West Dunbartonshire Council
Report by Chief Officer, Housing and Employability
Housing and Communities Committee:  20 November 2024
Subject: More Homes West Dunbartonshire Strategic Housing Investment
Plan 2025/26 – 2029/30
1. Purpose
1.1 This report seeks approval for the More Homes West Dunbartonshire Strategic
Housing Investment Plan (SHIP) for 2025/26 – 2029/30 which requires to be
submitted to the Scottish Government.
2. Recommendation
2.1  It is recommended that the Council:
i) Agree the draft SHIP 2025/26 - 2029/30 as appended to this report,
designed to continue the delivery of an ambitious programme of new
affordable homes in compliance with the West Dunbartonshire Local
Housing Strategy 2022 -2027 (Approved November 2021);
ii) Note the impact of the Affordable Housing Supply Programme financial
challenges and the mitigation measures being taken to maintain delivery
of new affordable housing to meet identified need; and
iii) Delegate authority to the Chief Officer, Housing and Employability to
implement the Strategic Housing Investment Plan in partnership with
relevant stakeholders.
3. Background
3.1 The Scottish Government requires local authorities to submit a Strategic Housing
Investment Plan (SHIP) each year.  The core purpose of the SHIP is to set out
the strategic investment priorities for new affordable housing over a five-year
period to achieve the outcomes contained in the Local Housing Strategy. 
3.2     The SHIP focuses on the delivery of affordable housing by location, type and
tenure and indicates how the programme will be resourced, particularly through
the Scottish Government’s Affordable Housing Supply Programme (AHSP)
funding and its Council House Building Programme component.
ITEM 9

Page 2

3.3      The SHIP sets out the funding priorities for new affordable housing in West
Dunbartonshire for the next five years, 2025/26 – 2029/30.   It complements the
West Dunbartonshire Local Housing Strategy 2022 - 2027 approved by Council
and submitted to the Scottish Government in November 2021.  
3.4   This SHIP 2025/26 – 2029/30 is presented in the context of a significant cut of %
in funding to the Scottish Government’s Affordable Housing Supply Programme
(AHSP) which provides grant support for projects in the plan.  
3.5     The planned West Dunbartonshire Council Annual Resource Planning
Assumption (RPA) from the Scottish Government to help deliver the SHIP,
including the Council’s own new build programme, was originally set at £10.795m
but this was revised downwards £8.477m, a reduction of 21.5%. A reduction of
this scale is a significant departure from our experience in recent years where we
have been successful in increasing our RPA outturn by picking up unspent
monies from other local authority areas. Ove the last five years this has equated
to around £15m in additional funding to West Dunbartonshire.   
3.6     Despite the impact of the budget cuts and ongoing inflationary pressure, this
SHIP sets out proposals for a continuation of the high levels of new affordable
housing delivery achieved in West Dunbartonshire over recent years.    
3.7 Where details are not yet known, the project grant levels have been estimated
based on current guidance with an estimated minimum £110K per unit being
projected for both Council and Housing Association schemes.  There remains a
disparity between Council and Housing Association grant levels, but it is
anticipated that a higher proportion of larger family homes in the Council
programme attracting a higher level of grant will even out average grant levels
across the providers.  
3.8     The Scottish Government grant funding required to deliver the priority projects
listed in the 5- year programme amounts to around £46m.   The programme
beyond the current financial year shows an over commitment of spend and will
need to be the subject of a smoothing exercise.  Despite this we remain confident
that the programme outlined can be delivered, even if some projects may delay. 
Ongoing discussion will take place with the Scottish Government’s More Homes
Division over resourcing this SHIP programme.   
4. Main Issues
4.1     The purpose of the SHIP is to set out the strategic investment priorities for
increasing provision of affordable housing through new build and buyback
programmes in support of outcomes contained in the Local Housing Strategy.
This SHIP sets out the planned housing investment programme for 5 years,
covering the period 2025/26 – 2029/30.

