WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 20 November 2024
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme
1. Purpose
1.1  This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Notes the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach,
including the first handovers of new homes at the zero carbon Clydebank
East development which represents the 500th new build the Council has
developed under the current More Homes programme;
(ii) Approve the updated estimated costs for O’Hare (Bonhill gap site)
development noted in section 4.4 of this report and authorise the Chief
Officer – Regulatory and Regeneration to conclude the award of the
Contract up to the updated estimated costs for the development of the
new homes at the O’Hare site;
(iii) Note the revised Resource Planning Assumption (RPA) following the
allocation of an additional £309k to support acquisitions related to
minimising the use of temporary accommodation referenced at sections
4.5-4.8 of this report: and
(iv) Note the increased Affordable Housing Supply grant benchmark levels
following a review undertaken by the Scottish Government highlighted at
section 4.9 of this report.
3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over one thousand new affordable homes in
ITEM 10

Page 2

West Dunbartonshire to date and includes the Council’s own ambitious New
House Building Programme.
3.2 The Council’s last full practical completion took place at the Queens Quay
development in September 2022 delivering twenty-nine new Council homes in
a key regeneration area as part of a wider development which has delivered
146 new social rented homes.  The homes were the first residential properties
to be heated from the Council’s Queens Quay District Heating Network. This
development was recognised at national housing sector awards winning the
following: -
 Best Residential Regeneration Project – Herald Property Awards
 Inside Housing Best Residential Development (Scotland)
3.3 These 29 new homes, are in addition to the completion of the Council’s first
fully dementia designed development at Creveul Court, Alexandria and other
exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton
Harbour and St Andrews, Clydebank.  The Council have now completed
twelve new build developments since 2013 and are the largest developer of
social homes in West Dunbartonshire delivering 508 new homes and 137
acquisitions through our buyback scheme to date as outlined in Table 1
below.  The 500th new build home in the More Homes West Dunbartonshire
delivery programme was delivered in October 2024 at our current Clydebank
East development:
Table 1:  Completed Council New Build and Acquisitions
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank 126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank 29 August 2022
Clydebank East, Clydebank 12 Ongoing
Buyback Acquisitions 137 Ongoing
Totals 645
3.4     The Strategic Housing Investment Plan (SHIP) 2024-2029, outlining West
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2023. The SHIP outline plans to meet
the Council Administration’s aim of delivering 2500 new affordable and social
rented homes over the next 10 years. A refreshed SHIP will be submitted to
the November meeting of the Housing and Communities Committee.

Page 3

4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic and economic recovery
plans, negating the impacts of the current cost of living crisis and combatting
poverty principally child and fuel poverty.  It is also clear that the need for
affordable homes has and will increase in the current ongoing economic
environment.
4.2 Our More Homes West Dunbartonshire approach is an ambitious plan that
aims to continue the positive momentum of the delivery of much needed
Council homes in West Dunbartonshire and will significantly assist the
Council’s aim to deliver 2500 new social and affordable homes by 2032.
4.3 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified several future development sites for new council homes
to address existing and new housing need. The design of these homes will
further develop, improve, and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low
carbon ambitions including passivhaus and other net zero carbon
opportunities.
4.4 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  An update on
each development site is provide below: -
Clydebank East:
This development will deliver eighty-eight new homes and has been designed
to meet the housing need within the wider West Dunbartonshire area. The
table below shows the housing mix:
House Type Sustainability Standard Number of New
Homes
Wheelchair Bungalow
3bed/4person
Net Zero 3
House 3bed/5person Net Zero 15
House 4 bed/7person Net Zero 12
House 5 bed/8 person Net Zero 8
Wheelchair Cottage Flat
1bed/2 person
Net Zero 4
Cottage Flat 2 bed/4 person Net Zero 4
Flat 1 bed/2person Net Zero 16
Flat 2 bed/4 person Net Zero 24
Wheelchair Flat 1 bed/2person Net Zero 2
Works commenced on this development in January 2023. The first 12 units
were handed over on 7th October 2024. Sectional handover number 2 is

