WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 26 February 2025
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme
1. Purpose
1.1      This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Notes the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach,
including the first handovers of new homes at the zero carbon Clydebank
East development which represents the 500th new build the Council has
developed under the current More Homes programme; and
(ii) Notes the remedial actions being undertaken by Council Officers in
response to Connect Modular entering into administration as the Gilmour
Avenue housing development contractor
3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over one thousand new affordable homes in
West Dunbartonshire to date and includes the Council’s own ambitious New
House Building Programme.
3.2 The Council’s last full practical completion took place at the Queens Quay
development in September 2022 delivering twenty-nine new Council homes in
a key regeneration area as part of a wider development which has delivered
146 new social rented homes.  The homes were the first residential properties
to be heated from the Council’s Queens Quay District Heating Network. This
development was recognised at national housing sector awards winning the
following: -
 Best Residential Regeneration Project – Herald Property Awards
 Inside Housing Best Residential Development (Scotland)
Item 11

Page 2

3.3 These 29 new homes, are in addition to the completion of the Council’s first
fully dementia designed development at Creveul Court, Alexandria and other
exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton
Harbour and St Andrews, Clydebank.  The Council have now completed
twelve new build developments since 2013 and are the largest developer of
social homes in West Dunbartonshire delivering 508 new homes and 137
acquisitions through our buyback scheme to date as outlined in Table 1
below.  The 500th new build home in the More Homes West Dunbartonshire
delivery programme was delivered in October 2024 at our current Clydebank
East development which will fully complete in April 2025:
Table 1:  Completed Council New Build and Acquisitions
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank 126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank 29 August 2022
Clydebank East, Clydebank 46 Ongoing
Buyback Acquisitions 158 Ongoing
Totals 700
3.4     The Strategic Housing Investment Plan (SHIP) 2025-2030, outlining West   
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2024. The SHIP outline plans to
contribute to meet the Council Administration’s aim of delivering 2500 new
affordable and social rented homes over the 10-year period 2022-2032.
4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic and economic recovery
plans, negating the impacts of the current cost of living crisis and combatting
poverty principally child and fuel poverty.  It is also clear that the need for
affordable homes has and will increase in the current ongoing economic
environment.
4.2 The Council’s More Homes West Dunbartonshire approach is an ambitious
plan that aims to continue the positive momentum of the delivery of much

Page 3

needed Council homes in West Dunbartonshire and will significantly assist the
Council’s aim to deliver 2500 new social and affordable homes by 2032.
4.3 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified several future development sites for new council homes
to address existing and new housing need. The design of these homes will
further develop, improve, and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low
carbon ambitions including passivhaus and other net zero carbon
opportunities.
4.4 The Council’s More Homes West Dunbartonshire approach has evidenced
strong support from council tenants and was recently highlighted as one of the
two key future spending priority areas for tenants through the comprehensive
tenant satisfaction survey undertaken in late 2024. 
4.5 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  An update on
each development site is provide below: -
Clydebank East:
This development will deliver eighty-eight new homes and has been designed
to meet the housing need within the wider West Dunbartonshire area. The
table below shows the housing mix:
House Type Sustainability Standard Number of New
Homes
Wheelchair Bungalow
3bed/4person
Net Zero 3
House 3bed/5person Net Zero 15
House 4 bed/7person Net Zero 12
House 5 bed/8 person Net Zero 8
Wheelchair Cottage Flat
1bed/2 person
Net Zero 4
Cottage Flat 2 bed/4 person Net Zero 4
Flat 1 bed/2person Net Zero 16
Flat 2 bed/4 person Net Zero 24
Wheelchair Flat 1 bed/2person Net Zero 2
Works commenced on this development in January 2023. The first 12 units
were handed over on 7th October 2024. Sectional handovers of the 3-, 4- and
5-bedroom houses have now been completed (46 units). The handover of the
flatted accommodation will begin at the end of February. Practical completion
and handover of all 88 new homes is currently estimated for the 11th April
2025.
All homes are designed to the Housing for Various Needs Standard (HfVN).
There will be nine fully Wheelchair (WCH) accessible properties. The 4- and 5
-bedroom homes have ground floor double bedrooms.

Page 4

The development at Clydebank East sees the completion of a major housing
led regeneration of a key priority regeneration area identified in the Local
Housing Strategy and will be the first fully zero carbon housing development
in West Dunbartonshire and marks a significant milestone in our transition to
net zero new homes approved at the August 2022 meeting of the Housing
and Communities Committee. 
We have previously reported award of above benchmark grant due to the
complexities of the development at Clydebank East this resulted in a total
grant award of £12.6m, this equates to over £143k grant per home and
around £4.68m more than the benchmark grant award this ensured the
delivery of the development without any negative impact on the wider Housing
Revenue Account.
Pappert, Bonhill
This development element of this development commenced in early March
2025, delivering the housing mix as follows: -
House Type Sustainability Standard Number of New
Homes
House 3bed/5 person Passivhaus 6
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6
The development is currently meeting all delivery targets and will be
completed in Summer 2025.
Mount Pleasant, Old Kilpatrick
The site started on 15th April 2024 and construction will last approximately one
year.
This is a 19-unit complex which is designed for elderly residents and will
deliver high quality amenity housing, the housing mix is outlined below for
information.
House Type Sustainability Standard Number of New
Homes
Bungalow 1bed/2person Net Zero 3
Flat 1bed/2person w/c Net Zero 4
Flat 1bed/2person Net Zero 4
Flat 2bed/4person Net Zero 8
Willox Park, Doveholm, Dumbarton

