ITEM 16 
WEST DUNBARTONSHIRE COUNCIL 
Report by the Chief officer Housing and Employability
Housing and Communities Committee: 20 November 2024 
Subject: Building Services Update 
1. Purpose 
1.1 The Purpose of this report is to advise Committee of changes to
Building Services establishment and delivery model and seek approval
to continue with procurement and tender processes. 
2. Recommendations 
2.1 It is recommended that Members: 
i. note the contents of this report. 
ii. approve the procurement processes to tender the requirements
listed within the table in section 4.6 of this report; and 
iii. delegate authority to the Chief Officer of  Regulatory and
Regeneration to award contracts to successful bidders 
3. Background 
3.1 Changes to the structure and delivery model of Building Services have
been implemented over the last two years and we are now in a position
to implement further improvements. 
3.2 A report was presented to the Strategic Review and Renewal Group on
17 October 2024 seeking approval to implement the phase 3 of the
Review of Building Services. This included the externalisation of the
reroofing programme and the resizing of the painter establishment
resource both of which were approved. 
3.3 Good progress continues to be made in contracting to ensure full
compliance with Council Standing Orders, Council Financial
Regulations and all Procurement Regulation.
4. Main Issues
4.1 Over the last two years, significant and unprecedented pressure on the
HRA budget has emerged, and HRA costs in both revenue and capital
budgets must be reviewed for Best Value.

Page 2

4.2 Building Services has delivered the Council’s capital funded reroofing
programme for over 15 years. Despite improvements in efficiencies and
productivity, continuing to deliver the programme in-house is not
economically viable when compared to costs of external contractors,
which are substantially cheaper. 
4.3 Very few tenants only blocks requiring new roofs remain and owners in
mixed tenure blocks seek the cheapest option possible. Obtaining
owner buy-in is proving difficult given these cost issues, which in turn
delays improvements in living conditions for our tenants in these
blocks. 
4.4 Officers are progressing with arrangements to externalise the Housing
Capital funded reroofing programme. 
4.5 Changes in the way empty homes are repaired to the Council’s relet
standard have also resulted in a significant reduction in the amount of
painter work which is carried out in void properties. This has resulted
in having more painters than there is work for, and consequently there
is a requirement to reduce the size of the painter establishment by 6. 
4.6 For Supply and Delivery of Building Materials, the following contracts
will be required to deliver a comprehensive repairs and maintenance
service for a period of up to four years from the date of let. They will be
of sufficient size, scope and duration to cover the estimated volume of
work for the period in question and will be awarded to suitably qualified
and competent suppliers and contractors. A review of the historic
spend on the previous versions of these contracts and estimated
volumes of known and expected works has taken place, costs identified
are expected to have increased over the intervening period and
projected costs are set out in the table below 
Requirement Total
Estimated
Annual
Value
Funded By
HRA
Revenue /
Capital and
CRA
Priority
Supply and delivery of Building
materials and building
sundries including: 
• Timber
• Paint
• Plumbing and heating
Materials
• Electrical Materials
• Trade Materials
• Building and roofing
• Ironmongery
• Tools
£4.5m
Revenue /
Capital High

Page 3

4.7 All procurement activity carried out by the Council in excess of £50,000
is subject to a contract strategy. The strategy for the contracts as
listed in the table at 4.2 will include but may not be limited to; contract
scope, service forward plan, the market, procurement model and
routes – including existing delivery vehicles, roles and responsibilities,
risks, issues and opportunities and on-going contract management. 
4.8 This procurement exercise will be conducted in accordance with the
Corporate Procurement Unit in close consultation with Building
Services officers and the provisions of Contract Standing Orders, the
Financial Regulations and relevant Public Procurement Regulations. 
4.9 The route to market will be to conduct a number of tenders calling off
from the Scotland Excel Construction Materials (1422) The use of an e-
Auction maximises commercial advantages and increases the
opportunities for savings. The use of E-Auctions will provide
transparency to all parties and allows the suppliers multiple
opportunities to bid. 
5. People Implications
5.1 18 craft team members work on the reroofing programme and at this
stage we are estimating a transfer of 10 with the remainder
accommodated within other workstreams in the service. 
5.2 As noted in 4.5, we are estimating a reduction of 6 posts from the
painter establishment of 20. 
5.2 The Transfer of Undertakings (Protection of Employment) Regulations
2006 (TUPE) implications are applicable in terms of the externalisation
of the Councils’ capital funded reroofing programme. 
5.3 Further communication and consultation will be carried out with
Building Services workforce and Trade Unions. 
5.4 Progressing these changes to Building Services establishment and
delivery models and procurement processes will require significant
Officer time resource from Building Services, Consultancy Services,
Housing Operations, Legal and Corporate Procurement teams. 
6. Financial Implications
6.1 It is too early to provide exact financial information as a result of
changes to the structure and delivery model of Building Services at this
stage. However, these will result in lower staff costs, lower reroofing
programme costs and less housing capital expenditure resulting in
marginally lower interest payments in future.
6.2 Costs of the support contracts will be funded by both Capital and
Revenue budgets through the Housing Revenue Account, Central

Page 4

Repairs Account and Housing Maintenance Trading Account.
6.2   Costs of contracts listed under 4.6 are included within existing budgets.
7. Risk Analysis
7.1 There are significant financial, operational and reputational risks facing
Housing and Building Services, and to the HRA in the coming period if
changes to Building Services establishment and delivery model are not
implemented. 
7.2 These changes will form part of actions in addressing the financial
challenges in the HRA budget in future years. 
7.3 On-going investment, in-line with business plans, will allow the Council
to meet its landlord duties, health and safety obligations and quality
standards, whilst providing appropriate asset management. 
7.2 Procurement related risks and mitigation/management measures will
be identified as part of the development of tendering strategies for the
individual requirements. 
8. Equalities Impact Assessment (EIA)
8.1 An Equalities Impact Assessment or screening as appropriate will be
carried out. 
9. Strategic Assessment
9.1 This report forms part of the financial governance of the HRA and
contributes to the Council’s Strategic Priorities and in particular
towards: 
i. improving local housing and environmentally sustainable
infrastructure; and 
ii. improving the wellbeing of communities. 
10. Consultation
10.1 Finance and Legal and Chiel Legal Officer have been consulted
regarding the changes to Building Services establishment and delivery
model and the setup of the contracts referred to in this report. 
10.2 The Corporate Procurement team have been consulted in the
development of this report. They will provide assistance and
professional guidance with the administration Pofettheer Bteanrdreyr exercises.
Chief Officer Housing & Employability
Date: 30 October 2024 
Page

Page 5

Persons to Contact: Martin Feeney – Building Services Manager,
Cochno Street, Clydebank, Telephone: 01389
738200, e-mail: mfeeney@west-dunbarton.gov.uk
Appendices: Nil
Background Papers: Nil
Wards Affected: All