Page 3

4.2    The funding for the projects will be from two principal sources:
 the allocation from the Scottish Government’s Affordable Housing Supply
Programme
 using financial reserves or borrowing from the developing organisation’s
own lending resources through the Housing Revenue Account.
4.3    The SHIP contains tables detailing the projects included in the proposed
programme.  It should be stressed that inclusion in the SHIP does not guarantee
scheme approval, as each proposal will require to go through a further detailed
project and financial appraisal before funding is committed.
4.4    All homes built through the SHIP will require to meet high quality requirements
including the Council’s Design Standard for Affordable Housing, which was
updated in November 2023, and which applies to all projects commencing after
April 2024. 
4.5     Feedback from the Scottish Government on the previous SHIP (2024 – 2029)
was received in July 2024.  The feedback highlighted the importance the Scottish
Government attaches to the SHIP as the expression of the Council’s housing
investment priorities.    The comments made were in the main very positive.  In
summary, the key comments were:
 The SHIP had a good fit in contributing towards meeting Local Housing
Strategy objectives.
 The Scottish Government welcomed the emphasis given in both the open
market purchase scheme and our new build programme to provision of
larger family homes.
 It was acknowledged that our housing priorities were consistent with the
delivery of our Rapid Rehousing Transition Plan
 The Scottish Government welcomed the Council’s ongoing ability to deliver a
robust, balanced new build programme, whilst contributing to the national
ambition
 The Council’s 10% quota requirement for wheelchair provision in new social
housing was welcomed and the work being done to improve the Dennystoun
Forge Gypsy Traveller was noted.
 While noting the collaborative work being done with the Health and Social
Care Partnership to address particular housing needs, the Scottish
Government has requested more of a narrative around how this engagement
has helped to inform the SHIP.  We recognise the need to better understand
the detailed specialist housing needs across different client groups and work
is being developed in partnership with the HSCP to achieve this.

Page 4

4.6    SHIP 2025/26 – 2029/30 Priority Projects
The priority projects for this period including those currently on site, are as   
shown in table 1 below.  All units are social rented unless otherwise stated and
unit numbers are draft in some cases.
Table 1: SHIP 2025/6- 2029/30: Priority Projects by Developer
Site/Developer Number of
West Dunbartonshire Council
Clydebank East (ex Multi Storey Flat site) 88
Pappert 26
Willox Park 17
Mount Pleasant, Old Kilpatrick 19
West Thomson Street/Clydebank Health Cen. 38
Dennystoun Forge 20
Bank St, Alexandria 22
Bonhill Gap Sites 34
Gilmour Avenue 2
Queen Mary Avenue 16
Buy backs 300
582 units
Dunbritton Housing Association
Golfhill Drive, Dalmonach 7
7 units
Caledonia Housing Association
Bellsmyre Regeneration Phase 1 27
Dalquhurn, Renton Phase 4, 5,6 75 (inc 25 SE)
Bellsmyre Regeneration Phase 2 33
135 units
Knowes Housing Association
Abbeylands Road, Faifley (ex-bowling club) 27
Buybacks 32
59 units
Dalmuir Park Housing Association
Buybacks 12
12 units
TOTAL PRIORITY PROJECTS 795
4.7   In total, the SHIP shows the development of around 795 new affordable homes
over the 5-year plan period. This level of development continues the ambitious
new affordable house building programme in West Dunbartonshire. The delivery

Page 5

of this ambitious plan will depend upon the support of our developing housing
association partners, an increase in funding from the Scottish Government and
continued Housing Revenue Account capital investment.
4.8    The SHIP will also provide support funding from the Affordable Housing Supply
Programme to assist the popular Buyback programme of ex- local authority and
Registered Social Landlord housing stock, as well as acquisitions from the
private sector including of-the-shelf homes from house builders. It is proposed
that around 300 units are acquired by the Council over the five years of the plan.
4.9   The funding estimated to deliver the Strategic Housing Investment Plan is an
approximate £46m. However, the resource planning assumption for this same
period is only around £40m.  To meet the requirements of the plan additional
Affordable Housing Supply Funding Programme funding is required to be
invested in West Dunbartonshire over the period of the plan. The first indication
of additional funding to support the deliver of social homes will be contained
within the forthcoming Scottish Government budget announcements.
4.10 Due to uncertainties over details of some of the proposed projects in the SHIP
and the availability of funding, the SHIP will require to demonstrate flexibility and
will be subject to continual monitoring and evaluation.  The SHIP lists a series of
future projects which we hope will feature in the programme as it progresses.  
Monitoring of progress will be carried out through the Council’s performance
management system and through key structures such as the Housing Providers
Forum, More Homes Project Board and programme review meetings with the
Scottish Government. 
4.11 The Council has carried out an analysis of potential projects against an objective
Prioritisation Scoring Matrix and scored them accordingly.  A number of factors
are considered including availability of land, type of housing being proposed,
compliance with Local Housing Strategy objectives, deliverability, and value for
money.   Where a project proposes an element of particular needs /specialist
provision, engagement takes place with the West Dunbartonshire Health and
Social Care Partnership.
5. People Implications
5.1 While there are no direct people implications.
6. Financial Implications
6.1 The programme of projects shown in the SHIP can only take place if both its two
principal funding streams, prudential borrowing through the Housing Revenue
Account and Scottish Government Affordable Housing Supply Programme grant,
are able to provide the required ongoing financial support.   It is estimated that
the total grant ask of the Affordable Housing Supply Programme would be
around £46m, requiring an annual allocation of more than £9m, more than this
year’s RPA award of only £8.477m.

