Page 1

Agenda
Housing and Communities
Committee
Date:  Wednesday, 20 November 2024
___________________________________________________________________
Time:  10:00 
___________________________________________________________________
Format:  Hybrid Meeting
___________________________________________________________________
Contact: Nicola Moorcroft, Committee Officer
Email: nicola.moorcroft@west-dunbarton.gov.uk     
committee.admin@west-dunbarton.gov.uk
Dear Member
Please attend a meeting of the Housing and Communities Committee as detailed
above.
Members will have the option to attend the meeting remotely or in person at the Civic
Space, 16 Church Street, Dumbarton G82 1QL.
The business is shown on the attached agenda.
Yours faithfully
PETER HESSETT
Chief Executive
Page 1

Page 2

Distribution:-
Provost Karen Murray Conaghan
Councillor Ian Dickson 
Councillor Gurpreet Singh Johal (Chair)
Councillor David McBride
Councillor John Millar 
Councillor Lawrence O’Neill
Councillor Lauren Oxley 
Councillor Chris Pollock
Councillor Martin Rooney
Councillor Hazel Sorrell (Vice Chair)
Councillor Sophie Traynor
All other Councillors for information
Chief Executive
Chief Officer – Housing and Employability
Chief Officer – Resources
Date issued: 7 November 2024
Audio Streaming
Audio recordings of the meeting (including the attendance or contribution of any party
participating or making a contribution) will be published on the Council’s website and
the Council’s host’s webcast/audio stream platform.
You should be aware that the Council is a Data Controller under the General Data
Protection Regulation.  Data collected during this audio stream will be retained in
accordance with the Council’s Privacy Notice* and Retention Schedules including,
but not limited to, for the purpose of keeping historical records and making those
records available via the Council’s internet site.
*http://www.west-dunbarton.gov.uk/privacy/privacy-notice/
Page 2

Page 3

HOUSING AND COMMUNITIES COMMITTEE
WEDNESDAY, 20 NOVEMBER 2024
AGENDA
1 STATEMENT BY CHAIR – AUDIO STREAMING
The Chair will be heard in connection with the above.
2 APOLOGIES
3 DECLARATIONS OF INTEREST
Members are invited to declare if they have an interest in any of the items of
business on this agenda and the reasons for such declarations.
4 RECORDING OF VOTES
The Committee is asked to agree that all votes taken during the meeting be
done by roll call vote to ensure an accurate record.
5 OPEN FORUM
The Committee is asked to note that no open forum questions have been
submitted by members of the public.
6 MINUTES OF PREVIOUS MEETING   7 - 13
Submit for approval, as a correct record, the Minutes of Meeting of the
Housing and Communities Committee held on 21 August 2024.
7 SCRUTINY REPORTS
a) POLICE SCRUTINY REPORT 15 - 25
Submit report by the Divisional Commander, Police Scotland providing
Members with an update on local policing in West Dunbartonshire.
Page 3

Page 4

b) FIRE AND RESCUE SCRUTINY REPORT          27 - 36
Submit report by the Local Senior Officer, Scottish Fire and Rescue
Service providing appropriate performance data measured against
priorities in the West Dunbartonshire Local Fire and Rescue Plan. 
8 HOUSING AND EMPLOYABILITY DELIVERY PLAN 2024/25 37 - 61
MID-YEAR PROGRESS REPORT
Submit report by the Chief Officer - Housing and Employability providing an
update on progress of the Housing and Employability Delivery Plan 2024/25.
9 ‘MORE HOMES WEST DUNBARTONSHIRE’ - STRATEGIC 63 - 96
HOUSING INVESTMENT PLAN (SHIP) 2025/26 – 2029/30 
Submit report by the Chief Officer - Housing and Employability seeking
approval for the More Homes West Dunbartonshire Strategic Housing
Investment Plan (SHIP) for 2025/26 – 2029/30 which requires to be submitted
to the Scottish Government.
10 ‘MORE HOMES WEST DUNBARTONSHIRE’ – WEST          97 - 109
DUNBARTONSHIRE COUNCIL AFFORDABLE HOUSING
SUPPLY DELIVERY PROGRAMME 
Submit report by the Chief Officer - Housing and Employability updating on the
progress of West Dunbartonshire’s More Homes Programme which oversees
the delivery of the Council’s new home building programme.
11  WEST DUNBARTONSHIRE – EMPTY HOMES 111 - 142
STRATEGY 2024-2029
Submit report by the Chief Officer - Housing and Employability seeking
approval of the new Empty Homes Strategy 2024 -2029.
12 HOUSING EMERGENCY ACTION PLAN 143 - 175
Submit report by the Chief Officer - Housing and Employability providing an
updating on the Housing Emergency Action Plan (HEDAP) which was
formulated to address the emergency following the Council’s housing
emergency declaration on 1st May 2024.
13/
Page 4

Page 5

13 HOUSING REPAIRS POLICY 177 - 214
Submit report by the Chief Officer - Housing and Employability seeking
approval for the introduction of a new West Dunbartonshire Housing Repairs
Policy which has been developed in partnership with Council tenants.
14      SCOTTISH SOCIAL HOUSING CHARTER ANNUAL 215 - 225    
BENCHMARKING AND MID-YEAR PROGRESS REPORT
Submit report by the Chief Officer - Housing and Employability providing
benchmarking information relating to 2023/24 and a mid-year update in terms
performance against the Scottish Social Housing Charter indicators and
meeting the requirements of the Scottish Housing Regulator’s Regulatory
Framework.
15 ‘INVOLVING YOU TO IMPROVE HOUSING SERVICES’ -       227 - 279
WEST DUNBARTONSHIRE COUNCIL’S TENANT
PARTICIPATION STRATEGY 2025- 2028
Submit report by the Chief Officer - Housing and Employability highlighting
statutory obligations in relation to tenant participation and seeking approval for
the new Tenant Participation Strategy entitled ‘Involving You to Improve
Housing Services’ covering the period 2025-2028.
16 HOUSING AND COMMUNITIES BUILDING SERVICES 281 - 285
UPDATE
Submit report by the Chief Officer - Housing and Employability advising of
changes to Building Services establishment and delivery model and seeking
approval to continue with procurement and tender processes.
17 HOUSING REVENUE ACCOUNT (HRA)  287 - 294
BUDGETARY CONTROL REPORT TO 31 AUGUST 24
(PERIOD 5)
Submit report by the Chief Officer – Resources providing advising of the
2024/2025 HRA revenue budget position on 31 August 2024 and the forecast
HRA reserves position as of 31 March 2025.
18/
Page 5

Page 6

18 GENERAL FUND HOUSING AND COMMUNITIES 295 - 303
FINANCIAL REPORT 2024/25 AS AT 31 AUGUST 2024
(PERIOD 5)
Submit report by the Chief Officer – Resources providing an update 
financial performance to 31 August 2024 (Period 5) of General Fund Revenue
services under the remit of the Housing and Communities Committee.
19 HOUSING AND COMMUNITIES CAPITAL MONITORING 305 - 311
REPORT TO 31 AUGUST 24 (PERIOD 5)
Submit report by the Chief Officer – Resources providing an update on the
HRA capital programme to 31 August 2024.
Page 6

Page 7

HOUSING AND COMMUNITIES COMMITTEE
At a Hybrid Meeting of the Housing and Communities Committee held in the Civic
Space, 16 Church Street, Dumbarton on Wednesday, 21 August 2024 at 10.00 a.m.
Present: Councillors Ian Dickson, David McBride, Michelle McGinty, John
Millar, Karen Murray Conaghan, Lawrence O’Neill, Martin
Rooney, Hazel Sorrell and Sophie Traynor.
Attending: Peter Barry – Chief Officer, Housing and Employability; John
Kerr, Housing Development and Homelessness Manager;
Martin Feeney, Building Services Manager; Nicola Pettigrew,
Housing Operations Manager; Nigel Ettles, Legal Officer; and
Nicola Moorcroft and Lauren Simeon, Committee Officers.
Also attending: Divisional Commander Gary L’Anson and Chief Superintendent
Kirsteen McLatchie, Police Scotland; Group Commander Fraser
Grant and Watch Commander Chris Spence, Argyll and Bute,
East and West Dunbartonshire, Scottish Fire and Rescue
Service.
Apologies: Apologies for absence were intimated on behalf of Councillors
Gurpreet Singh Johal, Jonathan McColl and Lauren Oxley.
Councillor Hazel Sorrell in the Chair
STATEMENT BY CHAIR – AUDIO STREAMING
Councillor Hazel Sorrell, Chair, advised that the meeting was being audio streamed
and broadcast live to the internet and would be available for playback.
DECLARATIONS OF INTEREST
It was noted that there were no declarations of interest in the item of business on the
agenda.
RECORDING OF VOTES
The Committee agreed that all votes taken during the meeting would be done by roll
call vote to ensure an accurate record.
ITEM 6
Page 7

Page 8

OPEN FORUM 
The Committee noted that no open forum questions had been submitted by
members of the public. 
MINUTES OF PREVIOUS MEETING 
The Minutes of the Meeting of the Housing and Communities Committee held on 1
May 2024 were submitted and approved as a correct record. 
SCRUTINY REPORTS 
(A)  POLICE SCRUTINY REPORT 
A report was submitted by the Divisional Commander, Police Scotland
providing Members with an update on local policing in West Dunbartonshire. 
After discussion and having heard the Divisional Commander and the Chief
Superintendent, in further explanation and in answer to Members’ questions,
the Committee agreed to note the update on policing in West Dunbartonshire. 
(B) FIRE AND RESCUE SCRUTINY REPORT 
A report was submitted by the Local Senior Officer, Scottish Fire and Rescue
Service providing appropriate performance data measured against priorities in
the West Dunbartonshire Local Fire and Rescue Plan. 
After discussion and having heard the Group Commander and the Watch
Commander in further explanation and in answer to Members’ questions, the
Committee agreed to note the update on the Local Fire and Rescue Plan in
West Dunbartonshire. 
MORE HOMES WEST DUNBARTONSHIRE – WEST DUNBARTONSHIRE
COUNCIL AFFORDABLE HOUSING SUPPLY DELIVERY PROGRAMME 
A report was submitted by the Chief Officer – Housing and Employability providing
an update on progress with West Dunbartonshire’s More Homes Programme which
oversees the delivery of the Council’s new home building programme. 
After discussion and having heard the Chief Officer – Housing and Employability and
the Housing Development and Homelessness Manager in further explanation and in
answer to Members’ questions, the Committee agreed:- 
(1) to note the content of the report and the progress made to date in the delivery
of the Council’s More Homes West Dunbartonshire approach, including the
Page 8

Page 9

forthcoming handover of new homes at the Clydebank East and Gilmour
Avenue development; 
(2) to approve the updated estimated costs for Braehead and Campbell Street
(Bonhill gap sites) and Bank Street development; 
(3) to approve the procurement exercise and to award the contract up to the
updated estimated costs for the projects above; 
(4) to approve the procurement exercise of a multi-disciplinary design team for
Clydebank Health Centre and to award the contract up to the approved costs
for the project; and 
(5) to approve the procurement and award of the Queen Mary Avenue Design
and Build development contract by the Chief Officer – Housing and
Employability, in consultation with the Procurement Manager, to appoint a
suitably experienced contractor to deliver the new homes within the approved
budget through an appropriate procurement framework. 
RAPID REHOUSING TRANSITION PLAN 
A report was submitted by the Chief Officer – Housing and Employability providing
an update on “Home at the Heart” the Rapid Re-housing Transition Plan (RRTP) for
the period 2019-24 and new approaches to homelessness. 
After discussion and having heard the Chief Officer – Housing and Employability,
in further the Committee agreed:- 
(1) to note the progress and challenges made in the five years of “Home at the
Heart”, which will inform a report to the Scottish Government at the end of
August 2024 and note the main objectives for Year 6 in paragraphs 4.17 -
4.32 of the report; 
(2) to note that the Council’s housing allocation letting target, for homeless
households remains at 64% for 2024/25 as set out in paragraph 4.25 of the
report and note that the Chief Officer – Housing and Employability will keep
the target under close review based on current modelling projections; 
(3) to note the continued uncertainty around future funding and specifically the
risk to the embedded Housing First approach; 
(4) to note that Scottish Government funding of £261,000 was awarded for
2024/25 for the specific delivery of the West Dunbartonshire Rapid Rehousing
Transition Plan; and 
(5)  to note the Housing Emergency Declaration and Action Plan update provided
in a separate committee paper. 
Page 9

Page 10

SCOTTISH SOCIAL HOUSING CHARTER/REGULATION ANNUAL UPDATE
REPORT 
A report was submitted by the Chief Officer – Housing and Employability providing
an annual progress report on meeting the requirements of the Scottish Social
Housing Charter and the Scottish Housing Regulator’s Regulatory Framework for
social housing including the approval of the Annual Assurance Statement. 
After discussion and having heard the Chief Officer – Housing and Employability, the
Housing Development and Homelessness Manager and the Building Services
Manager, in further explanation and in answer to Members’ questions, the
Committee agreed:- 
(1) to note the content of the current Engagement Plan published by the Scottish
Housing Regulator (SHR) in April 2024; 
(2) to note performance in terms of achieving the Scottish Social Housing Charter
(SSHC) outcomes during 2023/24; 
(3) to note that a comprehensive assessment of 2023/24 performance was
carried out and that this informed a Charter Improvement Plan covering all the
SSHC outcomes and the key areas of focus for the Housing Improvement
Board (HIB) during 2024/25, outlined at paragraph 4.13 of the report; 
(4) to note that this assessment of 2023/24 performance will inform the
production and publication of our annual Charter Performance Report; 
(5) to approve the Annual Assurance Statement (AAS) in Appendix 1 of the
report, to be signed by the Housing and Communities Committee Convener,
on behalf of the Housing and Communities Committee and submitted to the
Scottish Housing Regulator as per the regulatory requirement; and 
(6) that a further progress report on the Scottish Social Housing
Charter/Regulatory Framework will be submitted to the November 2024
meeting of the Committee, to include detailed benchmarking performance,
information against all local authorities in Scotland following the publication of
validated performance information. 
HOUSING EMERGENCY DECLARATION ACTION PLAN 
A report was submitted by the Chief Officer – Housing and Employability providing
an update on the Housing Emergency Declaration made on 1st May 2024. Outlining
an initial and high-level response through a Housing Emergency Declaration Action
Plan (HEDAP), formulated to address the situation. 
After discussion and having heard the Chief Officer – Housing and Employability in
further explanation and in answer to Members’ questions, the Committee agreed:- 
Page 10

Page 11

(1) to note and approve the Housing Emergency Declaration Action Plan in
Appendix 1 of the report; 
(2) to note the establishment of the Housing Emergency Project Board led by the
Chief Officer – Housing and Employability, supported by several Senior
Council Officers, to oversee the implementation and further development of
the Housing Emergency Declaration Action Plan; and 
(3) that the Chief Officer – Housing and Employability will present an update
report to the Housing and Communities Committee in November 2024. 
MOBILITY SCOOTER POLICY 
A report was submitted by the Chief Officer – Housing and Employability seeking
approval for the introduction of mobility scooter guidance and to note the amendment
to the tenancy agreement. 
After discussion and having heard the Chief Officer – Housing and Employability, the
Housing Development and Homelessness Manager and the Housing Operations
Manager, in further explanation and in answer to Members’ questions, the
Committee agreed to approve the Mobility Scooter Guidance in Appendix 1 of the
report. 
ANTI-SOCIAL BEHAVIOUR STRATEGY 
A report was submitted by the Chief Officer – Housing and Employability seeking
approval for the revised Anti-Social Behaviour Strategy 2024 – 2027. 
After discussion and having heard the Chief Officer – Housing and Employability, in
further explanation the Committee agreed:- 
(1) to note the content of the Anti-Social Behaviour Strategy 2024 – 2027; 
(2) to note the partnership approach and work to develop the Anti- Social
Behaviour Strategy 2024 – 2027, which sets out the collective position to
address unacceptable anti-social behaviour (ASB) throughout West
Dunbartonshire Communities; and 
(3) to approve the Anti-Social Behaviour Strategy 2024 – 2027 and delegates the
Chief Officer – Housing and Employability to publish and deliver the strategy
in conjunction with key partners. 
FORMER TENANT WRITE-OFF'S 
A report was submitted by the Chief Officer – Housing and Employability seeking
approval for the write-off of rent arrears for Quarter 1 of 2024/25 for former tenants. 
Page 11

Page 12

After discussion and having heard the Chief Officer – Housing and Employability, in
further explanation and in answer to Members’ questions, the Committee agreed to
approve the write-off of former tenant arrears accounts totalling £55,529.44. 
BUILDING SERVICES PROCUREMENT PROVISION UPDATE 
A report was submitted by the Chief Officer – Housing and Employability providing
an update on tender requirements information for Building Services, seeking
approval to continue with necessary procurement and tender processes and to allow
subsequent award of the contract. 
After discussion and having heard the Chief Officer – Housing and Employability, in
further explanation the Committee agreed:- 
(1) to note the contents of the report; 
(2) to approve the procurement processes to tender the requirements listed within
the table in paragraph 4.2 of the report; and 
(3) to delegate approval to award contracts to successful bidders to the Chief
Officer – Housing and Employability. 
GENERAL FUND HOUSING AND COMMUNITIES ACCOUNT TO PERIOD 3 
(30 JUNE 2024) 
A report was submitted by the Chief Officer – Resources providing an update on the
financial performance to 30 June 2024 (Period 3) of General Fund Revenue services
under the auspices of the Housing and Communities Committee. 
Having heard the Chief Officer – Housing and Employability in further explanation
the Committee agreed:- 
(1) to note the contents of this report showing the revenue budget forecast to
overspend against budget by £0.159m (4.4%) at the year-end; and 
(2) to note the progress on efficiencies incorporated into budgets for 2024/25. 
HOUSING REVENUE BCR TO PERIOD 3 
A report was submitted by the Chief Officer – Resources providing an update on the
HRA revenue financial performance to 30 June 2024 (Period 3). 
After discussion and having heard the Chief Officer – Housing and Employability in
further explanation the Committee agreed:- 
(1) to note the HRA revenue account forecasts an adverse variance of £0.082m.
The adverse variance would be offset by using £0.082m of HRA reserves;
Page 12

Page 13

(2) to note that the use of HRA reserves to address the projected adverse
variance will lead to the closure of HRA reserves balance of £0.886m which is
below the prudential target of £1.064m; and 
(3) to note that work continues to identify efficiencies across all areas of the HRA
revenue account budget, to allow HRA reserves to replenished and
maintained in line with the prudential target, while ensuring that services are
delivered and that there is no corresponding reduction in service provision. 
HOUSING CAPITAL BCR TO PERIOD 3 
A report was submitted by the Chief Officer – Resources providing an update on the
HRA capital financial performance to 30 June 2024 (Period 3). 
After discussion and having heard the Chief Officer – Housing and Employability in
further explanation the Committee agreed:- 
(1) to note the current position of the 2024/25 HRA capital budget and the HRA
capital plan; 
(2) to note that in-year financial performance was monitored against a 2024/25
capital expenditure budget of £73.664m and a 2024/25 capital income budget
of £10.003m; 
(3) to note that project life performance was monitored against a project life
expenditure budget of £319.738m and a project life income budget of
£54.577m; 
(4) to note that all projects are currently on track, regarding achieving the planned
completion dates and delivering within the updated capital budget; and 
(5) to approve the procurement and award of the CCTV upgrade project by the
Chief Officer – Housing and Employability, in consultation with the
Procurement Manager, as set out in paragraph 4.4 of the report, to appoint
the contractor of the returned tender, if the contract cost is within the
approved budget and the tender is in line with normal tender parameters. 
The meeting closed at 11.59 a.m. 
Page 13

Page 14

Page 14

Page 15

OFFICIAL
OFFICIAL
West Dunbartonshire
Performance Summary Report
Reporting Period: April 24 to September 24
Total Crime 1 Crime
Incidents Overall Dishonesty Domestic Abuse
Incidents
+6.2% +1.4% +15.4
+10.3 +18.9 -36.8%*
Road Deaths and
Serious Injuries
-12.9%*
Sexual Crime
-996*PYTD +30*PYTD, +76*5YR AVG +13*PYTD, +161*5YR AVG +101*PYTD, +86*5YR AVG
+71*PYTD, +138*5YR AVG +17*PYTD, +1*5YR AVG -7*on PYTD -275*PYTD
Violent Crime
Missing Counter Terrorism
-23*PYTD
-12.8%*
-23*PYTD, -20*5YR AVG
Common Assault
-25.8%
Housebreaking
Disorder 
Complaints
The National Terrorism Threat level is
SUBSTANTIAL
This means that an attack is likely. 
*PYTD = Previous Year to Date
*5YR = 5 year average
-0.02%
-6.8%
ITEM 7a
Page 15

Page 16

OFFICIAL
SECTION PAGE NUMBER 
Introduction 2 
Executive Summary 3
Demand Analysis 4
Acquisitive Crime 5
Public Protection 6
Road Safety 7
Serious Organized Crime 8
Violence 9
Antisocial Behaviour 10
Public Confidence - Complaints & Allegations 11
Introduction
I am pleased to present this performance summary report to the West Dunbartonshire Housing
Committee for its information and consideration. The Reporting Period for this report is cumulative for
Quarters 1 and 2 of 2024/25, with available figures being shown from 1st April 2024 through to 30th
September 2024. 
Please note that all data included in this report are management information and not official statistics.
All data are sourced from Police Scotland internal systems and are correct as of date of publication.
Unless stated otherwise numerical comparisons are against the previous year to date and the previous
five year average for the same data period specified.
Crimes and offences are grouped under recognised categories for statistical purposes.  The Scottish
Government defines these categories, as follows: 
Group 1 - Non Sexual Crimes of Violence Group 6 - Miscellaneous Offences
Group 2 - Sexual Crimes Group 7 - Offences relating to motor vehicles
Group 3 - Crimes of Dishonesty PYTD  - Previous Year to Date
Group 4 - Fire Raising, Malicious Mischief CYTD - Current Year to Date
Group 5 - Other (pro activity) Crimes
Page 16

Page 17

OFFICIAL 
PRIORITY
AREA EXECUTIVE SUMMARY
Acquisitive
Crime At the end of September 2024, acquisitive crime shows the slight increase of 12
crimes compared to the same period last year. An increase in both shoplifting
and mainly online social engineering fraud crime has continued to be offset by
reductions in theft by housebreaking at residential properties and common thefts. 
Public
Protection
Group 2 sexual crimes have seen an increase of 19% with 107 crimes recorded
compared to 90 at the end of September last year. This is largely due to a rise in
the number of Rape crimes recorded from 16 to 31 crimes, albeit this has been
attributed to an increase in non-recent reporting with more than half of all crimes
being non-recent in nature.  
Road Safety
& Road Crime
There have been no fatal road traffic collisions within West Dunbartonshire at the
end of Qtr. 2, which is a reduction from 1 in the same period last year. 
Road traffic collisions involving serious injuries have also reduced by over 30%
from 18 to 12, and collisions involving slight injuries have decreased from 16 to
13.
Serious
Organised
Crime 
At the end of September 2024 drugs supply crimes have seen an increase of
9.5% from 43 to 47 crimes while possession charges continue to see a reduction
from 330 to 258.  
Across Argyll & West Dunbartonshire 12 persons linked to serious and organised
crime (SAOC) have been arrested and £2,445,484 seized under the Proceeds
of Crime Act 2002 (POCA). 
Violence &
ASB
At the end of September 2024, Group 1 crimes of violence have increased with
759 crimes compared to 690 the previous year to date. Anti-social behaviour
(ASB) related crimes have risen from 596 to 689, due in part to the increased
summer police patrols dealing with the greater visitor numbers equating to:
breach of the peace (+39) and also an increase in detections of persons
consuming alcohol within a public place (where appropriate bye laws exist (+37).
1. Acquisitive Crime
2. Public Protection
3. Road Safety & Road Crime
4. Serious Organised Crime
5. Violence & Anti-social behaviour
WEST DUNBARTONSHIRE POLICING PRIORITIES 2023-2026
DEMAND ANALYSIS - * PYTD - PREVIOUS YEAR TO DATE CYTD - CURRENT YEAR TO DATE
Page 17

Page 18

OFFICIAL 
CRIME PYTD CYTD INCIDENTS PYTD CYTD
Total Crimes &
Offences 5255 5254 Total number of 
incidents 14,682 13,686
The total volume of crimes and offences recorded within West Dunbartonshire has remained fairly
consistent when compared to the previous year while the current figure is slightly above (+4.2%)
the previous 5-year average. Crimes of violence (+10.3%), sexual crimes (+19%) and acquisitive
crimes (+1.4%) continue to see an increase compared to the previous year and are currently
above the previous 5-year average which is in line with the post-covid trajectory.
Crimes against society such as drug and weapons offences have reduced by 1.2% with the
current figure (809) also 4.8% below the previous 5-year average (850). Crimes relating to
damage and reckless behaviour have also seen a reduction on last year from 503 to 484 (-19)
crimes. Both positive reductions in offence types that have a serious negative impact on society. 
Page 18

Page 19

OFFICIAL 
ACQUISITIVE CRIME
Shoplifting crimes have seen the highest increase among acquisitive crime (344 to
415) and remain above the previous 5-year average. This overall year-on-previous
year increase has decreased from Q1 from 24% to 20.05%. Year to date, 27 more
shoplifting crimes have been detected. This is in line with the national picture.
At the end of September 2024, thefts of motor vehicles have increased from 28 to 39
crimes, while the current figure is also 29.1% above the previous 5-year average (30).
Approximately 35% of crimes related to taking/driving a vehicle without consent of the
owner, while a further 10 crimes involved thefts of motorcycles. The detection rate has
increased by 4.9% from 46.4% to 51.3%.
There has been an increase in fraud crimes at the end of Qtr. 2 from 102 to 125 crimes,
which is above the 5-year average of 100. The increase is largely due to a rise in social
engineering frauds (+10) and online market frauds (+10). Both crimes tend to be
opportunist in nature. The detection rate for fraud crime is currently low at 8.8%, which
is a reduction from 24% PYTD. Perpetrators of such offences generally are based out
with the UK. 
Common thefts have seen a reduction compared to the PYTD from 248 to 241 crimes
but remain above the 5-year average of 219. The detection rate has reduced by 7.3%
from 31% to 23.7%.
The Preventions Team at L Division continue to deliver on-line safety talks to all groups
including those more vulnerable, elderly, via Women’s Aid & WD Carers etc. They have issued
extensive guidance on both social media and in the hard copy newspapers in an attempt to
reach all areas of society. Via our Youth Engagement Officers (YEO), we have put QR code-
based posters in schools warning of the dangers of Sextortion type offences and the many
pitfalls of being a perpetrator as well as a victim.
A very significant individual offender responsible for a high volume of retail thefts, committed
predominantly in Dumbarton, has now been identified and is currently remanded in custody
for a substantial period of time. Testament to the work of the Town Centre Officers.      
The area and businesses in the Lomond Shores development were targeted during
September, a total of 9 separate acquisitive crimes being committed. After a targeted policing
operation, two males were identified and charged with these offences, both are now subject
of home curfews which are being robustly policed.  
Page 19

Page 20

OFFICIAL 
The Victim Safeguarding Team established in the previous reporting period is proving to be very
effective regarding victim safety. It is allowing victims that additional period of engagement with
specialist officers when often historical crimes are being divulged allowing for enquiry to potentially
submit a stronger case to COPFS. This will potentially increase crimes reported but for the correct
reasons; by identifying and reporting crimes that may previously have gone unreported, this
additional support will hopefully increase confidence in the police.
The removal of the need for police officers to attend and speak with children residing within the
WD Children’s Houses who have returned after being missing, became the accepted policy during
this period, and has proved to be very successful, reducing demand on police resources while
reducing the risk of any upset being caused to the children.  
Officers from the Preventions Team are now sitting on the Suicide Prevention Group and are
involved in the implementation of a suicide prevention action plan for the area. 
At the end of September 2024, Group 2 crimes have increased by 18.9% (+17) compared to the
same period last year. The increase is largely due to a rise in rape offences, the majority of which
are historical reports, from 16 to 32 crimes, while sexual assaults have seen a reduction (-3).
Approximately 88% of rape crimes occurred in a private place and 91% were committed by persons
known to the victim. Similarly, around 66% of sexual assaults also occurred in a private place with
63% committed by persons known to the victim. Approximately 61% of rape crimes during this
reporting period relate to non-recent reports, which is an increase from 55% PYTD. The detection
rate for rape crime is currently at 51.6%, while the detection rate for sexual assaults has remained
fairly consistent reducing slightly from 51.4% to 50% year on year.
Crimes relating to indecent images/communications are currently unchanged compared to last year
crimes with the majority being committed by strangers via online platforms.
The number of domestic abuse incidents has increased by 15% compared to PYTD from 655 to 756.
There has been a 2.7% increase in the crime/incident conversion rate from 47.9% to 50.7%, in 383
of these 756 incidents, a crime has been established. The total number of domestic crimes recorded
has risen from 377 to 559 crimes as at the end of Qtr. 2. This shows on occasion, more than a single
offence is identified per incident.  
A total of 156 missing person reports had been recorded by the end of September 2024, which is a
reduction of almost 15% from 179 last year. 
PUBLIC PROTECTION
Page 20

Page 21

OFFICIAL 
At the end of Qtr. 2, there have been no fatal road collisions in West Dunbartonshire, which is a
reduction from 1 in the same period last year. Both serious and slight injuries have also reduced
33.3% from18 to 12 (-6) and 18.75% from 16 to 13 (-3) respectively. 
Offences relating to motor vehicles have also seen a reduction of 11.6% from 1485 to 1313 (-172),
due to a decrease in speeding offences (-131) and unlawful use of motor vehicle offences such as
using a motor vehicle without a test certificate and insurance offences (-133). Crimes such as
drink/drug driving offences (+33) and vehicle defect offences (+48) have seen slight increases
compared to PYTD. 
Road Traffic Casualties 2023/24 2024/25
Number of persons killed on our roads 1 0
Number of persons seriously injured 18 12
Number of persons slightly injured 16 13
Number of children seriously injured 0 0
The Roads Policing Unit (RPU) based at Dumbarton continue to provide high visibility patrols
across the road network covering the main arterial and local road infrastructure. It is believed
this policing activity is responsible for the decrease in speeding offences while the increase in
drink & drug driving offences and also defect related offences evidences the pro-active policing
style of these officers removing dangerous drivers and vehicles from the roads to the benefit of
all. The RPU are currently assessing the recent recommendations from the HMICS Inspection
of Road Policing to best implement changes to further improve the service being provided.      
Through the summer months the RPU continued to support the road safety campaigns through
the national calendar of activity. This included drink / drug driving, speeding and mobile phones
in July and child safety as the children returned to school. They increased road patrols to deal
with the increased volume of traffic in the area during the summer months, educating drivers
and enforcing the law as appropriate.
The National Motorcycle Unit provided support during this period to engage with the large
number of motorcyclists over the summer both visiting and passing through the area.
On the 25th of August, the Preventions Team, working in partnership with SFRS, West
Dunbartonshire Council and The Institute of Advanced Motorists (IAM) staged a Road-Smart
event at the West Dunbartonshire offices at Church St. The event involved members of the
public either having pre-booked an appointment, or attending on the day, being given a general
safety brief and advice around driving styles and standards followed by a supervised drive, in
their own vehicle, with a qualified IAM assessor. After driving a pre-agreed route, the assessor
provided feedback on driving style and habits to the driver and offered advice on possible
adjustments that could improve safety and driving standards. Participants who were younger or
less experienced, also took part in a Virtual Reality (VR) headset driving experience where, via
the VR headset, they were the passenger in a vehicle that was involved in an accident and they
literally had a front seat view of the potential consequences of being distracted at the wheel and
some idea of what it is like to be involved in a heavy impact crash.   
The team are currently planning similar school-based inputs delivered to driving aged children,
and those of an age who may be passengers in vehicles, in an attempt to prevent and lower
the likelihood of young drivers being involved in road accidents.    
ROAD SAFETY AND ROAD CRIME
Page 21

Page 22

OFFICIAL 
Across Argyll & West Dunbartonshire, 12 persons linked to serious and organised crime have been
arrested and £2,445,484 has been seized under POCA since 1st April 2024.
At the end of September 2024, drug supply charges have increased 9.3% from 43 to 47 crimes and
is also slightly above the previous 5-year average (45). Drug possession charges have seen a
reduction of 21.8% from 330 to 258. 
Detective Inspector Lavery has taken charge of the Serious & Organised Crime Team with a
focus on targeting Serious & Organised Crime Groups (SOCG) within the Division by working
alongside partners such as Trading Standards, Licensing etc in targeted operations to disrupt
the criminal activities of these illegal and exploitive enterprises.      
The figures showing drugs supply crimes having increased from 43 to 47 is testament to the
work of this department and the Community Policing Teams who are executing warrants
regularly. Such detections can, on occasion, be the result of weeks or months of detailed
planned intelligence led operations to identify and apprehend those involved in the supply of
controlled drugs.    
This work is further evidenced by the fact that Across Argyll & West Dunbartonshire 12 persons
linked to serious and organised crime (SAOC) have been arrested and £2,445,484 seized under
the Proceeds of Crime Act 2002 (POCA). A very substantial amount of money that will impact
on current and planned future criminal activity.  
Police Scotland have re-launched the Custody Referral Scheme to offer every person in police
custody, who require it, the opportunity to be referred to a support agency for drugs or alcohol
dependency which may have had a bearing on their behaviour resulting in the arrest. We are
facilitating phone or possibly face-to-face consultations, depending on the time of day and
availability of staff. We are seeking to provide an appropriate, non-police, counsellor the
opportunity to engage with the individual in an attempt to divert that person into counselling to
reduce the chance of re-offending while also improving the individual’s health and contribution
to society. Every person consenting will be referred by email for subsequent consultation if face-
to face interaction is not appropriate for any reason. Reducing the number of people addicted to
alcohol and / or drugs is the overall goal, doing so will reduce offending and re-offending stats. 
SERIOUS & ORGANISED CRIME
Page 22

Page 23

OFFICIAL 
VIOLENCE & ANTI-SOCIAL BEHAVIOUR
A substantial volume of violent crime is being committed within private dwellings which reduces
potential impact from increased police presence in certain areas. We are maximising our visible
uniformed presence in any areas identified through analytical work as being more likely to be
the location for ASB and / or violence. 
To date, our officers have conducted 439 searches of individuals for weapons, drugs, stolen
property and other items utilising the appropriate legislation while ensuring any search is
proportionate and necessary. From these searches, 30.3% have been positive which equates
to 133 offences.
The increase in the detection rate for robberies to 71.4% highlights the efforts and focus being
given to this serious offence. Officers are utilising all appropriate strategies and investigation
techniques to ensure we identify and report as many individuals involved in these crimes as
possible. 
Youth Engagement Officers continue to deliver inputs to the youths around personal safety and
the negative impact on the community of ASB.
Levels of violence in West Dunbartonshire have increased by 10.3% from 688 to 759 (+71)
crimes. Just over half of all crimes took place in a private place and 40% of public space crimes
were committed by persons known to the victim.
Robberies have increased from 15 to 21 crimes, 14 of which occurred in a public place (10 on a
public street and 4 at commercial premises). The remaining 7 crimes occurred within a residential
premise. Twelve robberies were committed by persons known to the victim and 9 were committed
by strangers. The detection rate for robbery has increased from 53.3% to 71.4%, which equates
to an additional 7 crimes being detected year on year.
Serious assaults have also seen a slight increase from 37 to 44 crimes with crimes being largely
spilt 60/40 in terms of public/private space and 66% were committed by persons known to the
victim (2 were domestic related). Approximately 45% of crimes were committed with the victim
and/or offender being under the influence of alcohol/drugs or both and half of all crimes involved
the use of a weapon. The detection rate has remained fairly consistent from 64.9% to 65.1%.
Page 23

Page 24

OFFICIAL 
Common assaults have increased slightly by 6.2% from 487 to 517 and are currently above the
5-year average (441), while common assaults on police and emergency workers have reduced
by 5% compared to PYTD. Common assaults were largely spilt 50/50 in terms of public and
private space loci. In 47% of public space crimes, offenders were known to victims. The detection
rate for common assaults overall has reduced marginally from 57.7% to 55.5%.
Across the recording period the number of ASB related calls to Police Scotland has reduced by
approx. 12.3% compared to last year. Group 6 crimes, which include ASB related offences have
increased by 16% with 689 crimes recorded compared to 594 PYTD, however the current figure
remains 1.2% below the previous 5-year average (698). 
VIOLENCE & ANTI-SOCIAL BEHAVIOUR
The 5% reduction in assaults on emergency workers is very pleasing, daily briefings are
providing advice and warnings to police officers of violent offenders who have, or have made,
threats to assault police officers, other emergency workers and staff. This allows officers
attending specific addresses, or when dealing with known individuals, to approach situations
in the appropriate manner to best protect themselves, colleagues and other members of the
public from violent behaviour. Being assaulted is not part of being an emergency worker.    
The Preventions Team which includes a full-time ASB disclosure officer continue to monitor
and collate ASB on a daily basis sharing with all partners involved in the provision of housing.
The team are conducting joint visits to individuals who are repeatedly appearing on ASB lists
to reduce the prospect of escalation.
Our Disclosure Officer has made nearly 300 disclosures during 2024 to housing providers and
West Dunbartonshire have successfully applied for, and been granted, four ASB Orders
against individuals this year. Restrictions placed on individuals via these orders restrict the
likelihood of them being involved in ASB and also increase the police powers to act when an
order is breached. We continue to work daily with partners to reduce ASB which continues to
show a reduction both against the previous year and against the 5-year average.
Page 24