Page 4

scheduled for 18th November 2024 and will include 3-, 4- and 5-bedroom
houses.
All houses are designed to the Housing for Various Needs Standard (HfVN).
There will be nine fully Wheelchair (WCH) accessible properties. The 4- and 5
-bedroom homes have ground floor double bedrooms. 
The development at Clydebank East will see the completion of a major
housing led regeneration of a key priority regeneration area identified in the
Local Housing Strategy and will be the first fully zero carbon housing
development in West Dunbartonshire and marks a significant milestone in our
transition to net zero new homes approved at the August 2022 meeting of the
Housing and Communities Committee. 
We have previously reported award of above benchmark grant due to the
complexities of the development at Clydebank East this resulted in a total
grant award of £12.6m, this equates to over £143k grant per home and
around £4.68m more than the benchmark grant award this ensured the
delivery of the development without any negative impact on the wider Housing
Revenue Account.
Pappert, Bonhill
This project enjoyed a site start date in early March, delivering the housing
mix as follows: -
House Type Sustainability Standard Number of New
Homes
House 3bed/5 person Passivhaus 6
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6
The development should be complete for handover in summer 2025.
Mount Pleasant, Old Kilpatrick
The site started on 15th April 2024 and construction will last approximately one
year.
This is a 19-unit complex which is designed for elderly residents and will
deliver high quality amenity housing, the housing mix is outlined below for
information.
House Type Sustainability Standard Number of New
Homes
Bungalow 1bed/2person Net Zero 3
Flat 1bed/2person w/c Net Zero 4

Page 5

Flat 1bed/2person Net Zero 4
Flat 2bed/4person Net Zero 8
Willox Park, Doveholm, Dumbarton
The development of seventeen new homes to be delivered at the former care
home site.
House Type Sustainability Standard Number of New
Homes
Flat 2bed/3person Net Zero 2
Flat 1 bed/2person Net Zero 15
This development has now been granted planning permission and a
contractor, McTaggart Construction, has been appointed to begin the
construction phase. Construction will commence in November on this project.
The net zero heat strategy will be delivered by ground source heat pump, as it
was felt that this solution to be preferable than an air source heat pump for
each home. 
Current tenants at Willox Park have been consulted throughout the design
process and this has continued with the contractor holding Q&A sessions.
Bonhill Gap Site Strategy
The pre-planning application process has commenced on the development of
the three separate gap sites delivering thirty-four new homes which are
contained within this wider development project outlined in the table below.
Planning has been submitted for all sites with approval expected to be
granted for Braehead and Campbell St in November and O’Hare
determination date set for 25/11/2024.
Site Braehead Campbell St O’Hare
1 bed 8
(4 WCH + 4 GN)
6 6
2 bed 3 (WCH)
3 bed 3
4 bed 2
5 bed 4
6 bed
7 bed 2
Total 17 11 6

Page 6

As has been noted to committee previously, the original design proposal for
the O’Hare development site did not achieve a positive financial viability
assessment and the design was revised, Committee is asked to note and
approve the updated estimated costs for the O’Hare project of £1,505,000 and
to develop a procurement strategy to appoint a contractor up to this estimated
cost.  The previous estimated costs for he revised design was £1,424,221.26.
This is a 5.7% increase that assumes an inflationary cost increase for when
the tender submissions return.
Bank Street, Alexandria
The development will consist of twenty-two sheltered/amenity housing units in
partnership with the HSCP. Planning has been submitted.
House Type Sustainability Standard Number of New
Homes
Flat 1bed/2person w/c Net Zero 22
Communal Room Net Zero 1
Staff Office Net Zero 1
A planning decision is expected at the end of November along with the return
of the tender submissions from contractors. Similar to Willox Park, tenants at
Gray Street have been consulted throughout the design process.
Clydebank Health Centre
Having received the feasibility report for the site, we aim to develop 20+ units
of sheltered housing to strategically improving the provision of sheltered
accommodation within Clydebank. We also aim to build around eighteen units
of mostly family housing.
We have discussed proposals with tenants at Young Street on the proposition
of developing a new sheltered complex on the old Clydebank Health Centre
site. This was met with a largely positive reaction and consultation with
tenants, staff and other stakeholders will continue throughout the design
process.
A multidisciplinary design team, led by Collective Architecture, who carried out
the feasibility study, have been appointed through the Scottish Procurement
Alliance framework to carry forward the above-mentioned site proposal
designs.
The demolition of the Health Centre was awarded to Caskie Ltd and works
commenced on the 3rd of June and the demolition programme is scheduled for
around 20 weeks. There has been a delay in the demolition due to issues with
gas disconnections. The estimated completion date of the site is now
2/12/2024.
Gilmour Avenue, Hardgate

