WEST DUNBARTONSHIRE COUNCIL
HRA REVENUE BUDGETARY CONTROL 2024/25
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31 August 2023
PERIOD 5
Budget
2024/25
Forecast
Spend
2024/25
£000 £000 £000 %
Employee Costs 7,661 7,283 (378) -5% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget
2024/25
Forecast
Spend
2024/25
£000 £000 £000 %
Other Expenditure 330 560 230 70% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget
2024/25
Forecast
Spend
2024/25
£000 £000 £000 %
Repairs & Maintenance 15,208 13,393 (1,815) -12% 
Main Issues
Mitigating Action
Anticipated Outcome
Variance Analysis
Subjective Analysis Forecast Variance
2024/25
RAG
Status
Officers have reviewed the repairs spend and identified a potential saving against the
2024/2025 repair and maintenance budget by transferring spend charged to revenue to the
capital programme. A review of specific workstreams identified revenue funded works that
extend the lifespan of the assets. Specifically work carried out in void properties to bring these
back to relet standard are significant and include component renewals.
Furthermore, the completion of an Electrical Installation Condition Report (EICR) is
complementary to the environmental sensor installation programme.
Subjective Description
Responsive and planned repair and maintenance services to houses and lockups and income recovered from tenant rechargeable and owner
occupier repairs.
Variance Narrative
A high  volume of repair orders and ongoing inflationary pressures are driving up costs, with the
most significant pressures across responsive repair and void repair budgets.
A year end underspend
A rent abatement overspend of £100k is forecast because demand is exceeding the new
reduced abatement budget. It is worth noting that the 2024/2025 rent abatement spend is
forecast to be circa £250,000 less than the 2023/2024 spend.
A year end overspend.
Forecast Variance
2024/25
Subjective Description
Rent abatements, support for young tenants, legal and banking expenses, and other sundry costs.
Variance Narrative
Subjective Analysis RAG
Status
Housing Operations and Building Service will continue to place the strictest controls over the
abatement process to minimise this spend.
Variance Analysis
Variance Analysis
Forecast Variance
2024/25
Subjective Description
Subjective Analysis RAG
Status
Cost of employees charged directly to the HRA.
Variance Narrative
An employee cost underspend is anticipated as management target staffing efficiencies,
including tighter controls on staff recruitment and overtime.
None required.
A year end underspend.
ITEM 17 -
APPENDIX 2

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
HRA REVENUE BUDGETARY CONTROL 2024/25
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31 August 2023
PERIOD 5
Budget
2024/25
Forecast
Spend
2024/25
£000 £000 £000 %
Void Loss (Council Tax / Lost Rents) 1,109 1,282 173 16% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget
2024/25
Forecast
Spend
2024/25
£000 £000 £000 %
Loan Charges 22,092 26,041 3,949 18% 
Main Issues
Mitigating Action
Anticipated Outcome
Variance Analysis
Subjective Analysis Forecast Variance
2024/25
RAG
Status
The Council will continue to actively manage its external / internal borrowing to ensure that it
minimises borrowing costs.
Subjective Description
Loans Fund repayments and the payment of interest and expenses on outstanding HRA debt.
Local authority borrowing costs for medium / long term Public Works Loan Board (PWLB) debt
and short term debt have remained  high. The higher interest rates are driving up HRA debt
financing costs. The HRA budget assumed that borrowing rates would reduce in 2024/2025.
Whilst Interest rates were originally expected to fall over the course of this year, we now expect 
rates to remain high for the remainder of ths financial year.
A year end overspend.
Variance Analysis
Forecast Variance
2024/25
Variance Narrative
Subjective Analysis RAG
Status
Variance Narrative
Council tax payments for longer term void houses are forecast to exceed budget. There is
limited  progress being made with utility companies as council  staff try and resolve debt on
meters and meter reconnections. The poor performance of the utility companies adversely
impacts on the length of time properties are void and leads to more empty properties incurring a
council tax liability.
Housing staff will continue to engage with utility companies to highlight meter issues that are
preventing properties being available for let. Housing and Building Services staff will continue to
prioritise the repair and subsequent allocation of longer term void properties.
A year end overspend.
Subjective Description
Lost rental income for void houses and lockups and the cost of council tax on long term void properties