Page 5

The development of seventeen new homes for the elderly at a former care
home site will comprise of the housing mix below.
House Type Sustainability Standard Number of New
Homes
Flat 2bed/3person Net Zero 2
Flat 1 bed/2person Net Zero 15
This development has now been granted planning permission and a
contractor, McTaggart Construction, has been appointed to begin the
construction phase. Construction will commence in November on this project.
The net zero heat strategy will be delivered by ground source heat pump, as it
was felt that this solution to be preferable than an air source heat pump for
each home. 
Current tenants at Willox Park have been consulted throughout the design
process and this has continued with the contractor holding Q&A sessions. 
We are currently working with the existing tenants to ensure they have an up-
to-date housing application live to make sure the process of moving into the
new facility is as easy and streamlined as possible.
Bonhill Gap Site Strategy
House Size Sustainability Standard Number of New
Homes
1bed wheelchair Net Zero 4
1 bed general needs Net Zero 16
2 bed wheelchair Net Zero 3
3 bed general needs Net Zero 3
4 bed general needs Net Zero 2
5 bed general needs Net Zero 4
7 bed general needs Net Zero 2
Planning has been submitted for all sites with approval granted for Campbell
St and forthcoming for Braehead and O’Hare development sites.
A contractor has been appointed to deliver the Campbell St and Braehead
development sites. The tender cost was returned over £2m below the
estimated cost of the job illustrating a competitive tender result. As illustrated
in the table above the developments feature large family homes.
The tender for O’Hare is due back 14th February 2025.
Bank Street, Alexandria
The development will consist of twenty-two sheltered/amenity housing units in
partnership with the HSCP. Planning has been submitted.

Page 6

House Type Sustainability Standard Number of New
Homes
Flat 1bed/2person w/c Net Zero 22
Communal Room Net Zero 1
Staff Office Net Zero 1
A planning decision was expected at the end of November. However there
has been a delay in planning consent.
The contract for this project has been awarded. This tender return has
returned a competitive price around £2m below the estimated delivery costs.
Similar to Willox Park, tenants at Gray Street have been consulted throughout
the design process and will be assisted to make the transition as smooth as
possible.
Clydebank Health Centre
Demolitions of the former health centre building was completed in late 2024.
Having received the feasibility report for the site, the Council plans to develop
20+ units of sheltered housing to reprovision existing sheltered housing
currently provided at Young Street, therefore strategically improving the
provision of sheltered accommodation within Clydebank. We also aim to build
around 10-15 units of mostly family housing.
The Council have discussed proposals with tenants at Young Street on the
proposition of developing a new sheltered complex on the old Clydebank
Health Centre site. This was met with a largely positive reaction and
consultation with tenants, staff and other stakeholders will continue
throughout the design process.
A multidisciplinary design team, led by Collective Architecture, who carried out
the feasibility study, have been appointed through the Scottish Procurement
Alliance framework to carry forward the above-mentioned site proposal
designs. They have begun the pre-application for Planning process along with
relevant consultation exercises. 
Gilmour Avenue, Hardgate
As part of the wider development of our Clydebank Gap Site strategy, the
Council identified a Housing Revenue Account site in the Hardgate area at
Gilmour Avenue.  The site was previously the location of timber garages on
concrete bases.  These have long since been demolished and the site has
been beset with fly tipping issues for several years.
The development started on site on 23/9/2024 and had a completion date of
14/2/25.  However, on the 3rd January 2025, Connect Modular, the main
contractor unfortunately entered administration. The Council is now working
towards the appointment of a new contractor with minimal delay to completion

Page 7

and are aiming to complete the homes this financial year.  The homes have
been delivered on site and are over 80% completed. The Council has secured
the site and taken over the site security contract.
Dennystoun Forge Gypsy/Traveller Site
The project has been scored and assessed as a priority in the new SHIP 2025
-2030, with a proposed site start in 2026/27.  Our in-house design team and
Procurement colleagues are proceeding to detail our plans.
Engagement continuous with the Dennystoun Forge community. Our focus
remains on decant options, where we are engaging with our Assets and
Planning colleagues on the possible use of an identified alternative site for
decanting during the works, and on procurement, where we have consulted
with other local authorities with experience of similar projects.   The decant
arrangements have thrown up a series of questions which we will be
discussing with the community.  While the costs for the decant site are likely
to be high, overall, we expect a saving to be achieved through giving the
eventual works contractor free access to the Dennystoun Forge site.
Queen Mary Avenue, Clydebank (Clydebank Gap Sites)
House Type Sustainability Standard Number of New
Homes
1 bed/2 person  Cottage Flat Net Zero 10
2 bed/3 person WCH Cottage Flat Net Zero 1
3 bed/4 person Cottage Flat Net Zero 1
3 bedroom terraced house Net Zero 3
4 bedroom semi-detached Net Zero 2
The transfer of the site at Queen Mary Avenue, Clydebank with vacant
possession at the cost of £140,000 from the Council’s General Fund to the
Housing Revenue Account for the delivery of new Council homes was
approved at the February meeting of the Housing and Communities
Committee and has now been concluded.
A main contractor has been appointed for the delivery of the proposed 17 new
homes. The Council has started the pre-application planning process and are
hopeful to submit for planning at the end of February. Community consultation
has been scheduled prior to the Planning submission.
Silverton Regeneration
The demolition for the 2 identified sites in Smollett Road and Dumbuie
Avenue has now been completed. We are currently engaging with our
colleagues in consultancy services around the design for the housing on the
site. 
Queens Quay, Site C, Clydebank