Page 25

OFFICIAL 
PUBLIC CONFIDENCE: COMPLAINTS & USER SATISFACTION
Overall satisfaction with Police Scotland
Police Scotland were in the top five for highest volume of 999 calls received across the UK Police
Forces. Average speed of answer for the month of July 2024 was 81% of calls answered within 10
secs.  
Average Speed of Answer UK Police Scotland
999 Calls 1,091,845 66,288
ASA 9.47 secs 11.26 secs
<10s 85.52% 81.1%
10-60s 12.03% 15.9%
>60s 2.09% 3.00%
Total of
290
responses
Chief Inspector Kirsten McLatchie
retained an overview of all local policing
activity in West Dunbartonshire as
Local Area Commander during this
reporting period. 
We have another 10 new Probationary
Officers commencing duty on Monday
4th of November in the division who will
be followed by a further 5 in December
and 10 early in 2025. A substantial
resource increase across the estate. 
User Satisfaction results show that
locally, public confidence levels remain
high within Argyll and West
Dunbartonshire with overall satisfaction
levels at 69%, which remains in line
with the position in 2022/23. 
69%
Satisfied/Very
Satisfied
Page 25

Page 26

Page 26

Page 27

West Dunbartonshire Performance Report
Q2 - 1st July 2024 - 30th September 2024
Annick
ITEM 7b
Page 27

Page 28

West Dunbartonshire Performance Report
Table of Contents
Local Fire and Rescue Service Plan Priorities 3
WestDunbartonshire Activity Summary   4
Domestic Safety - Accidental Dwelling Fires 5
Domestic Safety - Accidental Dwelling Fire Casualties 6
Unintentional Injury and Harm         7
Deliberate Fire Setting       8
Non-Domestic Fire Safety       9
Unwanted Fire Alarm Signals      10
S      2Page 28

Page 29

4 0 5 13 1 8
7 1 2 17 2 26
7 0 1 10 0 3
4 0 0 5 0 2
5 3 2 16 0 7
2 0 0 3 0 5
29 4 10 64 3 51
0% 300% 100% 14% -57% 0%
-2% 40% -4% -18% -20% -31%
1% 57% 28% 18% 12% 13%
Accidental
Dwelling
Fires
Accidental
Dwelling Fire
Casualties
Non-
Domestic 
Fire Safety
Unwanted
Fire Alarm
Signals
Unintentional
Injury and Harm
Deliberate
Fire Setting
Local Fire and Rescue Service Plan Priorities
Year on Year Change
3 Year Average Change
5 Year Average Change
Clydebank Central
Clydebank Waterfront
Dumbarton
Kilpatrick
Leven
Lomond
Total Incidents
The Local Fire and Rescue Service Plan has been developed to set out the priorities and objectives within West
Dunbartonshire and allows our local authority partners to scrutinise the performance outcomes of these priorities.      
We will continue to work closely with our partners in West Dunbartonshire to ensure we are all “Working Together for a
Safer Scotland” through targeting risks to our communities at a local level.
The plan has been developed to complement key partnership activity embedded across West Dunbartonshire`sCommunity
Plan and associated Delivery and Thematic plans. Through partnership working we will seek to deliver continuous
improvement in our performance and effective service delivery in our area of operations.
The Local Fire and Rescue Plan for West Dunbartonshireidentified six areas for demand reduction and is subject to regular
monitoring and reporting through the Police & Fire and Rescue Committee. A summary of the priorities and current activity
is detailed below with further detail and analysis contained within this performance report.
About the statistics within this report 
The activity totals and other statistics quoted within this report are published in the interests of transparency and
openness. They are provisional in nature and subject to change as a result of ongoing quality assurance and review.
Because all statistics quoted are provisional there may be a difference in the period totals quoted in our reports after
local publication which result from revisions or additions to the data in our systems. The Scottish Government publishes
official statistics each year which allow for comparisons to be made over longer periods of time.
* Regarding 3 Year Average and 5 Year Average percentages. These values indicate the percentage change
between the current 3 or 5 year average and the previous 3 or 5 year average. The value does not reflect the difference
between the current quarter against the 3 or 5 year average.
Activity levels have reduced by more than 5%
Activity levels have reduced by up to 5%
Activity levels have increased overall
3Page 29

Page 30

West Dunbartonshire Activity Summary
2020/21 2021/22 2022/23 2023/24 2024/25
122 156 138 105 111
62 87 74 68 69
158 216 176 137 132
342 459 388 310 312Total Incidents
All Special Services
All False Alarms
All Fires
0
100
200
300
400
500
2020/21 2021/22 2022/23 2023/24 2024/25
Total Incidents All Fires All Special Services All False Alarms
35%
19%
46%
36%
22%
42%
All Fires All Special Services All False Alarms
Incidents by Classification
Annual Average
5 Year Average
16.35%
12.82%
11.86%
10.58%
10.58%
9.29%
8.01%
2.88%
2.88%
1.92%
1.60%
1.60%
1.60%
1.28%
1.28%
False Alarm (UFAS)
False Alarm (Good Intent)
False Alarm (Dwelling)
Outdoor Fire
Dwelling Fire
Refuse Fire
Special Service - Effecting entry/exit
Special Service - RTC
Vehicle Fire
Special Service - Assist other…
Special Service - Removal of…
Special Service - Lift Release
Special Service - Flooding
Special Service - Other…
Other Building Fire
Top 15 Incident Types by % of Total Incidents
West Dunbartonshire OperationalTrends
00:00 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00
Mon
Tue
Wed
Thu
Fri
Sat
Sun
111
fires
primary &
secondary
special
services69
false
alarms
132
-4%
totalnumber of
incidents
312 1%
6%
fire & non-fire
casualties
14 100% economiccost of
ufas incidents
£100,470
Activityby Time of Day
1%
(6) (1)
(-5)
(2) (7)
4Page 30

Page 31

0% -2% 1%
Year on
Year
3 Year
Average *
5 Year
Average *
Main Source of Ignition
Domestic Safety - Accidental Dwelling Fires Domesti
Detection Present
79.3% 82.6%
Detection Actuated
Calls Made via Linked Alarms
75.9%
16
3 3 3 2
Cooking
appliance
Electricity supply Not known Smoking Related Other domestic
style appliance23
31
26
29 29
2020/21 2021/22 2022/23 2023/24 2024/25
44.8% 24.1%
51.7% 62.1%
No FirefightingAction Direct Firefighting
Heat/SmokeDamage Only Nofire Damage
Alcohol/Drug Impairment
13.8%
Distraction
37.9%
01 0203
04
05
06
07
08
09
101112131415
16
17
18
19
20
21
22 23 00
13.8%
Clydebank
Waterfront
24.1% 24.1%
Dumbarton
Kilpatrick Leven Lomond
13.8% 17.2% 6.9%
Clydebank
Central
Performance Summary
AccidentalDwelling Fires to Date
Main Source of Ignition
Accidental Dwelling Fires by Time of Day
Severity of Accidental Dwelling Fires
Human Factors
Automatic Detection & Actuation
AccidentalDwelling Fires Activity by Ward (% share)
(4) (7) (7)
(4) (5) (2)
(13) (7)
(15) (18)
(11) (4)
(23) (19)
(22)
5Page 31

Page 32

300% 40% 57%
Year on
Year
3 Year
Average
5 Year
Average
Domestic Safety - Accidental Dwelling Fire Casualties
Overcome by
gas, smoke or
toxic fumes, 75.0%
25.0%
0.0%
0.0%
0.0%
Breathing
Difficulties
(Other)
0
1
0 0 0
1
0
1 1
0
0 - 9 10 - 19 20 - 49 50 - 79 80+
Male
25%
Female
75%
2 2 2
1
4
2020/21 2021/22 2022/23 2023/24 2024/25
Clydebank
Central
0.0%
Clydebank
Waterfront
25.0% 0.0%
Dumbarton
Kilpatrick Leven Lomond
0.0% 75.0% 0.0%
Unintentional Injury or
01 02 03
04
05
06
07
08
09
101112131415
16
17
18
19
20
21
22 23 00
First Aid at Scene
Hospital -Serious Injuries
Hospital-Slight Injuries
Fatality
Performance Summary Fire Casualties by Time of Day
AccidentalDwelling Fire Casualties Year to Date
Nature of Injury
Extent of Harm
Age / Gender Profile
Accidental Dwelling Fire Casualties by Ward (% share)
(0) (1) (0)
(0) (3) (0)
(4) (0)
(0) (0)
25.0%
S      6Page 32

Page 33

100% -4% 28%
5 Year
Average
Year on
Year
3 Year
Average
Unintentional Injury or Harm
Cuts/Lacerations
Not known
Other
Head injury
Back / Neck
injury (spinal)
Collapse
20.0%
20.0%
20.0%
20.0%
10.0%
10.0%
0 0
1
4
3
0 0
2
0 0
0 - 9 10 - 19 20 - 49 50 - 79 80+
Male
80%
Female
20%
Clydebank
Central
Clydebank
Waterfront
20.0% 10.0%
Dumbarton
Kilpatrick Leven Lomond
0.0% 20.0% 0.0%
50.0%
Road Traffic Collision Water Rescue
Assisting Other Agencies
30.0% 0.0%
70.0%
01 0203
04
05
06
07
08
09
101112131415
16
17
18
19
20
21
2223 00
First Aid at Scene
Hospital -Serious Injuries
Hospital -Slight Injuries
20.0%
10.0% 20.0%
Fatality
40.0%
11 11
9
5
10
2020/21 2021/22 2022/23 2023/24 2024/25
Deliberate
Performance Summary
Non-Fire Casualties Year to Date
Non-Fire Casualties by Time of Day
Nature of Injury
Extent of Harm
Non-FireEmergency Activity
Age / Gender Profile
Non-FireCasualties by Ward (% share)
(5) (2) (1)
(0) (2) (0)
(0)(3)
(4) (2)
(2) (1)
(7)
S      7Page 33

Page 34

14% -18% 18%
Year on
Year
3 Year
Average
5 Year
Average
Deliberate Fire Setting
Clydebank
Central
Clydebank
Waterfront
26.6% 15.6%
Dumbarton
Kilpatrick Leven Lomond
7.8% 25.0% 4.7%
20.3%
87
111
94
56 64
2020/21 2021/22 2022/23 2023/24 2024/25
01 0203
04
05
06
07
08
09
101112131415
16
17
18
19
20
21
22 23 00
0.0%
17.2%
17.1%
14.9%
16.1%
15.6%
0.0%
82.8%
82.9%
85.1%
83.9%
84.4%
2016/17
2017/18
2018/19
2019/20
2020/21
2021/22
Primary Secondary
4
1
5
0
Other Buildings
Dwellings
Vehicles
Other Primary
27
27
Refuse
Other Secondary
342
459
388
310 312
72 92 80 47 54
0
200
400
600
0
200
400
600
2020/21 2021/22 2022/23 2023/24 2024/25
All Incidents Deliberate Secondary Fires
Non
Performance Summary
Deliberate Fires Year to Date
Deliberate Firesby Time of Day
Deliberate Firesby Classification
Primary Fire Ratio by Activity Type
Secondary Fire Ratio by Activity Type
Deliberate Fires Compared to Operational Activity
Deliberate Fires by Ward (% share)
(13) (17) (10)
(5) (16) (3)
8Page 34

Page 35

-57% -20% 12%
Year on
Year
3 Year
Average
5 Year
Average
Non Domestic Fire Safety
5
7
6
7
3
2020/21 2021/22 2022/23 2023/24 2024/25
Clydebank
Central
Clydebank
Waterfront
66.7% 0.0%
Dumbarton
Kilpatrick Leven Lomond
0.0% 0.0% 0.0%
33.3%
67%
33%
Accidental Deliberate Not Known
33.3% 33.3%
33.3% 66.7%
No FirefightingAction Direct Firefighting
Heat/SmokeDamage No FireDamage
1
1
1
Hospitals and medical care,
Hospital
Residential Home,
Nursing/Care
Residential Home,
Retirement/Elderly
Unwanted
01 0203
04
05
06
07
08
09
101112131415
16
17
18
19
20
21
2223 00Performance Summary
Non-Domestic Fires Year to Date
Non-Domestic Firesby Time of Day
Non-Domestic Fires by Nature of Origin
Non-Domestic Fires by Ward (% share)
Severity of Non-DomesticFires
Non-Domestic Fires by Premises Type
(1) (2) (0)
(0) (0) (0)
(1) (1)
(1) (2)
9Page 35

Page 36

0% -31% 13%
5 Year
Average
Year on
Year
3 Year
Average
Unwanted Fire Alarm Signals
82
144
101
51 51
2020/21 2021/22 2022/23 2023/24 2024/25
Clydebank Clydebank
Waterfront
51.0% 5.9%
Dumbarton
Kilpatrick Leven Lomond
3.9% 13.7% 9.8%
15.7%
18
12
9
3
2
Residential Home, Children's
Residential Home,
Nursing/Care
Hospitals and medical care,
Hospital
Other Residential, Hotel/motel
Other Residential, Sheltered
Housing - not self contained
16%
UFAS Percentage Against all Incidents
UFAS Percentage Against all False Alarms
39%
Human Influenceand Alarm Activations
33.3%
0.0
1.0
Mon Tue Wed Thu Fri Sat Sun
01 0203
04
05
06
07
08
09
101112131415
16
17
18
19
20
21
22 23 00
Performance Summary
Unwanted Fire Alarm Signals Year to Date
Unwanted Fire AlarmSignals by Ward (% share)
Unwanted Fire Alarm Signals by Time of Day
Unwanted Fire Alarm Signals- Top 5 Premises
Unwanted Fire Alarm Signals Activity Ratios
Average UnwantedFire Alarm Signals per Day
(312)
(17)
(8) (26) (3)
(2) (7) (5)
(132)
10Page 36

Page 37

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Housing and Employability
Committee: Housing and Communities Committee 20 November 2024
Subject:Housing and Employability Delivery Plan 2024/25 mid–year Progress
1 Purpose
1.1 This report sets out the mid -year progress of the Housing and Employability
Delivery Plan 2024/25.
2 Recommendations
2.1 It is recommended that Committee notes the progress achieved.
3 Background
3.1 In line with the Strategic Planning & Performance Framework, each Chief
Officer develops an annual Delivery Plan which sets out actions to help deliver
the Strategic Plan and address the performance challenges and service
priorities identified in the planning process. The Plan also provides an
overview of services and resources, including employees and budgets, sets
out the performance indicators (PIs) for monitoring progress and considers the
relevant risks.
3.2 The Housing and Employability Delivery Plan 2024/25 was presented to
Housing and Communities Committee on 1 May 2024 with a commitment to
report mid-year and year-end progress in November 2024 and May 2025
respectively.
4 Main Issues
4.1 Appendix 1 details the progress at this mid-year point.
4.2 The Delivery Plan for 2024/25 was supported by an action plan of activities to
be delivered over the year. At this mid-year point, one of the 27 actions have
been completed, 26 are progressing as planned and are anticipated to be
completed by 31 March 2025.  Appendix 1 details the progress on delivery of
this action plan.
4.3 Also included in the plan are 31 performance indicators which measure
progress across key areas and link to the Strategic Plan 2017-2022.  24 of the
performance indicators are monitored on a quarterly basis. Performance for
each quarter is summarised below, based on all data available at this time.
Appendix 1 details the progress for performance where target was missed.
PI Status Q1 Q2
Target met or exceeded 16 14
ITEM 8
Page 37

Page 38

Target narrowly missed 4 6
Target significantly missed 4 3
Not applicable 1
Total No. of available PIs 24 24
4.4 Significantly missed targets relate to the following PIs:
 Properties returned from repairs within target
 Average time (in days) to inspect and repair empty homes
 Average length of time (in hours) to complete emergency repairs
 Average time taken (in days) to complete non – emergency repairs
5 People Implications
5.1 There are no direct people implications arising from this report.
6 Financial & Procurement Implications
6.1 There are no direct financial or procurement implications arising from this
report.
7 Risk Analysis
7.1 Failure to deliver on the actions assigned to Housing and Employability may
have a direct impact on the delivery of the Council’s Strategic Plan. It is
essential that remedial action is taken to ensure strategic delivery plans
achieve the commitments detailed and approved.
8 Equalities Impact Assessment
8.1 Screening and impact assessments will be carried out on specific activities as
required.
9 Consultation
9.1 The delivery plans were developed through consultation with officers from the
strategic service areas.
10 Strategic Assessment
10.1 The delivery plans set out actions to support the successful delivery of the
strategic priorities and objectives of the Council.
Chief Officer: Peter Barry
Page 38

Page 39

Service Area: Housing and Employability 
Date: 22nd October 2024
_____________________________________________________________
Person to Contact: Nicola Docherty
nicola.docherty@west-dunbarton.gov.uk
Appendices: Appendix 1: Housing and Employability Delivery Plan
2024/25 – mid-year progress of Actions & PIs
Background Papers: Housing and Employability Delivery Plan 2024/25 –
Housing and Communities Committee, 1 May 2024
Strategic Planning & Performance Framework 2022/27
Wards Affected: All
Page 39

Page 40

H&E Delivery Plan Mid-Year Progress
1. Our communities
Objective 1. Our neighbourhoods are safe, resilient and inclusive
Q1 2024/25 Q2 2024/25Performance
Indicator Statu
s Value Targe
t
Short
Trend
Long
Trend
Statu
s Value Targe
t
Short
Trend
Long
Trend
Comments Owner
Number of incidents
directed to Police by
Public Space CCTV
team
261 100 231 100 Mid-year target exceeded. Nicola
Pettigrew
% of anti-social
behaviour cases
resolved
85.9
% 85% 104.7
% 96% Mid-year target exceeded. Nicola
Pettigrew
% of Public Space
CCTV cameras that
are operational
76.6
% 85% 88.3
% 85%
Target narrowly missed for mid-year
position. Despite this, quarter two saw
a marked improved improvement over
the last few quarters. We have
appointed a contractor to carry out the
upgrade works to full CCTV network.
This will see new and improved state
of art technology and increased
camera provision throughout WDC
Nicola
Pettigrew
ITEM 8-
APPENDIX 1
Page 40

Page 41

Action Status Progress Due Date Note Owner
Implement second phase of CCTV
equipment and infrastructure
modernisation and improvements
31-Mar-
2025
This action is progressing well and anticipated to be
completed by year end. To date we have finalised
costings with BT and gained approval at Housing and
Communities Committee in August and contract with BT
has been signed. We have confirmed with WDTRO
every 2nd landing to have CCTV. Our focus for the
remaining year is to commence the approved upgrades.
Nicola
Pettigrew
Objective 2. Our residents health and wellbeing remains a priority
Q1 2024/25 Q2 2024/25Performance
Indicator Statu
s Value Targe
t
Short
Trend
Long
Trend
Statu
s Value Targe
t
Short
Trend
Long
Trend
Comments Owner
% of Youth
Homelessness levels
in West
Dunbartonshire
18.6
% 20% 20.1
% 20%
Mid-year target met. Despite
narrowly missing target in Q2, we
have seen both a reduction in youth
homelessness presentations and a
reduction in level of youth
homelessness from 23% in 2023/24.
John Kerr
Action Status Progress Due Date Note Owner
Develop and introduce a new
preventative focused housing
access system
31-Mar-
2025
This action is progressing well. To date we have
developed the initial proposal as part of the Housing
Options service redesign and are working on the
proposal for the new housing access system in response
to the housing emergency declaration and preparation
John Kerr
Page 41

Page 42

Action Status Progress Due Date Note Owner
for homeless prevention duty.  The Housing (Scotland)
Bill was introduced in the Scottish Parliament on 26
March 2024 however we require clarity in terms of
implementation date to allow us to proceed with this
action.
Objective 3. Our residents are supported to increase life and learning skills
Action Status Progress Due Date Note Owner
Deliver new tenant participation
strategy
31-Mar-
2025
This action is progressing well and anticipated to be
completed by year end. To support the development of
the tenant participation strategy, tenant consultations
were carried out from May to September, responses
have been used to shape priority areas in the draft
strategy action plan.
John Kerr
2. Our Environment
Objective 6. Our neighbourhoods are sustainable and attractive
Page 42

Page 43

Q1 2024/25 Q2 2024/25Performance
Indicator Statu
s Value Targe
t
Short
Trend
Long
Trend
Statu
s Value Targe
t
Short
Trend
Long
Trend
Comments Owner
Tenancy Sustainment
Levels within Housing
First
100% 90% N/A
Target exceeded in quarter 1, no
further Housing First tenancies
were created in Q2 of 2024/25.
John Kerr;
Stefan
Kristmanns
Average length of
time to re-let
properties
28.9 30 27.6 30 Mid-year target exceeded. Nicola
Pettigrew
The number of
incidences of youth
homelessness in
West Dunbartonshire
is reduced
49 70 48 70
Mid-year target exceeded. We will
continue to monitor trend
information and deliver the key
objectives within our Rapid
Rehousing Transition Plan to
ensure we tackle youth
homelessness in West
Dunbartonshire effectively.
John Kerr
% of council
dwellings that meet
the Scottish Housing
Quality Standard
61.2
%
56.7
%
70.7
%
62.2
% Mid-year target exceeded. Alan Young
Action Status Progress Due Date Note Owner
Ensure compliance with tenant
safety standards (e.g. EICR, Gas
safety, Mould & Dampness)
31-Mar-
2025
This action is progressing well and anticipated to be
completed by year end. To date we have carried out a
self-assessment to assess compliance with Housing
regulator standards. Over the remaining year we will
develop a funding and delivery model in conjunction with
the rent setting exercise and implement necessary
Martin
Feeney;
John Kerr
Page 43

Page 44

Action Status Progress Due Date Note Owner
measures to ensure compliance around tenant safety
standards.
Ensure the Council’s Housing
stock maintains compliance with
the Scottish Housing Quality
Standard and reduce the number
of properties held in abeyance.
31-Mar-
2025
This action is progressing well and on track to be
completed at year end. The Capital Investment
programme for 24-25 continues to progress and
contribute to SHQS compliance.
Alan Young
Ensure the Council’s Housing
stock progresses towards the
achievement of the energy
efficiency standard for social
housing (EESSH).
31-Mar-
2025
This action is progressing well and on track to be
completed at year end. The Capital Investment
programme for 24-25 continues to progress EWI and
contribute to EESSH compliance.
Alan Young
Develop and introduce a wider
national rented home strategy
31-Mar-
2025
This action is progressing well. To date we have
responded to the publication of The Housing (Scotland)
Bill and reported back to the Housing Bill steering group.
Over the remaining year we will focus on carrying out a
needs analysis and consultation to prepare our strategy
ahead of presenting to committee for agreement.
John Kerr
Develop approach to the new
Social Housing Net Zero Standard
31-Mar-
2025
This action has progressed well. The Social Housing Net
Zero Standard will set out the regulations for how social
landlords heat residential properties, as well as how
energy efficient the buildings need to be. To date we
have provided a response, agreed through the Better
Homes Board, to the Scottish Government
consultation. Publication of the standard is currently
unknown which may impact on this agreed action.
John Kerr
Deliver on the More Homes
Programme
31-Mar-
2025
This action is progressing as planned. To date we have
agreed a new revised programme with the Scottish
Government. In the second half of the year, we will focus
John Kerr
Page 44

Page 45

Action Status Progress Due Date Note Owner
on developing and agreeing the new Strategic Housing
Investment Plan and completing the Clydebank East
housing development.
Deliver new Housing Asset
Management Strategy
31-Mar-
2025
This action is progressing as planned. To date we have
carried out a review of the current strategic requirements
and have updated the Better Homes Board. In the
second half of the year, we will focus on completing a
housing stock modelling exercise, strengthen the
resource requirements to deliver on our ambitions and
deliver the new Housing Asset Strategy, with Committee
approval.
John Kerr
Assess requirement for declaration
of housing emergency within West
Dunbartonshire.
31-Mar-
2025
This action is progressing as planned and anticipated to
be completed by year end. The Housing and
Communities Committee declared a Housing Emergency
on 1st May 2024, in response we have developed the
Housing Emergency Declaration Action Plan, identifying
key priority areas to be addressed over the coming year;
this was approved by the Housing and Communities
Committee in August 2024. Ongoing monitoring of the
action plan will be overseen by the Housing Emergency
Project Board and will be reported on a quarterly basis to
Committee.
John Kerr
Refresh our Strategic Housing
Investment Programme (SHIP)
31-Mar-
2025
This action is progressing well and is anticipated to be
completed by year end. To date we have reviewed our
resources; this was updated to members in August ‘24.
Over the remaining year we will focus on developing the
new SHIP and delivering the refreshed programme.
John Kerr
Implement digital improvement for
housing operations (mobile app)
31-Mar-
2025
This action is progressing well and anticipated to be
completed by year end. To date we have reviewed
Nicola
Pettigrew
Page 45

Page 46

Action Status Progress Due Date Note Owner
usage of the mobile app to ensure compliance with the
mobile app. We completed demonstrations to all housing
operations team on rent insights; with further roll out of
the rent insights commencing in September. We have
identified key tasks for the remaining year and over the
remaining year we will implement key tasks by identified
priority area.
Implement digital improvement for
housing operations (self serve
portal)
31-Mar-
2025
This action is progressing well. To date we have focused
on exploring the potential for automating a range of
housing processes, including housing applications,
medical applications. We anticipate a number of these
automations going live in late November 2024 and that
the action will be completed by year end.
Nicola
Pettigrew
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to meet
citizen
expectation and
service
standards
Risk of citizen dissatisfaction
due to us not doing what we say
we will when we say we will or
not completing required works
first time. 
03-Oct-
2024
To ensure citizens expectations
and service standards are met we
have identified key priority areas
within the Building Services
Improvement Plan, where
progress is reported to the
Building Service Board. We will
continue to monitor customer
satisfaction to assess the impact
of the improvements.
Martin
Feeney
Page 46

Page 47

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
deliver medical
adaptations in
agreed target
timescales
This is monitored to ensure
target timescale of 79 days
average for housing medical
adaptations is adhered to
ensure satisfaction with the
service and support those in
need of this service. 
21-Oct-
2024
Q1, Q2 Continues with good in-
year progress and continuing to
clear legacy jobs helping to
improve the overall position.
Average days performance
continues to improve and slightly
over target for Q1 (47 days) & on
target for Q2 (44 days) On track
overall for improvement and
reducing risk.
Alan Young
Failure to
achieve the
outcomes of the
Scottish Social
Housing Charter
The Scottish Social Housing
Charter sets out the standards
and outcomes that tenants and
customers should expect from
social landlords, in terms of the
quality and value for money of
the services they receive.
Failure to continue to meet
these could place the Council at
risk of the intervention powers of
the Scottish Housing Regulator
21-Oct-
2024
Assessment remains as previous,
however risk concerns have been
identified and included within the
Councils Annual Assurance
Statement which was submitted
to the Housing Regulator in
August 2024.
John Kerr
Failure to
deliver on
homelessness
prevention
The risk that, similar to other
Local Authorities we will be
unable to adequately meet
housing needs due to rising
costs and reduction in funding.
21-Oct-
2024
Assessment upgraded and linked
to the housing emergency
declaration 2024. Key aspect of
housing emergency action plan is
to accelerate homeless
prevention activities in advance of
homeless prevention duties as
noted in the current Housing Bill.
John Kerr
Page 47

Page 48

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
maintain
Housing Stock
The risk that Council’s Housing
Stock are not fully fit for purpose
with consequent adverse impact
on our ability to deliver efficient
and effective housing for
Council tenants.
21-Oct-
2024
No change to risk score,
programme for investment and
upgrades to council housing
continues into 24-25 and a further
five year programme to 28-29.
Alan Young
3. Our Economy
Objective 8. We will support our residents to access employment and training opportunities
Q1 2024/25 Q2 2024/25Performance
Indicator Statu
s Value Targe
t
Short
Trend
Long
Trend
Statu
s Value Targe
t
Short
Trend
Long
Trend
Comments Owner
Value (£) of debt
managed
£358,
210
£300,
000
£282,
259
£300,
000
Mid-year target exceeded. Despite
performance at quarter 2 narrowly
missing target, performance is on
track at the mid-year point.
Stephen
Brooks
Number of local
people entering
employment through
Working 4U
131 104 102 104
Mid-year target exceeded. Despite
performance at quarter 2 narrowly
missing target, performance is on
track at the mid-year point.
Stephen
Brooks
Number of local
people entering
education or training
243 162 476 259 Mid-year target exceeded. Stephen
Brooks
Page 48

Page 49

Q1 2024/25 Q2 2024/25Performance
Indicator Statu
s Value Targe
t
Short
Trend
Long
Trend
Statu
s Value Targe
t
Short
Trend
Long
Trend
Comments Owner
Number of local
people gaining a full
qualification
303 228 274 128 Mid-year target exceeded. Stephen
Brooks
Action Status Progress Due Date Note Owner
Review the current CLD Plan and
compile a new plan for the 2025 –
2028 planning period.
31-Mar-
2025
This action has been successfully completed. The CLD
plan 24-27 has been produced by the CLD Strategic
Group and will be published online by the end of October
24. Action plans for Youth Alliance, Adult Learning
Partnership and Community Development Alliance have
been developed and agreed with key stakeholders for
the duration of the new 3 Year CLD Plan.
Stephen
Brooks
Continue to develop access to
welfare rights and debt
management services
31-Mar-
2025
This action is progressing well and in track to be
completed by year end. The new triage process
introduced is working effectively with residents and
agencies referring to the welfare rights and debt teams
being contacted within 2/3 working days.  Number of
referrals remains high with the servicer continuing to
highlight the support on offer within West
Dunbartonshire.
Stephen
Brooks
Continue to provide access to
employability services
31-Mar-
2025
This action is progressing well and in track to be
completed by year end. Working4U continues to develop
and deliver employability services which meet the needs
of residents with barriers to accessing work as well as
offering in-work support.  Through the Strategic
Employability Group funding for delivery of employability
Stephen
Brooks
Page 49

Page 50

Action Status Progress Due Date Note Owner
services from partners has been commissioned for 24/25
and provision focuses on parents, vulnerable young
people, economically inactive people, people with
disabilities including mental health, community justice
service users, ethnic minorities and those who are long
term unemployed.
Continue to provide access to
community-based learning
opportunities
31-Mar-
2025
This action is progressing well and in track to be
completed by year end. The Adult Learning team are
working with West College Scotland to deliver a range of
SQA courses in the local community.  English for
Speakers of Other Languages remains in high demand
as new Scots settle in West Dunbartonshire.  Literacy
and digital learning continues to meet the needs of
residents.  Multiply funding is being used with partners to
develop and enhance the numeracy skills of service
users as well as enabling access to core skills
qualifications in numeracy and maths.
Youth focussed learning is offered through the Thrive
and Ready to Thrive programme for vulnerable young
people who require support with their personal
development.
Stephen
Brooks
Objective 9. We will work with partners to support economic development to deliver increased prosperity for our area
Page 50

Page 51

Q1 2024/25 Q2 2024/25Performance
Indicator Statu
s Value Targe
t
Short
Trend
Long
Trend
Statu
s Value Targe
t
Short
Trend
Long
Trend
Comments Owner
Total Value (£) of
Income Generated
£2,78
5,087
£1,30
0,000
£2,25
3,291
£1,30
0,000 Mid-year target exceeded. Stephen
Brooks
Number of local
people receiving
support through
Working 4U
2,046 1,534 2,349 1,700
Mid-year target exceeded. Stephen
Brooks
Action Status Progress Due Date Note Owner
Develop a new employability
partnership action plan
31-Mar-
2025
This action is progressing well and in track to be
completed by year end. The Strategic Employability
group chaired by W4U Manager continues to meet to
shape employability services for West Dunbartonshire
which are responsive to the needs of service users and
within the funders eligibility criteria.  Strategic Partners
are commencing discussions on a new 3 Year
Employability Plan – based on key performance
indicators and self-evaluation. Annual Action Plans for
No one left behind (NOLB) have been submitted to
Scottish Government for 24/25.  For UK Shared
Prosperity Fund (UKSPF) the delivery plan is monitored
and reported to the Glasgow City Region. 
Skills Development Scotland Quality Action Plan has
been submitted and approved for the Modern
Apprenticeship and Foundation Apprentice programmes.
Stephen
Brooks
Page 51

Page 52

Action Status Progress Due Date Note Owner
Explore the potential for securing
training and opportunities in the
carbon/green energy sectors
31-Mar-
2025
This action is progressing well and in track to be
completed by year end. Our Employer Engagement team
continues to work with green employers to identify their
needs addressing various issues such as recruitment;
grants; work placements; upskilling; and advice.  A
Business Breakfast took place on 27th June. This was a
joint event with Business Gateway to provide additional
advice and guidance on business funding and to build
partnerships with new employers, with a strong focus on
the green sector. In 2023/24 Working4U supported green
sector employers to fill 25 vacancies, roles included a
Net Zero Coordinator, Loft insulation Installer and
Recycling Operative.
Stephen
Brooks
Compile and publish the local child
poverty report to demonstrate our
actions to address poverty and
disadvantage
31-Mar-
2025
This action is progressing well and in track to be
completed by year end. A Child Poverty event was
hosted to share information about the range of services
working to tackle poverty and its impacts in West
Dunbartonshire.  Working4U worked in partnership with
the Improvement Service to undertake a self-evaluation
on partners knowledge of the impact of Child Poverty
and the accessibility of services to support families
locally.  The Family Prosperity network (FPN) has been
established. The self-evaluation findings and
recommendations and seven improvement statements
identified through the analysis of the survey responses
are to be discussed and agreed at the new FPN.  Child
Poverty report is near completion with final review
imminent.
Stephen
Brooks
Page 52

Page 53

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
respond to child
poverty
legislation will
have a
significant
impact on the
Council’s
reputation, more
importantly an
opportunity to
raise issues and
respond more
effectively to
child poverty
issues will be
lost
The Local Child Poverty Plan
sets out what we will do to
respond to child poverty, failure
to respond will have a significant
impact on the Council’s
reputation, more importantly an
opportunity to raise issues and
respond more effectively to child
poverty issues will be lost
21-Oct-
2024
We have established a process
for developing the local child
poverty report and will undertake
a self-evaluation to assess the
effectiveness of our approach.
The self-evaluation will inform
future developments
Stephen
Brooks
The cost of
living crisis will
lead to a
substantial
demand for
access to
welfare/debt
support
services.
We will monitor the changing
levels of demand and target our
resources to individuals and
areas that are most in need. We
will seek to work with partners to
ensure we receive appropriate
referrals who can benefit from
our support.
21-Oct-
2024
We have reviewed our processes
for dealing with referrals and
carrying out assessments. This
emphasises the need to respond
quickly to those most in need
while directing those with lower
levels of need to appropriate
partner and alternative sources of
support.
Stephen
Brooks
4. Our Council
Page 53

Page 54

Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Status Progress Due Date Note Owner
Workforce Planning: Develop and
implement wellbeing, employee
engagement, equality and learning
and development plans to enable
capabilities, improve resilience and
promotion of a diverse workforce
31-Mar-
2025
This action is progressing well. The management teams
within Housing and Employability have been
encouraging teams to update HR profiles to ensure
accurate recording of the diversity profile of the team.
Wellbeing continues to be a focus of the service ensuring
employees are aware of the range of supports available
to them through regular promotion of wellbeing supports
and workforce updates. In addition, absence
management is a key focus area and use of the Council
console tool has been promoted to support managers to
ensure absences are being managed well in areas such
as timely return to work meeting where appropriate.
Peter Barry
Workforce Planning: Develop and
implement employee life cycle
plans in line with the People First
Strategy to attract and retain the
workforce
31-Mar-
2025
This action is progressing well. The management teams
within Housing and Employability have focused attention
on areas such as Building Services and Housing
Operations. Reviewing recruitment and retention of key
roles to ensure efficiencies and key projects are
supported such as housing team leader, void
management and income generation posts will continue
to be the focus over the remaining year.
Peter Barry
Workforce Planning: Implement
service review process including
role design, use of new technology
and new ways of working to add
resilience, address gaps, and
31-Mar-
2025
This action is progressing well. The management teams
within Housing and Employability have been exploring
opportunities for efficiencies across a range of functions.
The focus in the first half of the year has been to review
spending on HRA and identify efficiencies and to review
Peter Barry
Page 54

