Democracy Spraffa

Item 12 - HRA Capital Budgetary Control Report Period 7

West Dunbartonshire Council · 26 February 2025
Back to Housing & Communities Committee — 26 February 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

WEST DUNBARTONSHIRE COUNCIL 
Report by the Chief Officer – Resources 
Housing & Communities Committee  – 26 February 2025
___________________________________________________________________ 
Subject:  Housing Revenue Account (HRA) Capital   
Budgetary Control Report to 31 October 24 (Period 7) 
1. Purpose 
1.1 This report provides an update on the HRA capital programme to 31 October 
2024. 
2. Recommendations 
2.1 Members are asked to: 
i) Note the current position of the 2024/2025 HRA capital budget and the
HRA capital plan. 
ii) Note that in year financial performance is monitored against a
2024/2025 capital expenditure budget of £73.664m and a 2024/2025
capital income budget of £10.003m, a one-year borrowing requirement
of £63.661m. 
iii) Note that project life performance is monitored against a five-year
project life expenditure budget of £319.738m and a project life income
budget of £54.577m, a five-year borrowing requirement of £265.161m. 
iv) Note that there are eighteen projects reporting off track with an
anticipated over / under spend against their 2024/2025 budgets, with a
forecast net underspend of £2.918m in 2024/2025. 
v) Note that all projects are currently on track to achieve their planned
completion dates and to deliver within their respective five-year project
life budgets.    
3. Background 
3.1 On 6 March 2024 the Council approved the updated Housing Revenue
Account Capital Plan for 2024/2025 to 2028/2029. 
3.2  Since then budget adjustments have taken place to bring forward in year 
project under/over spends during 2023/2024, to reflect up to date information
on progress delivering the plan and any need for budget acceleration and
budget deceleration from / to future years, and to update the expenditure and
income budgets for Affordable Housing Supply projects to reflect the
2023/2024 outturn and to reflect that the most recent cost and income
forecasts  The budget adjustments result in revised capital budgets as set out
in Exhibit 1.   
Item 12

Page 2

Exhibit 1: Revised HRA Capital Budget 2024/2025 – 20278/2029 
2024/25
BCR07 
(£m)
Project
Life
BCR07 
(£m) 
Project Life
March 24 
(£m)
Other Capital Expenditure  7.165 27.129  27.180
Major Component Replacement   19.795 92.604  92.604
Void Capital  4.902 19.212  20.712
Structural & Environmental   2.767 14.175  14.175
Support Costs  2.761 14.367  14.367
Affordable Housing Supply
Programme 
36.274 152.251  149.053
Total Expenditure  73.664 319.738  318.091
Total Income   10.003 54.577  47.029
Prudential Borrowing  63.661 265.161            271.062 
4. Main Issues 
4.1 Progress against the 2024/25 capital plan is detailed in: 
Appendix 1 – HRA Capital Summary BCR07 
Appendix 2 – HRA Capital Detail BCR07 
4.2  The HRA capital summary report at Appendix 1 reports that planned
expenditure and planned income are both in line with the overall project
budgets. Appendix 1 reports that there are twenty-eight capital projects where
expenditure / income budget is tracked over the multi-year life of the project
and twenty-nine projects classified as rolling programme projects /
contingency / fees, that is programmes of work where an annual budget is set
each year that takes account of demand, cost, and affordability. 
4.3  Appendix 2 shows all projects with approved in year and project life budgets
as well as forecast expenditure / income. The appendix highlights a
2024/2025 expenditure budget of £73.664m and a forecast spend of
£70.486m, an underspend of £3.178m (4.3% of the 2024/2025 budget) The
2024/2025 capital income budget is £10.003m, with a forecast income of
£9.743m.

Page 3

4.4 Commentary on the 2024/2025 expenditure variances are set out in Exhibit 2
below. 
Exhibit 2: Project Over / Underspends 2024/2025 
Project 
2024/2025
BCR07 
Forecast 
(£m) 
2024/2025
BCR07
Budget
(£m) 
2024/2025
Variance 
(£m)
Commentary
1 Special Need
Adaptations 
0.506 0.655 (0.149) • Reduced throughput
of capital
adaptations this
year 
• Inhouse adaptations
team is fully up to
date with its order
books.
• Improved
performance with
average time of 46
days. 
• Underspend will be
available for
reprofiling in future
years. 
2 Capitalised
Minor Works
4.116 3.000 1.116 • Transfer of Electrical
Installation
Condition Works
`spend to minor
works budget.
• Overspend will be
re-profiled over
future years. 
• Officers are
increasingly
directing minor
works requests to
the relevant planned
capital programme. 
3 Environmental
Sensors
1.620 2.000 (0.380) • Excellent progress
with this programme
with an anticipated
2,000 sensors due
to be installed this
year. 
• Underspend reflects
the mobilization

Page 4

Project 
2024/2025
BCR07 
Forecast 
(£m) 
2024/2025
BCR07
Budget
(£m) 
2024/2025
Variance 
(£m)
Commentary
period and
challenges in getting
access to
properties. 
• Underspend will be
available for
reprofiling in future
years. 
4 Roofing Works  2.201 2.500 (0.299) • Underspend reflects
the changing mix of
the capital
programme with an
increased number of
mixed tenure blocks
that require owner
consent before work
can start. This
necessary process
delay project start 
• Underspend will be
available for
reprofiling in future
years. 
5 Void House
Works 
5.438 4.902 0.536 • Transfer of
increased void
spend to HRA
capital account
following a review.
• Void delivery costs,
including overtime
on voids and
contractor spend,
have reduced as
void number have
reduced.
• Overspend will be
re-profiled over
future years. 
6 Environmental
Works
0.992 1.068 (0.076) • Reduced throughput
of environmental
works this year
because operatives
have also worked
across other HRA
service areas.