Page 6

6.2     In respect of the Council House Build element, financial modelling demonstrates
that the new council house building programme is beneficial to the Housing
Revenue Account.  However, care requires to be taken to ensure that the
prudential borrowing required is financially sustainable especially given rising unit
costs.  We recognise the high cost of delivering large family homes and those
constructed to passivhaus/net zero standard to meet need.
6.3      There is a risk that future resource allocation would suffer if the SHIP failed to
deliver on the programme contained in this SHIP, this is particularly alarming for
an area such as West Dunbartonshire that experiences high levels of poverty
impacting on homeless presentations which were key contributors to the Housing
Emergency declaration. 
6.4      To mitigate the impact of rising costs, the Council is continuing to lobby for
increased grant levels from the Scottish Government and where appropriate will
apply for above benchmark awards on a project-by-project basis particularly
when we are developing larger homes to meet an acute identified need within
West Dunbartonshire.
6.5 There are no specific procurement implications connected with this report.
7. Risk Analysis
7.1 Inevitably, with such a varied programme of projects there are risks that the
ambitious outputs set out in the SHIP will not be met.  A number of the projects
are at an early stage with site investigations not having been carried out or
infrastructural constraints fully known.
7.2      There is a risk that Affordable Housing Supply Programme funding will be
reallocated to other Council areas if the Council is unable to spend within any
financial year.  Housing Development staff will liaise regularly with Scottish
Government More Homes colleagues to address any concerns of this nature, to
maximise spend within West Dunbartonshire.
7.3 Monitoring of progress will be carried out through key structures such as the
Strategic Housing Providers Forum, More Homes Project Board and programme
review meetings with the Scottish Government.   A new SHIP will be submitted
annually to the Scottish Government each October and will be the subject of a
report to the Housing and Communities Committee.
8 Environmental Sustainability
8.1 The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision

Page 7

making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy.
9. Equalities Impact Assessment
9.1 An Equalities Impact Assessment has been carried out which predicted that the
strategy would have an overwhelmingly positive impact and is an appendix to this
report.  
9.2      All new housing supported through the programme will be compliant with the
West Dunbartonshire Design Standard and will meet the Housing for Varying
Needs requirements.  The West Dunbartonshire Design Standard requires
developers in the programme to provide higher standards than those required by
statute and are of particular benefit to those with mobility issues.  The SHIP
supports the delivery of specialist housing provision and generally allows for a
10% element in each project.
10. Consultation
10.1   The SHIP was drawn up in consultation with potential housing association
partners and the Scottish Government More Homes Division.    Where an interest
has been shown, detailed discussions have taken place with the prospective
developer on how the project could be accommodated in the programme.  
10.2 The West Dunbartonshire Tenants and Residents Organisation (WDTRO)
received a presentation on the proposed SHIP in October 2024 and feedback
has been positive and tenant representatives are strongly supportive of the
Council and partners new build plans.
10.3   The preparation of the SHIP has been a corporate task, involving all relevant
departments of the Council and has been carried out in collaboration with
colleagues in the Scottish Government More Homes Division.  The Health and
Social Care Partnership was an active partner in preparing the plans where there
was a significant element of specialist accommodation involved and a number of
projects were significantly amended as a result.   A particular example is at
WDC’s Clydebank Health Centre Project were plans have been redrawn to
include for the reprovisioning of the nearby Young Street sheltered housing
project.  
11. Strategic Assessment
11.1   This Strategic Housing Investment Plan presents the priorities for affordable and
deliverable housing development for the next five years as set out in the Local
Housing Strategy.  Having considered the Council's strategic priorities, this report
contributes significantly to all strategic priorities.

Page 8

Peter Barry, Strategic Lead, Housing and Employability
Date:    6 November 2024
Person to Contact: Jamie Dockery – Housing Development and Homelessness
Manager, Housing Development and Homelessness Team,
Housing and Employability, telephone: 07793717981, email:
john.kerr@west-dunbarton.gov.uk
Jamie Dockery – Senior Housing Development Officer,
Housing Development and Homelessness Team, Housing
and Employability, email: Jamie.dockery@west-
dunbarton.gov.uk
Appendices:  Appendix 1: Strategic Housing Investment Plan
2025/26 - 2029/30
Appendix 2:    Equalities Impact Assessment October 2024
Background Papers: West Dunbartonshire Council’s Local Housing Strategy 2022-
2027
Wards Affected: All