Page 55

Action Status Progress Due Date Note Owner
establish opportunities for
efficiencies
staffing structures to ensure they are efficient and
compliant with the WDC standard operating model taking
into consideration future service needs. In addition,
technology efficiencies such as automation of functions
has been reviewed and implemented and a training
program to support use of environmental sensors has
been introduced. Work will continue over the remaining
year to implement any identified efficiencies.
Workforce Planning: Develop and
implement learning and
development plans and
development opportunities to
improve capabilities and resilience
within the workforce
31-Mar-
2025
This action is progressing well. The management teams
within Housing and Employability have thus far focused
attention on reviewing succession planning within
services and ensuring skill transfer and upskilling of key
roles. Scoping exercises for future skill needs have been
undertaken and over the coming year work will continue
to review needs and implement any changes.
Peter Barry
Objective 11. Our Council is adaptable and focused on delivering best value for our residents
Q1 2024/25 Q2 2024/25Performance
Indicator Statu
s Value Targe
t
Short
Trend
Long
Trend
Statu
s Value Targe
t
Short
Trend
Long
Trend
Comments Owner
% of properties
returned from repairs
within target
58% 80% 70% 80%
Mid-year target not achieved,
despite this significant progress
has been made in quarter 2 to
reduce the total number of void
properties towards target level.
This whilst restricting overtime
Martin Feeney
Page 55

Page 56

Q1 2024/25 Q2 2024/25Performance
Indicator Statu
s Value Targe
t
Short
Trend
Long
Trend
Statu
s Value Targe
t
Short
Trend
Long
Trend
Comments Owner
worked and work completed by
sub-contractors. Whilst financial
controls put in place are delivering
the required outcome.
Average time taken
(in days) to complete
medical adaptations
47.5 44 44 44
Mid-year target narrowly missed
with an average of 45.75 days per
quarter. Despite this significant
progress has been made in quarter
2 to bring performance back into
line with target levels and is on
track to meet year end
performance.
Alan Young
Average time (in
days) to inspect and
repair empty homes
19.7 12 15 12
Mid-year target not achieved. This
challenging target is measured in
calendar days. Despite not
achieving the target in quarter 2,
good progress continues to be
made to reduce the total number of
void properties to target level. This
whilst restricting overtime worked
and work completed by sub-
contractors. Whilst financial
controls put in place are delivering
the required outcome.
Martin Feeney
Percentage of repairs
appointments kept
91.5
% 93% 92.5
% 93%
Mid-year target narrowly missed.
Work is ongoing to improve the
quality of repair descriptions and
Martin Feeney
Page 56

Page 57

Q1 2024/25 Q2 2024/25Performance
Indicator Statu
s Value Targe
t
Short
Trend
Long
Trend
Statu
s Value Targe
t
Short
Trend
Long
Trend
Comments Owner
allocated schedule of rates (SORs)
which will result in more repairs
being completed as appointed. It is
anticipated full year performance
will improve on 2023/2024
outcome. 
% of properties that
require a gas safety
record which had a
gas check and record
completed by the
anniversary date
100% 100% 100
%
100
% Mid-year target met. Martin Feeney
Percentage of
reactive repairs
carried out completed
right first time
85% 91% 87.7
% 91%
Mid-year target narrowly missed.
Work is ongoing to reduce the
number of out of target repairs; this
is impacting significantly on
reported performance as out of
target repairs are recorded fails. It
is anticipated performance will
improve in future quarters and full
year outcome will improve upon
2023/2024. 
Martin Feeney
% of tenants satisfied
with the repairs and
maintenance service
88.9
%
87.5
%
88.3
%
87.5
%
Mid-year target exceeded. Martin Feeney
Average length of
time (in hours) taken 4.82 4 4.89 4 Mid-year target not achieved.
Despite this, performance in the Martin Feeney
Page 57

Page 58

Q1 2024/25 Q2 2024/25Performance
Indicator Statu
s Value Targe
t
Short
Trend
Long
Trend
Statu
s Value Targe
t
Short
Trend
Long
Trend
Comments Owner
to complete
emergency repairs
first half of 24/25 has improved
upon the 2023/2024 outturn. It is
anticipated performance will
continue to improve as work
continues to ensure only legitimate
repairs are categorised as
emergencies which will reduce the
numbers to manageable and
appropriate levels going forward. 
% of council rent that
was lost due to
houses remaining
empty
0.84
% 1% 0.71
% 1% Mid-year target exceeded. Nicola
Pettigrew
Average time taken
(in days) to complete
non-emergency
repairs
12.75 10 13.4
1 10
Mid-year target not achieved. Work
is ongoing to reduce the number of
out of target repairs, and to
improve the categorisation of
repairs. This will allow improved
work planning freeing up slots to
schedule non-emergency reactive
repairs ensuring these are
completed quicker. It is anticipated
performance will improve in future
quarters. 
Martin Feeney
Page 58

Page 59

Action Status Progress Due Date Note Owner
Implement improvement plan for
Building Services – year 4
31-Mar-
2025
This action is progressing well. To date we have
identified key priorities and developed an action plan for
the coming year, this was approved at the Building
Services Board where progress will be regularly updated.
We have carried out a review of service delivery and will
seek approval at Strategic Renewal and Review Group
(SRRG) in October '24 and report outcomes to Housing
and Communities Committee (HACC). Over the
remaining year we will undertake a job evaluation
exercise appropriate to service needs.
Martin
Feeney
Implement improved void
management process to ensure
sustained reduction in number of
void properties
31-Mar-
2025
This action is progressing well and anticipated to be
completed by year end. To date we have achieved a
significant reduction in the average cost to bring a void
property back to the Councils' relet standard to end of Q2
2024/2025 compared to outturn for 2023/2024. Over the
remaining year we will continue to progress key actions
in the void improvement action plan and implement any
identified improvements to ensure efficiency around void
management.
Martin
Feeney
Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
Failure to
implement
IHMS system
across building
services
The effective implementation of
the IHMS system will delivery
efficiency, improve case
tracking, capture customer
satisfaction and improve service
delivery.
03-Oct-
2024
IHMS has been fully implemented
within Building Services. There
are still however incidents of
erroneous data in system
although are reducing. We will
continue to monitor and respond
Martin
Feeney
Page 59

Page 60

Risk Description Current
Assessment
Target
Assessment
Date
Reviewed Note Owner
to development opportunities
within the IHMS system.
Action Status
Overdue
Not on track
In Progress and on track
Completed
PI Status
Target significantly missed
Target narrowly missed
Target met or exceeded
Risk Status
Alert
High risk
Warning
Long Term Trends
Improving
No change
Declining
Short Term Trends
Improving
No change
Declining
Page 60

Page 61

OK
Page 61

Page 62

Page 62

Page 63

West Dunbartonshire Council
Report by Chief Officer, Housing and Employability
Housing and Communities Committee:  20 November 2024
Subject: More Homes West Dunbartonshire Strategic Housing Investment
Plan 2025/26 – 2029/30
1. Purpose
1.1 This report seeks approval for the More Homes West Dunbartonshire Strategic
Housing Investment Plan (SHIP) for 2025/26 – 2029/30 which requires to be
submitted to the Scottish Government.
2. Recommendation
2.1  It is recommended that the Council:
i) Agree the draft SHIP 2025/26 - 2029/30 as appended to this report,
designed to continue the delivery of an ambitious programme of new
affordable homes in compliance with the West Dunbartonshire Local
Housing Strategy 2022 -2027 (Approved November 2021);
ii) Note the impact of the Affordable Housing Supply Programme financial
challenges and the mitigation measures being taken to maintain delivery
of new affordable housing to meet identified need; and
iii) Delegate authority to the Chief Officer, Housing and Employability to
implement the Strategic Housing Investment Plan in partnership with
relevant stakeholders.
3. Background
3.1 The Scottish Government requires local authorities to submit a Strategic Housing
Investment Plan (SHIP) each year.  The core purpose of the SHIP is to set out
the strategic investment priorities for new affordable housing over a five-year
period to achieve the outcomes contained in the Local Housing Strategy. 
3.2     The SHIP focuses on the delivery of affordable housing by location, type and
tenure and indicates how the programme will be resourced, particularly through
the Scottish Government’s Affordable Housing Supply Programme (AHSP)
funding and its Council House Building Programme component.
ITEM 9
Page 63

Page 64

3.3      The SHIP sets out the funding priorities for new affordable housing in West
Dunbartonshire for the next five years, 2025/26 – 2029/30.   It complements the
West Dunbartonshire Local Housing Strategy 2022 - 2027 approved by Council
and submitted to the Scottish Government in November 2021.  
3.4   This SHIP 2025/26 – 2029/30 is presented in the context of a significant cut of %
in funding to the Scottish Government’s Affordable Housing Supply Programme
(AHSP) which provides grant support for projects in the plan.  
3.5     The planned West Dunbartonshire Council Annual Resource Planning
Assumption (RPA) from the Scottish Government to help deliver the SHIP,
including the Council’s own new build programme, was originally set at £10.795m
but this was revised downwards £8.477m, a reduction of 21.5%. A reduction of
this scale is a significant departure from our experience in recent years where we
have been successful in increasing our RPA outturn by picking up unspent
monies from other local authority areas. Ove the last five years this has equated
to around £15m in additional funding to West Dunbartonshire.   
3.6     Despite the impact of the budget cuts and ongoing inflationary pressure, this
SHIP sets out proposals for a continuation of the high levels of new affordable
housing delivery achieved in West Dunbartonshire over recent years.    
3.7 Where details are not yet known, the project grant levels have been estimated
based on current guidance with an estimated minimum £110K per unit being
projected for both Council and Housing Association schemes.  There remains a
disparity between Council and Housing Association grant levels, but it is
anticipated that a higher proportion of larger family homes in the Council
programme attracting a higher level of grant will even out average grant levels
across the providers.  
3.8     The Scottish Government grant funding required to deliver the priority projects
listed in the 5- year programme amounts to around £46m.   The programme
beyond the current financial year shows an over commitment of spend and will
need to be the subject of a smoothing exercise.  Despite this we remain confident
that the programme outlined can be delivered, even if some projects may delay. 
Ongoing discussion will take place with the Scottish Government’s More Homes
Division over resourcing this SHIP programme.   
4. Main Issues
4.1     The purpose of the SHIP is to set out the strategic investment priorities for
increasing provision of affordable housing through new build and buyback
programmes in support of outcomes contained in the Local Housing Strategy.
This SHIP sets out the planned housing investment programme for 5 years,
covering the period 2025/26 – 2029/30.
Page 64

Page 65

4.2    The funding for the projects will be from two principal sources:
 the allocation from the Scottish Government’s Affordable Housing Supply
Programme
 using financial reserves or borrowing from the developing organisation’s
own lending resources through the Housing Revenue Account.
4.3    The SHIP contains tables detailing the projects included in the proposed
programme.  It should be stressed that inclusion in the SHIP does not guarantee
scheme approval, as each proposal will require to go through a further detailed
project and financial appraisal before funding is committed.
4.4    All homes built through the SHIP will require to meet high quality requirements
including the Council’s Design Standard for Affordable Housing, which was
updated in November 2023, and which applies to all projects commencing after
April 2024. 
4.5     Feedback from the Scottish Government on the previous SHIP (2024 – 2029)
was received in July 2024.  The feedback highlighted the importance the Scottish
Government attaches to the SHIP as the expression of the Council’s housing
investment priorities.    The comments made were in the main very positive.  In
summary, the key comments were:
 The SHIP had a good fit in contributing towards meeting Local Housing
Strategy objectives.
 The Scottish Government welcomed the emphasis given in both the open
market purchase scheme and our new build programme to provision of
larger family homes.
 It was acknowledged that our housing priorities were consistent with the
delivery of our Rapid Rehousing Transition Plan
 The Scottish Government welcomed the Council’s ongoing ability to deliver a
robust, balanced new build programme, whilst contributing to the national
ambition
 The Council’s 10% quota requirement for wheelchair provision in new social
housing was welcomed and the work being done to improve the Dennystoun
Forge Gypsy Traveller was noted.
 While noting the collaborative work being done with the Health and Social
Care Partnership to address particular housing needs, the Scottish
Government has requested more of a narrative around how this engagement
has helped to inform the SHIP.  We recognise the need to better understand
the detailed specialist housing needs across different client groups and work
is being developed in partnership with the HSCP to achieve this.
Page 65

Page 66

4.6    SHIP 2025/26 – 2029/30 Priority Projects
The priority projects for this period including those currently on site, are as   
shown in table 1 below.  All units are social rented unless otherwise stated and
unit numbers are draft in some cases.
Table 1: SHIP 2025/6- 2029/30: Priority Projects by Developer
Site/Developer Number of
West Dunbartonshire Council
Clydebank East (ex Multi Storey Flat site) 88
Pappert 26
Willox Park 17
Mount Pleasant, Old Kilpatrick 19
West Thomson Street/Clydebank Health Cen. 38
Dennystoun Forge 20
Bank St, Alexandria 22
Bonhill Gap Sites 34
Gilmour Avenue 2
Queen Mary Avenue 16
Buy backs 300
582 units
Dunbritton Housing Association
Golfhill Drive, Dalmonach 7
7 units
Caledonia Housing Association
Bellsmyre Regeneration Phase 1 27
Dalquhurn, Renton Phase 4, 5,6 75 (inc 25 SE)
Bellsmyre Regeneration Phase 2 33
135 units
Knowes Housing Association
Abbeylands Road, Faifley (ex-bowling club) 27
Buybacks 32
59 units
Dalmuir Park Housing Association
Buybacks 12
12 units
TOTAL PRIORITY PROJECTS 795
4.7   In total, the SHIP shows the development of around 795 new affordable homes
over the 5-year plan period. This level of development continues the ambitious
new affordable house building programme in West Dunbartonshire. The delivery
Page 66

Page 67

of this ambitious plan will depend upon the support of our developing housing
association partners, an increase in funding from the Scottish Government and
continued Housing Revenue Account capital investment.
4.8    The SHIP will also provide support funding from the Affordable Housing Supply
Programme to assist the popular Buyback programme of ex- local authority and
Registered Social Landlord housing stock, as well as acquisitions from the
private sector including of-the-shelf homes from house builders. It is proposed
that around 300 units are acquired by the Council over the five years of the plan.
4.9   The funding estimated to deliver the Strategic Housing Investment Plan is an
approximate £46m. However, the resource planning assumption for this same
period is only around £40m.  To meet the requirements of the plan additional
Affordable Housing Supply Funding Programme funding is required to be
invested in West Dunbartonshire over the period of the plan. The first indication
of additional funding to support the deliver of social homes will be contained
within the forthcoming Scottish Government budget announcements.
4.10 Due to uncertainties over details of some of the proposed projects in the SHIP
and the availability of funding, the SHIP will require to demonstrate flexibility and
will be subject to continual monitoring and evaluation.  The SHIP lists a series of
future projects which we hope will feature in the programme as it progresses.  
Monitoring of progress will be carried out through the Council’s performance
management system and through key structures such as the Housing Providers
Forum, More Homes Project Board and programme review meetings with the
Scottish Government. 
4.11 The Council has carried out an analysis of potential projects against an objective
Prioritisation Scoring Matrix and scored them accordingly.  A number of factors
are considered including availability of land, type of housing being proposed,
compliance with Local Housing Strategy objectives, deliverability, and value for
money.   Where a project proposes an element of particular needs /specialist
provision, engagement takes place with the West Dunbartonshire Health and
Social Care Partnership.
5. People Implications
5.1 While there are no direct people implications.
6. Financial Implications
6.1 The programme of projects shown in the SHIP can only take place if both its two
principal funding streams, prudential borrowing through the Housing Revenue
Account and Scottish Government Affordable Housing Supply Programme grant,
are able to provide the required ongoing financial support.   It is estimated that
the total grant ask of the Affordable Housing Supply Programme would be
around £46m, requiring an annual allocation of more than £9m, more than this
year’s RPA award of only £8.477m. 
Page 67

Page 68

6.2     In respect of the Council House Build element, financial modelling demonstrates
that the new council house building programme is beneficial to the Housing
Revenue Account.  However, care requires to be taken to ensure that the
prudential borrowing required is financially sustainable especially given rising unit
costs.  We recognise the high cost of delivering large family homes and those
constructed to passivhaus/net zero standard to meet need.
6.3      There is a risk that future resource allocation would suffer if the SHIP failed to
deliver on the programme contained in this SHIP, this is particularly alarming for
an area such as West Dunbartonshire that experiences high levels of poverty
impacting on homeless presentations which were key contributors to the Housing
Emergency declaration. 
6.4      To mitigate the impact of rising costs, the Council is continuing to lobby for
increased grant levels from the Scottish Government and where appropriate will
apply for above benchmark awards on a project-by-project basis particularly
when we are developing larger homes to meet an acute identified need within
West Dunbartonshire.
6.5 There are no specific procurement implications connected with this report.
7. Risk Analysis
7.1 Inevitably, with such a varied programme of projects there are risks that the
ambitious outputs set out in the SHIP will not be met.  A number of the projects
are at an early stage with site investigations not having been carried out or
infrastructural constraints fully known.
7.2      There is a risk that Affordable Housing Supply Programme funding will be
reallocated to other Council areas if the Council is unable to spend within any
financial year.  Housing Development staff will liaise regularly with Scottish
Government More Homes colleagues to address any concerns of this nature, to
maximise spend within West Dunbartonshire.
7.3 Monitoring of progress will be carried out through key structures such as the
Strategic Housing Providers Forum, More Homes Project Board and programme
review meetings with the Scottish Government.   A new SHIP will be submitted
annually to the Scottish Government each October and will be the subject of a
report to the Housing and Communities Committee.
8 Environmental Sustainability
8.1 The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
Page 68

Page 69

making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy.
9. Equalities Impact Assessment
9.1 An Equalities Impact Assessment has been carried out which predicted that the
strategy would have an overwhelmingly positive impact and is an appendix to this
report.  
9.2      All new housing supported through the programme will be compliant with the
West Dunbartonshire Design Standard and will meet the Housing for Varying
Needs requirements.  The West Dunbartonshire Design Standard requires
developers in the programme to provide higher standards than those required by
statute and are of particular benefit to those with mobility issues.  The SHIP
supports the delivery of specialist housing provision and generally allows for a
10% element in each project.
10. Consultation
10.1   The SHIP was drawn up in consultation with potential housing association
partners and the Scottish Government More Homes Division.    Where an interest
has been shown, detailed discussions have taken place with the prospective
developer on how the project could be accommodated in the programme.  
10.2 The West Dunbartonshire Tenants and Residents Organisation (WDTRO)
received a presentation on the proposed SHIP in October 2024 and feedback
has been positive and tenant representatives are strongly supportive of the
Council and partners new build plans.
10.3   The preparation of the SHIP has been a corporate task, involving all relevant
departments of the Council and has been carried out in collaboration with
colleagues in the Scottish Government More Homes Division.  The Health and
Social Care Partnership was an active partner in preparing the plans where there
was a significant element of specialist accommodation involved and a number of
projects were significantly amended as a result.   A particular example is at
WDC’s Clydebank Health Centre Project were plans have been redrawn to
include for the reprovisioning of the nearby Young Street sheltered housing
project.  
11. Strategic Assessment
11.1   This Strategic Housing Investment Plan presents the priorities for affordable and
deliverable housing development for the next five years as set out in the Local
Housing Strategy.  Having considered the Council's strategic priorities, this report
contributes significantly to all strategic priorities.
Page 69

Page 70

Peter Barry, Strategic Lead, Housing and Employability
Date:    6 November 2024
Person to Contact: Jamie Dockery – Housing Development and Homelessness
Manager, Housing Development and Homelessness Team,
Housing and Employability, telephone: 07793717981, email:
john.kerr@west-dunbarton.gov.uk
Jamie Dockery – Senior Housing Development Officer,
Housing Development and Homelessness Team, Housing
and Employability, email: Jamie.dockery@west-
dunbarton.gov.uk
Appendices:  Appendix 1: Strategic Housing Investment Plan
2025/26 - 2029/30
Appendix 2:    Equalities Impact Assessment October 2024
Background Papers: West Dunbartonshire Council’s Local Housing Strategy 2022-
2027
Wards Affected: All
Page 70

Page 71

West Dunbartonshire Council
Strategic Housing Investment Plan
2025/26 – 2029/30
Draft Final 01 November 2024
ITEM 9 -
APPENDIX 1
Page 71

Page 72

TABLE OF CONTENTS
1.Introduction..........................................................................................................................................2
2.Background...........................................................................................................................................3
3.Funding ..............................................................................................................................................5
4.SHIP 2025/26 - 2029/30 PRIORITY PROJECTS.......................................................................................7
5.Priority Projects..................................................................................................................................11
6.Developer Contributions.....................................................................................................................15
7.Constraints..........................................................................................................................................15
8.Local Authority Assistance in the Delivery of the SHIP.......................................................................16
9.Delivery ............................................................................................................................................17
10.Energy Efficiency, Environmental Standards and Sustainability.......................................................17
11.Equalities Issues................................................................................................................................18
12.Strategic Environmental Assessment (SEA)......................................................................................19
13.Monitoring........................................................................................................................................19
14.Feedback...........................................................................................................................................20
Page 72

Page 73

1.INTRODUCTION
1.1 This new Strategic Housing Investment Plan (SHIP) sets out West Dunbartonshire Council’s funding priorities for affordable housing in
West Dunbartonshire for the next five years in line with the West Dunbartonshire More Homes Better Homes Local Housing Strategy
2022-2027.
1.2 Every Council is required to submit an annual Strategic Housing Investment Plan (SHIP) to the Scottish Government. The SHIP sets out the
funding priorities for affordable housing in West Dunbartonshire for the next five years in line with the West Dunbartonshire More
Homes Better Homes Local Housing Strategy 2022-2027. The SHIP is an operational document rather than a strategic one.
1.3 This SHIP 2025/26 – 2029/30 is presented in the context of a significant cut in the Scottish Government’s Affordable Housing Supply
Programme which provides grant support for projects in the plan. In December 2023, the Scottish Government announced that its 2024-
25 Scottish Budget will see spend on building social homes slashed by almost £200m – a reduction of around 27%.
1.4 The planned West Dunbartonshire Council Annual Resource Planning Assumption (RPA) from the Scottish Government to help deliver
the SHIP including the Council’s own new build programme was originally set at £10.795m but this has been revised downwards
£8.477m, a reduction of 21.5%.
1.5 The SHIP sets out the revised plan for the delivery of new affordable housing and the measures we propose to put in place to mitigate the
impact of the cuts.  The SHIP will endeavour to maximise the programme of high-quality new homes in West Dunbartonshire in response
to the growing housing crisis. 
Page 73

Page 74

2.BACKGROUND
2.1 Each year every Council is required to submit a Strategic Housing Investment Plan (SHIP) to the Scottish Government. The West
Dunbartonshire SHIP 2024/25 – 2028/29 was approved by West Dunbartonshire’s Housing and Communities Committee in November 2023 and
submitted to the Scottish Government.
2.2 The SHIP sets out the funding priorities for affordable housing in West Dunbartonshire for the next five years in line with the West
Dunbartonshire More Homes Better Homes Local Housing Strategy 2022-2027. The SHIP is an operational document rather than a strategic one.
2.3 The SHIP detailed West Dunbartonshire Council’s plans to assist in the delivery of the Scottish Government’s target to provide 110,000
affordable homes by 2032, with at least 70% of these homes being for social rent.    The 2024/25 – 2028/29 SHIP aimed to deliver around 747
new social rented homes in West Dunbartonshire over its five-year period.  The figure for this new SHIP is around 763.
2.4 Housing Services worked with all appropriate Council service areas and consulted with the WDTRO and the West Dunbartonshire Health
and Social Care Partnership in the preparation of the Plan. Consultation took place with the RSLs operating in West Dunbartonshire through the
Housing Providers Forum and regular programme/liaison arrangements. The Scottish Government More Homes Division Glasgow and Clyde
Area Team contributed to the preparation of the SHIP.   
2.5 To assist in advance planning of housing investment, the Scottish Government advises local authorities annually of their minimum
Resource Planning Assumptions (RPA). Our RPA for 2024/25 was provisionally set at £10.795m with a prospect of an additional allocation of
£3.0m, reflective of WDC’s recent good development performance and ability to take up slack from other authorities’ programmes. 
2.6 On the basis of the funding assumptions, a healthy development programme was set out in the SHIP showing plans for a range of new
housing projects across West Dunbartonshire, reflective of identified housing needs and priorities.
2.7 In December 2023, the Deputy First Minister and Cabinet Secretary for Finance set out the Scottish Government’s proposed spending
and tax plans for the Scottish Budget 2024/2025. The announcement revealed that the Scottish Government was proposing a reduction in the
overall Housing and Buildings Standards budget from £738m this year to £533m next. This represents a cut of around £200m or 27%. These
Page 74

Page 75

budget proposals were agreed in February 2024. As consequence of this, the WDC RPA for 2024-2025 was revised downwards from a minimum
of £10.795m to £8.477m, a reduction of £2.318m. 
2.7 To deliver the priority projects only shown in this SHIP it is estimated that a receipt of £47.4m Affordable Housing Supply Grant will be
required. This will only be possible if our annual Grant Planning Target from the Scottish Government is returned to recent years’ figures.  
2.8 WDC Housing and Communities Committee on 1st May noted that we are scenario planning the impact of the 24% reduction in the
2024/25 RPA and that this may have the following impacts:
• No new projects being approved in 2024/25 because of existing commitments within the programme without the developing organisations
front funding their development.
•A reduced RPA allocation of £2.318m (21.5%), representing a loss of a minimum of that figure to the wider West Dunbartonshire economy;
•A potential 32 less homes being delivered on an annual basis in West Dunbartonshire because of the reduction in funding (160 within the
lifecycle of the current Strategic Housing Investment Plan);
• Higher levels of homelessness and housing need.
2.9 The national capital resources available for future RPAs will depend on future budget decisions by the Scottish Parliament. In the
absence of future year budget assumptions, and to aid programme management, we have been advised by the Scottish Government to operate
carry-forward limits for the years 2025-26 – 2027-28 of 80%/60%/40% of current year RPA levels.
2.10 The Scottish Government is updating its SHIP Guidance, but it is unclear whether this will be issued in advance of the 30th October 2024
deadline for submission of the new SHIP.
2.11 On 1st May 2024, the Housing and Communities Committee declared a housing emergency in West Dunbartonshire, becoming the fifth
local authority to do so by that date.  On 15th May 2024, the Scottish Government too declared a housing emergency, formally recognising the
scale of the problem.
Page 75

Page 76

3.FUNDING
3.1 Funding for the projects in the SHIP programme comes from two principal sources:
 the allocation from the Affordable Housing Supply Programme and
 funding from the housing providers’ sources, primarily private borrowing by RSLs and Prudential borrowing by the Council.
3.2 As noted above, our annual AHSP Resource Planning Assumption stood at £10.795m, with a possible £3.0m of additional funds. This
has dropped to £8.477m.
3.3 While we have been notified of the revised 2024/25 RPA figure there is still uncertainty beyond this date.  Colleagues in the More Homes
division recognise the importance of funding certainty in delivering new build programmes and have undertaken to address this issue as soon as
revised programmes are firmed up.  In the meantime, we have been advised that an element of over-programming should be applied to the SHIP
to allow for slippage.
3.4 Our last SHIP welcomed the then newly introduced benchmark figures which applied a welcome 16.9% uplift to the grant levels in June
2023. We have been advised that a further uplift of 5% has now been introduced, the detail of which is due soon.  While this grant level
significantly helped the viability of projects, it means that the overall budget will not stretch as far as previously, with the potential to reduce
outputs. 
3.5 For the costing of the SHIP, unless detailed costs were known, it was assumed that both Council and RSLs projects would be seeking an
average grant figure of £110,000. The current baseline benchmark support figures are £95,741 per unit for RSLs and £87,763 for Councils (3-
person equivalent plus additional quality measures).  These grants are augmented by additional quality benchmark measures which attract
extra funding.   Due to the extra levels of scrutiny involved, projects above benchmark take longer to approve.
3.6 To give a context on the current grant levels, Table 1 shows the awards for the projects which are presently on site in West
Dunbartonshire.
Page 76

Page 77

Table 1:  Current Projects - AHSP Grant Awards
Project Developer Units Grant Total Unit Grant/Unit Price
Pappert WDC 26 2,471,066 95,041* / 349,253
Clydebank East WDC 88 12,604,632 143,234 /  363,137
Bellsmyre Ph 1 Caledonia HA 27 3,375,000 150,000/300,000 est
Dalquhurn Ph 4 Caledonia HA 25 2,696,552 107,892 /224,050 est
Mt Pleasant WDC 19 1,837,922 96,733 / 263,148
Bonhill Gap Sites WDC 31 4,600,000 est 148,387 est / 330,950
Gilmour Ave WDC 2 191,252 95,626 / 274,075
* Pappert also in receipt of £48,077 grant per unit from the SG Void and Derelict Land Fund.
3.7 In response to the current and projected funding difficulties, the Scottish Government has set up an advisory board of leading housing
development players to consider innovative ways in which the budget can be increased, including through the involvement of more institutional
investors.   
3.8 We will seek to explore with partner RSLs any opportunities to support the programme with funding from their financial reserves or
other sources. Some development partners are known to hold significant reserves that could be employed to ameliorate the funding crisis. In
joint discussions with the SG and RSLs we will give consideration to the use of front funding, whereby the RSL would meet the costs in the early
part of the project with the SG guaranteeing their contribution at a later date. Such an arrangement would require agreement from the SG, and
careful management of the programme, but it is an approach that has been employed in the past when funding was also particularly
constrained. We have reached agreement with one RSL over their front funding during 2024/25, on the understanding that the grant will be
guaranteed payable in 2025/26. 
4.SHIP 2025/26 - 2029/30 PRIORITY PROJECTS
Page 77

Page 78

4.1        The SHIP contains a table showing the projects which are currently on site or are due on site during 2025/26. The table 2 below provides an
update and shows where progress has been made since the last SHIP was published in November 2023.
Table 2: Projects Currently On-Site/Due on Site 2025/26
Revised September 2024
Project/Developer Units Status in SHIP November 2024 Update at September 2024
Clydebank East/WDC 88
Site Start Jan 2023
Est Completion Spring 2025 but
sectional handovers from
October 2024 
Site Start Jan 2023
Est Completion Spring 2025 but sectional
handovers from October 2024 
Pappert, Alexandria/WDC 26 Site Start March 2024
Est Completion May 2025
Site Start March 2024
Est Completion May 2025
Willox Park/WDC 17 Est Site Start October 2024
Est Completion Winter 2025
Est Site Start Jan 2026
Est Completion Jan 2027
Mount Pleasant, Old Kilpatrick/
WDC 19 Site Start April 2024
Est Completion May 2025
Site Start April 2024
Est Completion May 2025
Bank St, Alexandria/WDC 22 Est Site Start January 2025
Est Completion Autumn 2025
Est Site start May 2025
Est Completion May 2026
West Thomson Street
(Clydebank Health
Centre)/WDC
42 Est Site Start July 2025
Est Completion December 2026
Est Site October 2025
Est Completion December 2026
Abbeylands Road, Faifley
(Bowling Club) / Knowes HA 27 Est Start Spring 2025
Est Completion Summer 2026
Est Site Start August 2025
Est Completion November 2026
Bellsmyre Regeneration Phase
1/Caledonia HA 27 Est Site Start November 2023
Est Completion February 2025
Est Site Start November 2024
Est Completion
Page 78

Page 79

Dalquhurn Phase 4/ Caledonia
HA 25 Est Site Start November 2023
Est Completion November 2024
Site Start 01 July 2024
Est Completion July 2025
Golfhill Drive, Alexandria/
Dunbritton HA 7 Est Site Start Spring 2024
Est Completion Spring 2025
Est Site Start March 2025
Est Completion March 2026
Bonhill Gap Sites/WDC 34 Est Site Start January 2025
Est Completion Spring 2026
Est Site Start April 2025
Est Completion May 2026
Dalquhurn Phase 5 & 6/
Caledonia HA 25SR/25SE Est site Start 2024
Est Completion September 2025
Est Site Start June 2025
Est Completion December 2026
Gilmour Avenue,
Hardgate/WDC 2 Est Site Start August 2024
Est Completion November 2024
Site Start 23 September 2024
Est Completion February 2025
Dennystoun Forge/WDC 20 N/A Est Site Start September 2025
Est Completion September 2026
Queen Mary Avenue,
Drumry/WDC 16 est N/A Est Site Start October 2025
Est Completion October 2026
4.2   The SHIP lists sites which are less fully developed but which could feature in future years. Table 3 lists these sites but removes ones
that now seem unlikely to be viable in the short to medium term.
Table 3: Future Sites
Project Comments
Smollett/ Dumbuie WDC wish to build replacement homes where defective ones are being demolished.
Bellsmyre Regeneration Phases 3,4,5 Caledonia HA plan further phases to their regeneration programme, providing 78 units across
four sites.
Page 79

Page 80

Auld St, Dalmuir Dalmuir Park are working on plans to provide 32 units here.
Cottage Hospital Dumbarton Dunbritton HA are in negotiation to acquire this site from the NHS to build 8 homes.
Dumbain Avenue, Haldane Wheatley Group have drawn up plans for 23 units at this site which sits within the LL&T National
Park.
Ottowa Crescent, Dalmuir Discussions with a developer over a 20-unit development on the site of a former care home. WDC
most likely to be the developer.
Artizan Centre, Dumbarton Town
Centre WDC hope to provide some housing as part of a wider town centre regeneration project.
BMQ, Mountblow The Council is in the process of the demolishing these three multi-storey blocks and plans to
provide new homes in their place. Understood to be a very difficult site to develop.
Mitchell Way The Council and some RSL developers have expressed an interest providing the housing element
of the Alexandria Town Centre regeneration.  
28 Bridge St, Alexandria WDC looking to convert/ or build anew the old hostel unit previously operated by Preparation for
Life.
Skypoint and Edinbarnet, Faifley There is development interest should social housing form part of the school reprovisioning
project.
Sheltered Housing Reprovioning Up to two sheltered housing complexes may be considered for reprovisioning due to accessibility
issues.
Bridge St, Alexandria Dunbritton HA Dunbritton HA are looking at reprovisioning of their specialist housing complex, possibly through
major refurbishment and change of client group.
Page 80

Page 81

5.PRIORITY PROJECTS
5.1  When preparing the annual SHIP, each year the Council issues a “call for sites” to potential developing RSLs. Applications are then scored
to help prioritise our limited resources.
5.2 Projects considered for inclusion in the SHIP are subject to a matrix-based scoring analysis to assess their relative merits.  Various
criteria are employed in assessing and prioritising the projects:
 The strategic priorities of the Council including contributing to Covid-19 recovery plans
 Contribution towards meeting assessed housing need and demand and especially supply of
larger family homes and contributing to alleviating child poverty objectives
 Meeting regeneration /Planning objectives including support for 20 minute neighbourhood
principles
 Contribution towards satisfying specialist/ particular needs housing demand including those of
the Gypsy Traveller community
 Degree of Low carbon/energy efficiency
 SIMD Scoring
 Affordability/deliverability
 Deliverability including site constraints

 Level of subsidy required
The results of the exercise are contained inAnnexe B Scoring Matrix.
We have amended the criteria in view of the housing emergency, the ongoing homelessness crisis, and the need to give increased priority
around child poverty.
Page 81

Page 82

5.3 The priority projects for this period, including those currently on site, are as shown in table 4 below. Buybacks/ROTS, which are an
important element of our strategy to increase the supply of affordable housing, are also included in these tables.  All units are social rented
unless otherwise stated and unit numbers are draft in some cases.
Table 4: SHIP 2025 - 2030: Priority Projects by Developer*
Site/Developer Number of Units
West Dunbartonshire Council
Clydebank East (post 25/26) 55
Pappert 26
Willox Park 17
Mount Pleasant 19
Bank St 22
West Thomson Street/Clydebank Health
Centre 38
Bonhill Gap Sites 34
Gilmour Avenue 2
Dennystoun Forge 20
Queen Mary Avenue 16
Buybacks/ROTS 300
Page 82

Page 83

Units  549
Knowes Housing Association
Abbeylands Road, Faifley
(ex bowling club) 27
Buybacks/ROTS 32
Units   59
Dunbritton Housing Association
Golfhill Drive, Dalmonach 7
Units   7
Caledonia Housing Association
Bellsmyre Regeneration Phase 1 27
Dalquhurn Phases 4, 5&6 75*(inc 25 shared
equity)
Bellsmyre Regeneration Phase 2 33
Units   135
Dalmuir Park Housing Association
Page 83

Page 84

Buybacks/ROTS 12
Units  12
TOTAL PRIORITY PROJECTS 762
* All homes are social rented unless otherwise stated and it includes projects currently on site.
5.4 Annexe A of this report, Affordable Housing Supply Programme: Years 2025/26 -2029/30 provides further details of the projects
contained in this SHIP.
5.5 WDC operates a very popular “Buy Back” scheme whereby the Council can re-purchase vacant Right to Buy and other houses which are
on the market, to help meet strategic housing objectives, including regeneration projects.  The scheme has grown significantly in recent years
with support from the AHSP. The buyback scheme provides support to the Rapid Rehousing Transition Plan and other strategic priorities.
Criteria apply to the buyback programme to ensure that the properties being considered will help address housing need.  For example, in
response to the identified high demand, we place an emphasis on acquiring larger family homes in this and in any West Dunbartonshire RSL
Rental Off the Shelf schemes (ROTS).  The Scottish Government are supporting larger family home acquisitions with above benchmark grant
awards where appropriate.  
Currently we are estimating that 300 units will be acquired by the Council through this route as well a further number by RSLs via ROTS. While
budget pressures might suggest that these figures could reduce, extra money allocated to the National Acquisition scheme may bolster this side
of the new supply programme.
5.6 Excluding the reserve projects, the SHIP shows the provision of almost 770 affordable rented homes over the 5-year plan period. The
delivery of this ambitious plan will depend upon the ongoing support of our developing RSL partners and, in particular, appropriate funding from
the Scottish Government.
5.7 While almost all projects contained in this SHIP are for social rent, a small number of shared equity units are proposed by Caledonia HA.
Further investigation of the market for alternative tenures requires to has been carried out which suggests there may be an interest in certain
Page 84

