WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Housing and Communities Committee: 20 November 2024
___________________________________________________________________
Subject: Housing Revenue Account (HRA) Capital  
Budgetary Control Report to 31 August 24 (Period 5)
1. Purpose
1.1 This report provides an update on the HRA capital programme to 31 August
2024.
2. Recommendations
2.1 Members are asked to:
i) Note the current position of the 2024/2025 HRA capital budget and the
HRA capital plan.
ii) Note that in year financial performance is monitored against a
2024/2025 capital expenditure budget of £73.664m and a 2024/2025
capital income budget of £10.003m, a one-year borrowing requirement
of £63.661m.
iii) Note that project life performance is monitored against a five-year
project life expenditure budget of £319.738m and a project life income
budget of £54.577m, a five-year borrowing requirement of £265.161m.
iv) Note that there are six projects reporting off track with an anticipated
over / under spend against their 2024/2025 budgets, with a forecast net
overspend of £0.334m in 2024/2025.
v) Note that all projects are currently on track to achieve their planned
completion dates and to deliver within their respective five-year project
life budgets.
3. Background
3.1 On 6 March 2024 the Council approved the updated Housing Revenue
Account Capital Plan for 2024/2025 to 2028/2029.
3.2 Since then budget adjustments have taken place to bring forward in year
project under/over spends during 2023/2024, to reflect up to date information
on progress delivering the plan and any need for budget acceleration and
budget deceleration from / to future years, and to update the expenditure and
income budgets for Affordable Housing Supply projects to reflect the
2023/2024 outturn and to reflect that the most recent cost and income
forecasts  The budget adjustments result in revised capital budgets as set out
in Exhibit 1.
ITEM 19

Page 2

Exhibit 1: Revised HRA Capital Budget 2024/2025 – 20278/2029
2024/25
BCR05 
(£m)
Project Life
BCR05 
(£m)
Project Life
March 24 
(£m)
Other Capital Expenditure 7.165 27.129 27.180
Major Component Replacement  19.795 92.604 92.604
Void Capital 4.902 19.212 20.712
Structural & Environmental  2.767 14.175 14.175
Support Costs 2.761 14.367 14.367
Affordable Housing Supply Programme  36.274 152.251 149.053
Total Expenditure 73.664 319.738 318.091
Total Income  10.003 54.577 47.029
Prudential Borrowing 63.661 265.161           271.062
4. Main Issues
4.1 Progress against the 2024/25 capital plan is detailed in:
Appendix 1 – HRA Capital Summary BCR05
Appendix 2 – HRA Capital Detail BCR05
4.2 The HRA capital summary report at Appendix 1 reports that planned
expenditure and planned income are both in line with the overall project
budgets. Appendix 1 reports that there are twenty-nine capital projects where
expenditure / income budget is tracked over the multi-year life of the project
and twenty-eight projects classified as rolling programme projects, which is
programmes of work where an annual budget is set each year that takes
account of demand, cost, and affordability.
4.3 Appendix 2 shows all projects with approved in year and project life budgets
as well as forecast expenditure / income. The appendix highlights a
2024/2025 expenditure budget of £73.664m and a forecast spend of
£73.998m, a net overspend of £0.334m (0.005% of the planned 2024/2025
spend) The 2024/2025 capital income budget is £10.003m, with a forecast
income of £10.003m.
4,4 Commentary on the 2024/2025 expenditure variances are set out in Exhibit 2
below.
Exhibit 2: Project Over / Underspends 2024/2025
Project 
2024/2025
BCR05 
Forecast 
(£m) 
2024/2025
BCR05 
Budget
(£m) 
2024/2025
Variance 
(£m)
Commentary
Special Need Adaptations 0.552 0.655 -0.103 • Reduced throughput of capital adaptations this
year
• Inhouse adaptations team is fully up to date
with its order books.
• Improved performance with average time of 46
days.
• Underspend will be available for reprofiling in
future years.

Page 3

Project 
2024/2025
BCR05 
Forecast 
(£m) 
2024/2025
BCR05 
Budget
(£m) 
2024/2025
Variance 
(£m)
Commentary
Capitalised Minor Works 3.964 3.000 0.964 • Transfer of Electrical Installation Condition
Works `spend to minor works budget.
• Overspend will be re-profiled over future years.
• Officers are increasingly directing minor works
requests to the relevant planned capital
programme.
Environmental Sensors 1.365 2.000 -0.635 • Excellent progress with this programme with an
anticipated 2,000 sensors due to be installed
this year.
• Underspend reflects the mobilization period
and challenges in getting access to properties.
• Underspend will be available for reprofiling in
future years.
Roofing Works  2.033 2,500 -0.467 • Underspend reflects the changing mix of the
capital programme with an increased number of
mixed tenure blocks that require owner consent
before work can start. This necessary process
delay project start
• Underspend will be available for reprofiling in
future years.
Void House Works 5.733 4.902 0.831 • Transfer of increased void spend to HRA capital
account following a review.
• Void delivery costs, including overtime on voids
and contractor spend, have reduced as void
number have reduced.
• Overspend will be re-profiled over future years.
Environmental Works 0.910 1.068 -0.158 • Reduced throughput of environmental works
this year because operatives have also worked
across other HRA service areas.
• Underspend will be available for reprofiling in
future years.
Contingency - 0.100 -0.100 • Contingency released to offset cost pressures
across the HRA capital account.
0.334
4.5 Budget assumptions are required to forecast costs / income, especially where
projects span multi-year and project finances have yet to be finalised. It is
therefore likely that the projected year end budgetary position will change
during the year.
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.

Page 4

7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there
are several variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.
(b) Because of current market conditions, inflation is at an all-time high and
interest rates continue to be volatile. To forecast for the full year costs
budget assumptions have been required. These assumptions continue to
change regularly and therefore it is likely the projected year end
budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted
during the compilation of this report. 
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
________________
Laurence Slavin
Chief Officer – Resources
Date: 20 November 2024
Person to Contact: Jim McCarron
Business Partner, Finance 07772 322055
E-mail: james.mccarron@west-dunbarton.gov.uk
Appendices: Appendix 1 - HRA Capital Summary BCR05
Appendix 2- HRA Capital Details BCR05  
Background Papers:
Housing Revenue Account (HRA) Capital Investment Programme, Revenue Budget, and Rent
Levels for 2024/25 - Council 6 March 2024.
Wards Affected    All Wards