on the proposition of
developing a new sheltered complex on the old Clydebank Health Centre site.
This was met with a largely positive reaction and consultation with tenants,
staff and other stakeholders will continue throughout the design process. A
future consultation of the proposal is set up for Young Street Residents and
the wider community on the 30th April.
A multidisciplinary design team, led by Collective Architecture, who carried out
the feasibility study, have been appointed through the Scottish Procurement
Alliance framework to carry forward the above-mentioned site proposal
designs. They have begun the pre-application for Planning process along with
relevant consultation exercises.  Therefore, we now require to carry out a
wider procurement exercise to award and appoint a main contractor to deliver

Page 6

the new build development at West Thomson Street, Clydebank within the
agreed programme budget.
Proposed Housing Mix:
House Type Type Number of New
Homes
Terraced House 3 bed 5 person 4
Terraced House 4 bed 6 person 5
Terraced House 5 bed 7 person 2
Cottage Flat 1 bed 2 person 2
Cottage Flat 3 bed 5 person 2
Sheltered/Amenity Flat 1 bed 2 person 27
Gilmour Avenue, Hardgate
As part of the wider development of our Clydebank Gap Site strategy, the
Council identified a Housing Revenue Account site in the Hardgate area at
Gilmour Avenue.  The site was previously the location of timber garages on
concrete bases.  These have long since been demolished and the site has
been beset with fly tipping issues for several years.
The development started on site on 23/9/2024 and had a completion date of
14/2/25.  However, on the 3rd January 2025, Connect Modular, the main
contractor unfortunately entered administration. The Council is now working
towards the appointment of a new contractor and are aiming to complete the
homes in May.  The homes have been delivered on site and are over 80%
completed. The Council has secured the site.
Dennystoun Forge Gypsy/Traveller Site
The project has been scored and assessed as a priority in the new SHIP 2025
-2030, with a proposed site start in 2026/27.  Our in-house design team and
procurement colleagues are supporting Housing to detail our plans.
Engagement is continuous and positive with the Dennystoun Forge
community. Our focus remains on decant options, where we are engaging
with other Council teams on the possible use of an identified alternative site
for decanting during the works, and on procurement, where we have
consulted with other local authorities with experience of similar projects.   The
decant arrangements have thrown up a series of questions which we will be
discussing with the community.  While the costs for the decant site are likely
to be high, overall, we expect a saving to be achieved through giving the
eventual works contractor free access to the Dennystoun Forge site.  We
have had positive dialogue with the Scottish Government and discussions will
continue at a meeting on 12th May regarding the Gypsy Traveller
Accommodation Fund to become part of the Affordable Housing Supply
Programme.

Page 7

Queen Mary Avenue, Clydebank (Clydebank Gap Sites)
Proposed Housing Mix
House Type Type Number of New
Homes
Cottage Flat 1 bed 2 person 10
Wheelchair Cottage Flat 2 bed 3 person 1
Cottage Flat 3 bed 4 person 1
Terraced House 3 bed 6 person 3
Semi Detached 4 bed 8 person 2
A main contractor CCG has been appointed for the delivery of the proposed
17 new homes. The Council has started the pre-application planning process
and planning was submitted in March.  The team are working towards a start
date on site of October 2025.
Silverton Regeneration
The demolition for the 2 identified sites in Smollett Road and Dumbuie
Avenue has now been completed. We are currently developing a design
proposal and will carry out a feasibility assessment. 
Queens Quay, Site C, Clydebank
The Council has been developing a design to deliver a projected twenty units
on this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network.
.
Pre-planning response was received on the 25 February highlighting concern
of the WDC development proceeding in isolation. We have adopted a
proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have conducted valuations on the
adjacent site to Queens Quay C with a view to purchasing additional land to
deliver more affordable housing in the Queens Quay regeneration site. If this
is achieved, we would seek to develop a mixed tenure approach to any
expanded development site delivering one hundred new affordable homes.
We are seeking discussion with CRL (Clydeside Regeneration Limited) to
progress the possibility of acquiring this additional land and will be able to
draw down Scottish Government grant to enable this. However, because of
the uncertainties surrounding potential delivery timescales for this project and
the reduced funding it is no longer allocated funding within the current
Strategic Housing Investment Programme.
Buyback Programme
Total number of properties purchased in 2024/25 financial year 33
Total Purchase Value                         £3,103,000

Page 8

4.6 In 2024/25 the Council’s Annual Resource Planning Assumption (RPA) from
the Scottish Government supporting the delivery of the SHIP was reduced to
£8.167m which represented a cut of around 24%.  However, for 2025/26 the
RPA has been increased to a minimum of £10.757m this will significantly
assist in the delivery of the Council’s SHIP.
4.7 The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper.
5. People Implications
5.1 The delivery of the More Homes delivery programme is managed through
existing resource within the Housing Development & Homelessness team
funded from the Housing Capital Investment Programme. 
6. Financial and Procurement Implications
Financial
6.1 The Council has to date delivered 584 new homes for social rent; these
additional homes bring council tax revenue of around £810k per year to West
Dunbartonshire Council.  The new homes also bring in around £3m of annual
rental income to the Housing Revenue Account.
6.2 On 5 March 2025 supported by tenant representatives the Council approved
the Housing Capital Programme 2025-2030 which saw significant resources
committed to the delivery of new council homes in West Dunbartonshire.  A
net expenditure budget of £69m for the affordable housing supply programme
is factored into the HRA Capital Programme.  As it currently stands, it is
anticipated that this programme will complete on project life budget.
6.3 Housing and Finance Officers will continue to assess the ongoing affordability
of future developments within the context of the Housing Revenue Account
Business Plan.
Procurement
PROPERTY SIZE PURCHASED
6 apt 1
5 apt 3
4 apt 12
3 apt 5
2 apt 12

Page 9

6.4 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within 4.5 of this report will
continue to be prioritised. Where the contract award is less than £213,000,
authority is delegated to the Chief Officer in consultation with the Procurement
Manager to instruct the award of contracts for the planned revenue and
capital spend detailed in this report to suppliers providing the most
economically advantageous offer to the Council.
6.5 All procurement activity conducted by the Council more than £2m is.
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic, and environmental impact for the
Council through the relevant procurement processes will be developed in line
with procurement policy.
7. Risk Analysis
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis.
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel.
8 Environmental Sustainability
8.1 The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy.
9. Equalities Impact Assessment (EIA)
9.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
10. Consultation

Page 10

10.1 As part of a rent consultation exercise, 92% of respondents indicated their
support for the Council’s ambitious plans to deliver the Housing Revenue
Account (HRA) new council house build programme. In addition, there was
positive support for the wider delivery of new build housing as part of the
Local Housing Strategy consultation.  Regular updates on new build
development are provided to the West Dunbartonshire Tenants and Residents
Organisation at the bi-monthly liaison meetings.
11. Strategic Assessment
11.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
11.2 Having considered all the Council’s strategic priorities, this report, and the
provision of new supply social housing for rent contributes greatly to all the
Council’s strategic priorities.
Peter Barry
Chief Officer, Housing and Employability
Date: 23 April 2025
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk
Mikayla Deeley, Senior Housing Development Officer,
Housing Development and Homelessness Team,
Housing and Employability: email mikayla.deeley@west-
dunbarton.gov.uk
Appendices: None
Background Papers: West Dunbartonshire Council’s Local Housing Strategy
West Dunbartonshire Council’s Strategic Housing
Investment Plan
Local Housing Strategy, Health Inequalities Impact
Assessment
Wards Affected: All