Page 85

areas of West Dunbartonshire. WDC plans to establish two limited liability partnerships to deliver alternative affordable tenures; Mid-market
rent and Home Ownership Made Easy.
5.8 More than ever before, due to the funding uncertainty, the SHIP will require to show flexibility and be subject to continual monitoring to
best deliver on its objectives. Projects which fall behind on their programmed dates may be overtaken by ones in the “shadow programme.”  As
it stands, the programme is predicated on front funding being available for a number of projects.  The More Homes Board will be the lead
monitoring vehicle with input from programme review meetings with the Scottish Government and developers.
5.9 The SHIP scoring matrix contains a longer list of projects which have been brought forward for consideration. These are considered to be
reserve projects. If there is slippage, or if additional funding becomes available, some of these projects may be introduced into the programme.
We will remain open to consideration of other projects which may be presented during the course of this plan period, indeed these would be
welcomed, though bearing in mind that resources are likely to be much more limited during this period.
6.DEVELOPER CONTRIBUTIONS
6.1 At present there is no Affordable Housing Policy in West Dunbartonshire, and there is no projected receipt from this source. The
introduction of NPF4 may signal a change in how housing site allocations are made by tenure in West Dunbartonshire. Further discussions will
take place with our Planning colleagues in the consultation over the new Local Development Plan.
7.CONSTRAINTS
7.1 Scottish Government guidance indicates that SHIPs should have an emphasis on deliverability.  In preparing the SHIP, every effort has
been made to take account of any constraints that may affect the delivery of the projects and this is taken account of in the assessment
scoring. We have also taken cognisance of the funding cuts as well as the increased average unit costs, especially for our much-needed larger
family homes.  There is recognition that many of the larger and easier sites, including a number of the ex-school sites, have been developed in
previous years and that the programme outlined in this Plan may be more problematic to achieve. The SHIP will require to demonstrate
Page 85

Page 86

flexibility in programming of its projects and it is understood that the programme may have to be further elongated to match available
resources.
7.2 A number of the projects contained in this SHIP are at the early stage of their development and the full issues/constraints are not
known at this stage. For example, a number of the projects contained within the SHIP are not at the stage of having the necessary Planning
consents or Building Warrants.
8.LOCAL AUTHORITY ASSISTANCE IN THE DELIVERY OF THE SHIP
8.1 The Council is committed to assist where possible in the delivery of the SHIP projects within the context of the More Homes West
Dunbartonshire initiative as outlined in the Local Housing Strategy.
8.2 Within the Council, the officers’ More Homes Board monitors the delivery of the new council home element of the programme and will
continue to seek to identify additional sites to extend the Council’s new build programme, supported by prudential borrowing, the AHSP and the
Council’s rent pooling strengths. The Council has drawn up a Housing Emergency Action Plan which features the need to increase the supply of
affordable homes and this plan is monitored and given impetus through the More Homes Board.
8.3 Land has previously been made available by the Council at below market value to facilitate the development of affordable housing to
meet identified needs. However, there is a need to balance this against the Housing Revenue Account’s interests and the very significant
pressures facing Council budgets.   In addition, the Council is mindful of the need to balance the provision of private sector and affordable
housing sites to meet our Housing Supply Targets.
8.4 Vacant sites in the Housing Revenue Account, or areas of surplus stock, have generally been made available to support the development
of social rented housing where appropriate.  The costs of acquiring all sites will be reviewed on a case-by-case basis and the Council as a
developing organisation and our partner housing associations will be expected to review their ability to make full use of existing assets and
borrowing capacity.  
Page 86

Page 87

8.5 Housing will continue work closely with Planning colleagues to ensure an adequate supply of development land to meet the increased
targets within the context of the Local Development Plan and through the More Homes Board.  As noted above, in light of the introduction of
NPF4 further consideration will be given to how housing sites are allocated by tenure through the Planning process. 
8.6 Throughout the lifetime of this new Strategic Housing Investment Plan, the Council will continue to explore options around innovative
delivery mechanisms to expand the supply of affordable housing.
9.DELIVERY
9.1 In terms of the procurement arrangement noted above, there may be an opportunity in the future to widen the scope to include other
partner developers in the programme. In addition, scoping will continue of other new frameworks as they become available to ensure the
delivery of the programme and of best value.
9.2 Officers from the Housing Development team regularly engage with local house builders interested in the delivery of affordable housing
in West Dunbartonshire, either through partnering RSLs or directly with the CouncilWesAt the time of writing such discussions are taking place
over two projects in the Clydebank area.  
10.ENERGY EFFICIENCY, ENVIRONMENTAL STANDARDS AND SUSTAINABILITY
10.1 Local Authorities are among a wide range of public bodies required to meet the duties place on them by the Climate Change (Scotland)
Act 2009.   In this context, developments arising from the SHIP must take account of the change agenda. New Build developments must
contribute to the Single Outcome Agreement local outcome commitment to reduce fuel poverty.
10.2 In tandem with this new SHIP, the Council is introducing a revised and updated version of its pioneering higher standard for all Council
and Housing Association homes being built in West Dunbartonshire, the West Dunbartonshire Design Standard.
Page 87

Page 88

The Standard applies to all new build projects being supported by the Affordable Housing Supply Programme in the SHIP programme and
requires these homes will achieve Net Zero or Passivhaus standard and Energy Efficiency Rating of B.  As well as improving energy efficiency, the
policy encourages better accessibility, external design, and internal space standards. The inclusion of such a standard at this stage anticipates
the forthcoming Scottish-wide regulation on this issue.
10.3 As well as using the more commonly employed air source heating pumps we are investigating the use of ground source heating systems
(GSH) which, while currently more expensive to install, may prove to be more efficient and easier to maintain in the longer term. Efficiencies
may be achieved by grouping these heating systems to serve a housing project and this is an area for possible development. It is hoped that the
installation of exhaust air pumps will provide a cost-efficient heating, hot-water, and ventilation solution in some of our new developments.
10.4 The Council continues to encourage the consideration of district heating systems or other innovative measures that contribute to
meeting climate change objectives. The innovative district heating scheme at Queens Quay, Clydebank is being rolled out to nearby projects
including housing ones.
11.EQUALITIES ISSUES
11.1 West Dunbartonshire Council is committed to delivering good quality services which are underpinned by a clear understanding of
Equality and Diversity and to promoting and sustaining equality and inclusion, and equality and diversity principles.
11.2 An equalities impact assessment was carried out on this SHIP which predicted that the measures proposed would have an
overwhelmingly positive impact. 
12.STRATEGIC ENVIRONMENTAL ASSESSMENT (SEA)
Page 88

Page 89

12.1 A Strategic Environmental Assessment (SEA) pre-screening report has been carried out in respect of the parent Local Housing Strategy.
The Council has determined that a SEA is not required in this instance. 
13.MONITORING
13.1 Monitoring of progress will be carried out through the Council’s performance management system and through key structures such as the
Strategic Housing Providers Forum, the Housing Improvement Board, the More Homes Board and programme review meetings with the Scottish
Government.  A new SHIP will be submitted annually to the Scottish Government each October following approval by the Housing and
Communities Committee
14.FEEDBACK
For more information, or if you want this information in a different format or language, please use the contact details below:
Page 89

Page 90

Housing Development Team
Housing Development and Homelessness
Housing and Employability
West Dunbartonshire Council
John Kerr    Housing Development and Homelessness Manager
Phone: (01389) 737889
Email: John .Kerr@ west-dunbarton.gov.uk
Jamie Dockery    Senior Housing Development Officer
Phone:
Email: Jamie.Dockery@ west-dunbarton.gov.uk
Jackie McRory    Senior Housing Development Officer
Phone: (01389) 737591
Email: Jackie.McRory@ west-dunbarton.gov.uk
Emily Dorrian   Senior Housing Development Officer
Phone:
Email: Emily.Dorrian@ west-dunbarton.gov.uk
Page 90

Page 91

Assessment No 1082 Owner edorrian2
Resource Regeneration, Environment and
Growth
Service Housing and Employment
FirstName Surname Job Title
Head Officer Jamie Dockery Senior Housing Development
Officer
Members Jamie Dockery, Senior Housing Development Officer
Emily Dorrian, Senior Housing Development Officer
(Please note: the word 'policy' is used as shorthand for strategy policy
function or financial decision)
Policy Title SHIP 2025-2030 (Strategic Housing Investment Plan)
The aim, objective, purpose and intended out come of policy
The Strategic Housing Investment Plan (SHIP) 2025 – 2030 sets out the funding
priorities for affordable housing in West Dunbartonshire for the next five years as
outlined in the West Dunbartonshire More Homes Better Homes Local Housing
Strategy 2022-2027.  The SHIP is an operational document rather than a strategic
one.
Service/Partners/Stakeholders/service users involved in the development
and/or implementation of policy.
The SHIP sits within the Local Housing Strategy and has been underpinned by the
Council’s commitment to promoting and sustaining equality and inclusion, and equality
and diversity
principles.
Does the proposals involve the procurement of any goods or services? No
If yes please confirm that you have contacted our procurement services to
discuss your requirements.
No
SCREENING
You must indicate if there is any relevance to the four areas
Duty to eliminate discrimination (E), advance equal opportunities (A) or
foster good relations (F)
Yes
Relevance to Human Rights (HR) Yes
Relevance to Health Impacts (H) Yes
Relevance to Social Economic Impacts (SE) Yes
Who will be affected by this policy?
The Strategic Housing Investment Plan (SHIP) may affect the whole population of West Dunbartonshire.
Who will be/has been involved in the consultation process?
West Dunbartonshire Equality Forum was consulted and fed into the final text of the Local Housing
Strategy which underpins the SHIP.   The  Housing Development team provides regular SHIP updates at 
the Strategic Housing Providers Forum,  the More Homes Board and the WDTRO.
ITEM 9 -
APPENDIX 2
Page 91

Page 92

Please outline any particular need/barriers which equality groups may have in relation to
this policy list evidence you are using to support this and whether there is any negative
impact on particular groups.
Specific group to
consider
Needs Evidence Impact
Age                           The SHIP seeks to support
people of all ages access
appropriate housing.  
We know that households
with children and older
people are more likely to
experience poverty 
meanwhile young adults are
more likely to experience
homelessness.
West Dunbartonshire has a
higher than average share of
older people and child poverty
rates are an area of focus and
concern. 
Ensure that new home
delivery achieves a
balance across the age
and needs spectrum. 
Our current SHIP places
an emphasis on larger
family homes to target
this identified housing
need. We also continue
to develop options for
older people.
Disability                    Council services need to be
accessible to disabled
people. 
Those affected by a
disability may not be able to
occupy the home if it does
not meet their needs. 
Scotland's 2022 Census
recorded 28% of  people's
day to day activity were
limited by a disability.
This is evidenced in high
demand for accessible housing
high and exceeds current
supply. 
Ensure that new homes
meet the highest
accessibility standards. 
The current SHIP places
an emphasis on town
centre locations and 20
minute neighbourhoods,
acknowledging that good
access to amenities is
important for everyone
but particularly for those
with disabilities.
Gender Reassign               Limited available statistics
in West Dunbartonshire but
the recent census shows
0.03% of WDC's population
over 16 were transgender or
had a trans history. 
Transgender people  are
victim to higher than
average levels of abuse,
both in domestic
relationships and in public
and thus may need
particular housing support
(Scottish Government,
2013). 
Through the LHS is was
identified that WDC is likely to
have gaps with equality
monitoring  and work is
underway to improve equalities
monitoring
The development of new
homes can help improve
access to housing and in
doing so seeks to
address
the impact of inequality
and discrimination on
persons regardless of
gender, sexual
orientation, race,
religion/belief age their
social or
economic status or
whether they are
transgender.
Marriage & Civil
Partnership 
Some needs will cross cut
with sex and sexual
orientation
Limited available statistics
in West Dunbartonshire.
Through the LHS is was
identified that WDC is likely to
have gaps with equality
monitoring  and work is
underway to improve equalities
monitoring
Criss cuts with sex and
sexual orientation but no
specific impacts in terms
of marriage and civil
partnership
Page 92

Page 93

Pregnancy &
Maternity        
Cross cuts with sex Through the LHS is was
identified that WDC is likely to
have gaps with equality
monitoring  and work is
underway to improve equalities
monitoring
The development of new
homes can help improve
access to housing and in
doing so seeks to
address
the impact of inequality
and discrimination.  New
homes will provide
appropriate storage for
prams and easier
access.  The ongoing
development family
sized homes helps to
assist people who have
recently had children
access appropriate
housing,.
Race                          The Council needs to take
into account, potential
different housing needs of
come ethnic groups, for
example Gypsy Travellers.
Through the LHS is was
identified that WDC is likely to
have gaps with equality
monitoring  and work is
underway to improve equalities
monitoring.
Overcrowding is more likely for
some BME groups.
There is an
understanding that some
of our ethnic minority
groups have particular
housing needs and this
is something we are
building upon in the
SHIP and through the
LHS.
Religion and Belief           'Race' and religion and
belief are not the same
however there is some
cross cutting due to
concentration of some
groups in some religions.
The 2022 Scotland Census
shows 42% of people report
having no religion but for
those having a religion can
be a source of harassment
and discrimination,
particularly for those who
belong to non-Christian
religions.
Through the LHS is was
identified that WDC is likely to
have gaps with equality
monitoring  and work is
underway to improve equalities
monitoring
To some extent cross cuts with
race
To some extent cross
cuts with Race. The
development of new
homes can help improve
access to housing and in
doing so seeks to
address
the impact of inequality
and discrimination.
Sex                           Limited available statistics
in West Dunbartonshire.
Women make up 90% of
lone parents, and 45% of
lone parents are income
deprived.
Through the LHS is was
identified that WDC is likely to
have gaps with equality
monitoring  and work is
underway to improve equalities
monitoring
The development of new
homes can help improve
access to housing and in
doing so seeks to
address
the impact of inequality
and discrimination.
Sexual Orientation  Limited available statistics
in West Dunbartonshire.
1/4 of those who identify as
Lesbian, Bi-sexual, gay or
other reported being
discriminated in the past 12
months, compared to 8%
heterosexual people (SHS,
2018).
Through the LHS is was
identified that WDC is likely to
have gaps with equality
monitoring  and work is
underway to improve equalities
monitoring
The development of new
homes can help improve
access to housing and in
doing so seeks to
address
the impact of inequality
and discrimination.
Page 93

Page 94

Human Rights                  The Human Rights Act
recognises the right to have
people's housing needs
met.
UNCRC Article 6
Life, survival and
development
Every child has a right to life
and to develop to their full
potential.
The SHIP supports the aims of
the Human Rights Act 1988 in
respect of access to homes.
The SHIP notes the need to
tackle child poverty and
supports children's and young
people's rights by ensuring
supply of suitable family
housing.
The SHIP identifies
opportunities for the
development of new
homes which can
improve access to
homes. This supports
both European
Convention and UNCRC
rights.
Health                      West Dunbartonshire has
been identified as an area
of high deprivation and poor
health issues. 
Through the LHS is was
identified that WDC is likely to
have gaps with equality
monitoring  and work is
underway to improve equalities
monitoring
The development of new
homes can help address
needs identified in
respect of specialist
housing.   The SHIP
requires that each
project supported by the
programme contains at
least 10% specialist
housing, the nature of
the specialist housing to
be agreed in
consultation with the
West Dunbartonshire
HSCP.
Social & Economic
Impact     
It is recognised that new
housing development is an
important economic driver in
any local economy.   At last
measurement 27% of
households in WDC
experienced fuel poverty but
these statistics were before
recent price increases.
It is estimated for every 10,000
new homes built generates
£443million capital spend,
£1,9b additional output, 38,400
jobs and £94million in taxes
(SFHA 2020).
Ensure that new
development maximise
their impact on their
local communities
including through
community benefits,
such as local
employment and
apprenticeships.   New
homes must be energy
efficient and in doing so
will have lower fuel bills
and this is important for
supporting households
to utilize their household
budgets effectively. 
Cross Cutting          Important that we look at
cross cutting impacts and
intersectionality
The SHIP represents an
opportunity to deliver quality
new homes for the spectrum of
needs across West
Dunbartonshire and provide
wider social and economic
benefits. 
The development of new
homes can help improve
supply of home and in
doing so improve access
to housing and in doing
so seeks to address
the impact of inequality
and discrimination on
persons regardless of
gender, sexual
orientation, race,
religion/belief age their
social or
economic status or
whether they are
transgender.
Page 94

Page 95

Actions
Page 95

Page 96

Policy has a negative impact on an equality group,but is still to be implemented, please
provide justification for this.
The SHIP does not have a negative impact on an equality group.
Will the impact of the policy be monitored and reported on an ongoing bases?
The SHIP will be renewed every year and the LHS every 5 years, with an annual review. We are
committed to improving equality monitoring and using this data to improve and quality ensure our service
design and delivery. The SHIP delivery will be subject to ongoing monitoring through the More Homes
Board and Strategic Housing Providers Forum.
Q7 What is you recommendation for this policy?
Intoduce
Please provide a meaningful summary of how you have reached the recommendation
EIA 1082 details impacts:   The development of new homes can help improve access to housing
and in doing so seeks to address the impact of inequality and discrimination on persons, for
examples related to sex,  sexual orientation, race, religion/belief age their social or economic
status or whether they are transgender, and combinations of these.
In particular, our design standard and requirement for at least 10% of homes to be suitable for 
wheelchair users represents a particular opportunity to ensure that our homes will benefit our
tenants and communities. The SHIP notes the need to tackle child poverty and supports children's
and young people's rights by ensuring supply of suitable housing.
The annual update provides an opportunity to ensure that our ambitions reflect latest best practice
and confirm that there will be an overall benefit to residents of West Dunbartonshire and the local
economy.   This is particularly vital during this period of housing emergency.  The
implementation of the SHIP supports the Council’s key strategic priorities, and we will carefully
continue to monitor its impact.
Page 96

Page 97

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 20 November 2024
__________________________________________________________________
Subject: More Homes West Dunbartonshire – West Dunbartonshire Council
Affordable Housing Supply Delivery Programme
1. Purpose
1.1  This purpose of this report is to provide the Housing and Communities
Committee an update on progress with West Dunbartonshire’s More Homes
Programme which oversees the delivery of the Council’s new home building
programme.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Notes the content of the report and the progress made to date in the
delivery of the Council’s More Homes West Dunbartonshire approach,
including the first handovers of new homes at the zero carbon Clydebank
East development which represents the 500th new build the Council has
developed under the current More Homes programme;
(ii) Approve the updated estimated costs for O’Hare (Bonhill gap site)
development noted in section 4.4 of this report and authorise the Chief
Officer – Regulatory and Regeneration to conclude the award of the
Contract up to the updated estimated costs for the development of the
new homes at the O’Hare site;
(iii) Note the revised Resource Planning Assumption (RPA) following the
allocation of an additional £309k to support acquisitions related to
minimising the use of temporary accommodation referenced at sections
4.5-4.8 of this report: and
(iv) Note the increased Affordable Housing Supply grant benchmark levels
following a review undertaken by the Scottish Government highlighted at
section 4.9 of this report.
3. Background
3.1 In West Dunbartonshire the Affordable Housing Supply Programme (AHSP) is
delivered through a More Homes West Dunbartonshire strategic approach
which has successfully delivered over one thousand new affordable homes in
ITEM 10
Page 97

Page 98

West Dunbartonshire to date and includes the Council’s own ambitious New
House Building Programme.
3.2 The Council’s last full practical completion took place at the Queens Quay
development in September 2022 delivering twenty-nine new Council homes in
a key regeneration area as part of a wider development which has delivered
146 new social rented homes.  The homes were the first residential properties
to be heated from the Council’s Queens Quay District Heating Network. This
development was recognised at national housing sector awards winning the
following: -
 Best Residential Regeneration Project – Herald Property Awards
 Inside Housing Best Residential Development (Scotland)
3.3 These 29 new homes, are in addition to the completion of the Council’s first
fully dementia designed development at Creveul Court, Alexandria and other
exemplar developments in Haldane, Aitkenbar, Bellmsyre, Dumbarton
Harbour and St Andrews, Clydebank.  The Council have now completed
twelve new build developments since 2013 and are the largest developer of
social homes in West Dunbartonshire delivering 508 new homes and 137
acquisitions through our buyback scheme to date as outlined in Table 1
below.  The 500th new build home in the More Homes West Dunbartonshire
delivery programme was delivered in October 2024 at our current Clydebank
East development:
Table 1:  Completed Council New Build and Acquisitions
Project No. of
Units
Completion
Date
Granville Street (Phase 1), Clydebank 24 July 2013
Miller Road, Alexandria 15 October 2013
Granville Street (Phase 2), Clydebank 9 February 2014
Central Bellsmyre, Dumbarton 36 December 2014
Hillstreet Square, Dumbarton 37 August 2015
Second Avenue, Clydebank 40 April 2018
Creveul Court, Alexandria 22 April 2021
Aitkenbar Primary School 55 July2021
Haldane Primary School 58 August 2021
St Andrews, Clydebank 126 October 2021
Dumbarton Harbour, Dumbarton 45 December 2021
Queens Quay, Site B, Clydebank 29 August 2022
Clydebank East, Clydebank 12 Ongoing
Buyback Acquisitions 137 Ongoing
Totals 645
3.4     The Strategic Housing Investment Plan (SHIP) 2024-2029, outlining West
Dunbartonshire’s Affordable Housing Supply Programme through the More
Homes West Dunbartonshire approach was approved by the Housing and
Communities Committee in November 2023. The SHIP outline plans to meet
the Council Administration’s aim of delivering 2500 new affordable and social
rented homes over the next 10 years. A refreshed SHIP will be submitted to
the November meeting of the Housing and Communities Committee.
Page 98

Page 99

4. Main Issues
More Homes West Dunbartonshire - Delivery Programme
4.1 Building new affordable homes has an important role to play in revitalising
local economies and assisting with post-pandemic and economic recovery
plans, negating the impacts of the current cost of living crisis and combatting
poverty principally child and fuel poverty.  It is also clear that the need for
affordable homes has and will increase in the current ongoing economic
environment.
4.2 Our More Homes West Dunbartonshire approach is an ambitious plan that
aims to continue the positive momentum of the delivery of much needed
Council homes in West Dunbartonshire and will significantly assist the
Council’s aim to deliver 2500 new social and affordable homes by 2032.
4.3 As the biggest affordable housing developer in West Dunbartonshire, the
Council has identified several future development sites for new council homes
to address existing and new housing need. The design of these homes will
further develop, improve, and exceed current best practice, providing
sustainable homes using innovative technology and delivering on our low
carbon ambitions including passivhaus and other net zero carbon
opportunities.
4.4 The Strategic Housing Investment Plan and HRA Capital Plan outlined the
plans the Council have for meeting their new build ambitions.  An update on
each development site is provide below: -
Clydebank East:
This development will deliver eighty-eight new homes and has been designed
to meet the housing need within the wider West Dunbartonshire area. The
table below shows the housing mix:
House Type Sustainability Standard Number of New
Homes
Wheelchair Bungalow
3bed/4person
Net Zero 3
House 3bed/5person Net Zero 15
House 4 bed/7person Net Zero 12
House 5 bed/8 person Net Zero 8
Wheelchair Cottage Flat
1bed/2 person
Net Zero 4
Cottage Flat 2 bed/4 person Net Zero 4
Flat 1 bed/2person Net Zero 16
Flat 2 bed/4 person Net Zero 24
Wheelchair Flat 1 bed/2person Net Zero 2
Works commenced on this development in January 2023. The first 12 units
were handed over on 7th October 2024. Sectional handover number 2 is
Page 99

Page 100

scheduled for 18th November 2024 and will include 3-, 4- and 5-bedroom
houses.
All houses are designed to the Housing for Various Needs Standard (HfVN).
There will be nine fully Wheelchair (WCH) accessible properties. The 4- and 5
-bedroom homes have ground floor double bedrooms.
The development at Clydebank East will see the completion of a major
housing led regeneration of a key priority regeneration area identified in the
Local Housing Strategy and will be the first fully zero carbon housing
development in West Dunbartonshire and marks a significant milestone in our
transition to net zero new homes approved at the August 2022 meeting of the
Housing and Communities Committee. 
We have previously reported award of above benchmark grant due to the
complexities of the development at Clydebank East this resulted in a total
grant award of £12.6m, this equates to over £143k grant per home and
around £4.68m more than the benchmark grant award this ensured the
delivery of the development without any negative impact on the wider Housing
Revenue Account.
Pappert, Bonhill
This project enjoyed a site start date in early March, delivering the housing
mix as follows: -
House Type Sustainability Standard Number of New
Homes
House 3bed/5 person Passivhaus 6
House 3bed/5 person Net Zero 6
House 4bed/6person Net Zero 4
House 4bed/7person Net Zero 1
Flat 2bed/3person w/c Net Zero 3
Flat 1 bed/2person Net Zero 6
The development should be complete for handover in summer 2025.
Mount Pleasant, Old Kilpatrick
The site started on 15th April 2024 and construction will last approximately one
year.
This is a 19-unit complex which is designed for elderly residents and will
deliver high quality amenity housing, the housing mix is outlined below for
information.
House Type Sustainability Standard Number of New
Homes
Bungalow 1bed/2person Net Zero 3
Flat 1bed/2person w/c Net Zero 4
Page 100

Page 101

Flat 1bed/2person Net Zero 4
Flat 2bed/4person Net Zero 8
Willox Park, Doveholm, Dumbarton
The development of seventeen new homes to be delivered at the former care
home site.
House Type Sustainability Standard Number of New
Homes
Flat 2bed/3person Net Zero 2
Flat 1 bed/2person Net Zero 15
This development has now been granted planning permission and a
contractor, McTaggart Construction, has been appointed to begin the
construction phase. Construction will commence in November on this project.
The net zero heat strategy will be delivered by ground source heat pump, as it
was felt that this solution to be preferable than an air source heat pump for
each home. 
Current tenants at Willox Park have been consulted throughout the design
process and this has continued with the contractor holding Q&A sessions.
Bonhill Gap Site Strategy
The pre-planning application process has commenced on the development of
the three separate gap sites delivering thirty-four new homes which are
contained within this wider development project outlined in the table below.
Planning has been submitted for all sites with approval expected to be
granted for Braehead and Campbell St in November and O’Hare
determination date set for 25/11/2024.
Site Braehead Campbell St O’Hare
1 bed 8
(4 WCH + 4 GN)
6 6
2 bed 3 (WCH)
3 bed 3
4 bed 2
5 bed 4
6 bed
7 bed 2
Total 17 11 6
Page 101

Page 102

As has been noted to committee previously, the original design proposal for
the O’Hare development site did not achieve a positive financial viability
assessment and the design was revised, Committee is asked to note and
approve the updated estimated costs for the O’Hare project of £1,505,000 and
to develop a procurement strategy to appoint a contractor up to this estimated
cost.  The previous estimated costs for he revised design was £1,424,221.26.
This is a 5.7% increase that assumes an inflationary cost increase for when
the tender submissions return.
Bank Street, Alexandria
The development will consist of twenty-two sheltered/amenity housing units in
partnership with the HSCP. Planning has been submitted.
House Type Sustainability Standard Number of New
Homes
Flat 1bed/2person w/c Net Zero 22
Communal Room Net Zero 1
Staff Office Net Zero 1
A planning decision is expected at the end of November along with the return
of the tender submissions from contractors. Similar to Willox Park, tenants at
Gray Street have been consulted throughout the design process.
Clydebank Health Centre
Having received the feasibility report for the site, we aim to develop 20+ units
of sheltered housing to strategically improving the provision of sheltered
accommodation within Clydebank. We also aim to build around eighteen units
of mostly family housing.
We have discussed proposals with tenants at Young Street on the proposition
of developing a new sheltered complex on the old Clydebank Health Centre
site. This was met with a largely positive reaction and consultation with
tenants, staff and other stakeholders will continue throughout the design
process.
A multidisciplinary design team, led by Collective Architecture, who carried out
the feasibility study, have been appointed through the Scottish Procurement
Alliance framework to carry forward the above-mentioned site proposal
designs.
The demolition of the Health Centre was awarded to Caskie Ltd and works
commenced on the 3rd of June and the demolition programme is scheduled for
around 20 weeks. There has been a delay in the demolition due to issues with
gas disconnections. The estimated completion date of the site is now
2/12/2024.
Gilmour Avenue, Hardgate
Page 102

Page 103

As part of the wider development of our Clydebank Gap Site strategy we
identified a Housing Revenue Account site in the Hardgate area at Gilmour
Avenue.  The site was previously the location of timber garages on concrete
bases.  These have long since been demolished and the site has been beset
with fly tipping issues for several years.
The development started on site on 23/9/2024 and has a completion date of
14/2/25.
Connect modular, the contractor, is having a day of learning about
construction with the local primary school, Goldenhill Primary, and the pupils
will be invited to watch the housing modules arrive on site.
Dennystoun Forge Gypsy/Traveller Site
The project has been scored and assessed as a priority in the new SHIP 2025
-2030, with a proposed site start next financial year.  Our in-house design
team and Procurement colleagues are proceeding to detail our plans.
Engagement continuous with the Dennystoun Forge community. Our focus
remains on decant options, where we are engaging with our Assets and
Planning colleagues on the possible use of an identified alternative site for
decanting during the works, and on procurement, where we have consulted
with other local authorities with experience of similar projects.   The decant
arrangements have thrown up a series of questions which we will be
discussing with the community.  While the costs for the decant site are likely
to be high, overall, we expect a saving to be achieved through giving the
eventual works contractor free access to the Dennystoun Forge site.
Queen Mary Avenue, Clydebank (Clydebank Gap Sites)
The transfer of the site at Queen Mary Avenue, Clydebank with vacant
possession at the cost of £140,000 from the Council’s General Fund to the
Housing Revenue Account for the delivery of new Council homes was
approved at the February meeting of the Housing and Communities
Committee and has now been concluded. 
The demolition contract for the units was awarded to Caskie Ltd. The
programme started on 6th July and was completed in September 2024.
An Employer’s Agent/QS has been procured to assist moving this Design and
Build project forward.
Silverton Regeneration
The demolition for the two identified sites in Smollett Road and Dumbuie
Avenue started on 2/10/24 and the contract period is 6 weeks. We are
currently developing a design for future replacement housing on the site. 
Page 103

Page 104

Queens Quay, Site C, Clydebank
The Council has been developing a design to deliver a projected twenty units
on this site to complement the housing mix within sites A and B.  This
development will also be designed to meet low/zero carbon principles and
linked to the Queens Quay district heating network.
.
Pre-planning response was received on the 25 February highlighting concern
of the WDC development proceeding in isolation. We have adopted a
proactive response to this issue and have developed masterplan diagrams
incorporating the surrounding sites and have conducted valuations on the
adjacent site to Queens Quay C with a view to purchasing additional land to
deliver more affordable housing in the Queens Quay regeneration site. If this
is achieved, we would seek to develop a mixed tenure approach to any
expanded development site delivering one hundred new affordable homes.
We are seeking discussion with CRL (Clydeside Regeneration Limited) to
progress the possibility of acquiring this additional land and will be able to
draw down Scottish Government grant to enable this. However, because of
the uncertainties surrounding potential delivery timescales for this project and
the reduced funding it is no longer allocated funding within the current
Strategic Housing Investment Programme.
Buyback Programme
Total number of properties purchased in 2024/25 financial year 17
Total Purchase Value   £1,673,700
We have completed nine purchases since the last board and that includes five
larger family properties comprising of three bedrooms or more.
4.5    The West Dunbartonshire Strategic Housing Investment Plan 2024/25 –
2028/29 (SHIP) was approved by West Dunbartonshire’s Housing and
Communities Committee in November 2023 and submitted to the Scottish
Government.  Our Council Annual Resource Planning Assumption (RPA) from
the Scottish Government supporting the delivery of the SHIP was £10.795m. 
The budget cut has reduced this figure to £8.167m for 2024/25, a cut of 24%.
4.6   In September 2024, the Scottish Government revised 2024-25 RPAs with
immediate effect to take into account an additional £40m acquisition funding. 
While the Scottish Government recognised that all local authorities are facing
a range of housing and homelessness pressures, the allocation of this funding
was predicated on the Scottish Government’s perception that because of
enduring pressures experienced by a handful of local authorities over a
number of years have that this funding should be targeted.
4.7 Using a methodology based on consistently high temporary accommodation
numbers as an indicator of acute need this funding was targeted to five local
authorities, and 80% of the £40m was allocated to these five local authority
areas (Edinburgh, Fife, Glasgow, South Lanarkshire, and West Lothian). The
Page 104

Page 105

remaining 20% of the £40m has been allocated across the other twenty-seven
local authority areas, using the same distribution methodology, to inform each
local authority area’s share. 
4.8 The additional allocation of the £40m for West Dunbartonshire Council is
£309k and the total RPA for 2024-25 for the Council is now £8.477m. The
additional £309k requires to be directed towards acquisitions to help address
temporary accommodation pressures.
4.9 As of 10th October 2024, updated affordable housing investment grant
benchmark levels were introduced.  These were informed by adjusting the
data from the Scottish Social Housing Tender Price Index for the entire 2023
calendar year – resulting in an increase of 5% across the board. An additional
quality measure benchmark of £4,560 per unit (at the three-person equivalent
level) has also been introduced to account for key changes introduced by the
February 2023 revision of building regulations. The revised benchmark levels
are illustrated in the table below: -
Revised Affordable housing investment benchmarks (from 10/10/24):
Baseline
benchmarks
Project type
West Highland,
Island authorities,
and remote/ rural
Argyll
Other rural City and urban
RSL social
rent
£117,222
(3 person
equivalent)
£101,878
(3 person
equivalent)
£95,741
(3 person
equivalent)
Council social
rent
£101,878
(3 person
equivalent)
£92,673
(3 person
equivalent)
£87,763
(3 person
equivalent)
RSL mid-
market rent
£71,806
(3 person
equivalent)
£69,351
(3 person
equivalent)
£65,669
(3 person
equivalent)
Council mid-
market rent
£65,055
(3 person
equivalent)
£63,214
(3 person
equivalent)
£60,145
(3 person
equivalent)
Additional quality measure
benchmarks
Homes delivered to Section 7, Silver
Level, of the 2019 Building £2,455 per home
Page 105

Page 106

Regulations in respect of Energy for
Space Heating (that is, full Bronze
Level plus Aspect 2 of Silver Level).1
(3 person equivalent benchmark)
Homes delivered to the updated
provisions for energy performance,
ventilation and assessment of
overheating risk introduced through
building regulations in February
2023.2
£4,560 per home
(3 person equivalent benchmark)
Provision of balconies within flatted
developments to enable people to sit
outside, where the provision of
private or communal outdoor space
cannot otherwise be accommodated.
£4,910 per home
(3 person equivalent benchmark)
Provision of space for home working
or study – to note that this
benchmark does not apply to
projects meeting current Housing for
Varying Needs standards3. In all
other circumstances, grant applicants
should demonstrate that additional
space is necessary to deliver this
measure in order for this benchmark
to apply i.e. it is not possible to
incorporate this within the design of
the homes under current space
standards.4
£4,297 per home
(3 person equivalent benchmark)
Digitally-enabling – when a tenant
gets the keys to their home they
should be able to arrange for an
internet connection to ‘go live’
without the internet service provider
having to provide additional cabling
to the premises.5
£369 per home
(3 person equivalent benchmark)
Installation of ducting infrastructure
for electric vehicle charge point
connectors.
£614 per connector
(3 person equivalent benchmark)
Installation of electric vehicle charge
points (excluding installation of
ducting infrastructure).6
£614 per charge point
(3 person equivalent benchmark)
Installation of automatic fire
suppression systems.
£3,682 per home
(3 person equivalent benchmark)
Page 106

Page 107

Installation of zero direct emissions
heating systems.7
£4,910 per home
(3 person equivalent benchmark)
4.10    The increase in the grant benchmark is welcomed and will assist in ensuring
the affordability of the new build programme.  However, the additional grant
funding requires to be delivered from the current RPA for 2024/25 which will
increase pressure on the funding available this financial year.  For future
years we await the outcome of the Scottish Government budget proposals in
December this year which we hope will provide some added certainty
regarding future years funding availability to deliver the Affordable Housing
Supply Programme.
4.11 The Housing Development Team are continuously looking for opportunities to
provide additional new build council homes and will bring any potential site to
the Housing and Communities Committee with as much information as
possible as part of the regular More Homes update paper.
5. People Implications
5.10 The delivery of the More Homes delivery programme is managed through
existing resource within the Housing Development & Homelessness team
funded from the Housing Capital Investment Programme. 
6. Financial and Procurement Implications
Financial
6.1 On 6 March 2024 Council approved the Housing Capital Programme 2023-
2028 which saw significant resources committed to the delivery of new council
homes in West Dunbartonshire.  An expenditure budget of £155m for the
affordable housing supply programme is factored into the HRA Capital
Programme this will be updated to reflect the income and expenditure
highlighted within this report.  As it currently stands, it is anticipated that this
programme will complete on project life budget.
6.2 Housing and Finance Officers will continue to assess the ongoing affordability
of future developments within the context of the Housing Revenue Account
Business Plan.
Procurement
6.3 All new development sites will be subject to new detailed procurement
strategies and the opportunities highlighted within 4.5 of this report will
continue to be prioritised. Where the contract award is less than £213,000,
authority is delegated to the Chief Officer in consultation with the Procurement
Manager to instruct the award of contracts for the planned revenue and
Page 107