Page 7

As part of the wider development of our Clydebank Gap Site strategy we
identified a Housing Revenue Account site in the Hardgate area at Gilmour
Avenue.  The site was previously the location of timber garages on concrete
bases.  These have long since been demolished and the site has been beset
with fly tipping issues for several years.
The development started on site on 23/9/2024 and has a completion date of
14/2/25.
Connect modular, the contractor, is having a day of learning about
construction with the local primary school, Goldenhill Primary, and the pupils
will be invited to watch the housing modules arrive on site. 
Dennystoun Forge Gypsy/Traveller Site
The project has been scored and assessed as a priority in the new SHIP 2025
-2030, with a proposed site start next financial year.  Our in-house design
team and Procurement colleagues are proceeding to detail our plans.
Engagement continuous with the Dennystoun Forge community. Our focus
remains on decant options, where we are engaging with our Assets and
Planning colleagues on the possible use of an identified alternative site for
decanting during the works, and on procurement, where we have consulted
with other local authorities with experience of similar projects.   The decant
arrangements have thrown up a series of questions which we will be
discussing with the community.  While the costs for the decant site are likely
to be high, overall, we expect a saving to be achieved through giving the
eventual works contractor free access to the Dennystoun Forge site.
Queen Mary Avenue, Clydebank (Clydebank Gap Sites)
The transfer of the site at Queen Mary Avenue, Clydebank with vacant
possession at the cost of £140,000 from the Council’s General Fund to the
Housing Revenue Account for the delivery of new Council homes was
approved at the February meeting of the Housing and Communities
Committee and has now been concluded. 
The demolition contract for the units was awarded to Caskie Ltd. The
programme started on 6th July and was completed in September 2024.
An Employer’s Agent/QS has been procured to assist moving this Design and
Build project forward.
Silverton Regeneration
The demolition for the two identified sites in Smollett Road and Dumbuie
Avenue started on 2/10/24 and the contract period is 6 weeks. We are
currently developing a design for future replacement housing on the site.

Page 8

Queens Quay, Site C, Clydebank
The Council has been developing a design to deliver a projected twenty units
on this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network.
.
Pre-planning response was received on the 25 February highlighting concern
of the WDC development proceeding in isolation. We have adopted a
proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have conducted valuations on the
adjacent site to Queens Quay C with a view to purchasing additional land to
deliver more affordable housing in the Queens Quay regeneration site. If this
is achieved, we would seek to develop a mixed tenure approach to any
expanded development site delivering one hundred new affordable homes.
We are seeking discussion with CRL (Clydeside Regeneration Limited) to
progress the possibility of acquiring this additional land and will be able to
draw down Scottish Government grant to enable this. However, because of
the uncertainties surrounding potential delivery timescales for this project and
the reduced funding it is no longer allocated funding within the current
Strategic Housing Investment Programme.
Buyback Programme
Total number of properties purchased in 2024/25 financial year 17
Total Purchase Value                 £1,673,700
We have completed nine purchases since the last board and that includes five
larger family properties comprising of three bedrooms or more.
4.5    The West Dunbartonshire Strategic Housing Investment Plan 2024/25 –
2028/29 (SHIP) was approved by West Dunbartonshire’s Housing and
Communities Committee in November 2023 and submitted to the Scottish
Government.  Our Council Annual Resource Planning Assumption (RPA) from
the Scottish Government supporting the delivery of the SHIP was £10.795m. 
The budget cut has reduced this figure to £8.167m for 2024/25, a cut of 24%.
4.6   In September 2024, the Scottish Government revised 2024-25 RPAs with
immediate effect to take into account an additional £40m acquisition funding. 
While the Scottish Government recognised that all local authorities are facing
a range of housing and homelessness pressures, the allocation of this funding
was predicated on the Scottish Government’s perception that because of
enduring pressures experienced by a handful of local authorities over a
number of years have that this funding should be targeted.
4.7 Using a methodology based on consistently high temporary accommodation
numbers as an indicator of acute need this funding was targeted to five local
authorities, and 80% of the £40m was allocated to these five local authority
areas (Edinburgh, Fife, Glasgow, South Lanarkshire, and West Lothian). The

Page 9

remaining 20% of the £40m has been allocated across the other twenty-seven
local authority areas, using the same distribution methodology, to inform each
local authority area’s share. 
4.8 The additional allocation of the £40m for West Dunbartonshire Council is
£309k and the total RPA for 2024-25 for the Council is now £8.477m. The
additional £309k requires to be directed towards acquisitions to help address
temporary accommodation pressures.
4.9 As of 10th October 2024, updated affordable housing investment grant
benchmark levels were introduced.  These were informed by adjusting the
data from the Scottish Social Housing Tender Price Index for the entire 2023
calendar year – resulting in an increase of 5% across the board. An additional
quality measure benchmark of £4,560 per unit (at the three-person equivalent
level) has also been introduced to account for key changes introduced by the
February 2023 revision of building regulations. The revised benchmark levels
are illustrated in the table below: -
Revised Affordable housing investment benchmarks (from 10/10/24):
Baseline
benchmarks
Project type
West Highland,
Island authorities,
and remote/ rural
Argyll
Other rural City and urban
RSL social
rent
£117,222
(3 person
equivalent)
£101,878
(3 person
equivalent)
£95,741
(3 person
equivalent)
Council social
rent
£101,878
(3 person
equivalent)
£92,673
(3 person
equivalent)
£87,763
(3 person
equivalent)
RSL mid-
market rent
£71,806
(3 person
equivalent)
£69,351
(3 person
equivalent)
£65,669
(3 person
equivalent)
Council mid-
market rent
£65,055
(3 person
equivalent)
£63,214
(3 person
equivalent)
£60,145
(3 person
equivalent)
Additional quality measure
benchmarks
Homes delivered to Section 7, Silver
Level, of the 2019 Building £2,455 per home