Page 5

Project 
2024/2025
BCR07 
Forecast 
(£m) 
2024/2025
BCR07
Budget
(£m) 
2024/2025
Variance 
(£m)
Commentary
• Underspend will be
available for
reprofiling in future
years. 
7 Contingency 0.000 0.100 (0.100) • Contingency
released to offset
cost pressures
across the HRA
capital account. 
8 Clydebank East  9.896 9.700 0.196 • Good progress with
development and is
ahead of previous
projection
• 32 homes handed
over to date 
9 Pappert 
Expenditure 
7.446 9.653 (2.207) • Development now
on site and cash
flow accurately
based on agreed
programme of works
and this is reflected
in the projection 
• No impact on overall
project budget or
timescales and
development on
track 
Pappert 
Income 
(2.803) (3.303) 0.500 • Affordable Housing
Supply Programme
grant funding
reprofiled 
10 Queen Mary
Avenue 
0.010 0.120 (0.110) • Affordable Housing
Supply Programme
grant funding
reprofiled

Page 6

Project 
2024/2025
BCR07 
Forecast 
(£m) 
2024/2025
BCR07
Budget
(£m) 
2024/2025
Variance 
(£m)
Commentary
11 Queens Quay
Site C
Expenditure 
0.000 1.000 (1.000) • Underspend reflects
delays progressing
this project within a
financial viability
assessment 
Queens Quay
Site C
Income 
0.000 (1.000) 1.000 • The acquisition
grant funding
because of the
project not been
taken forward 
12 Dennystoun
Forge
0.060 0.250 -0.190 • Revised projection
based on
development project
plan 
13 Future New
Build & Related
Regeneration
Projects /
Professional
Fees 
0.500 1.015 -0.515 • Ongoing review of
the programme
allowed non
committed funds to
be released to offset
cost pressures
across the HRA
capital account. 
Future New
Build & Related
Regeneration
Projects 
Income 
(0.200) 0.000 (0.200) • Ongoing review of
the programme
allowed non
committed funds to
be released to offset
cost pressures
across the HRA
capital account. 
14 Buyback Grant
Income
(2.417) (2.858) 0.441 • Revised projection
based on the
distribution of
Scottish
Government
acquisition funding 
15 7 – 9 Gilmour
Avenue 
Income 
(0.215) (0.195) (0.020) • Revised projection
based on the
application of the
Strategic Local
Programme

Page 7

Project 
2024/2025
BCR07 
Forecast 
(£m) 
2024/2025
BCR07
Budget
(£m) 
2024/2025
Variance 
(£m)
Commentary
16 Bank Street 
Income 
(0.518) 0.000 (0.518) • Revised projection
based on the
application of the
Strategic Local
Programme 
17 Bonhill Gap
Sites 
Income 
(0.514) 0.000 (0.514) • Revised projection
based on the
application of the
Strategic Local
Programme 
18 Silverton 
Income
(0.429) 0.000 (0.429) • Revised projection
based on the
application of the
Strategic Local
Programme 
(2.918) 
4.5 Budget assumptions are required to forecast costs / income, especially where
projects span multi-year and project finances have yet to be finalised. It is
therefore likely that the projected year end budgetary position will change
during the year. 
5. Option Appraisal 
5.1 No option appraisal was required for this report. 
6. People Implications 
6.1 There are no people implications. 
7. Financial and Procurement Implications 
7.1 The report notes the projected in-year financial position for capital budgets.

Page 8

8. Risk Analysis 
8.1 The main risks are as follows: 
(a) The reported variances should be viewed in the knowledge that there
are several variable factors which could arise between now and 31
March which could affect the year end results for capital budgets. 
(b) Because of current market conditions, inflation is at an all-time high and
interest rates continue to be volatile. To forecast for the full year costs
budget assumptions have been required. These assumptions continue to
change regularly and therefore it is likely the projected year end
budgetary position will change from that reported. 
9. Equalities Impact Assessment (EIA) 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability 
10.1 No assessment of environmental sustainability was required in relation to this
report. 
11. Consultation 
11.1 All services involved in delivering the capital budgets have been consulted
during the compilation of this report. 
12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council. 
________________
Laurence Slavin
Chief Officer – Resources
Date: 26 February 2025 
Person to Contact: Jim McCarron 
Business Partner, Finance 07772 322055  
E-mail: james.mccarron@west-dunbarton.gov.uk 
Appendices: Appendix 1 -  HRA Capital Summary BCR07 
Appendix 2-  HRA Capital Details BCR07 
Background Papers: 
Housing Revenue Account (HRA) Capital Investment Programme, Revenue
Budget, and Rent Levels for 2024/25 - Council 6 March 2024. 
Wards Affected           All Wards