Page 108

capital spend detailed in this report to suppliers providing the most
economically advantageous offer to the Council.
6.4 All procurement activity conducted by the Council more than £2m is
subject to a contract strategy. The contract strategy for new housing
development within the HRA Capital Programme will be developed by the
Corporate Procurement Unit in consultation with Housing Development
Officers. The contract strategy will include, but is not limited to; contract
scope, service forward plan, the market, procurement model and routes –
including existing delivery vehicles, roles and responsibilities, risks, issues
and opportunities and on-going contract management. Opportunities to
maximise the positive social, economic, and environmental impact for the
Council through the relevant procurement processes will be developed in line
with procurement policy.
7. Risk Analysis
7.1 All Council new build projects have their own Risk Register which highlights
the risk within and out-with the project team’s control.  These are maintained
and adjusted on an on-going basis.
7.2 With any new build project there is a risk that as the projects develop the cost
increases beyond the estimated contract cost.  Any additional borrowing
requirements, or conversely, cost savings will be reported to future meetings
of the Housing and Communities Committee. However, this is mitigated
through a target cost model approach in our current contract arrangements
within the Scottish Procurement Alliance (SPA) framework and Scotland
Excel.
8 Environmental Sustainability
8.1 The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy.
9. Equalities Impact Assessment (EIA)
9.1 The proposal does not alter any existing policy or pattern of service delivery
and so is not considered to require an equalities impact assessment.
10. Consultation
10.1 As part of a rent consultation exercise, 92% of respondents indicated their
support for the Council’s ambitious plans to deliver the Housing Revenue
Account (HRA) new council house build programme. In addition, there was
positive support for the wider delivery of new build housing as part of the
recent Local Housing Strategy.  Regular updates on new build development
Page 108

Page 109

are provided to the West Dunbartonshire Tenants and Residents Organisation
at the bi-monthly liaison meetings.
11. Strategic Assessment
11.1 The Local Housing Strategy is the overarching document setting out the
strategic direction for housing across all tenures and informs the future
investment in housing and related services across West Dunbartonshire.
11.2 Having considered all the Council’s strategic priorities, this report, and the
provision of new supply social housing for rent contributes greatly to all the
Council’s strategic priorities.
Peter Barry
Chief Officer, Housing and Employability
Date: 7 November 2024
Person to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk
Mikayla Deeley, Senior Housing Development Officer,
Housing Development and Homelessness Team,
Housing and Employability: email mikayla.deeley@west-
dunbarton.gov.uk
Appendices: None
Background Papers: West Dunbartonshire Council’s Local Housing Strategy
Local Housing Strategy, Health Inequalities Impact
Assessment
Wards Affected: All
Page 109

Page 110

Page 110

Page 111

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 20 November 2024
___________________________________________________________________
Subject:  West Dunbartonshire –Empty Homes Strategy 2024-2029
1. Purpose
1.1 The purpose of this report is to seek approval of the new Empty Homes
Strategy 2024 -2029.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Approve the revised Empty Homes Strategy 2024 -2029; and
(ii) Approve the target to return 125 homes back into use over the period of
the strategy.
3. Background
3.1 West Dunbartonshire Council employs an Empty Homes Officer to provide
advice and assistance to owners of long term empty private homes; that is
properties that have been empty longer than six months.
3.2 The Scottish Government has recognised and prioritised the issue of empty
properties by asking Local Authorities to demonstrate in their Local Housing
Strategies how the issue of empty homes is being addressed.
3.3 According to Scottish Government figures, in September 2023, there were
46,217 long term empty homes across Scotland. West Dunbartonshire
Council has 494 long term empty homes.
3.4 The Scottish Government has a vision of a Scotland where every home is
occupied, and no homes are left empty for significant periods of time without
good reason. There is a clear ambition to see empty homes services
operating in every area of Scotland and for existing services to be enhanced
where possible.
3.5 The Scottish Government’s ‘Housing to 2040’ has an ambition to deliver
100,000 homes over the period to 2032 and sets priorities that empty homes
can help to deliver.
3.6 West Dunbartonshire had 1095 homeless presentations in the year 2023/24.
and for the same period there were 5995 people on the waiting list.
ITEM 11
Page 111

Page 112

3.7 Returning empty homes to use can help provide additional housing in the
private sector and for social housing. It can help the authority deliver on the
Local Housing Strategy’s priorities and objectives.
 Housing Need and Demand - by making more properties available to be
lived in
 Promoting Quality Homes - those properties below tolerable standard
are likely to be renovated to at least the repairing standard.
 Homelessness and Housing Options - empty homes returned to use
can help to alleviate some of the demand for social housing and provide
more choice.
 Place and Community - Places and communities are vitally important to
both our resident’s health and well-being, and returning empty homes to
use can remove the blight on a local community and help to create
sustainable communities.
3.8 West Dunbartonshire’s housing stock is predominately split between home
ownership at 56% and Registered Social Landlords and Local Authority
housing stock at 37%. The private rented sector only accounts for 6% of the
housing stock. Less than 1% of the housing stock is a second home.
3.9 The previous Empty Homes Strategy 2021-2024 aimed to return 75 empty
homes back into use. During the period of the strategy, eighty-three properties
of varying type, size and location have been brought back into use to
provide the communities of West Dunbartonshire with more available
housing.
4. Main Issues
4.1 The main reason for a property being empty in West Dunbartonshire is due to
deceased owners. These properties can be difficult to bring back into use
particularly where the person has died intestate.
4.2 West Dunbartonshire Council does also have long term empty private homes
where owners cannot be traced, others have refused to engage and address
the impact the empty property has on the neighbourhood and maintenance
concerns have also been ignored.
4.3 Empty homes present challenges to those living in the vicinity of the empty
property where they can experience increased vandalism, anti-social
behaviour and impacts on emergency services, i.e. Police and Fire Service.
4.4 The Empty Homes Officer works closely with the Lead Buy Back Officer to
help identify long term empty homes that meet the needs and demands for
housing in West Dunbartonshire.
4.5 The only enforcement action available to assist Empty Homes Officers to
return properties back into use is Compulsory Purchase Orders. However,
these are time consuming and costly for local authorities. The Scottish
Page 112

Page 113

Government has committed to reviewing Compulsory Purchase Orders and
has set up Compulsory Purchase Reform group to oversee the review.
4.6 The Scottish Government had intended to legislate to introduce a Compulsory
Sale Order power for vacant land and buildings. This would allow local
authorities to force long term empty homes onto the open market. This would
give the Empty Homes Officer an additional tool in those instances where all
other means of engaging with the owner have been exhausted. The intended
legislation that would introduce these powers had been delayed because of
BREXIT and then further delayed because of the COVID-19 pandemic. The
Scottish Government is still considering this option; however, it is not included
in the current Housing Bill.
4.7 The Empty Homes Officer collaborates closely with colleagues in Corporate
Debt, Environmental Health, Planning, Building Standards, Regeneration,
and Criminal Justice to try and overcome any obstacles preventing a home
being returned to use.
4.8 On 1 May 2024, the Housing and Communities Committee declared a
housing emergency in West Dunbartonshire, becoming the fifth local authority
to do so by that date. On 15 May 2024 the Scottish Government too declared
a housing emergency, formally recognising the scale of the problem.
4.9 Case studies 1 and 2 in the strategy document (appendix 1) show the wider
financial advantages of the Empty Homes Officer work in bringing homes back
into use. These cases resulted in Council Tax debt of £43,835.65 and
£71,815.72 in care home costs being collected.  This sum totals £115,651.37
being collected at the point of sale that would otherwise have remained
outstanding without the intervention of the Empty Homes Officer.
5. People Implications
5.1 There are no direct people implications because of this report.  The Council
continues to fund the Empty Homes Officers from the Housing Revenue
Account.
6. Financial and Procurement Implications
6.1 There are no direct procurement implications in relation to this report.
6.2 There are financial benefits to returning empty homes back into use with the case
studies resulting in £115,651.37 being collected when the house sales
concluded. For those properties purchased as a buy back this will also provide
additional rent in perpetuity.
6.3 As at the end of June, the total outstanding council tax debt to West
Dunbartonshire Council attributed to empty homes in the private sector was
£874k, with an average debt per property of around £1.8k.
Page 113

Page 114

7. Risk Analysis
7.1 There is no significant identifiable risk associated with the approval and
implementation of the revised Empty Homes Strategy.
8 Environmental Sustainability
8.1 The delivery of our housing investment programme is within the approved
More Homes zero carbon approach. Our current and future approach to
strategic housing asset management will continue to prioritise a ‘zero carbon’
approach to decision making and deliverability and this will be done the aims
of the Housing Asset Management Strategy and the Council’s Climate
Change Strategy.
9. Equalities Impact Assessment
9.1 An Equality, Health and Human Rights Impact Assessment has been carried
out on the draft Empty Homes Strategy and found no substantive negative
impacts. A copy of the assessment as Appendix 2 of this report.
10. Consultation
10.1 A key element in the development of the revised Empty Homes Strategy was
seeking the views of the West Dunbartonshire Tenants and Residents
Organisation, the Scottish Empty Homes Partnership, and internal
stakeholders.
10.2 The consultation gathered views on the draft strategy and the feedback was
used to update the strategy.
11. Strategic Assessment
11.1 Having considered the Council's strategic priorities, this report contributes
significantly to all five strategic priorities and specifically to improve local
housing and bring empty properties back into use.
Peter Barry
Chief Officer, Housing & Employability
Date:  6 November 2024
___________________________________________________________________
Person to Contact:  John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness Team,
Housing and Employability, telephone: 07793717981, email:
john.kerr@west-dunbarton.gov.uk
Page 114

Page 115

Appendices:
Karen Rae, Empty Homes Officer, Housing Development
and Homelessness Team, Housing and Employability,
telephone: 07793717981, email: karen.rae@west-
dunbarton.gov.uk
1. Draft Empty Homes Strategy 2024 -2029
2. Equalities Impact Assessment, November 2024 - To Follow
Background Papers:    1. Equalities Impact Assessment, November 2024
2. Local Housing Strategy 2022-2027
Wards Affected:  All
Page 115

Page 116

West Dunbartonshire
Empty Homes Strategy
(Private Sector) 2024/29
ITEM 11 - APPENDIX 1
Page 116

Page 117

2
Contents
1. Introduction......................................................................................................................................2
1.1 What is meant by Empty Homes?..............................................................................................3
2. The Legislative and Policy Context for Empty Homes.....................................................................4
2.1 Statutory Requirements..............................................................................................................4
2.2 The National Policy Context for Empty Homes..........................................................................4
2.3 The Local Policy Context for Empty Homes...............................................................................7
3. Evidencing the Need to Tackle Empty Homes in West Dunbartonshire.........................................11
3.1 Profiling Empty Homes.............................................................................................................11
3.2 Long Term Empty Homes.........................................................................................................11
3.3 Housing Need and Demand.....................................................................................................14
3.4 Homelessness..........................................................................................................................14
3.5 Temporary Accommodation......................................................................................................15
3.6 Private Rented Sector..............................................................................................................16
4. Local Action, Challenges & Barriers in Tackling Empty Homes.....................................................17
4.1 Empty Homes Projects and Initiatives in West Dunbartonshire...............................................17
4.2 Challenges and Barriers to Tackling Empty Homes.................................................................21
5. The Strategy for Tackling Empty Homes in West Dunbartonshire.................................................23
6. Empty Homes Action Plan.............................................................................................................24
7. Monitoring Progress and Evaluating..............................................................................................26
7.1 Evaluation.................................................................................................................................26
8. Consultation & Engagement..........................................................................................................26
1. Introduction
Page 117

Page 118

3
West Dunbartonshire Council is pleased to present this Strategic Empty Homes Strategy covering
the period 2024 – 2029.
This Empty Homes Strategy seeks to:
 Set a target of returning 125 empty homes back into use in West Dunbartonshire over the
period of this strategy.
 Support homeowners to bring empty homes back into use, increasing local housing options
and meeting housing need.
 Enable housing regeneration, placemaking and neighbourhood improvement activity which
improves community safety, environmental quality, and housing condition.
 Make a positive contribution to the building reuse and repurposing agenda aligned to the
Council’s wider ambitions for tackling climate change.
The Empty Homes Strategy’s main purpose is to provide a clear picture of how we aim to return
empty private homes back into use. By tackling empty homes this will contribute to meeting housing
needs over the Authority, assist in the regeneration of our communities, support our local economy
and climate change.
The Scottish Government’s Housing to 2040 has an ambitious vision of what housing should look
like over the next two decades and a plan of how they see this should be achieved. By bringing
empty homes back into use this will help deliver on the priorities:
• More homes at the heart of great places
• Affordability and Choice
• Affordable warmth and zero emissions homes
• Improving the quality of homes
The Empty Homes Strategy aligns with the Local Housing Strategy 2022-2027, theme of Place and
Community.
The previous Empty Homes Strategy 2021-2024 aimed to return 75 empty homes back into use.
During the period of the strategy, we have reported to the Scottish Empty Homes Partnership that
83 properties of varying type, size and location have been brought back into use to provide the
communities of West Dunbartonshire with more available housing.
Since the previous Strategy we have: -
• Moved from having a part-time Empty Homes Officer to a full-time Officer, from July
2022.
• And further developed working relationships with colleagues in Building Standards,
Environmental Health, Planning, Regeneration and Social Work (Criminal Justice).
1.1 What is meant by Empty Homes?
In this Empty Homes Strategy, empty homes have been classified using the following definitions:
Page 118

Page 119

4
• Long term empty properties. These are dwellings that have been empty for 6 months or more and
are liable for council tax. The most recent figures published by the Scottish Government show that
there were 494 long term empty properties in West Dunbartonshire in September 2023.
• Unoccupied exemptions. These are properties which are empty and exempt from paying council
tax. The most recent figures published by the Scottish Government show that there were 848
unoccupied exemptions in West Dunbartonshire in September 2023. There is no requirement for a
property to have been empty for more than 6 months before it can be included in this category.
• Second homes. Homes which are furnished and lived in for at least 25 days in a 12-month period
but not as someone’s main residence. The most recent figures published by the Scottish
Government show that there were 19 second homes in West Dunbartonshire in September 2023.
Understanding why homes become empty can play a significant role in bringing the properties back
into use, some reasons for homes becoming empty can include:
• Inheritance and ownership difficulties
• They do not want to become a private landlord.
• Repossessions
• Major repairs and lack of resources
• Difficulty engaging or location of owners.
For owners, empty homes can have considerable financial impacts in terms of lost rental income,
mortgage payments, council tax, insurance, maintenance, and security. Empty Homes can therefore
pose the potential for significant financial loss.
From a wider community perspective, empty homes can cause a negative appearance in terms of
place, undermine regeneration efforts, prevent common works from taking place and lower the
value of nearby properties. Furthermore, properties which are inactive within the housing market do
not contribute to economic activity within communities and do not help with homelessness
prevention or meeting housing need.
This Empty Homes Strategy focuses on long term empty properties, setting out the approaches that
the Council and partners will take to bring homes back into use. Having said this, it should be noted
that unoccupied exemptions may include properties where the previous owner has died and/or
properties that have been repossessed. The Empty Homes Strategy also sets out approaches for
bringing these properties back to use.
This Empty Homes Strategy can therefore deliver significant economic and financial benefits to
West Dunbartonshire communities, local businesses, owners, landlords and residents by
contributing to:
• enhancing housing supply to meet housing need.
• reducing homelessness by increasing housing options
• achieving Net Zero Targets and carbon savings through the retrofitting of existing properties as an
alternative to new supply
• reducing neighbourhood complaints and the avoidable deployment of public resources
• reducing requirements for Police and Fire Services to attend empty homes.
• financial returns for owners by realising asset value or generating rental income.
• improving aesthetic appearance and sense of place within a community
• progressing common works to improve housing standards across other homes.
Page 119

Page 120

5
2. The Legislative and Policy Context for Empty
Homes
There is a rich and diverse policy context for tackling empty homes in Scotland, which supports the
delivery of empty homes activity and influences the contribution that empty homes can make to
national, local and community objectives.
It is important that this Empty Homes Strategy supports and helps deliver national housing
outcomes and targets, whilst also reflecting the local needs and priorities set out by community
planning and housing partnerships.
This Empty Homes Strategy is set within the wider Community Planning and Local Housing
Strategy for the Council and its partners. The Strategy defines the contribution that empty homes
can make to local strategic priorities and meeting the targets set out in Scotland’s first national
Housing Strategy: ‘Housing to 2040’. The national and local strategic framework that supports and
enables the delivery of the Empty Homes Strategy is set out in more detail below.
2.1 Statutory Requirements
There are a number of statutory requirements placed on West Dunbartonshire Council and those
that relate directly or indirectly to bringing empty homes back into use, are as follows:
• Local Government Finance (Unoccupied properties etc.) (Scotland) Act 2012. This allows local
authorities to charge increased Council Tax on certain homes that have been empty over a year.
• The Housing (Scotland) Act 2011 which places a duty on local authorities to develop a Local
Housing Strategy (LHS) which set out the local authority’s and local partners’ vision for the supply of
housing across all tenures and types of housing provision.
• Local authorities’ duties to homeless people including a statutory responsibility to anyone
threatened with, or experiencing, homelessness.
• House Condition (Housing (Scotland) Act 2006, Section 10) creates duties to have in place a Below
Tolerable Standard Strategy, Housing Renewal Area Policy, and Scheme of Assistance Strategy
• Tackling the effects of Climate Change – Section 44 of the Climate Change (Scotland) Act 2009
• Fuel Poverty (Targets, Definition and Strategy) (Scotland) Act 2019 introduces a new statutory
target for reducing fuel poverty. The target is that by 2040, as far as reasonably possible, no
household, in any Local Authority area, in Scotland is in fuel poverty; and, in any event, no more
than 5% of households, in any local authority area in Scotland are in fuel poverty. No more than 1%
of households in Scotland should be in extreme fuel poverty.
This legislative framework not only places powers and duties on West Dunbartonshire Council but
offers mechanisms which can drive empty homes activity and intervention including enforcement
action, advice, assistance, and investment.
2.2 The National Policy Context for Empty Homes
The national policy context places the empty homes agenda within a framework of strategic
ambitions around housing, place, community, net zero and the Scottish economy. Whilst there are
currently no statutory requirements for local authorities regarding empty homes, the Scottish
Government is keen to encourage empty homeowners to bring properties back into use and in
particular, to increase affordable housing supply in Scotland to tackle shortages in this sector.
Page 120

Page 121

6
There are currently eleven National Outcomes describing what the Scottish Government wants to
achieve. By proactively tackling empty homes and bringing them back into use, the Council and
partners can contribute to delivery of several of these as shown below.
National Outcome Empty Homes Contribution
Economy: We have a globally
competitive, entrepreneurial,
inclusive, and sustainable
economy
Assisting and enabling empty homeowners to bring their
properties back into use, provides greater housing choice,
improves the aesthetic appearance of communities, and can
contribute to making communities more robust and resilient
through investment, job creation and greater local spend
Fair work and business: We
have thriving and innovative
businesses, with quality jobs
and fair work for everyone
Empty homes can contribute to fair work and local business
agendas through job creation, spend on materials and
resources, learning and development of a skilled workforce
and increasing the number of households accessing services,
amenities
Communities: We live in
communities that are inclusive,
empowered, resilient and safe
Tackling empty homes improves community safety,
encouraging greater levels of resident occupation to reduce
security risks and enhance neighbourhood quality
Poverty: We tackle poverty by
sharing opportunities, wealth,
and power more equally
Empty homes that are brought back into use can contribute to
increasing the supply of affordable housing and therefore
assist in tackling the poverty agenda.
Environment: We value, enjoy,
protect, and enhance our
environment
Refurbishment and retrofitting have significantly less impact
on the environment and carbon emissions than newbuild
housing activity. Empty homes can contribute to increasing
housing choice and supply whilst reducing impact on
consumption and production.
Bringing empty homes back into use safeguards properties at
risk by allowing works to be carried out not only for that
property but others where there are communal repairs.
Ensuring properties are protected and lived in increases
housing supply and provides a better environment for those
who wish to live in communities in the future
Health: We are healthy and
active
Psychologists have long known that people's surroundings
can influence their moods and mental health. The mental and
physical wellbeing of people who live in the same street as an
empty home can be adversely affected as the condition of the
house deteriorates and it becomes the focus of anti-social
behaviour. People living in areas with high levels of long-term
empty homes may be more prone to depression due to the
decline of their neighbourhood. Bringing empty homes back
to use can help people to rediscover a sense of place and
remove the negative stresses and risks to physical health that
people living next door to an empty home may face.
Table 1 Empty Homes impact on achieving National Outcomes
Empty homes have an important role to play in helping to deliver the right homes, in the right places
for people across Scotland. The Scottish Government’s Housing to 2040 strategy sets an ambitious
Page 121

Page 122

7
vision of what housing should look like over the next two decades and a plan on how to achieve this
vision.
Bringing empty homes back into use will help deliver all priorities set out in the Housing to 2040
strategy as follows:
Affordable warmth and zero emissions homes:
 Help to drive down carbon emissions caused by
housing and housing construction.
 Assist with reduced heating and operational
carbon emissions through retrofitting for
improved energy performance.
More homes at the heart of great places:
 Help to meet demand for affordable housing in
areas of most need.
 Contribute to the regeneration and revitalising of
town centres, villages, and rural communities.
Affordability and choice:
 Contribute to delivering 100,000 affordable
homes between 2021/22 and 2031/32.
 Ensure as wide a range as possible of property
types and tenures across Scotland.
Improving the quality of all homes:
 Supporting the renovation of existing homes and
returning them back to use
 Improving the quality of housing stock and the
aesthetic appearance of neighbourhoods.
Furthermore, the new National Planning Framework 4 (NPF4) 1 Policy 9 ‘Brownfield, vacant and
derelict land, and empty buildings’, encourages development proposals for the reuse of existing
buildings, taking into account their suitability for conversion to other uses. NPF4 therefore promotes
the sustainable reuse of buildings such as empty homes.
Within NPF4 Policy 17 ‘Rural Homes’ supports development proposals for new homes in rural areas
where the development is suitably scaled, sited, and designed to be in keeping with the character of
the area, it also supports the reuse of redundant and unused buildings.
NPF4 Policy 27 ‘City, town, local and commercial centres’, supports development proposals for the
re-use of a vacant building within city/ town centres where it can be demonstrated that the existing
use is no longer viable, and the proposed change of use adds to viability and vitality of the area.
1 https://www.gov.scot/binaries/content/documents/govscot/publications/strategy-plan/2023/02/national-
planning-framework-4/documents/national-planning-framework-4-revised-draft/national-planning-framework-4-
revised-draft/govscot%3Adocument/national-plannin
Page 122

Page 123

8
The conversion, or reuse of vacant upper floors of properties within city/town centres for residential
conversion of empty homes will therefore be supported.
In 2021 West Dunbartonshire Council launched a Climate Change Strategy that sets out the
Council’s response to setting a long-term target for West Dunbartonshire to reach net zero by 2045.
From this a Climate Change Action Plan was established to detail how the Council will deliver and
monitor its Climate Change efforts with one of the themes being for its housing stock to become
more energy efficient. As some empty homes are former local authority stock; by working with the
Buy Back Lead Officer the Empty Homes Officer can refer appropriate properties and once
purchased they can then be included in any ongoing capital programme to improve the energy
efficiency i.e. external wall insulation helping to meet the Council with its net zero ambitions. Empty
homes within the private sector can also access financial assistance to increase energy efficiency of
buildings and reduce fuel poverty, aligning with the Council’s Local Heat and Energy Efficiency
Strategy (LHEES). Retrofitting and maintaining existing domestic properties help to reduce the
construction of new homes and subsequently mitigates environmental impacts and wider supply
chain carbon emissions.
2.3 The Local Policy Context for Empty Homes
The West Dunbartonshire Council Local Housing Strategy (LHS) is at the heart of the arrangements
for housing and planning through its links with the Local Development Plan and its strategic role in
directing investment in housing and housing related services.
The West Dunbartonshire Council LHS sets out a strategic vision for the delivery of housing and
housing services and the outcomes that partners are seeking to achieve to meet housing need. The
LHS sets out the approach to increasing housing supply, meeting housing need and demand,
preventing and alleviating homelessness, delivering specialist housing, improving private sector
housing conditions and energy efficiency, addressing fuel poverty, and delivering the housing
contribution to meeting net zero targets. More specifically, the LHS defines tackling empty homes as
a key area for action, partnership, and investment.
The LHS priorities and objectives are:
Housing Need and Demand
 Need and demand projections.
 Housing land availability
 Housing supply targets
 New build by the different tenures
Promoting Quality Homes
 How we will improve the quality of the house stock across all tenures
 Housing and the Climate Change Strategy
 Fuel poverty.
 The Energy Efficiency Standards for Social housing (EESSH)
 WDC Housing Asset Management Strategy
 Supporting Owner Occupiers and Private Landlords with their homes
Page 123

Page 124

9
 New build housing design requirements and the West Dunbartonshire Design Standard
 Below Tolerable Standard homes
Homelessness and Housing Options
 The Council’s statutory requirements on homelessness
 Evidence about homelessness
 Homelessness Prevention and Housing First
 The Scottish Government’s Prevention Review Group
 The Rapid Rehousing Transition Plan
 Prison Leavers
 Armed forces housing advice
 Our Leaving Care Housing Protocol
 The Hospital Discharge Protocol
 Young People
 No Home for Domestic Abuse.
Place and Community
 Place making as a public health priority.
 Place making and climate change.
 Place making and Planning policy.
 20-minute Neighbourhoods
 Town Centres
 Regeneration and Housing Renewal priorities
 Empty Homes Strategy
 Compulsory Sales and Purchase Orders
 Buy back strategy.
 Tenant Participation
Supported, Specialist and Particular Needs Housing
 Housing and the Health and Social Care Partnership
 Need and demand for specialist accommodation.
 Older people’s housing
 Accessible housing and delivery of wheelchair housing
 People with disabilities and supported housing.
 Aids and Adaptations
 Care and Repair
Page 124

Page 125

10
 Technology supported housing.
 Dementia housing
 People with needs
 Offender and prison leaver pathways
 Gypsy Traveller Communities
 Other groups such as Ethnic minorities, Travelling Show people, LGBT+ communities, and Key
workers.
Returning empty homes to use can help the authority deliver on a number of the above priorities
and objectives. Housing Need and Demand by making more properties available to be lived in,
Promoting Quality Homes as those properties below tolerable standard are likely to be renovated
to at least the repairing standard. Homelessness and Housing Options where empty homes
returned to use can help to alleviate some of the demand for social housing and provide more
choice. Place and Community, as places and communities are vitally important to both our
resident’s health and well-being, returning empty homes to use can remove the blight on a local
community and help to create sustainable communities.
The Community Empowerment (Scotland) Act 2015 (CE Act) introduced a requirement for all local
Community Planning Partnerships (CPP) to prepare and publish a Local Outcomes Improvement
Plan (LOIP) which: sets out the local outcomes which the CPP will prioritise for improvement to
reduce inequalities and add maximum value to each community, and; identifies smaller areas within
the local authority area which experience the poorest outcomes, leading to Locality Plans to
improve outcomes on agreed priorities for these communities being prepared and produced.
The vision for the West Dunbartonshire Council Local Outcomes Improvement Plan (LOIP) is to
develop a West Dunbartonshire where all of our residents are:
 Flourishing
 Independent
 Nurtured
 Empowered
The LOIP has the following strategic priorities and outcomes:
Page 125

Page 126

11
CPWD Strategic Priority CPWD Outcomes
A Flourishing West Dunbartonshire
 Our economy is diverse and dynamic creating opportunities
for everyone
 Our local communities are sustainable and attractive
 Increased and better-quality learning and employment
opportunities
 Enhanced quality and availability of affordable housing
options
An Independent West
Dunbartonshire
 Adults and older people are able to live independently in the
community
 Quality of life is improved for our older residents
 Housing options are responsive to changing needs over time
A Nurtured West Dunbartonshire
 All West Dunbartonshire children have the best start in life
and are ready to succeed
 Families are supported in accessing education, learning and
attainment opportunities
 Improved life chances for all children, young people, and
families
An Empowered West
Dunbartonshire
 We live in engaged and cohesive
communities
 Citizens are confident, resilient, and responsible
 Carers are supported to address their needs
A Safe West Dunbartonshire
 Improved community justice outcomes ensure West
Dunbartonshire is a safe and inclusive place to live
 All partners deliver early, and effective interventions targeted
at reducing the impact of domestic abuse
 Residents live in positive, health promoting local
environments where the impact of alcohol and drugs is
addressed
 Our residents are supported to improve their emotional and
mental health and wellbeing
Page 126

Page 127

12
3. Evidencing the Need to Tackle Empty Homes in
West Dunbartonshire
This Empty Homes Strategy has been informed by a clear understanding of the extent and nature of
empty homes across West Dunbartonshire Council and their impact on neighbourhoods,
communities, homeowners, and local residents. To achieve this, a robust evidence base has been
developed by the Council and partners detailing the number and types of empty homes across West
Dunbartonshire, as well as important contextual information on tenure estimates, unmet housing
need, the incidence of homelessness, the role of the private rented sector and housing condition
and quality issues.
This evidence base provides us with a strong understanding of the scale of empty homes as well as
the challenges faced in bringing them back into use. This analysis is crucial to informing our
decisions on how partnerships, investment and innovation should guide empty homes activity and
interventions. Our analysis of empty homes arising from this evidence, is detailed below:
3.1 Profiling Empty Homes
Table 2 details the scale of ineffective housing stock in West Dunbartonshire Council providing a
helpful measure of the number of homes which are not in use and are not contributing to meeting
housing need on a permanent basis. The table shows that empty homes, both ‘long-term empty
dwellings’ and ‘dwellings with unoccupied exemptions,’ account for 2.9% of all dwellings in West
Dunbartonshire with less than 1% of the housing stock recorded as being a second home.
Housing Stock West Dunbartonshire Council
Total Dwellings 46,068
Long-term Empty Dwellings 494
Dwellings with Unoccupied Exemptions 848
Second Homes 19
Table 2: Housing Stock Scotland (NRS Household Estimates published June 2023)
3.2 Long Term Empty Homes
Table 3 sets out how levels of long- term empty and unoccupied dwellings in West Dunbartonshire
compare with levels in Scotland as a whole. The table shows that the overall levels of long-term
empty dwellings and dwellings with unoccupied exemptions in West Dunbartonshire are less than
the Scottish average. However, the percentage of unoccupied exemption figure is slightly higher
than the Scottish average.
According to the Scottish Government’s Housing Statistics 2022 & 2023: key trends summary 2 
West Dunbartonshire’s housing stock is predominately split between home ownership at 56% and
Registered Social Landlords and Local Authority housing stock at 37%. The private rented sector
only accounts for 6% of the housing stock. Less than 1% of the housing stock is a second home.
West Dunbartonshire has one of the lowest rates of home ownership, and we have one of the largest
percentages of local authority housing stock compared to other local authorities.
2 Annual+Charts+and+Tables+2024.xlsx (live.com)
Page 127

Page 128

13
% of dwellings
long term empty
(all)
% of dwellings
long term empty
(12 months+)
% of dwellings
unoccupied
exempt
% of Scottish
vacant housing
stock
West Dunbartonshire 2.9% 1.1% 1.8% 1.7%
Scotland 3.4% 1.7% 1.7% 3.4%
Table 3: Long term empty properties and unoccupied dwellings in West Dunbartonshire and
Scotland (NRS Households and Dwellings in Scotland published June 2023)
Table 4 illustrates the number of long-term empty dwellings and dwellings with unoccupied
exemptions in West Dunbartonshire (taken from Council Tax records in June 2024). The figures have
been broken into areas and it shows the numbers and percentage for each of the areas. According to
Council Tax records Alexandria and Dumbarton combined have over 1,000 more registered
properties for council tax. This is more than the combined Clydebank and Old Kilpatrick areas.
Collectively Alexandria and Dumbarton have a slightly higher proportion of empty properties.
Postcode
Long Term Empty
and unoccupied
dwellings
Total stock
% of homes that are long-
term empty and
unoccupied dwellings
% of housing stock
In West
Dunbartonshire
Alexandria 257 11493 2.2% 0.6%
Clydebank 508 19811 2.6% 1.1%
Dumbarton 389 12307 3.2% 0.8%
Old
Kilpatrick
37 2529 1.5% 0.1%
Total 1,191 46,140 2.6% 2.6%
Table 4: Long-term Empty Homes
The map below illustrates that empty homes are spread over the authority and are not concentrated in
one particular area.
Page 128

Page 129

14
Table 5 details the breakdown of homes in each Council Tax Band in West Dunbartonshire Council
with the highest levels of long-term empty homes and unoccupied exemptions. The table indicates
that bands A and B in all areas of West Dunbartonshire have the highest amount of long-term empty
properties and are therefore more likely to be flats, current and former Local Authority housing stock
and/or Registered Social Landlord housing stock. Where there are mixed tenure blocks of flats it
can be difficult for the Local Authority to get agreement from other owners to proceed with common
works, and for the Authority to meet its obligations to meet the Scottish Housing Quality Standards
in these mixed tenure blocks.
Geography Total
dwellings
%
Band
A
%
Band
B
%
Band
C
%
Band
D
%
Band
E
%
Band
F
%
Band
G
%
Band
H
Alexandria 257 2.8% 11% 3.2% 2.4% 1.8% 0.3% 0.1% 0%
Clydebank 545 16% 19% 4.3% 3.6% 2.0% 0.8% 0.3% 0%
Dumbarton 389 11.2% 12.8% 4.0% 2.4% 1.7% 0.2% 0.1% 0.3%
Total % 2.6% 30% 42.8% 11.5% 8.4% 5.5% 1.3% 0.5% 0.3%
Table 5: Number and % Empty Properties by Council Tax Band
Table 6 breaks down all empty homes into the length of time they have been empty. From the table
we can conclude that the majority of empty homes within West Dunbartonshire have been empty for
under 3 years. The next category of empty homes is those empty between 5- 10 years. The longer
a home is empty the harder it is to bring it back into use.
West
Dunbartonshire
Alexandria Clydebank Dumbarton
Length of time empty No. of
Empty
Homes
% of
Empty
Homes
No. of
Empty
Homes
% of
Empty
Homes
No. of
Empty
Homes
% of
Empty
Homes
No. of
Empty
Homes
% of
Empty
Homes
6-12 months 187 15.7% 64 5.4% 60 5.0% 64 5.4%
1-2 Years 180 15.1% 17 1.4% 84 7.1% 79  6.6%
2-3 Years 139 11.7% 79 6.6% 47 4.0% 13 1.1%
3-4 Years 15 1.3% 5 0.4% 7 0.6% 3 0%
4-5 Years 10 0.8% 2 0.2% 5 0.4% 3 0.3%
5-10 Years 65 5.5% 21 1.8% 35 2.9% 9 0.8%
10 Years + 18 1.5% 14 1.2% 0 0% 4 0.3%
Table 6: Empty Property Timescales
While unoccupied exemptions include properties which are empty and unfurnished for less than 6
months, local authority dwellings awaiting demolition, and some other homes empty for less than six
months; the term also covers privately owned properties that are empty due to the property being
repossessed, the death of a previous owner, the owner being in long term care or detention,
dwellings last occupied by charitable bodies, dwellings empty under statute and some other
privately owned homes that have been empty for six months or longer.
Some of the reasons for properties being empty in West Dunbartonshire are detailed in table 7. The
main reason for property being empty in West Dunbartonshire is due to deceased owners. These
properties can be difficult to bring back into use particularly where the person has died intestate.
The family can find the situation difficult to deal with due to emotional attachment, meaning they are
often reluctant to address the empty home. In situations like this it can take a considerable amount
Page 129