Page 8

The Council has been developing a design to deliver a projected twenty units
on this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network.
.
Pre-planning response was received on the 25 February highlighting concern
of the WDC development proceeding in isolation. We have adopted a
proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have conducted valuations on the
adjacent site to Queens Quay C with a view to purchasing additional land to
deliver more affordable housing in the Queens Quay regeneration site. If this
is achieved, we would seek to develop a mixed tenure approach to any
expanded development site delivering one hundred new affordable homes.
We are seeking discussion with CRL (Clydeside Regeneration Limited) to
progress the possibility of acquiring this additional land and will be able to
draw down Scottish Government grant to enable this. However, because of
the uncertainties surrounding potential delivery timescales for this project and
the reduced funding it is no longer allocated funding within the current
Strategic Housing Investment Programme.
Buyback Programme
Total number of properties purchased in 2024/25 financial year 28
Total Purchase Value                         £2,635,000
The twenty-eight acquisitions include fourteen larger family properties
comprising of three bedrooms or more. The strategic approach to acquire
homes that are aligned to housing need and the increased home valuations in
West Dunbartonshire have required that we amend our target for 2024/25
from sixty acquisitions to forty through the buyback scheme. However,
additional buyback acquisitions will be delivered through the National
Acquisition Scheme, Ukrainian Long Term Resettlement Fund and local
housing association schemes which will ensure the Strategic Housing
Investment Plan target of sixty acquisitions is achieved.
4.6    The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper.
5. People Implications
5.1 The delivery of the More Homes delivery programme is managed through
existing resource within the Housing Development & Homelessness team
funded from the Housing Capital Investment Programme. 
6. Financial and Procurement Implications

Page 9

Financial
6.1 On 6 March 2024 Council approved the Housing Capital Programme 2023-
2028 which saw significant resources committed to the delivery of new council
homes in West Dunbartonshire.  An expenditure budget of £155m for the
affordable housing supply programme is factored into the HRA Capital
Programme this will be updated to reflect the income and expenditure
highlighted within this report.  As it currently stands, it is anticipated that this
programme will complete on project life budget.
6.2 Housing and Finance Officers will continue to assess the ongoing affordability
of future developments within the context of the Housing Revenue Account
Business Plan.
6.3 The Council has to date delivered 542 new homes for social rent, these
additional homes bring council tax revenue of around £670k per year to West
Dunbartonshire Council.
Procurement
6.4 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within 4.5 of this report will
continue to be prioritised. Where the contract award is less than £213,000,
authority is delegated to the Chief Officer in consultation with the Procurement
Manager to instruct the award of contracts for the planned revenue and
capital spend detailed in this report to suppliers providing the most
economically advantageous offer to the Council.
6.5 All procurement activity conducted by the Council more than £2m is
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic, and environmental impact for the
Council through the relevant procurement processes will be developed in line
with procurement policy.
7. Risk Analysis
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis.
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings

Page 10

of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel.
8 Environmental Sustainability
8.1 The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy.
9. Equalities Impact Assessment (EIA)
9.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
10. Consultation
10.1 As part of a rent consultation exercise, 92% of respondents indicated their
support for the Council’s ambitious plans to deliver the Housing Revenue
Account (HRA) new council house build programme. In addition, there was
positive support for the wider delivery of new build housing as part of the
recent Local Housing Strategy.  Regular updates on new build development
are provided to the West Dunbartonshire Tenants and Residents Organisation
at the bi-monthly liaison meetings.
11. Strategic Assessment
11.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
11.2 Having considered all the Council’s strategic priorities, this report, and the
provision of new supply social housing for rent contributes greatly to all the
Council’s strategic priorities.
Peter Barry
Chief Officer, Housing and Employability
Date: 13 February 2025
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk

Page 11

Mikayla Deeley, Senior Housing Development Officer,
Housing Development and Homelessness Team,
Housing and Employability: email mikayla.deeley@west-
dunbarton.gov.uk
Appendices: None
Background Papers: West Dunbartonshire Council’s Local Housing Strategy
Local Housing Strategy, Health Inequalities Impact
Assessment
Wards Affected: All