Page 10

Regulations in respect of Energy for
Space Heating (that is, full Bronze
Level plus Aspect 2 of Silver Level).1
(3 person equivalent benchmark)
Homes delivered to the updated
provisions for energy performance,
ventilation and assessment of
overheating risk introduced through
building regulations in February
2023.2
£4,560 per home
(3 person equivalent benchmark)
Provision of balconies within flatted
developments to enable people to sit
outside, where the provision of
private or communal outdoor space
cannot otherwise be accommodated.
£4,910 per home
(3 person equivalent benchmark)
Provision of space for home working
or study – to note that this
benchmark does not apply to
projects meeting current Housing for
Varying Needs standards3. In all
other circumstances, grant applicants
should demonstrate that additional
space is necessary to deliver this
measure in order for this benchmark
to apply i.e. it is not possible to
incorporate this within the design of
the homes under current space
standards.4
£4,297 per home
(3 person equivalent benchmark)
Digitally-enabling – when a tenant
gets the keys to their home they
should be able to arrange for an
internet connection to ‘go live’
without the internet service provider
having to provide additional cabling
to the premises.5
£369 per home
(3 person equivalent benchmark)
Installation of ducting infrastructure
for electric vehicle charge point
connectors.
£614 per connector
(3 person equivalent benchmark)
Installation of electric vehicle charge
points (excluding installation of
ducting infrastructure).6
£614 per charge point
(3 person equivalent benchmark)
Installation of automatic fire
suppression systems.
£3,682 per home
(3 person equivalent benchmark)

Page 11

Installation of zero direct emissions
heating systems.7
£4,910 per home
(3 person equivalent benchmark)
4.10    The increase in the grant benchmark is welcomed and will assist in ensuring
the affordability of the new build programme.  However, the additional grant
funding requires to be delivered from the current RPA for 2024/25 which will
increase pressure on the funding available this financial year.  For future
years we await the outcome of the Scottish Government budget proposals in
December this year which we hope will provide some added certainty
regarding future years funding availability to deliver the Affordable Housing
Supply Programme.
4.11 The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper.
5. People Implications
5.10 The delivery of the More Homes delivery programme is managed through
existing resource within the Housing Development & Homelessness team
funded from the Housing Capital Investment Programme. 
6. Financial and Procurement Implications
Financial
6.1 On 6 March 2024 Council approved the Housing Capital Programme 2023-
2028 which saw significant resources committed to the delivery of new council
homes in West Dunbartonshire.  An expenditure budget of £155m for the
affordable housing supply programme is factored into the HRA Capital
Programme this will be updated to reflect the income and expenditure
highlighted within this report.  As it currently stands, it is anticipated that this
programme will complete on project life budget.
6.2 Housing and Finance Officers will continue to assess the ongoing affordability
of future developments within the context of the Housing Revenue Account
Business Plan.
Procurement
6.3 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within 4.5 of this report will
continue to be prioritised. Where the contract award is less than £213,000,
authority is delegated to the Chief Officer in consultation with the Procurement
Manager to instruct the award of contracts for the planned revenue and

Page 12

capital spend detailed in this report to suppliers providing the most
economically advantageous offer to the Council.
6.4 All procurement activity conducted by the Council more than £2m is
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic, and environmental impact for the
Council through the relevant procurement processes will be developed in line
with procurement policy.
7. Risk Analysis
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis.
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel.
8 Environmental Sustainability
8.1 The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy.
9. Equalities Impact Assessment (EIA)
9.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
10. Consultation
10.1 As part of a rent consultation exercise, 92% of respondents indicated their
support for the Council’s ambitious plans to deliver the Housing Revenue
Account (HRA) new council house build programme. In addition, there was
positive support for the wider delivery of new build housing as part of the
recent Local Housing Strategy.  Regular updates on new build development

Page 13

are provided to the West Dunbartonshire Tenants and Residents Organisation
at the bi-monthly liaison meetings.
11. Strategic Assessment
11.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
11.2 Having considered all the Council’s strategic priorities, this report, and the
provision of new supply social housing for rent contributes greatly to all the
Council’s strategic priorities.
Peter Barry
Chief Officer, Housing and Employability
Date: 7 November 2024
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk
Mikayla Deeley, Senior Housing Development Officer,
Housing Development and Homelessness Team,
Housing and Employability: email mikayla.deeley@west-
dunbarton.gov.uk
Appendices: None
Background Papers: West Dunbartonshire Council’s Local Housing Strategy
Local Housing Strategy, Health Inequalities Impact
Assessment
Wards Affected: All