Page 130

15
of time and perseverance from the Empty Homes Officer to get the property brought back into use, if
at all.
Another issue is where owners have been taken into care, leaving their home empty. In many cases
the property will lie empty until either someone acting on the behalf of the owner is legally permitted
to act on behalf of the owner and takes action to sell the home, or the owner dies.
If brought back to use, these properties may contribute towards delivery of national policy outcomes
and LHS priorities. However, there is a high likelihood of them remaining empty without Empty
Homes Officer intervention. Table 7 provides an indication of the number of unoccupied exemptions
in West Dunbartonshire that may fall into these categories.
Property Description No. Empty Properties
All unoccupied exemptions; of which
Deceased Owners 271
Under renovation 3
Held for minister 5
Provides/receives care 58
Repossession 5
Receiving empty home discount (over 6months
empty)
114
Other 11
Table 7: Unoccupied Exemption Description
3.3 Housing Need and Demand
Empty homes activity contributes to increasing housing supply to meet the demand for affordable
and market housing in West Dunbartonshire. Bringing empty homes back to use can also support
West Dunbartonshire to meet its statutory duty to the prevent homelessness wherever possible and
to mitigate the impact of homelessness where it cannot be prevented and increase provision of
specialist housing units across categories such as wheelchair, amenity and sheltered.
West Dunbartonshire Local Housing Strategy (2022-2027) forecasts the housing estimates for
market and affordable housing, for the period 2012-2029. On average West Dunbartonshire needs a
minimum of 80 new social homes per annum and 150 private homes per annum. Returning empty
homes to use can help to relieve some of the housing pressures within the Council area. This is
important when we consider that West Dunbartonshire declared a housing emergency in May 2024.
3.4 Homelessness
Tackling homelessness has been a focus of Scottish Government policy and the legal and
regulatory framework which has been put in place means that Scotland has some of the strongest
rights in the world for anyone experiencing homelessness.
Local authorities have a statutory duty:
• to provide advice and information about the prevention of homelessness
Page 130

Page 131

16
• to carry out a robust homelessness assessment within 28 days
• for the provision of suitable temporary accommodation for those who require it
• to secure the provision of permanent accommodation when assessed as homeless.
• to assess support needs for those found to be “homeless or threatened with
homelessness unintentionally” and who we have reason to believe requires a support
assessment.
West Dunbartonshire declared a housing emergency in May 2024 due to the demand on its housing
services and the increasing use of temporary accommodation resulting in breaches of the
unsuitable accommodation order.
Table 8 provides a summary of the homeless applications received by West Dunbartonshire and
Scotland as a whole.
Applications 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24
West Dunbartonshire 1037 1022 1053 1205 1217 1095
Scotland 36,778 37,053 34,345 35,759 39,006 40,685
Table 8:
Homeless Applications
Table 9 provides us with the 5 main reasons for persons seeking assistance from the Homeless
Team. The most common reason is for those being asked to leave their accommodation and often
this can be attributed to a parent asking a young person to leave, an example of this could be the
home is overcrowded, or their relationship has become untenable.
Main Reasons for Homeless
Applications
2018-
19
2019-
20
2020-
21
2021-
22
2022-
23
2023-
24
Asked to leave 264 263 291 383 419 367
Dispute within household /
relationship breakdown: non-violent 185 153 245 229 228 229
Dispute within household: violent or
abusive 169 215 233 245 212 187
Other reason for leaving
accommodation / household 135 81 78 83 92 72
Discharge from prison / hospital /
care / other institution 45 49 34 45 49 51
Table 9: Main
Reasons
3.5 Temporary Accommodation
Table 10 provides us with the details of the demand for temporary accommodation. This shows an
increase for temporary accommodation which affects the availability of housing stock. There has
been an increase on the number of persons being placed in bed and breakfast accommodation
breaching the Unsuitable Accommodation Order. This has been reported to the Scottish Housing
Regulator.
Use of Temporary
Accommodation 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24
West Dunbartonshire 988 1026 1070 1176 1173 1224
Page 131

Page 132

17
Table 10: Use of temporary
accommodation
3.6 Private Rented Sector
West Dunbartonshire Council has a relatively small private rented sector accounting for around 6%
of the housing stock. A Help to Rent scheme was introduced to help clients with an identified
housing need, access the private rented sector by providing the initial deposit. The amount of the
deposit payable is limited to the Local Housing Allowance rates for the relevant size of
accommodation. Many private lets charge considerably more than the local housing allowance
rates, and this can be a barrier to clients on lower incomes accessing the private rented sector.
However, not all clients require assistance with the deposit and the numbers below cover all clients
housed in the private rented sector.
Homeless Outcome 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24
Private Rented Tenancy 10 20 26 18 7 19
Table 11: Private Rented
Sector
Page 132

Page 133

18
4. Local Action, Challenges & Barriers in Tackling
Empty Homes
As well as evidencing the need to tackle empty homes in West Dunbartonshire the Empty Homes
Strategy builds upon the activity and interventions which have succeeded in bringing empty homes
back into use; as well as specific local challenges and barriers to tackling empty homes.
The Strategy therefore builds on successes that have been achieved by projects and initiatives
within West Dunbartonshire as well as innovation in empty homes activity across Scotland, other
parts of the UK and elsewhere as the basis of piloting or programming future activity.
4.1 Empty Homes Projects and Initiatives in West Dunbartonshire
West Dunbartonshire has incorporated the following initiatives to help bring empty properties back
into use: -
Buy Back Scheme – this is where we can purchase former local authority housing stock, and we
will also consider purchasing other stock that meets tenant demand for the style, type, and location
of the house. The Empty Homes Officer can identify long term empty homes that could be suitable
as buy-backs.
Matchmaker Scheme – this is where owners can register their home for sale, and we then try to
match the property to prospective purchasers who have also registered for the scheme. Owners will
receive the details of the interested parties and they can then decide who they wish to contact to
arrange a viewing of the property. This allows the owner to remain in control of the discussions and
sale of the empty home.
Empty Home Loan – this is a fund of £150,000 that West Dunbartonshire received from the
Scottish Government. As the loan was unused a survey was issued to empty homeowners. The
results of the survey indicated that the main reason for the loan being unused was that the criteria
was too restrictive. A loan variation request has been sent to the Scottish Government and we await
their response.
Help to Rent Scheme – this is where the Empty Homes Officer can provide assistance to clients
interested in the private rented sector. It is another tool that can be used to encourage homeowners
to return their home to use.
Town Centre Regeneration – The Empty Homes Officer will be working closely with colleagues in
the Regeneration Team to provide support to engage with empty homeowners for the purposes of
improving the buildings in the Town Centre conservation area.
Council Tax - The Empty Homes Officer works closely with colleagues in Council Tax and
Corporate Debt to ensure that any outstanding debt can be collected, where appropriate.
Compulsory Purchase Orders - The Scottish Government are keen for local authorities to use
compulsory purchase orders to bring empty homes back into use. However, Compulsory Purchase
Orders will be viewed as an option of last resort for properties that are structurally unsound, unsafe,
or are otherwise putting communities at risk but we will always seek to work with owners and
landlords before taking a CPO forward.
Compulsory Sale Orders – the Scottish Empty Homes Partnership (SEHP) has been advocating
for the Scottish Government to introduce Compulsory Sale Orders for some time. In the SEHP
Page 133

Page 134

19
Annual Report 2023-2024 they continue to recommend the introduction of Compulsory Sale orders
and Compulsory Rental Orders as tools to bring empty homes back into use. West Dunbartonshire
Council will support this initiative if it becomes available.
Page 134

Page 135

20
Case Study 1
This semi-detached property had been empty since 2015.
The owner had been admitted to hospital and while the house was empty there was a flood at the
property causing extensive damage. The owner did not have the funds to repair the damage and
was unable to occupy the property on their release from hospital and moved in with a friend.
The Empty Homes Officer (EHO) received complaints about vermin in the garden and the general
condition of the garden and traced the owner’s whereabouts from Council Tax records. The owner
engaged for a while and was keen to sell but then we had the arrival of the pandemic, lockdowns
and contact was lost.
After several visits and correspondence issued, the owner finally engaged with the EHO late 2023.
By this time, the owner’s health had deteriorated, and they informed the EHO that they were unable
to get out and about. The owner agreed to allow their friend to act on their behalf. The friend and
EHO visited the empty home and discussed the options available. The friend agreed the house
would have to be sold as the owner did not have the funds available to get the house up to standard
for them to live in, but they were not interested in selling at auction. Information about local estate
agents was provided to the owner.
Soon after a further visit was made to discuss the owner’s decision. The owner confirmed that they
had been in contact with a developer and had accepted an offer with the sale due to conclude in a
matter of weeks.
The EHO kept in contact with both the owner and the developer during the house sale which
concluded in January 2024. Information about VAT savings were shared with the developer.
The developer has since renovated the house to a high standard with the work completed in April.
The house was quickly put back up for sale and sold at the closing date. The house will now be
occupied for the first time in 9 years.
Before Renovation After Renovation
Page 135

Page 136

21
Before Renovations
Case Study 2
This end terrace is a former West Dunbartonshire Council property and has been empty since 2014.
The owner had moved to receive care and then passed away. The Empty Homes Officer contacted
the deceased owner’s legal representative who advised they were unable to take any action
regarding the empty house as they required the court to appoint an executor; they also advised that
this was a complicated estate. The legal representative advised that once an executor was
appointed, they would then have to appoint genealogists. The Empty Homes Officer kept in contact
with the legal representative for updates and they confirmed the intention was to sell the house
once the estate was approved by the court. The Empty Homes Officer shared information about the
buyback scheme, and they confirmed the executor wanted to pursue this. The Empty Homes Officer
liaised with the Buyback Lead Officer who confirmed that this house met the criteria for a buyback
and would be considered for purchase.
The Empty Homes Officer met with the executor who confirmed their intention to proceed with the
buyback scheme, however the court had still to legally appoint them as the executor. Due to further
delays and complications the executor was not appointed until earlier 2024.
The house has now been purchased by West Dunbartonshire Council and is now being renovated,
and once complete will provide social housing for someone with the relevant housing need.
Page 136

Page 137

22
4.2 Challenges and Barriers to Tackling Empty Homes
There are a number of key challenges and barriers to tackling empty homes in West Dunbartonshire
which require to be proactively addressed by the development and delivery of this Empty Homes
Strategy.
Engagement. It can be difficult for Empty Homes Officer to get engagement from the empty
homeowner and for the empty homeowner to remain in contact with the Officer.
Scale of Empty Homes. Empty Homes are identified through council tax reports where a discount
or exemption has been awarded to the council tax account either as a long-term empty home or an
unoccupied dwelling. However, not all long-term empty homes are reported, and we plan to
introduce an online reporting form where members of the public can easily access the form and
provide details of the empty property.
Tracing Owners. Tracing owners can be particularly challenging. We have a service agreement
with two genealogist companies who will try to trace owners on our behalf. There is no charge for
this service. The Empty Homes Officer also has access to a system used by many British local
authorities to try to trace owners.
Relevant Information. The Empty Homes Officer ensures that the suite of information leaflets
available for empty homeowners are kept up to date. The leaflets range from information about
supplier discounts to the possible VAT savings for works being carried out to empty homes, which
can result in considerable savings for the homeowner.
Vandalism and Antisocial Behaviour. Empty homes are often a blight on the local community and
can attract unwarranted attention causing the empty home to become a concern to those living
within the neighbourhood of the empty home. The Empty Homes Officer will work closely with
colleagues in the Antisocial Behaviour Team and Environmental Health where complaints of
antisocial behaviour around empty homes have been identified.
Common Repair Works. An empty home can be located within a tenement flat or adjoined to other
houses with a common interest i.e. chimneys, roofs. If the empty home is not being maintained the
deterioration of the property can affect the adjoining properties. Homeowners may be unable to
trace the absent owner to discuss the common works required. Disputes over common repairs are
relatively common for empty properties.
Financing Repairs. Many empty homes require significant works to bring it up to the repairing
standard and many owners do not have the financial resources to carry out the necessary works.
With recent increases in the cost of both materials and labour following the pandemic, this can have
a negative effect on the owner being able to afford the repairs.
These challenges have been identified through the development of the empty homes evidence base
and by engaging with local partners and stakeholders involved in empty homes activity.
Some of the key local barriers to developing and implementing a strategic approach to empty
homes includes:
• Resources: West Dunbartonshire Council received funding for an empty home loan fund but
to date the loan has not been used. A survey was conducted, and it concluded that
homeowners felt the loan was too restrictive. A loan variation has been sent to the Scottish
Government and we await their decision.
Page 137

Page 138

23
• Legal complexities:- Challenging cases where owners can’t be traced, or ownership is in
dispute can be extremely time consuming.
• Legal or financial constraints - West Dunbartonshire Council will consider using
Compulsory Purchase Orders, but it will be viewed as an option of last resort for properties
that are structurally unsound, unsafe, or are otherwise putting communities at risk but we will
always seek to work with owners and landlords before taking a Compulsory Purchase Order
forward.
• Council Tax Increased Empty Home Levy – West Dunbartonshire Council had a
discretionary policy whereby owners could receive discretion from the increased levy for a
set period of time. In December 2022, this policy ended. The ending of this policy may have
prevented owners from completing work to bring the property up to habitable standard.
Since April 2024, the Scottish Government has amended the Local Government Finance
(Unoccupied properties etc. (Scotland) Act 2012, so all new owners no longer automatically
have the increased council tax levy applied to the account, they are excluded from the
increased levy for 6months.
• Lack of awareness of empty homes work and the opportunities for advice and
assistance: - Greater marketing and communication to raise awareness and encourage
engagement would be beneficial.
• Shortage of tradespeople or materials: - Homeowners who are engaging with the Empty
Homes Officer have reported that they have to wait some time for tradespeople to be
available, and that the costs for both labour and materials have increased significantly.
Page 138

Page 139

24
5. The Strategy for Tackling Empty Homes in West
Dunbartonshire
This Empty Homes Strategy sets out how the Council and partners will work together over the next
5 years to proactively tackle the impact of empty homes on communities, neighbourhoods,
homeowners, and residents across West Dunbartonshire.
To achieve this, the following aim has been set for the Empty Homes Strategy:
• TO RETURN 125 EMPTY PROPERTIES BACK INTO USE OVER THE TERM OF THE
STRATEGY
This aim provides the overarching vision for empty homes in West Dunbartonshire. It sets out what
the Council and partners want to achieve in tackling empty homes and reflects the level of ambition
agreed with delivery partners. It also reflects the strategic aim of the Scottish Empty Homes
Partnership to ‘bring as many privately-owned empty homes back into use as possible.’ It will also
reflect the ambitions of the Local Housing Strategy to provide safe and vibrant communities, 20-
minute neighbourhoods as existing properties may already fall within this criteria, it may also help to
provide specialist housing i.e. wheelchair accessible in areas where we do not have this type of
accommodation.
The key issues identified to bring empty homes back into use are detailed below:
Help alleviate the effects of homelessness and the waiting list within West Dunbartonshire
West Dunbartonshire has declared a housing emergency due to the increase in housing demand
and the lack of accommodation available. Homeless and waiting lists figures have been increasing
and although there continues to be a new build programme, this is not the only option to reduce
these numbers. Returning empty homes into use can be another tool to reduce these numbers.
Support Town Centre Regeneration
The Empty Homes Officer works closely with the Regeneration team to help locate absent owners.
As the Council Tax Legislation prevents the sharing of information with the Regeneration Team, the
Empty Homes Officer will work as an intermediary to trace these absent owners and attempt to
engage with them. The Empty Homes Officer can also provide information to allow any necessary
works to have reduce rated, and sometimes zero rated, VAT which will have a significant financial
benefit for those undertaking significant works.
Reduce the number of long-term empty problem properties.
The Empty Homes Officer receives reports from Council Tax bi-annually for all properties with an
empty home exemption/discount and for those properties where the owner has died, repossessions,
housing to be demolished etc. The purpose of these reports is to allow the Empty Homes Officer to
contact the owner(s). Initially a letter and empty home survey will be issued and when returned this
allows the Empty Homes Officer to tailor any support identified from the survey. Cases remain open
until the house has been returned to use.
Collaborate with the Buy Back Lead Officer to assist with bringing long term empty homes
back into use.
The Local Housing Strategy aims to acquire housing that can increase the stock of WDC social
housing and potentially assist with bringing empty homes back into use. By working with the Buy
Back Lead Officer suitable long term empty homes can be identified and discussions can be had
with the owners where appropriate.
Page 139

Page 140

25
6. Empty Homes Action Plan
The following Action Plan has been developed to enable the Council and partners to plan, deliver, monitor, and evaluate the impact of empty
homes activity over the next 5 years. It sets a framework for partnership working and investment that reflects strategic objectives and creates a
route map for delivering the aim of the Empty Homes Strategy.
The Action Plan sets out a range of milestones detailing the activity associated with implementation. The Action Plan, activities and targets will
be reviewed annually to ensure partners are able to respond flexibly to changes in need across West Dunbartonshire.
Objective 1 Maximise the re-use of Empty Homes Milestones
Action – to return 125 empty properties into use over the term of the
strategy.
 Maintain a private sector database of empty homes.
 Receive bi-annual reports from Council Tax
 Work with Council Tax to ensure records are as accurate
as possible.
 Engage with the Council’s media team to highlight empty
homes and the support available.
 Ensure that the reporting of empty homes is easily
accessible.
 Review standard letters.
Objective 2 Help alleviate the effects of homelessness and the     Milestones
Waiting list in West Dunbartonshire
Action - Manage the Help to Rent Scheme for WDC  Work with private landlords to encourage them to
engage with the scheme.
 Report annually to the Housing and Communities
Committee
 Ensure appropriate staff are aware of the scheme and
how to refer.
Objective 3 Support Town Centre Regeneration     Milestones
Action - Engage with Planning and the Regeneration Team for town centre
improvements.
 Help to identify priority properties and assist with
reaching out to absent and long-term empty
homeowners.
 Maximise grant funding for owners where available.
Page 140

Page 141

26
Objective 4 Reduce the number of long term empty problem properties     Milestones
Action - Effective processes are in place to address properties that are in
serious disrepair.
 Identify the most appropriate course of action to
address issues with the empty home and instigate
enforcement action for those owners who fail to co-
operate.
 Influence the development of the Local Housing Strategy
with regard to the value in tackling empty homes in the
private sector.
 manage the Empty Home Loan fund.
 Identify and pursue potential sources of funding to
develop further empty homes incentive scheme
including with external organisations’ and partners
 Encourage owners to consider the matchmaker scheme
to bring their home back into use.
 Work with colleagues in Building Standards, Planning,
Environmental Health and Regeneration to address
problem empty homes.
Objective 5 Buy Backs   Milestones
Action - Collaborate with the Buy Back Lead Offi cer to assist with bringing long
term empty homes back into use.
 Promote the Buy Back scheme on the Empty Homes
webpages.
 Work with the Buy Back Offi cer to identify relevant
opportunities to purchase housing that meets the needs
and demands of WDC.
Page 141

Page 142

27
7. Monitoring Progress and Evaluating
The actions scheduled under each strategic objective, have been developed into the detailed Action
Plan along with milestones, in Chapter 6. It also sets out resources and partner responsibilities to
guide implementation and delivery. This Action Plan provides a strong basis for monitoring progress
in implementing the Empty Homes Strategy on a regular basis.
In order to monitor progress and achievements the following monitoring arrangements will be
adopted:
• Number of empty homes returned to use each year of the strategy.
• Annual updates of Action Plan where appropriate
• Number of buy backs returned to use each year.
7.1 Evaluation
It is important to ensure that the evaluation of the Empty Homes Strategy is reported to relevant
partners and stakeholders as well as internally within the local authority. This evaluation reporting
will include:
• demonstrating progress against actions that contribute to the LHS, RRTP, Community Plan
and Corporate Plan
• the wider partnership frameworks which are achieving shared or national objectives.
This regular programme of evaluation with provide the Council and partners with an opportunity to
understand:
• the progress that has been achieved
• current position
• delivery improvements required.
This approach will provide an assessment of the successes and challenges associated with tackling
empty homes and provides a transparent approach to improvement planning and scrutiny.
8. Consultation & Engagement
Consultation has been central to the development of this strategy and views were sought from the
West Dunbartonshire Tenants & Residents Organisiation (WDTRO), staff, other relevant
departments, and the Scottish Empty Homes Partnership. A formal consultation process for the draft
strategy was carried out from 28th June 2024 to 30 September 2024 and the Empty Homes
Strategy reflected the views of partners and stakeholders on the development of priorities and
actions within the Strategy.
Page 142

Page 143

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 20 November 2024
___________________________________________________________________
Subject:     West Dunbartonshire Housing Emergency Declaration Action Plan
1. Purpose
1.1 The purpose of this report is to provide members with an update on the Housing
Emergency Action Plan (HEDAP) which was formulated to address the
emergency following the Council’s housing emergency declaration on 1st May
2024.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Note the progress to date and the implementation of the key actions of the
Housing Emergency Declaration Action Plan as summarised in section
4.1 – 4.6 of this report and in the action plan update within Appendix 1 of
this report;
(ii) Note the intention to hold a Housing Summit in early 2025 and that the
Chief Officer, Housing and Employability will continue to bring an update
report to future Housing and Communities committee meetings regarding
the housing emergency declaration.
3. Background
3.1 On 1 May 2024 Housing and Communities Committee unanimously agreed to
declare a Housing Emergency in West Dunbartonshire Council (WDC). The
reasons behind the motion being raised was due to the extreme pressures facing
housing and homelessness service in WDC.
3.2 This was despite positive achievements of the service to help manage the acute
housing need in West Dunbartonshire including the following:
 262 households prevented from experiencing homelessness,
 Significant progress in reducing the number of empty homes (council
voids)
 The construction of new council homes at the following development sites
Clydebank East, Mount Pleasant, Pappert and Gilmour Avenue.
3.3 Despite this, housing demand has increased rather the expected reduction and
therefore and the following metrics highlight the pressures on the housing and
homelessness systems within West Dunbartonshire.
ITEM 12
Page 143

Page 144

 Over five thousand on the Council’s housing waiting lists,
 274 households in temporary accommodation awaiting an offer of
permanent housing, of those households eighty-nine have children within
them, and
 the anticipation of more than 1100 new homeless assessments to be made
during the 2024/25 reporting period.
3.4 As reported previously to committee the Council has been unable to fulfil all our
statutory duties under homelessness legislation and has incurred 68 breaches of
the Unsuitable Accommodation Order (UAO) following 274 households being
placed in Bed & Breakfast Accommodation during 2023/24.
3.5 The increased supply of new social homes is the key element to help address the
demand pressures, The funding cut to the wider Affordable Housing Supply
Programme funding of around 24%, significantly contributed to the Housing
Emergency Declaration.
3.6 West Dunbartonshire Council were the fifth local authority to declare a housing
emergency following declarations made in Argyll and Bute, Edinburgh, Glasgow,
and Fife. Since the West Dunbartonshire declaration, a further seven local
authorities have followed suit and made a housing emergency declaration (South
Lanarkshire, West Lothian, Angus, Scottish Borders, Dumfries and Galloway,
Aberdeen and East Renfrewshire). Therefore 12 of 32 Scottish local authorities
have declared housing emergencies, including four of the six housing stock
transfer authorities.
3.6 Significantly on the 15th of May 2024, the Scottish Government declared a
National Housing Emergency in the Scottish Parliament although the
implications of this are not known at the time of writing.
4. Main Issues
4.1 The action plan has four main themes they are as follows:
 Theme 1 - Deliver and maintain More Homes - West Dunbartonshire
approach to the delivery of affordable housing,
 Theme 2 - Make Best Use of Existing Stock,
 Theme 3 - Enhancing Housing Access and the prevention of
homelessness,
 Theme 4 - Strengthen the Financial viability and capacity of the Housing
Revenue Account and associated Housing and Homelessness budgets.
Page 144

Page 145

4.2 There have been three Project Board meetings in total since the declaration.
Some progress to date includes key performance indicators being agreed to
help monitor the end to the emergency.  To date there has been progress on all
the 61 actions as follows.
Completed
4
In progress/on track
57
Missed target date
0
The project board has agreed further progress will be made via existing
governance arrangements and reported to the Housing Emergency Project
Board.  A full progress report is attached as Appendix 1 of this report and some
highlights are summarised in the sections below: - 
Deliver and maintain More Homes - West Dunbartonshire approach to the
delivery of affordable housing.
4.3 Key actions include the Housing Convenor having written to the Housing
Minister to reinstate the funding cut to the Affordable Housing Supply
Programme funding and to express disappointment to the Scottish
Government regarding our funding allocation of the £40 million acquisition
funding (£309k (0.77%)) and temporary accommodation funding of £2million
(£15k (0.75%)) and our concerns over the distribution formula used which
favoured council areas with higher population levels rather than the
homelessness pressures.  The homelessness statistics bulletin published in
September highlighted that West Dunbartonshire continues to have the highest
rate of homelessness in Scotland at a rate of 235 homelessness presentation
per 10,000 people considerably higher than the national average figure of 131.
The Council’s new Strategic Housing Investment Plan has also been
developed and will be presented to the Housing and Communities Committee
in November 2024.  Excellent progress has also been made with respect our
More Homes approach and the first handovers have been achieved at the
Clydebank East development site.
Make Best Use of Existing Stock
4.4 Progress includes the action to work in partnership with others to address
delays caused with energy suppliers and the introduction a pre letting process
for transfer applicants. Both have made significant progress and are near
completion.  A new Empty Homes Strategy has also been developed and will
be submitted to the Housing and Communities Committee in November.
Enhancing Housing Access and the prevention of homelessness
4.5 Progress has included the establishment of the Access to Housing have been
which will be used to drive forward these actions within this theme. The transfer
Page 145

Page 146

led approach for new builds has been established and is being rolled out
therefore is now complete.  The online common housing application form has
made significant progress and nearing completion once formal approval is
given by our Registered Social Landlords (RSL) partners.
Strengthen the Financial viability and capacity of the Housing Revenue
Account (HRA) and associated Housing and Homelessness budgets.
4.6 These actions are being discussed and taken forward via the HRA Value for
Money group with the key aim of strengthening the Housing Revenue Account
to help deliver housing and regeneration priorities. 
4.7 To further help tackle the housing emergency we plan to host a housing
emergency summit in early 2025.  The aim is to gather key stakeholders in a
local and national context to strengthen partnership working and to find further
solutions in the short and long term. 
4.8 It has also been agreed for our RSL partner involvement their contribution will
come through the Strategic Housing Provider Forum and as a result the
frequency of these meetings have been increased to ensure accelerated
progress.
4.9 In addition to the actions that have formulated the Housing Emergency
Declaration Action Plan a number of key performance indicators have also
been introduced and will be reported to the Housing Emergency Project Board
on a quarterly basis.  These KPIs are designed to help signify the ambition to
exit the current housing emergency status within West Dunbartonshire.
5. People Implications
5.1 Initial analysis of the action plan do not indicate any people implications.
However, many of the actions involved are additional tasks not within current
remits therefore may lead to additional staffing resources which we would seek
for approval at futures committees if required.
6. Financial and Procurement Implications
6.1 The Housing Emergency Declaration Action Plan (HEDAP) will need to be
considered within the context existing resources available to West
Dunbartonshire Council across both the General Fund and Housing Revenue
Account (HRA). There is currently no additional Grant or Subsidy funding
available to Councils because of declaring a Housing Emergency.
6.2 The Housing Emergency Project Board will consider how existing resources
can be utilised to ensure delivery of the HEDAP. This will include a review of
Core Budgets and any Temporary Funding Sources which may be utilised.
6.3 If we are unable to increase supply and reduce demand will lead to continued
pressures on temporary accommodation and ultimately Bed & breakfast use
which has financial implications. Any funding reviews and subsequent
implications would be brought to future committees. 
Page 146

Page 147

6.4 There are no procurement implications to note.
7. Risk Analysis
7.1 Regular breaches of statutory homelessness duties partly triggered the
declaration of the Housing Emergency, and it is highly probable these will
continue without focussed, cross Council and Partnership action led through
the Housing Emergency Project Board.
7.2 The Council is also likely to experience significant legal, regulatory, and
reputational risk due to shortages of housing supply and related services.
Mitigation of these risks are included within the HEDAP, and these will be
managed through the Housing Emergency Project Board.
8 Environmental Sustainability
8.1 The delivery of new homes is within the approved More Homes zero carbon
approach. Our current and future approach to strategic housing asset
management will continue to prioritise a ‘zero carbon’ approach to decision
making and deliverability and this will be done the aims of the Housing Asset
Management Strategy and the Council’s Climate Change Strategy.
9. Equalities Impact Assessment (EIA)
9.1 An EIA has been carried out and there are no negative equalities impacts due to
this update.  A separate EIA screening will be conducted for any policy changes
because of the implementation of the HEDAP.
10. Consultation
10.1 The draft Housing Emergency Declaration Action Plan (HEDAP) was consulted
with a range of key stakeholders including the West Dunbartonshire Tenants
and Residents Organisation. The implementation of the HEDAP is predicated
on a consultative and collaborative focus and several key stakeholders are
represented on the Housing Emergency Project Board.
11. Strategic Assessment
11.1 Having considered the Council's strategic priorities, this report contributes
significantly to all strategic priorities.
Peter Barry
Chief Officer, Housing and Employability
Date: 6th November 2024
___________________________________________________________________
Person/s to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk
Page 147

Page 148

Claire McKay – Housing Development Co-ordinator,
Housing Development and Homelessness Team, Housing
and Employability, email: Claire.Mckay@west-
dunbarton.gov.uk
Appendices: 1. Housing Emergency Action Plan, October 2024
Background Papers:   Housing Emergency Declaration, Housing and Communities
Committee, May 2024
Report to Housing and Communities Committee; Housing
Emergency Action Plan
Homelessness Statistics Bulletin, Scottish Government,
September 2024
Wards Affected:  All
Page 148

Page 149

Housing Emergency Declaration action plan
Generated on: 06 November 2024
Report Layout: Housing Scorecard with Action and PI codes
Icon Name
1 - Deliver and maintain More Homes - West Dunbartonshire approach to the delivery of affordable housing.
Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
Issue letter to the Housing
Minister highlight the
Housing Emergency
declaration and requesting
that the full AHSP is
restored.
30-Aug-
2024
Yes Letter issued to
minister - covering
Acquistion funding and
the new temp
accommodation
funding and concerns
over the forumla used
to distrubute signed
off by Convener
Highlight within SHIP and
Programming Process the
impacts of cuts to the AHSP
31-Oct-
2024
Yes Draft SHIP submitted
to Scottish
Government
Participate in a number of
Member and Officer groups
and influence agenda to
maximise AHSP budget
settlement
31-Mar-
2025
No
H/HEDAP/2024/
001 Continue to
lobby SG for
increase in AHSP
funding in
partnership with
COSLA/SOLACE/
ALACHO
31-Mar-
2025
Review impact of discussions
with Scottish Government
31-Mar-
2025
No
John Kerr
Presentation to West
Dunbartonshire Strategic
Housing Providers Forum
30-Aug-
2024
Yes Complete and call for
sites requested
Carry out prioritisation
exercise
21-Oct-
2024
Yes Completed milestone
and included within
SHIP
ITEM 12 -
APPENDIX 1
Page 149

Page 150

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
002 Refresh
Strategic
Housing
Investment Plan
to ensure the
delivery of new
homes to meet
acute housing
need in West
Dunbartonshire
29-Nov-
2024
Draft SHIP approved by More
Homes Project Board
31-Oct-
2024
Yes Draft SHIP approved
by More Homes Board
(October), submitted
to Scottish
Government pending
formal Housing and
Communities
Committee Approval
John Kerr
H/HEDAP/2024/
003 Deliver new
Strategic
Housing
Investment Plan
31-Oct-
2024
Draft submitted to SG.
Report seeking
approval going to
HACC on 20
November 2024.
Jamie Dockery
H/HEDAP/2024/
004 Deliver the
Council's
approved new
build
programme for
24/25 helping
meet the
identified
housing need.
01-Mar-
2025
New build programme
remains on track with
sites in operation at
Clydebank East,
Mount Pleasant,
Pappert and Gilmour
Avenue
Dawn Conner
SHIP to be prepared and
draft submitted to the
Scottish Government by
October 31
31-Oct-
2024
Yes Milestone achieved,
SHIP expected to
receive formal
approval from Housing
and Communities
Committee in
November
Page 150

Page 151

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
Develop and acquire More
Homes Project Board
approval for proposal to
ensure the acceleration and
prioritisation of new home
delivery.
31-Dec-
2024
No More Homes Project
Board approved the
acceleration of the
Queen Mary Avenue
development (October
2024).  Assessments
being made in terms
of other approved and
committed projects.
H/HEDAP/2024/
005 Examine
ways to
accelerate new
build delivery
considering
housing
emergency
declaration
31-Dec-
2024
Develop revised Strategic
Local Programme in
partnership with Scottish
Government
Yes Programme in place
and shadow
programme identified
and will be confimed
within forthcoming
SHIP
John Kerr
17 buy backs completed so
far this financial year
(11 Larger properties 3 bed
+ & 6 non larger 1 & 2 beds)
We have a further 8 under
offer awaiting completion
(2 Larger properties 3 bed +
& 6 non larger 1 & 2 beds)
Yes
H/HEDAP/2024/
006 Scale up
and extend the
Buy Back
Scheme to meet
the key housing
demand factors
including the
provision of
temporary
accommodation
31-Oct-
2024
The buyback scheme
has been scaled up
through £10m of
additional funding
over the next 5 years
in addition for
2024/25 we have
been awarded an
additional £309k to
secure buyback
acquisitions that
directly take
households out of
temporary
accommodation, our
stated priority is
families with children.
We have completed 13 buy
backs so far in this financial
year, with another 9
properties under offer,
awaiting completion. 7 of
these properties have been
let so far, with 4 of the lets
going to homeless
applicants.
Yes Laura Hanna
Page 151

Page 152

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
Participate in Housing
Investment task force
discussions
25-Sep-
2024
Yes Annoucement of
£100m funding to
support delivery of
MMR which will allow
£500m investment
across Scotland. 
Proposals being
developed in West
Dunbartonshire which
will allow any
opportunities to be
realised
Continue to develop own
proposals in partnership with
external agencies and
potential investors
30-Nov-
2024
No Discussions ongoing
H/HEDAP/2024/
007 Explore
innovative
housing
investment and
partnership
models to
maximise
housing
investment
approaches
31-Dec-
2024
Proposal paper to More
Homes Project Board in
December to define policy
31-Dec-
2024
No This action may slip
into January
depending on the
Scottish Government
budget annoucements
John Kerr
H/HEDAP/2024/
008 In
partnership with
the Scottish
Government
review the
planning and
consenting
system
considering the
national housing
emergency to
increase the
scale and pace
of development
across all
tenures
31-Dec-
2024
Action being
progressed within a
wider national context
Peter Barry;
Alan Douglas
Detail development priorities
within SHIP
31-Oct-
2024
Yes Prioritisation exercise
carreid out as part of
SHIP process
Page 152

Page 153

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
009 Review HRA
resource
allocation across
the Council to
help
facilitate/deliver
new build
programme
31-Dec-
2024
This is a ongoing key
activity within the
More Homes Project
Board and Service
Manager will provide
an update report to
the Board in
December 2024
Housing Develop service
design to be completed
31-Dec-
2024
No
John Kerr
Approval for Gilmour Avenue
modular development
25-Sep-
2024
Yes Scottish Government
approval September
2024 and homes now
in development
Develop revised approach
based on review and share
with development partners
31-Dec-
2024
No
H/HEDAP/2024/
010 Explore an
approach to
develop modular
and other forms
of innovative
housing by
working in
partnership with
other housing
providers
31-Dec-
2024
Review Gilmour development 31-Dec-
2024
No
John Kerr
H/HEDAP/2024/
011 Examine the
capacity of the
HRA to deliver
agreed housing
ambitions
31-Jan-
2025
Action being
progressed and will
meet target Peter Barry
Participation in Scottish
Government trawl process
30-Sep-
2024
Yes Participation
confirmed
Special More Homes Board
scheduled for November to
look at the opportunities with
other service departments.
29-Nov-
2024
No
H/HEDAP/2024/
012 Engage with
public and
private sector
landowners to
increase the
HRA landbank
and support
development in
line with the
refreshed
Strategic
Housing
Investment Plan
31-Mar-
2025
Discussions ongoing
with one housing
developer re potential
for them to landbank
housing opportunities,
model to be explored
further.
Plan agreed at More Homes
Board to inform delivery
plans from 2025/26
31-Mar-
2025
No John Kerr
H/HEDAP/2024/ 31-Mar- Action planned to John Kerr
Page 153

Page 154

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
013 Review
Affordable
Housing Design
Standard
2025
commence in early
2025 and will conclude
within target
H/HEDAP/2024/
014 Increase
provision of Mid-
Market Rent
properties as a
viable housing
option for
homeless and
housing
applicants
30-Apr-
2026
Proposal is being
taken forward
following May
committee approval,
however we now await
clarity following the
Programme for
Government
annoucements
John Kerr
Icon Name
2 - Make Best Use of Existing Stock
Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
015 Continue to
Improve our
approach to
empty council
homes with a
strengthened
focus on
reducing void
time and letting
longer term
empty homes
and negating
any use of
unsuitable
accommodation.
31-Dec-
2024
Ongoing action being
taking forward within
wider improvement
plan.
Martin Feeney
Page 154

Page 155

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
Implement and monitor
measures to improve the
control and generation of non
essential repairs.
30-Aug-
2024
Yes Milestone complete
with on-going
monitoring in place.
Whilst training and
briefings have reduced
the throughput of
unjustified repairs;
monitoring is carried
out and reviewed at
weekly team
meetings.  
Based on performance and
progress made on reducing
the number of empty homes
agree to continue to monitor
and postpone any decision
on a fixed term moratorium.
27-Sep-
2024
Yes Milestone complete.
Progress made on
reducing the number
of empty homes to
end of September
without over reliance
on the use of sub
contractors and
overtime informed the
decision to postpone
any decision on a fixed
term moratorium to
not carryout non-
essential repairs. A
further review will be
completed before the
end of quarter 3 to
consider if this action
should be
implemented.    
Continue to implement
improvement actions in the
void management
improvement plan including
increasing productivity and
reducing the average cost to
bring a empty home back to
the Councils' relet standard.
29-Nov-
2024
No
Page 155

Page 156

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
016 Consider a
fixed term
moratorium on
non-essential
housing repairs
to focus activity
around bring
empty homes
back into use
20-Dec-
2024
Action on track for
completion by
extended target date.
New measure
implemented to
improve the
throughput of
unnecessary non-
urgent repairs,
improved
management of the
work carried in a void
property and
improved performance
and productivity has
provided necessary
evidence to confirm it
isn't necessary to
consider a fixed term
moratorium on non-
essential repairs at
this time. Monitoring
will continue and
consideration of the
introduction of this
measure will be taken
prior to the end of
quarter 3.    
Review evidence to make
final decision on a 3 month
(last quarter of 2024/2025)
moratorium on non-essential
housing repairs to focus
resources on the repair of
the Councils' housing
properties.
13-Dec-
2024
No
Martin Feeney
Complete review of
referral/communication
processes between void team
and Helptomove
30-Sep-
2024
Yes Review of existing
referral process
completed
Page 156

Page 157

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
Engage with Consumer
Scotland to discuss problems
encoutered and provide case
studies to support national
focus on holding energy
companies accountable to
resolve meter issues more
efficiently
30-Sep-
2024
Yes Completed, session
held with Consumer
Scotland with Housing
Operations and
Building Services
Reps.  Case studies of
longer term meter
void problems shared
to support national
discussions on the
matter to find resolve
Introduce new report from
heltp the move to identify
move in's with no end date
meter readings to enable
more accuarate billing
information
30-Sep-
2024
Yes Completed -
helpthemove now
send weekly reports
for ‘move ins’ with no
end meter reads. 
Introduce weekly monitoring
report for support worker to
track progress of complex
meter issues and update to
teams
30-Sep-
2024
Yes Completed and in
place.  Weekly
spreadsheet
introduced which
tracks/updates on
progress.  Shared as
part of weekly laison
void meetings
Page 157

Page 158

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
Review liaison arrangements
with Helpthemove ensuring
appropriate representation to
input to operational
challenges
30-Sep-
2024
Yes Action complete -
representation
reviewed and new void
reps added to laison
meetings, this now
includes HB, WDC
Support Worker and
void maintenance
officers
Meetings focus on
opeational challenges
and complex meter
problems to ensure
what help the move
are advising/assisting
us with the support
worker & HTM are
doing as quickly as
possible.
Develop escalation process
with helpthemove on more
problematic meter problems
30-Nov-
2024
No Helpthemove have
identified senior officer
in Scottish Power to
assist, OVO/SSE
covered under
Helpthemove contract.
Discussions underway
and complaints
submitted with
escalation to Ofgem
being progressed. 
Process map to be
developed to reflect
Review wider billing
arrangements process
30-Nov-
2024
No Discussions to be
progressed with
Building Services
colleagues to establish
current process and
any issues, thereafter
discuss with
helptomove
Page 158

Page 159

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
017 Develop a
process
including
exploring
potential
partnering
arrangements to
address lengthy
delays by
energy suppliers
in the reletting
process.
31-Dec-
2025
Explore other providers to
establish if can provide
additional support to
helpthemove arrangements
Yes Enquiries completed
with GEC, who
confirmed would
arrange for meter
installs on projects
subject to cost.  No
additional service to
helpthemove provided Nicola
Pettigrew
H/HEDAP/2024/
018 Accelerate
the reduction of
private sector
empty homes by
delivering a new
Long Term
Empty Homes 
Strategy
30-Nov-
2024
Seek HACC approval of new
strategy - aim to bring 25
properties per year back into
use
30-Nov-
2024
No Consultation ended
30/9/24
Draft strategy being
updated for HACC in
November 2024 Karen Rae
Carry put early consultation
with tenants to inform
revised Repairs Policy and
ensure tenant priorities are
delivered.
30-Jun-
2024
Yes Complete - early
consultation complete,
over 1000 responses
received and tenant
feedback will help
inform development of
revised policy. 
HRA Value for Money Group
to develop revised Repairs
Policy which will meets
tenant priorites and reflects
input from key stakeholders.
31-Aug-
2024
Yes Complete - draft
Repairs Policy agreed
and following further
period of consultation
approval for policy to
be sought from
Housing and
Communities
Committee in
November 2024. 
Page 159

Page 160

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
019 Deliver with
tenant
representatives
a new repairs
policy
30-Nov-
2024
Seek approval for revised
Repairs Policy from Housing
and Communities Commitee
November 2024.
20-Nov-
2024
No On track - report
prepared and will be
considered by
Committee 20 Nov
2024. 
Stefan
Kristmanns
H/HEDAP/2024/
020 Ensure new
repairs policy
achieves key
objectives
30-Nov-
2024
Implementation plan
developed and will be
delivered following
Committee approval
Martin Feeney
Review and agree the new
70% allocation to transfer
applicants for all new builds
30-Aug-
2024
Yes new protocol written
and agreed between
Housing operations
and Hoomeless
services.
ongoing allocations
discussion to complete
Review current transfer
incentive scheme
30-Nov-
2024
No
H/HEDAP/2024/
021 Review and
promote
Allocations
Policy flexibilities
and enhanced
Transfer
Incentive
Scheme linked
to the review of
the Housing
Allocations
approach
31-Dec-
2024
new media/drive for
downsizing etc
31-Dec-
2024
No
Claire McKay
Introduce notification to
Repair and Maintenance
Manager on voids properties
due for return on back of
transfer move in advance of
sign-up
30-Sep-
2024
Yes Completed -
introduced as part of
Clydebank East new
build development. 
This model will be
used for all future new
build sites
Introduce robust pre-
allocation house assessments
proess which embeds
ongoing discussions with
Building Services to highlight
condition of voids and
recharges as required
30-Sep-
2024
Yes Complete - Process
revised as part of
Clydbank East
development,  This
model/approach will
be used for all future
new build sites
Page 160

Page 161

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
Introduced homeless liaison
meetings in advance
handover dates to identify
existing WDC tenants with
open homeless case
30-Sep-
2024
Yes Completed and in
place - implemented
for Clydebank East
development, phase 1
underway with other
phases to follow.  This
model/approach will
be used for all future
sites.
Prepare lettings initiative
action plan
30-Sep-
2024
Yes Complete - action plan
shared and consulted
internally for
Clydebank East. 
Same model will be
used for future sites
Identify properties for each
quota and engage with
relevant teams to finalise
31-Oct-
2024
Yes Completed -
Clydebank East new
build, model/approach
will be same for future
sites
H/HEDAP/2024/
022 Actively
introduce a pre
letting process
initially linked to
the transfer led
allocation
process for new
build social
housing
31-Dec-
2024
Review house assessment
form to ensure capturing
relevant information via HO
mobile app
31-Dec-
2024
No Mobile app working
group established,
initial area of NTV in
place with other
service areas to
follow.  Next phase is
PTV and SM has
discussed house
assessment being
incorporated into this
action
Nicola
Pettigrew
Project board to agree
options for HACC following all
feasibility studies and
financial reviews
Linked to action H/RRTP/19-
24/064
30-Nov-
2024
No
HACC approval on options 28-Feb-
2025
No
Page 161

Page 162

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
023 Deliver the
recommendation
s from the
Supported
Housing Review
31-Dec-
2025
Action progressing as
planned, key initial
milestone on track.
Carry out procurement
exercise to meet new needs
and options agreed
31-May-
2025
No
Claire McKay
H/HEDAP/2024/
024 Carry out a
comprehensive
assessment of
our housing
stock to ensure
it can deliver the
key priorities
within the Local
Housing
Strategy
28-Feb-
2025
Action has its own
project plan which
remains on track to
deliver by February
2025
Jackie McRory
1000 Homes 31-Oct-
2024
Yes Achieved within
target
H/HEDAP/2024/
025 Continue to
roll out our
approach to
address
condensation,
dampness and
mould within our
homes through
the use of smart
technology that
strengthens
housing
management
31-Mar-
2025
We have almost
installed
environmental sensors
in 1000 homes and
four new BSOs have
been recruited to start
proactively responding
to dashboard.
2000 homes 31-Mar-
2025
No
Emily Dorrian
H/HEDAP/2024/
026 Deliver new
proactive
approach to
ensure our
housing stock
continues to
meet all
statutory
31-Mar-
2025
Proposal developed
and shared within
senior housing
team/Better Homes
Board
Initial Proposal developed 30-Nov-
2024
No
John Kerr
Page 162

Page 163

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
compliance
requirements
Obtain baseline data to
support VFM in promoting
mutual exchange options
with applicants
30-Sep-
2024
Yes Completed - BF has
obtained basic metrics
and ave saving woudl
be £2400 on MX
Review functionality and best
practice with HomeSwapper
30-Sep-
2024
Yes Completed
Introduce quarterly
marketing information via
social media, tenants news
to maximise awareness
29-Nov-
2024
No BF to progress and
share content with
Home Swapper
working group
Add opt our option to
housing application form
29-Nov-
2024
No Online application
form in progress to be
implemented, include
option as part of
revised form
Complete marketing
awareness campaign to
increase use of
homeswapper
31-Mar-
2025
Yes Completed -
text/social media
information, increase
in sign up by 39%. 
Prepare paper to ouline
required additional resource
needing to support increased
capacity of home swapper
31-Mar-
2025
No To be progressed via
home swapper
working group
H/HEDAP/2024/
027 Maximise
use of Home
Swapper to
meet rehousing
need of transfer
applicants
31-Mar-
2025
Review VFM annual costing
of home swapper and
consider if in-house platform
could be developed (similar
to rent insights approach)
31-Mar-
2025
No NP has initially
discussed with BF, to
be discussed further at
next Homeswapper
working group to
scope out feasibility
Nicola
Pettigrew
Gather all information on all
leases for an overview
30-Nov-
2024
No
Page 163

Page 164

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
028 Review of
all current lease
agreements
within context of
housing
emergency
(e.g., Safe as
Houses scatter
flats and impact
on generating
homelessness)
31-Mar-
2025
Action on track and
information gathering
exercise will complete
by end of November
to allow the key
element of the action
to be delivered
Review all leases and decide
whether best use of housing
stock
31-Mar-
2025
No
John Kerr
H/HEDAP/2024/
029 Deliver
housing Capital
Investment
Programme to
ensure all
homes meet the
Scottish Housing
Quality Standard
31-Mar-
2025
Work is progressing
well with 24-25
Capital investment
Programme work
streams that
contribute to SHQS.
Mid-year SHQS
position is meeting
target.
Alan Young
H/HEDAP/2024/
030 Maximise
the use of
existing housing
systems to
support effective
stock
management
31-Mar-
2025
Action remains on
track, lead officer
identified to work
closely with the
systems team in
developing asset
management module
on QL Housing
Management System
Graham
Watters
Icon Name
3: Enhancing housing access & prevention of homelessness
Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
031 Develop and
implement
transfer led
31-Aug-
2024
Action has been
achieved but will be
monitored and a
report will follow
Committee Approval in place
and ensure ongoing tenant
support
30-Aug-
2024
Yes Completed
John Kerr
Page 164

Page 165

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
approach to new
build housing
allocations
initially to the More
Homes Project Board
recommending any
refinements following
a review of Clydebank
East detailing we are
making allocations
based on housing
need and there is
visibility that it is
tackling
homelessness.
H/HEDAP/2024/
032 Strengthen
strategic
leadership
approach with
HSCP regarding
housing
emergency
31-Dec-
2024
HSCP represented on
the Housing
Emergency Project
Board.
29-Nov-
2024
No
Peter Barry;
Margaret-Jane
Cardno
H/HEDAP/2024/
033 Establish a
Task Force
approach to
engage public
bodies to
promote
prevention
measures linked
to the Housing
(Scotland) Bill
31-Mar-
2024
Task Force established
to coordinate the
response to the
elements of the
Housing Bill.  It was
agreed that a sub
group work in meeting
this key action
John Kerr
Finalise draft of strategy
following consultation (Aug
until Dec)
31-Dec-
2024
No
Seek HACC approval of new
strategy
28-Feb-
2025
No
Page 165

Page 166

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
034 Develop a
new refreshed
strategic
approach to the
prevention of
homelessness
through the
delivery of a
Housing
Solutions
Strategy
01-Apr-
2025
Action remains on
track and it is
anticipated the new
Housing Solutions
Strategy will be
presented to the
Housing and
Communities
Committee in
February 2025.
Embed and deliver new
strategy
01-Apr-
2025
No
Claire McKay
VAWG partnership supportive
of action H/HEDAP/2024/038
but will be carrying out a self
assessment of the group
where Prevention will be a
key element
30-Nov-
2024
NoH/HEDAP/2024/
035 In
partnership with
Violence Against
Women
Partnership
deliver a
refreshed focus
on preventing
negative
housing
situations as a
result of
domestic abuse.
31-Dec-
2024
Action on track
deliver action
H/HEDAP/2024/038
31-Dec-
2024
No Claire McKay
H/HEDAP/2024/
035a Full
implement the
introduction of
the Housing
Solutions
Service following
on from the
Homelessness
Service redesign
31-Dec-
2024
Good progress being
made in delivering the
service restructure
implementation plan. 
We await the outcome
of the job evaluation
assessments for a
number of posts
before moving on to
the final stage of the
restructure.
Joanne
Sutherland
Page 166

Page 167

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
Agree in principle online form
and tweak to ensure all
apects covered
30-Sep-
2024
Yes meeting 26/09 - all
partners agreed to
form following last
amendments and will
look for formal
agreement from
management
comittees
RSL to seek Committee
approval on form before
being finalised
30-Nov-
2024
No
Agree data sharing
agreement and Information
to be used on the website for
all involved and link
15-Dec-
2024
No
H/HEDAP/2024/
036 In
partnership with
local RSLs
develop and
implement a
common
application form
for all social
housing
providers in
West
Dunbartonshire
as part of the
development of
a Common
Housing Register
31-Dec-
2024
Agree Launch online form 31-Dec-
2024
No
Claire McKay
H/HEDAP/2024/
037 Introduce a
comprehensive
housing options
interviews at
application stage
to manage
demand and
options
31-Jan-
2025
Action on track and
linked to
035a/41/42/46/47/48
of this action plan Joanne
Sutherland
Decision paper for Housing
Imporvement Board to agree
the extent of the review
31-Aug-
2024
Yes paper presented and
agreed on 26/08
meeting of Co-ordinators to
agree the remit
30-Sep-
2024
Yes Co-ordinators meet on
02/09 - agreed remit
draft updated remit
and process to be
agreed on 24/09
new paper to HIB agreeing
new proposals of the remit
31-Oct-
2024
Yes Oct HIB as September
wont go ahead
update guidance and
relevant policies on agreed
remit
31-Dec-
2024
No
Page 167

Page 168

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
038 Review
remit of Housing
Allocations Panel
to reflect a
homelessness
prevention
perspective
(domestic, at
risk, others that
would otherwise
present)
31-Jan-
2025
communicate and update
new remit to all staff
31-Jan-
2025
No
Claire McKay
Joint meeting between
Homelessness and Housing
operations focusing cases
who do not have an offer
06-Dec-
2024
No
Review current open
Homeless cases with children
06-Dec-
2024
No to idenitfy those in
temporaray
accommodation, those
on offer and still
waiting.
identify actions for
those who are no on
offer
Using addiitonal Temporary
accommodation funds to
focus on acquisitions for
those households in temp
with children waiitn on offers
31-Dec-
2024
No
H/HEDAP/2024/
039 Deliver a
refreshed
process which
will ensure that
time in
minimised for
children in all
forms of
temporary
accommodation
31-Jan-
2025
Action on track and
key milestones will be
delivered through
sprint completion
process.
following on idenitfy any new
processes to be implemented
and rolled out to help
continually reduce times
children spend in temporary
accommodation
31-Jan-
2025
No
Claire McKay
Carry out recent research
around stigma and homeless
with view to creatign further
actions to take foward
15-Dec-
2024
No
Page 168

Page 169

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
040 Design and
deliver a
dynamic public
awareness
campaign
focused on the
realities of
homelessness
and housing
need
31-Jan-
2025
Action on track with
awareness plan due to
launch in early 2025
Liaise with WDC comms
team on appropriate
campaign actions
31-Dec-
2024
No
Donna
Kirkwood
H/HEDAP/2024/
041 Review of
Pathway 1 cases
(i.e., those
homeless but
not in temporary
accommodation)
over 6 months
to assess if in
stable
accommodation
(and close if this
is confirmed)
31-Mar-
2025
Ongoing process and
completed for both Q1
and Q2 and reported
to Housing
Improvement Board
Joanne
Sutherland
H/HEDAP/2024/
042 Introduce a
consistent
assessment of
housing and
support needs
regardless of if a
tenant or
presenting as
homeless
31-Mar-
2025
Action on track – the
review of support
processes has
informed new housing
solutions service and
once complete the
principles behind this
action will be enacted
31-Jan-
2025
No
Claire McKay;
Joanne
Sutherland
H/HEDAP/2024/
043 Develop and
implement a
new approach to
resettlement
and
humanitarian
schemes
31-Mar-
2025
Action on track and
will be led by
Resettlement and
Support Co-ordinator
once in post Claire McKay
Page 169

Page 170

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
044 Minimise
and eradicate
the use of
unsuitable
accommodation
for homeless
households
31-Mar-
2025
Action on track
performance in Q1
and Q2 has seen a
reduction in breaches
of the unsuitable
accommodation order.
Joanne
Sutherland
Objective 1 - whole system
approach
01-Apr-
2025
No
Objective 2 - rapid rehousing
(16 weeks)
01-Apr-
2025
No
Objective 3 - interim housing
options
01-Apr-
2025
No
H/HEDAP/2024/
045 Deliver the
outcomes of the
Rapid Rehousing
Transition Plan
30-Apr-
2025
Action on track –
positive progress has
been made and was
reported to the August
meeting of the
Housing and
Communities
Committee Objective 4 - housing first 01-Apr-
2025
No
Claire McKay
H/HEDAP/2024/
046 Explore
expanding a
homelessness
prevention
approach and
better managed
demand for
temporary
accommodation
30-Apr-
2025
Action on track –
increased focus on
homelessness
prevention is the
cornerstone of the
new Housing Solutions
service.
Joanne
Sutherland
H/HEDAP/2024/
047 Introduce a
"Mediation First"
approach to
housing
applications for
16-19 year-olds
(as a
homelessness
prevention
approach)
31-Dec-
2024
Action on track and
will be delivered
within refreshed
Housing Solutions
service. Joanne
Sutherland
H/HEDAP/2024/
048 Implement
31-Dec-
2024
Action on track –
linked to Housing John Kerr
Page 170

Page 171

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
a ‘One Door’
preventative
housing access
system under
one service to
prepare for new
prevention
duties.
Solutions service
redesign
H/HEDAP/2024/
049 Upscale the
Housing First
programme
through
collaborative
commissioning
31-Mar-
2025
Action on track and
additional resource
capability has been
commissioned to
support the delivery of
Housing First across
West Dunbartonshire
Claire McKay
H/HEDAP/2024/
050 Deliver and
implement in
partnership with
RSL a Common
Housing Register
for West
Dunbartonshire
31-Mar-
2026
Action on track – Good
progress being made
with key housing
association partners Claire McKay
Icon Name
4: Strengthen the Financial viability and capacity of the Housing Revenue Account and associated Housing and Homelessness budgets
Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
051 Complete
the review of
Building
Services Repairs
and Maintenance
service costs to
deliver
immediate
efficiencies to
the HRA
01-Dec-
2024
Action on track and
some outputs already
achieving necessary
impact.
Martin Feeney
Page 171

Page 172

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
H/HEDAP/2024/
052 Explore
innovative
housing
investment and
partnership
models to
maximise
housing
investment
approaches
31-Jan-
2025
Action on track and
progress being
monitored through
Better/More Homes
Project Boards
John Kerr
H/HEDAP/2024/
053 Carry out
review of HRA
contributions to
other non-
housing Council
service areas
31-Dec-
2024
Action on track
Peter Barry
H/HEDAP/2024/
054 Examine the
capacity of the
HRA and the
Council's
General Fund to
deliver agreed
housing
ambitions
31-Jan-
2025
Action on track
Peter Barry;
Laurence
Slavin
H/HEDAP/2024/
055 Develop a 3
year rental
strategy in
partnership with
tenants to
ensure tenant
priorities and
strategic
housing
ambitions can be
delivered
28-Feb-
2025
Action on track and
will be subject to
forthcoming rent
consultation exercise
Stefan
Kristmanns
H/HEDAP/2024/
056 Review
31-Mar-
2025
Action on track – Good
progress being made Peter Barry
Page 172

Page 173

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
Building
Services
structures and
external
contractors to
ensure best
value
H/HEDAP/2024/
057 Working
with other local
authority
partner re-
examine housing
finance position
in Scotland to
promote the
delivery of new
social housing
including the
treatment of
historic HRA
Capital Debt
31-Mar-
2025
Action on track –
ALACH) (Association
of Local Authority
Chief Officers) has
tabled this through
the Housing
Investment taskforce
agenda and a
response is awaited
form the Scottish
Government
Claire McKay
H/HEDAP/2024/
058 Review
homelessness
services funding
with aim of
being able to
reduce level of
temporary
accommodation
and free up staff
resource
31-Mar-
2025
Action on track
John Kerr
H/HEDAP/2024/
059 Develop a
refreshed
funding delivery
model for the
delivery of new
housing in light
of increased
borrowing levels
31-Mar-
2025
Action on track – New
grant benchmark rates
are now in place which
will assist ongoing
affordability John Kerr
Page 173

Page 174

Code & Title Status Progress Due Date Comment Milestone Due Date Done Comment Assigned To
exploring
increased grant
benchmark
levels
H/HEDAP/2024/
060 Directly
lobby the
Scottish
Government to
ensure the cost
of achieving net
zero in social
housing is met
with national
funding to
ensure rental
income can be
utilised for
improving
current and
developing new
social housing.
31-Mar-
2025
Action on track and
our view has been
presented at a
number of sector
forums.  We await the
publication of the
Social Housing net
zero standard to
assess any future
implications Claire McKay
Action Status
Cancelled
Overdue; Neglected
Unassigned; Check Progress
Not Started; In Progress; Assigned
Completed
PI Status
Alert
Long Term Trends
Improving
Short Term Trends
Improving
Page 174

Page 175

Warning
OK
Unknown
Data Only
No Change
Getting Worse
No Change
Getting Worse
Risk Status
Alert
High Risk
Warning
OK
Unknown
Page 175

Page 176

Page 176

Page 177

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 20 November 2024
___________________________________________________________________
Subject:       West Dunbartonshire Housing Repairs Policy
1. Purpose
1.1 The purpose of this report is to seek approval for the introduction of a new
West Dunbartonshire Housing Repairs Policy which has been developed in
partnership with Council tenants.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Approve the revised Repairs Policy attached as Appendix 1 to this
report; and
(ii) Invite the Chief Officer Housing and Employability to take appropriate
actions to ensure the policy is implemented immediately.
3. Background
3.1 West Dunbartonshire Council is committed to delivering a high quality,
efficient and effective responsive repairs service to all our tenants.
3.2 However, one of the drivers of tenant dissatisfaction identified following the
comprehensive Tenant Satisfaction Survey carried out in late 2022 related to
the repairs service and as part of our wider service response we committed
to conducting a review and developing a revised Repair Policy which would
improve the service delivered to tenants.
4. Main Issues
4.1 The key aim of the revised policy is to deliver a high quality, efficient and
effective responsive repairs service, that will provide a safe, secure and
healthy living environment, in a manner which delivers value for money, high
rates of customer satisfaction, maintains properties in a good and safe state of
repair and contributes to maximising the quality and long-term life of our
housing stock.
4.2 In order to deliver on this aim the policy sets out the following objectives:
ITEM 13
Page 177

Page 178

 To ensure that our properties are well maintained, with repairs carried out
when required, giving tenants reasonable choices about when work is
done.
 To carry out repairs right first time and provide a good value, reliable and
customer centred service.
 To comply with legal responsibilities and implement best practice, ensuring
value for money.
4.3 The policy sets out the relevant statutory and regulatory context related to the
delivery of our responsive repairs service and provides the following
commitments aimed at delivering the objectives outlined above:
 We will ensure that tenants are provided with clear information on their
repair responsibilities.
 We will provide an emergency repair service 24 hours a day, 365/366
days a year.
 We will provide an accessible service that has a range of ways that
tenants can easily contact to report a repair.
 We will provide a service which identifies and logs all repair requests
efficiently and effectively, minimising the need to carry out pre-inspections.
 We will carry out repairs by appointment where appropriate and within our
published target timescales and complete these with minimum disruption
and right first time where possible.
 We will carry out post inspections of a range of repairs to ensure that they
are completed to a high standard.
 We will give tenants the opportunity to comment on the standard of the
service received and will use this feedback to continuously improve our
service.
 We will reclaim costs from those who wilfully, or through neglect, cause
damage to their home via the implementation of our Rechargeable Repairs
Process.
4.4 Feedback received from tenants during the consultation process has been
key to informing the revised Repairs Policy and important elements of the
repairs service highlighted by tenants and addressed in the draft policy
include:
 Providing clear information around the type of repairs the Council is
responsible for and the repairs that tenants are responsible for.
 Providing clearer definitions of our different repairs categories so that they
are easier to understand.
 Providing clarity that repair target times begin when a repair is reported.
Page 178

Page 179

 Outlining clearly the level of service tenants can expect around repair
appointments and improved communication via text and email.
4.5 In addition to this, the following key changes being proposed as part of the
revised policy:
 Reducing the target timescale for carrying out Urgent Repairs from 10
days to 5 days.
 Extending the target timescale for carrying out Planned Repairs from 40
days to 60 days.
4.6 Aiming to carry out Urgent Repairs more quickly aligns with the key aim of the
policy, which is to provide an efficient and effective repairs service that
delivers high rates of customer satisfaction.
4.7 This proposal will deliver significant improvements for all tenants and better
reflect the trend across the sector by the top performing local authority social
landlords.
4.8 Planned Repairs include repairs requiring a scaffold, fencing repairs or repairs
that affect more than one property. Whilst these vary in volume and type from
year to year, the numbers are low compared to Emergency, Urgent and
Routine Repairs.
4.9 Extending the target timescales for these types of repairs reflects the time that
the planning element takes, with a 60-day target deemed to be more realistic
and will help deliver the improvement being proposed in relation to Urgent
Repairs.
4.10 Revised repairs categories and target timescales are outlined in the table
below:
Repair Category Target Timescale
Emergency Repair 24 hours
Urgent Repair 5 working days
Routine Repair 20 working days
Planned Repair 60 working days
4.11 The review of the policy also highlighted the need to agree a definition of
complex repairs which we have not had up until now. These are repairs which
we recognise will be challenging to be completed within a defined timescale
and examples would include:
 When an inspection has identified the need for structural works to be
carried out.
 Repairs that require an installation such as a bathroom suite or part of a
kitchen to be removed for the repair to be carried out and then reinstated.
Page 179

Page 180

 Repairs that require specialist materials or equipment to be sourced
before being carried out.
 Repairs that require the consent of owners’ prior before works being
carried out.
4.12 When a repair is identified as a complex repair, we will take forward works as
quickly as possible and keep tenants informed of the planned nature of the
works required and likely timescales for completion.
5. People Implications
5.1 There are no direct people implications because of this report. If approved,
the delivery of the revised Repairs Policy will be supported by an
implementation plan that will include staff guidance and training and a revised
performance monitoring framework for the responsive repairs service.
6. Financial and Procurement Implications
6.1 There are no direct financial or procurement implications in relation to this report.
The revised Repairs Policy will be delivered from within existing budgets.
7. Risk Analysis
7.1 There is no significant identifiable risk associated with the approval and
implementation of the revised Repairs Policy
8 Environmental Sustainability
8.1 The delivery of our housing maintenance programme is part of our current
and future approach to strategic housing asset management will continue to
prioritise a ‘zero carbon’ approach to decision making and deliverability and
this will be done the aims of the Housing Asset Management Strategy and the
Council’s Climate Change Strategy.
9. Equalities Impact Assessment (EIA)
9.1 Equalities legislation requires that new or significantly changing policies
should be subject to an assessment of their impact on the wellbeing of certain
groups of people. As such an Equalities Impact Assessment was conducted
as part of the development of the revised Repairs Policy.
9.2 This assessment is attached as Appendix 2 to this report and the key finding
is that there is nothing the in policy that would lead to negative impacts for
people or communities and that the policy will have an overall positive impact
as it aims to improve the level of service provided to all tenants.
9.3 The policy should have an overall positive impact on those with disabilities as
it specifically recognises that the service provided can be tailored for disabled
people.
Page 180

Page 181

10. Consultation
10.1 A key element in the development of the revised Repairs Policy was seeking
the views of tenants and a full summary of the consultation process is
attached as Appendix 3 to this report.
10.2 The aim of the consultation was to get views of our tenants on how important
key aspects of the repairs service are to them and to use this feedback to
ensure that tenant priorities were front and centre right at the start of the
process and fully taken account of as the policy was being reviewed and
updated.
10.3 A survey was published on the Council’s website in June 2024 and was
promoted via the Tenant Participation Facebook page, the West
Dunbartonshire Tenant and Residents Organisation (WDTRO) and individual
Tenant and Residents Associations (TRA’s). A text message or email was
also sent to those tenants we have these contact details for with a link to
complete the survey. Over one thousand responses were received, and this
feedback was central to the elements of the policy outlined at 4.3 being fully
addressed in the revised policy.
10.4 There was also close engagement with the WDTRO throughout the
consultation period. WDTRO members are supportive of the proposed
changes being made in relation to target timescales for repairs and also read
the draft policy and provided feedback in relation to the wording being clear,
easy to understand and tenant friendly.
10.5 The WDTRO were also asked to provide their views on the definition of
complex repairs and feedback was that the definition was sensible and that
they would be supportive of this definition being adopted and included in
future staff guidance as part of the process of implementing the revised policy.
11. Strategic Assessment
11.1 Having considered the Council's strategic priorities, this report contributes
significantly to all five strategic priorities and specifically to improve local
housing and environmentally sustainable infrastructure.
Peter Barry
Chief Officer, Housing & Employability
Date: 6 November 2024
___________________________________________________________________
Person to Contact:        John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness Team,
Housing and Employability, telephone: 07793717981, email:
john.kerr@west-dunbarton.gov.uk
Page 181

Page 182

Stefan Kristmanns, Senior Housing Development Officer,
Housing Development and Homelessness Team, Housing
and Employability, email: stefan.kristamanns@west-
dunbarton.gov.uk
Appendices: 1. Draft Repairs Policy October 2024
2. Draft Repairs Policy Equalities Impact Assessment
3. Draft Repairs Policy Consultation Summary
Background Papers:
Wards Affected:  All
Page 182

Page 183

West Dunbartonshire Council
Responsive Repairs Policy
Draft October 2024
ITEM 13 -
APPENDIX 1
Page 183

Page 184

2
Contents
Section No. Title Page No.
1 Introduction and scope of the policy 3
2 Policy context 3
3 Aims and objectives of the policy 4
4 Repair responsibilities 5
5 Reporting a repair 8
6 Repair categories and target completion timescales 9
7 Carrying out repairs 13
8 Individual circumstances 15
9 Performance monitoring 16
10 Review 16
Page 184

Page 185

3
Section 1
Introduction and scope of the policy
Introduction
West Dunbartonshire Council is committed to delivering a high quality, efficient and effective
responsive repairs service to all our tenants, in a manner which delivers high rates of
customer satisfaction.
Responsive repairs are those that are carried out in response to you notifying us of a problem
or defect within your home. This policy sets out the relevant statutory and regulatory context
related to the delivery of our responsive repairs service, it provides information around repair
responsibilities so you know the type of repairs we’re responsible for and the repairs that you,
our tenants, are responsible for and outlines the different repair categories and the level of
service you can expect from us as we deliver this service.
Scope of the policy
The policy outlines the service we provide in relation to responsive repairs and provides
information about what cyclical maintenance programmes we have in place. The policy refers
to our approach to rechargeable repairs where relevant and this is outlined in more detail in
our Rechargeable Repairs Process available on our website. The policy does not cover
improvements carried out as part of our capital investment programme or our approach to
void repairs (repairs carried out when a property is empty).
This policy applies to tenants who have a Scottish Secure Tenancy, a short Scottish Secure
Tenancy or occupants who have an occupancy agreement for temporary or supported
accommodation with West Dunbartonshire Council.
Section 2
Policy context
We aim to make sure the service we provide not only meets our legal obligations but reflects
best practice where possible. The policy was developed taking tenant views into account and
within context of the following statutory and regulatory framework:
The Housing (Scotland) Act 1987 which outlines the tolerable standard, which is
the minimum standard that applies to all residential dwellings including social rented homes.
The Housing (Scotland) Act 2001 which details landlords’ repairing obligations and
introduced the Right to Repair Scheme.
The Scottish Secure Tenancy Agreement based on the Housing (Scotland) Act 2001,
which includes the following key commitment:
“During the course of your tenancy, we will carry out repairs or other work necessary to keep
the house in a condition which is habitable, wind and watertight and reasonably fit for human
habitation. We will carry out all repairs within a reasonable period of becoming aware that the
Page 185

Page 186

4
repairs need to be done. Once begun, the repairs will be finished as soon as reasonably
possible. All repairs will be done to the standard of a competent contractor, using good
quality material.”
The Housing (Scotland) Act 2006 which introduced a revised tolerable standard.
The Scottish Social Housing Charter which sets out the outcomes and standards that all
social landlords should be delivering for their tenants and other customers. The outcome
most relevant to this policy is:
 Charter Outcome 5: Repairs, Maintenance and Improvements - social landlords manage
their business so that tenants’ homes are well maintained, with repairs and
improvements carried out when required, and tenants are given reasonable choices
about when work is done.
There are also a series of health and safety duties and regulations that are in place to ensure
tenants, staff, and contractors are living and working in a safe environment.
Section 3
Aim and objectives of the policy
Aim of the policy
The key aim of this policy is to deliver a high quality, efficient and effective responsive repairs
service, which will provide a safe, secure and healthy living environment, in a manner which
delivers value for money, high rates of customer satisfaction, maintains properties in a good
and safe state of repair and contributes to maximising the quality and long-term life of our
housing stock.
Objectives of the policy
The main objectives of the are:
 To ensure that our properties are well maintained, with repairs carried out when required,
and giving you reasonable choices about when the work is done.
 To carry out repairs right first time and provide a good value, reliable and customer
centered service.
 To comply with legal responsibilities and implement best practice, ensuring value for
money.
How we will deliver these objectives
 We will ensure you are provided with clear information on your repair responsibilities.
 We will provide an emergency repair service 24 hours a day, 365 days a year.
 We will provide an accessible service which provides a range of ways that you can easily
contact to report a repair.
Page 186

Page 187

5
 We will provide a service which identifies and logs all repair requests efficiently and
effectively, minimising the need to carry out pre-inspections.
 We will carry out repairs by appointment where appropriate and within our published
target timescales and complete these with minimum disruption and right first time where
possible.
 We will carry out post inspections of a range of repairs to ensure they are completed to a
high standard.
 We will give you the opportunity to comment on the standard of the service received and
use this feedback to continuously improve our service.
 We will reclaim costs from those who wilfully, or through neglect, cause damage to their
home via the implementation of our Rechargeable Repairs Process.
Section 4
Repair responsibilities
The responsibility for repairing and maintaining homes is shared between the Council as your
landlord and you as the tenant.
Our responsibilities to you
As your landlord, we are responsible for repairing and maintaining the structure of your home
and for the repair and maintenance of common areas. This includes the fixtures and fittings
which supply gas, electricity, water and drainage (your gas or electricity provider is
responsible for the supply and for any repair issues relating to your electricity or gas meter). If
you live in a block of flats, we are also responsible for any communal facilities provided.
To ensure your home is maintained to a safe standard, we will carry out repairs to:
 the structure of your home (chimney, roof, walls, drains, floors ceilings and stairs).
 the external fabric of your home (external doors, windows, gutters, downpipes).
 the plumbing system within your home (including the water tank, pipe work and
stopcocks).
 the heating within your home (radiators, storage heaters, panel heaters, any pipe work).
 the water heating system within your home (boiler, immersion heater, any pipe work).
 kitchen and bathroom fittings (including toilet, bath, basins/sinks, cupboards, worktops,
pipe work).
 electrical wiring and fittings (sockets, light fittings, light switches, mains operated smoke
detectors).
 internal doors, door surrounds and skirting boards.
 boundary walls, fences, paths, gates, driveways, and any garden structure put in place by
the Council.
 bin areas and clothes poles.
Page 187

Page 188

6
Common repairs
Where there are homeowners in a block, responsibility for repairs and maintenance of
common areas is shared between us and the homeowners.
This may impact the repairs and planned maintenance carried out to common areas such as
roofs, external walls, gutters, fences, paths, and stairs.
We will carry out emergency and urgent repairs to common areas which are a risk to health
and safety or to prevent further damage and will recharge homeowners for their share of the
cost.
For other planned repairs or cyclical maintenance programmes, owners need to agree to
contribute to the cost of these works to allow them to proceed. We will work to encourage
participation to gain agreement to take these works forward, although this can cause delays
in work being carried out to Council owned properties.
Your responsibilities as a tenant
You are responsible for taking reasonable care of your home and you must report to us
promptly, any repairs or damage tom your home which are our responsibility. You must also
take action to prevent further damage once a fault has been identified.
You are also responsible for the internal decoration of your home, for carrying out minor
repairs and for the maintenance of any appliances or garden structures you install or accept
at the start of your tenancy.
Whilst you are not responsible for carrying out repairs which are due to fair wear and tear,
your responsibilities do include the following:
 All internal decoration including the provision and fitting of floor and window coverings.
 Repairing minor cracks or holes in walls and ceilings that can reasonably be filled before
decorating.
 Taking action to avoid condensation by heating and ventilating your home, not blocking
air vents and opening windows.
 Replacing lost or stolen keys.
 Repairing any damage caused by you, your family, or any visitors to your home.
 Reporting any criminal damage or vandalism to the police and obtaining an incident number.
 Renewing plugs and chains to baths, sinks and basins.
 Replacing a broken or damaged toilet seat.
 The fitting of any additional locks.
 The purchase and installation of any doorbell, door chain or door nameplate.
 The purchase and installation of consumable items, such as electrical plugs and light bulbs
(not communal lighting).
 Resetting tripped switches or fuses.
 Attempting to clear any minor plumbing blockages.
 The maintenance of any heating system that you install (permission would be required).
Page 188

Page 189

7
 The maintenance of any appliances that you install, such as a cooker, hob, or fire.
 The maintenance of any fittings installed or accepted at the start of your tenancy, such as
shelves or built-in wardrobes.
 The maintenance of television aerials and reception equipment that you install.
 The maintenance of your garden, including grass, hedges and trees and ensuring that it
is kept clear of debris.
 The maintenance of fences, gates, sheds, and any other garden structure that you install
or accepted at the start of your tenancy.
Where you ask us to carry out work that is your responsibility, we will recharge you for the
cost. This includes helping you to gain access to your home if you have lost your keys or had
them stolen and are locked out. You will also be recharged for repairing damage caused by
you, your family, or by visitors to your home. Further detail is outlined in our Rechargeable
Repairs Process.
Alterations, improvements, and adaptations
You must ask for written permission from us before you carry out any alterations or
improvements to your home, including:
 the renewal of, or alteration to your kitchen or bathroom.
 the installation of a shower.
 the renewal of, or alteration to electrical work.
 the installation of laminate flooring.
 the installation of external structures, such as fencing, gates or sheds.
We will recharge you the cost of any repairs necessary to make good any unauthorised,
unsafe or unsuitable alterations that you carry out. Further detail about gaining permission is
provided at Alterations and Improvements.
If you, or a member of your family need an adaptation to assist you accessing or getting
around your home or with independent living, medical adaptations can be carried out by us.
These adaptations could include ramps, showers, handrails, door alterations or path
widening. Further detail is provided is provided at Council Housing Adaptations.
Allowing access to you home
You are responsible for providing access to your home to carry-out repairs and maintenance
to your home, including any pre-inspection that may be required. We will give you reasonable
notice of our requirement for access (except in the case of an emergency) and aim to carry-
out repair work by appointment where possible (see Section 7 “Carrying out repairs”).
Allowing access is vitally important when related to your safety. For example, we are required
by law to carry out a gas safety check in your home once a year and an Electrical Installation
Condition Report in your home every 5 years. You must allow access for this to be carried
out, if you do not, we will force access to your home under the terms of your tenancy
agreement. In circumstances where this is necessary, we will recharge you for the cost of
this. Further detail is provided at Gas Safety.
Page 189

Page 190

8
You should ensure areas are clear for our operatives to work to avoid any issues which could
prevent a repair being carried out. This may include clearing work surfaces, emptying
cupboards, taking down curtains, moving furniture away from an area or lifting carpets or
laminate flooring.
Section 5
Reporting a repair
We aim to provide a service that is accessible and convenient for you and have a range of
ways to easily contact to report a repair.
You should report repairs that are our responsibility as soon as reasonably possible, to
prevent further damage and ensure the property does not fall into disrepair.
Reporting an Emergency Repair
The Council provides an emergency repair service 24 hours a day, 365 days a year for emergency
repairs which are necessary due to a threat or danger to health and safety, or there is a risk of
serious loss or damage to a property.
You cannot report an emergency repair online.
Freephone 0800 073 8708 to report an emergency repair during office hours.
 8:30am to 4:30pm Monday to Thursday
 8:30 to 4:00 Friday
Freephone 0800 197 1004 out-with normal working hours.
Reporting a Non-emergency Repair
Freephone 0800 073 8708 during office hours.
Online Repairs Reporting Form
Emailing housing.repairs@west-dunbarton.gov.uk
Gas Central Heating Repairs
For repairs to your gas central heating or hot water you can contact City Technical direct on 0333
202 0708 or 0800 073 0341.
Should you have a suspected gas leak call National Grid on 0800 111 999 (calls to 0800 numbers
are now free from a mobile phone).
Page 190

Page 191

9
Section 6
Repair categories and target completion
timescales
We aim to provide a service which identifies and logs all repair requests efficiently and
effectively, minimising the need to carry out pre-inspections.
However, to ensure the right operative, with the correct materials is tasked to carry-out a
repair, it may be necessary in some instances for a pre-inspection to be carried out.
This could be in circumstances where:
 the person reporting the repair is unable to fully explain the problem.
 measurements and/or technical specifications are needed to carry out work.
 the source of the problem needs to be properly identified.
 specialist materials or equipment may be required.
 it may not be clear who is responsible for the repair.
Repairs reported will be assigned one of the following repair categories with a target
timescale for completion, ensuring the most urgent repairs are carried out first.
Emergency Repair
The repair issue may cause a threat or danger to health and safety or where quick action is
required to prevent further loss or damage to a property.
Examples of an emergency repair include:
 a total loss of heating or hot water.
 unsafe power, electrical socket, or light fitting.
 serious water/plumbing leaks to prevent further damage.
 insecure external window, door, or lock.
 the removal of serious fire risks (clearing/removing objects).
 the removal of serious environmental risks (such as blockages to bin chutes).
 make safe any danger due to damage to the structure of a building (e.g. slates, other
roofing defects, masonry).
 security lighting that poses a threat or danger.
 close lighting that poses a threat or danger.
 lock change/forced entry if you cannot access your property.
 faulty door entry system if you cannot access your property.
Emergency repairs will be attended to and made safe within 24 hours of being reported. Where
possible, we will carry out the full repair, however if this is not possible, we will carry out
temporary repairs immediately to make the situation safe, and then return to complete follow up
repair work identified.
Page 191

Page 192

10
All follow-on repairs from emergency repairs will be treated as separate works orders and be
recorded as a non-emergency repair. There should be no time lapse between the completion
of the emergency work and the raising of any follow-on non-emergency repairs.
Urgent Repair
These are repairs that are not emergencies but need to be carried out quickly to prevent
more damage to a property or undue risk to a tenant.
Examples of an urgent repair include:
 minor plumbing leaks.
 central heating faults.
 non-emergency electrical work.
 extractor fan in kitchen or bathroom not working.
 faulty door entry systems (where you can still gain entry to your home).
 reglazing a window.
 floor in danger of collapse (unknown infestation/rot).
 renewal of faulty electric shower where this is the only bathing amenity.
 renewal of storage heater.
 renewal of immersion heater.
 renewal of insecure entrance door.
 insecure manhole.
 repair slabs/steps presenting a trip hazard.
Urgent repairs will be carried out within 5 working days of being reported.
Routine Repair
These repairs are not emergencies or urgent but are of a routine nature and are not part of
an existing cyclical maintenance programme. Routine Repairs could be due to normal wear
and tear and would apply where no danger exists.
Examples of a routine repair include:
 all non-urgent internal repairs including plaster work.
 sealing around windows and doors.
 replacing ceilings following water ingress.
 gutter and roof repairs which are not dangerous and where scaffolding is not required.
 burst underground water main.
Routine repairs will be carried out within 20 working days of being reported.
Page 192

Page 193

11
Planned Repairs
These are day-to-day repairs which are general maintenance repairs and are not part of an
existing cyclical maintenance programme. Planned repairs may involve working at height
(scaffold platforms) and could include repairs that affect more than one property and where it
would be more cost effective to respond and deliver on a planned basis rather than carrying
out individual routine repairs. Planned repairs are likely to require a pre-inspection to fully
determine the scope of work required.
Examples of planned repairs include:
 gutter and roof repairs which are not dangerous and where scaffolding is required.
 blocked gutters or rainwater pipes where scaffolding is required.
 gutter cleaning
 external roughcasting which is not dangerous.
 dry and wet rot works which is not dangerous.
 fencing repairs.
Whilst the length of time to complete planned repairs will vary, dependent on the volume and
type of work, the aim is that these will be carried out within 60 working days of being
reported.
Cyclical Maintenance
In addition to responding to reported repairs, we have a range of cyclical maintenance
programmes in place to ensure the safety of tenants and that we meet our statutory and
regulatory obligations.
These programmes include:
 an Electrical Installation Condition Report carried out every 5 years.
 annual gas safety checks including the boiler.
 annual cleaning and testing of smoke, carbon monoxide and heat detectors.
 annual sprinkler system maintenance and testing.
 annual dry riser maintenance and testing.
 annual cleaning and testing of large capacity cold water cisterns aimed at preventing
legionella.
 annual testing of water pumps in high rise buildings.
 annual maintenance of air source/other source heat pumps.
 annual maintenance of domestic ventilation systems.
 annual communal fan cleaning.
 6 monthly lift maintenance.
 6 monthly laundry maintenance.
Page 193

Page 194

12
Right to Repair
The Housing (Scotland) Act 2001 introduced the Right to Repair Scheme which gives you the
right to have small urgent repairs up to the value of £350 carried out within a given timescale.
These repairs are known as 'qualifying' repairs and the type of repairs covered by the
scheme and the timescales within which these should be carried out are outlined below:
1 Day Target
Blocked Flue to Open fire or Boiler
Blocked or leaking foul drains, soil stacks or toilet
Blocked sink, bath or drain
Total loss of electricity
Insecure external window, door or lock
Unsafe access path or step
Significant leaks or flooding from water or heating pipes, tanks or
cisterns
Total or partial loss of Gas supply
Total or partial loss of heating with no alternative heating
Only toilet in the house not flushing
Unsafe electrical sockets or lighting socket or fitting
Total loss of water supply
3 Day Target
Partial loss of water supply
Partial loss of electricity
Loose or detached banister or handrail
Unsafe timber flooring or stair tread
7 Day Target
Extractor fan in kitchen or bathroom not working
How do I know if I can use the scheme?
When you report a repair, we will let you know if it is a “qualifying repair” and covered by the
scheme. If we have not started the repair within the timescale shown above, you have the
right to approach an alternative contractor nominated by us for the trade needed to do the job
for you.
If we arrange to carry out the repair within the target date but did not gain access to your
home, the Right to Repair scheme does not apply
We will not consider claims for jobs not included in this list and you will have to pay for the
work yourself if you go ahead and arrange for repairs to be done. If you are not sure whether
the repair is covered by the scheme you can telephone 0800 073 8708 or email your enquiry
to housing.repairs@west-dunbarton.gov.uk 
Page 194

Page 195

13
What happens next?
If we have started but not completed the repair within the maximum time, you will be entitled
to £15 compensation.  If we have not started the repair, we can arrange for an alternative
contractor to carry out the repair. If this happens, you will be entitled to £15 compensation for
the inconvenience.
This alternative contractor has the same length of time to carry out the repair as we did. If
they do not carry out the repair within the time limit set, you will be entitled to another £3
compensation for each working day until the repair has been completed.
This £3.00 daily compensation starts when the alternative Contractor has not met the
timescale for the repair from the time you contact them. This amount can add up to a
maximum compensation payment of £100 for any one repair.  If you are in arrears or owe
money to the Council, any compensation due will be used to pay these debts with any
remainder issued to you.
Section 7
Carrying out the repairs
Appointments
Where appropriate, we will carry out non-emergency repairs by appointment, within our target
timescales for the repair category and will aim to carry out the repair right first time where
possible.
An appointment will be agreed with you, or person reporting the repair on your behalf, and
will be either:
 a morning appointment – operative will arrive between 8.00am and 12 noon or
 an afternoon appointment - operative will arrive between 12.30pm and 4.00pm.
Appointments will also be given for any pre-inspection that is necessary where access to
your home is required. Repairs identified at any pre-inspection will be discussed with you and
a further appointment agreed for the works required where this is possible. This appointment
will be within the target completion timescale from the date the repair was reported.
When an appointment is agreed you should:
 provide an up-to-date contact number or email address to allow us to make contact with
you.
 ensure a responsible adult over the age of 16 will be at the property to allow access at
the agreed appointment time.
 ensure areas are clear for our operatives to work to avoid any issues that would prevent
a repair being carried out. This may include clearing work surfaces, emptying
cupboards, taking down curtains, moving furniture away from an area or lifting carpets
or laminate flooring.
If an agreed appointment is no longer suitable, you should contact us as soon as possible
and we will re-arrange to a more convenient date and time.
Page 195

Page 196

14
Right First Time
We aim to carry out repairs Right First Time where possible. To meet this definition, a repair
must be completed within the target completion timescale and without the need for an
operative to be recalled due to a defect with the original repair, within the reporting year.
Due to the nature of some repairs, one or more visits may be planned to carry out the works.
If the repair is completed within the target timescale and works are discussed with you and
delivered as planned, the repair will be considered completed right first time (if there is
subsequently no recall due to a defect with the repair carried out).
Service commitments
When an up-to-date contact number or email address is available, we will keep you updated
with the status of a repair from reporting until completion.
 We will send you a text or email to confirm the agreed repair appointment or pre-
inspection appointment.
 Where possible we will include an estimate of the time it will take to carry out the repair.
 We will send you a reminder text or email the day before the appointment.
 We will send you a text or email when the operative is on their way on the day of the
appointment.
We will also ensure that when attending your home:
 all members of staff will wear an ID badge and introduce themselves.
 all members of staff will be smart and appropriately dressed or wear a uniform.
 all members of staff will be polite and treat you with respect and dignity.
 operatives carrying our repair works will explain the nature of the work before it
commences.
 all members of staff will follow appropriate health and safety requirements.
 the quality of repair work is carried out to a high standard.
 all members of staff will take care to minimise disruption, prevent damage to your home,
protect it from dust and paint and remove all work-related rubbish.
 repairs are carried out Right First Time where possible. This will not always be at the first
visit, as some repairs will require more than one planned visit to be completed (e.g. multi-
trade jobs).
 when a repair is complete, we will send you a text or email asking for feedback in terms
of satisfaction with the service provided in respect of that repair.
We expect you to treat our staff and contractors with respect and dignity when they are in
your home. For health and safety reasons, pets and young children should be kept away
from the area whilst a repair is being carried out. Anyone present in your home must also
ensure they do not smoke or vape whilst operatives are there to work. Not meeting these
expectations could result in work not being carried out.
Page 196

Page 197

15
Missed appointments due to no access
It is important you provide us access to your home to carry-out repair work. This helps us
deliver an efficient, reliable and customer centered service.
If an operative does not obtain a response when they arrive at your home, we will attempt to
contact you if a contact number is available. If we do not have up to date contact details and
are still unable to gain access, a card will be left where this is possible, asking you to contact
us.
In these circumstances the repair will be cancelled, and it is your responsibility to contact us
to arrange a new appointment. When a repair is cancelled due to no access, a text or email
will be sent to you confirming this.
Quality Assurance
Regular inspections are carried out when works are in progress to ensure staff are following
appropriate health and safety requirements, minimising disruption and preventing damage to
your home.
Post work inspections are carried out on a range of repairs to ensure the work has been
carried out to the high standards required.
On completion of repair work we will contact you asking for feedback in terms of satisfaction
with the service provided and use this feedback to continuously improve the service we
provide.
For more information you can read our Quality Policy Statement.
Whilst we are committed to providing the best quality of service that we can, in circumstances
where we have done something wrong, failed to do something that you expected or have not
treated you with courtesy, you can use our Complaints Procedure.
Section 8
Individual circumstances
We aim to deliver the best service possible to all our tenants but realise in certain
circumstances the service will need to be tailored to accommodate individuals and their
needs.
Those who may benefit from their individual circumstances being considered could include
but are not limited to:
 tenants with particular communication needs, for example BSL users or people who
are hard of hearing.
 tenants with a physical impairment (such as a wheelchair or walking frame user).
 tenants with learning difficulty or disability.
 tenants with an advanced terminal illness.
Page 197

Page 198

16
When a repair is reported, let us know if there are relevant circumstances and every attempt will
be made to ensure reasonable adjustments can be made. This could include carrying out some
repairs more quickly than normal or agreeing specific arrangements for appointments (such as
knocking loudly, allowing for extra time for a door to be answered or contacting a third party to
facilitate access).
Section 9
Performance monitoring
We will monitor our performance in relation to delivering the commitments within this policy
using a range of key performance indicators.
This will include monitoring how well we are meeting the target timescales outlined and the
following indicators which are part of the Scottish Social Housing Charter.
Average length of time to complete emergency repairs
Average length of time to complete non-emergency repairs
% of repairs completed Right First Time
The number of times we did not meet our statutory obligation to complete a
gas safety check within 12 months
% of tenants satisfied with the repairs and maintenance service
We will share this information with tenants and ensure that we use it to continuously improve
service delivery.
Section 10
Review
We will review this policy every three years or earlier if required, for example to comply with
any legislative changes.  We will consult tenants and other relevant stakeholders when
carrying out a review.
Page 198

Page 199

This document is also available in other languages, large print and audio format on request.
Arabic
British Sign Language users can contact us via contactSCOTLAND-BSL, the on-line
British Sign Language interpreting service.
The Council contact number is 01389 XXXXXX
Chinese (Cantonese)
Gaelic
Tha an sgrìobhainn seo cuideachd ri fhaighinn ann an cànanan eile, ann an clò mòr, agus ann an cruth
claisneachd ma thèid iarraidh
Hindi
Polish
Punjabi
Ukrainian
Цей документ також доступний іншими мовами, великим шрифтом та в аудіоформаті за запитом.
Urdu
  01389 737527
 West Dunbartonshire Council, 16 Church Street, Dumbarton, G82 1QL
  communications@west-dunbarton.gov.uk
Page 199

Page 200

Assessment No 1056 Owner skristmanns
Resource Regeneration, Environment and
Growth
Service Housing and Employment
FirstName Surname Job Title
Head Officer Stefan Kristmanns Housing Development
Coordinator
Members Peter Barry, Chief Officer Housing and Employability
John Kerr, Housing Development and Homelessness Manager
Martin Feeney, Building Services Manager
Nicola Pettigrew, Housing Operations Manager
Alan Young, Housing Asset and Investment Manager
Stefan Kristmanns, Housing Development Coordinator
James McCarron, Finance Business Partner
Craig Wilson, Building Services Maintenance Manager
Suzanne Bannister, Team Leader Housing Operations
(Please note: the word 'policy' is used as shorthand for strategy policy function
or financial decision)
Policy Title Housing Repairs Policy
The aim, objective, purpose and intended outcome of policy
Aim of the policy
The key aim of this policy is to deliver a high quality, efficient and effective responsive
repairs service, that will provide a safe, secure and healthy living environment, in a
manner which delivers value for money, high rates of customer satisfaction, maintains
properties in a good and safe state of repair and contributes to maximising the quality
and long-term life of our housing stock.
Objectives of the policy
The main objectives of the are:
•To ensure that our properties are well maintained, with repairs carried out when
required, and giving you reasonable choices about when the work is done.
•To carry out repairs right first time and provide a good value, reliable and customer
centered service.
•To comply with legal responsibilities and implement best practice, ensuring value for
money.
Service/Partners/Stakeholders/service users involved in the development
and/or implementation of policy.
Housing and Employability Service
West Dunbartonshire Tenants and Resident Organisation
West Dunbartonshire Equalities Forum
Does the proposals involve the procurement of any goods or services? Yes
If yes please confirm that you have contacted our procurement services to
discuss your requirements.
No
SCREENING
You must indicate if there is any relevance to the four areas
ITEM 13 -
APPENDIX 2
Page 200

Page 201

Duty to eliminate discrimination (E), advance equal opportunities (A) or
foster good relations (F)
Yes
Relevance to Human Rights (HR) Yes
Relevance to Health Impacts (H) Yes
Relevance to Social Economic Impacts (SE) Yes
Who will be affected by this policy?
All tenants who receive a housing repairs service from West Dunbartonshire Council as their landlord.
Who will be/has been involved in the consultation process?
Survey in June 2024 open to all WDC tenants asking how important various aspects of our repairs policy
are to them. This consultation was key in shaping the content of the draft policy.
Engagement with the West Dunbartonshire Tenants and Residents Organisation (WDTRO) in
August/September 2024 outlining content of draft policy, asking for feedback in relation to clarity of the
language used and WDTRO members also offered to proof read document.
Further consultation September 2024 asking for views/comments on draft policy, the content of which was
shaped by tenant feedback received in main consultation exercise. Specific questions asked about how
well the policy delivered on tenant priorities outlined. This consultation was highlighted to the West
Dunbartonshire Equalities Forum, Tenant and Resident Associations and our Interested Tenants Register.
A full consultation summary document will be included in the report to the Housing and Communities
Committee in November 2024 seeking approval for the revised policy.
Page 201

Page 202

Please outline any particular need/barriers which equality groups may have in relation to
this policy list evidence you are using to support this and whether there is any negative
impact on particular groups.
Specific group to
consider
Needs Evidence Impact
Age                          This policy needs to serve
the needs of people from
across age groups.
For older people there are
more likely to be cross cutting
issues noted under disability
accessibility of services.
The needs of Children and
young people cross cut with
UNCRC considerations.
The policy should have
an overall positive
impact and it aims to
improve the level of
service provided to all
tenants.
Disability                 We need to ensure that
services are accessible to
disabled people.  The policy
recognises that in certain
circumstances the service
will need to be tailored to
accommodate individuals
and their needs.
Those who may benefit
from their individual
circumstances being
considered include but are
not limited to:
• tenants with particular
communication needs for
example, BSL users, or
people who are hard of
hearing
• tenants with a physical
impairment, such as a
wheelchair or walking frame
user
• tenants with a learning
difficulty or disability
• tenants with an advanced
terminal illness
When a repair is reported
every attempt will be made to
ensure reasonable
adjustments can be made. This
could include carrying out
some repairs more quickly than
normal or agreeing specific
arrangements for appointments
(such as knocking loudly,
allowing for extra time for a
door to be answered or
contacting a third party to
facilitate access).
The policy also contains a
commitment that those that
need an adaptation to assist
accessing or getting around
their home or with independent
living, medical adaptations can
be carried out by us. These
adaptations could include
ramps, showers, handrails,
door alterations or path
widening.
The policy should have
an overall positive
impact and it aims to
improve the level of
service provided to all
tenants but specifically
recognises that the
service provided can be
tailored for disabled
people.
Gender Reassign    We need to consider any
differential impact
No evidence of any differential
impact
Neutral
Marriage & Civil
Partnership 
Under the Equality Act 2010
married people and civil
partners should be treated
equally.
This policy will apply equally to
married people and civil
partners.
Neutral
Pregnancy &
Maternity        
Cross cuts with sex Cross cuts with sex Cross cuts with sex,
Positive
Race                         It is more likely that some
BME people might face
languages barriers in
accessing services.
People from non-white
minority ethnic groups are
This document is available in
other languages.
As this policy is implemented
the level of service provided
will not be impacted by the
income of the tenant.
The policy should have
an overall positive
impact and it aims to
improve the level of
service provided to all
tenants.
Page 202

Page 203

more likely to be in relative
poverty after housing costs
compared to those from the
‘White - British’ and ‘White -
Other’ groups
Religion and Belief Muslim adults are more
likely to be in poverty
compared to adults of
Christian and other faiths
and those with no religion.
Some, but not all, of the
higher poverty risk for
minority ethnic groups and
Muslims can be explained
by their lower average age.
As this policy is implemented
the level of service provided
will not be impacted by the
income of the tenant.
The policy should have
an overall positive
impact and it aims to
improve the level of
service provided to all
tenants.
Sex                           We need to be aware of
how policies may
differentially effect men and
women in particular
circumstances.
Women head 90% of single
parent families and are more
heavily involved in caring for
relatives than men. It is
important that repair
arrangements are adequate for
meeting the needs people who
may be juggling multiple tasks.
Women are more likely to be in
relative poverty than men,
because for example gender
pay gaps, and women making
up 90% of single parents
Estimates for single fathers are
not available due to small
sample sizes.
Women rely more on public
services than men.
A clear and sufficiently
flexible policy will be
especially beneficial for
women.
Sexual Orientation Relative poverty are rates
higher for LGB+ adults
compared to heterosexual
people.
As this policy is implemented
the level of service provided
will not be impacted by the
income of the tenant.
The policy should have
an overall positive
impact and it aims to
improve the level of
service provided to all
tenants.
Human Rights        The Human Rights Act
incorporates the European
Convention on Human
Rights (ECHR) into UK law.
This policy will not impinge
human rights and in
particular will support:
• Article 8 “right to respect
for private and family life,
home and correspondence”.
UNCRC Considerations, in
this circumstance
'protection' and 'provision'
are relevant.
The key aim of this policy is to
deliver a high quality, efficient
and effective responsive
repairs service, that will
provide a safe, secure and
healthy living environment, in a
manner which delivers value
for money, high rates of
customer satisfaction,
maintains properties in a good
and safe state of repair.
Having a comprehensive
and clear written policy
in place helps protects
people rights, including
the rights of children and
young people.
Page 203

Page 204

Health                     The Council has a focus on
Health and Wellbeing in its
strategic plan.
Having an improved policy with
clearer information protects
mental and physical health
Positive
Social & Economic
Impact     
The Council has a focus on
reducing poverty and child
poverty
Being a social renter is a
strong proxy measure in terms
of relative poverty. An
improved policy is beneficial to
Council Tenants.
Positive, better
maintained properties
contribute to economic
wellbeing and reduce
costs to renters 
Cross Cutting         A key cross cutting issue is
ensuring that both the policy
and the service is easily
accessible to all tenants.
The WDC BSL action Plan
24-30, commits to
increasing ease of access
to services for BSL users.
We need to have due
regard to the Consumer
Duty of relevant Strategic
Decisions, no additional
impact assessment is
required as the needs of
consumers are covered in
this circumstance through
the rest of this assessment.
The policy codifies and
improves our approach to
repairs.
People and communities can
and are effected by how issues
and circumstances cross cut.
The policy recognises this, in
terms of how repairs will be
organised to ensure that
peoples’ circumstances are
taken into account.
The policy follows the
Communicating Effectively
Guidance and in addition the
WDTRO played a role in proof
reading the policy and
providing feedback in terms of
the language used. We plan to
make a BSL video highlighting
the policy. The policy has a key
aim of providing a service that
is accessible and includes a
range of ways to easily contact
to report a repair.
Note above the range of
positive outcomes
anticipated. There is
nothing the in policy that
would lead to negative
impacts for people or
communities, or tenants.
Page 204

Page 205

Actions
Page 205

Page 206

Policy has a negative impact on an equality group,but is still to be implemented, please
provide justification for this.
Will the impact of the policy be monitored and reported on an ongoing bases?
Q7 What is you recommendation for this policy?
Please provide a meaningful summary of how you have reached the recommendation
EIA 1056: The Housing repairs policy brings information on the existing approach to repairs and
improvements such as shorter waiting time standard for essential repairs. This will have positive
impact for all tenants but especially people who may be more vulnerable in some circumstances
for example disabled people, older people, women and BME groups. Human Rights e.g. Right to
Family Life and Children's rights are also protected by improving the approach to repairs and
information on repairs. Care has been taken to ensure the document is as accessible as possible in
terms of language use and availability of alternate formats. A program of publicity and
information will support these goals.
Page 206

Page 207

Housing Services Consultation Summary
Name of consultation: Review of Housing Repairs Policy
Person responsible: Stefan Kristmanns, Housing Development Coordinator
Consultation start date: 12 June 2024
Consultation end date: 27 September 2024
Its aims and
objectives?
The aim of the consultation was to get views from our tenants on how
important key aspects of the repairs service are to them.
The key objective was to use this feedback to ensure that tenant
priorities were front and centre right at the start of the process and fully
taken account of as the policy was being reviewed and updated.
We also aimed to communicate changes and improvements that were
being proposed as a result of this review to the West Dunbartonshire
Tenants and Residents Organisation (WDTRO) and to tenants more
broadly and get their views and feedback in advance of the draft policy
being finalised.
Who was invited
to get involved?
All current WDC tenants were invited to participate and provide their
views.
Specific engagement with the WDTRO was also part of the consultation
process and the views of the West Dunbartonshire Equality Forum were
also sought.
Methods used to
invite and
promote tenants
to get involved?
We developed a short survey made up of 6 questions seeking the views
of tenants on how important key aspects of the repairs service are to
them.
The survey opened and was published on the Council’s website on 12
June 2024. A text message or email was sent to those tenants we had
these contact details for with a link to complete the survey.
The survey was also promoted via the Tenant Participation Facebook
page, the West Dunbartonshire Tenant and Residents Organisation
(WDTRO) and individual Tenant and Residents Associations (TRA’s).
The consultation was highlighted to the WDTRO at the WDC/WDTRO
Liaison meeting in June 2024. Following a revised policy being drafted
by Council officers and based on tenant feedback, a briefing note was
ITEM 13 - APPENDIX 3
Page 207

Page 208

2
provided in advance of the WDC/WDTRO liaison meeting on 22 August
2024.
The purpose of this briefing was twofold. Firstly to provide feedback in
relation to the consultation exercise, outline how the content of the draft
policy had been shaped by tenant feedback and inform the WDTRO of
the key changes being proposed in terms of target timescales for
certain categories of repairs.
Secondly, the key asks of the WDTRO were to comment on the content
of the draft policy and the changes being proposed and for the WDTRO
members to read over the draft policy to ensure the wording was clear ,
tenant friendly and provide us with feedback.
A follow-up discussion was held with council officers and the WDTRO
and their Committee meeting on 12 September 2024. A further survey
was also posted on the Council’s website, inviting tenants more broadly
to provide their views on the draft policy and the views of the West
Dunbartonshire Equality Forum were also sought.
Who took part? Just over 1000 individual responses were received, representing
around 10% of all council tenants.
There was also on-going engagement with the WDTRO throughout the
consultation process.
What good
practice or
minimum
standards can
you evidence as
part of your
consultation?
A key element of good practice was to seek tenant views right at the
start of the process and fully take these into account as the policy was
being reviewed and updated.
A variety of advertising methods were used to highlight and promote the
different elements of the consultation which ran from 12 June 2024 to
27 September 2024.
Outcome of the
consultation?
The key feedback from tenants via the consultation is outlined below:
How important are the various ways they are available to report a
repair?
Page 208

Page 209

3
90.2%
56.4%
44.7%
by phone by email via the online Repairs
Reporting Form
100%
80%
60%
40%
20%
0%
 Feedback showed that being able to report a repair by phone is
by far the most important to tenants, with 90.2% of those
responding saying this was very or fairly important to them.
How important to you is it that there are target timescales to carry out
different types of repairs?
84.9%
7.7%
5.4%0.8% 1.2%
Very important Fairly important Important Slightly
important
 Feedback showed that 92.6% of the tenants responding said that
target timescales for repairs to be completed was very or fairly
important to them.
Page 209

Page 210

4
How important to you is it that a repair is carried out within these target
timescales?
85.1%
8.1%
5.3%0.6% 0.8%
Very important Fairly important Important Slightly
important
 Feedback showed that 93.2% of the tenants responding said that
it was very or fairly important to them that repairs are carried out
within agreed target timescales.
How important to you is it that a repair appointment is agreed within
these target timescales?
85.4%
7.8%
5.4% 0.5% 0.9%
Very important Fairly important Important
Slightly important
Not at all important
 Feedback showed that 93.2% of the tenants responding said that
it was very or fairly important to them that a repair appointment is
agreed with them within the target timescales.
Page 210

Page 211

5
How important to you is it that the repair is carried out at the agreed
appointment time?
86.1%
8.3% 4.4%0.5% 0.7%
Very important Fairly important Important Slightly
important
 Feedback showed that 94.4% of the tenants responding said that
it was very or fairly important to them that a repair is carried out
at the agreed appointment time.
How important to you is it that the repair is explained when completed.
69.6%
14.3%
12.2%
1.8% 2.1%
Very important Fairly important Important Slightly
important
 Feedback showed that 83.9% of the tenants responding said that
it was very or fairly important to them that a repair is carried out
at the agreed appointment time.
Page 211

Page 212

6
WDTRO members were supportive of the proposed changes being
made in relation to target timescales for repairs, specifically of the
proposal to reduce target timescales for Urgent Repairs from 10 days to
5 days.
WDTRO members read the draft policy and the feedback received was
that the wording was clear, tenant friendly and easy to understand.
The WDTRO were also asked to provide their views on the definition of
complex repairs. The need for such a definition was identified during the
review process. It refers to instances where we recognise it will be
challenging to complete a repair within a defined timescale. Whilst this
is pre-dominantly an operational issue and not specifically referred to in
the Repairs Policy, good practice would be to discuss any such
definition with tenants. Feedback from the WDTRO was that the
definition was sensible and that they would be supportive of this
definition being adopted and for tenants to be advised when any
reported repair was being characterized as being complex. This
definition will be included in future staff guidance as part of the process
of implementing the revise policy.
The feedback received via second survey was limited and more mixed.
Only 72 responses were received but as the survey was asking for
views on the draft policy as opposed to what elements of the service
are the most important, participants would have to have read the policy
to fully participate. At this stage of the process the views of the West
Dunbartonshire Equality Forum were also sought.
How did the
consultation
influence decision
making?
This consultation feedback was key to informing the review which was
undertaken and to the development of a draft Responsive Repairs
Policy.
The feedback was key to ensuring that the draft policy:
 Delivers an enhanced level of service tenants can expect around
repair appointments and improved communication via text and
email.
 Retains target timescales for all categories of repairs.
 Provides clearer definitions of our different repairs categories with
additional examples, so that they are easier to understand
 Provides clear information around the type of repairs the Council
is responsible for and the repairs that tenants are responsible for.
 Provides clarity that repair target times begin when a repair is
reported.
Page 212

Page 213

7
Following feedback from the second stages of the survey, some
improvements were made to the wording used in the policy document.
Tenants will also have an opportunity at the Pre- HACC Forum to add
any final comments on the draft Repairs Policy and these will be
conveyed to the Committee by the Housing Convener.
Are you able to demonstrate this?
Yes through the survey results and content of the draft policy.
How was
feedback about
the consultation
and final decision
given?
Feedback was provided to tenants via the summer edition of Housing
News. Our thanks was communicated to those that had participated
and a commitment given that the feedback provided would be used to
help inform the revised policy.
Further feedback was provided in the autumn edition of the Housing
News which provided detail of the numbers that had participated,
broadly outlined the feedback that had been received and how this
would shape the revised policy.
Following the meeting of the Housing and Community Committee
meeting on 20th November 2024 we will highlight the outcome of the
consultation and subsequent policy changes to tenants in a Housing
News article, update the Council’s website and send tenants and text or
emailing with a link to further increase awareness.
Was the eight week timescale observed?                                       Yes      
Was equal opportunities information collected?                              Yes
Did you check
with participants
that they were
happy with the
opportunities
given to make
their views known
and that they felt
that we listened
and acted upon
them?
This was done directly with the WDTRO who provided positive
feedback.
This was not done directly with the wider number of tenants that
participated but feedback was provided via the Housing News with the
message that tenant opinion would shape the content of the revised
policy.
The fact that the response rate in the consultation was so high, provides
credible insight into the views of tenants.
What worked
well, what didn’t
work well – or any
other comments
you have.
The first stage of the consultation worked particularly well with high
numbers of tenants participating and providing their views. Using the
QL Housing Management System to send emails or texts to tenants we
have up to date contact details helped promote the consultation and
resulted in a high response rate and also meant that tenants not already
involved in participation provided their views. The feedback received
Page 213

Page 214

8
was key to the development of the draft policy and ensuring that it
delivers in terms of tenant priorities.
There was less participation at the second stage of the consultation but
this was expected to an extent, as it was asking for feedback on the
draft policy that had been developed and it was recognized that in order
to fully participate and provide feedback at this stage, would require a
higher level of time commitment.
Page 214

Page 215

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee: 20 November 2024
___________________________________________________________________
Subject:  Scottish Social Housing Charter Annual Benchmarking and Mid-Year
Progress Report
1. Purpose
1.1 The purpose of this report is to provide members with benchmarking information
relating to 2023/24 and a mid-year update in terms of how the Council’s Housing
and homelessness service is performing against the Scottish Social Housing
Charter indicators and meeting the requirements of the Scottish Housing
Regulator’s Regulatory Framework.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) Notes the content of this report recognising how the Council performed
compared to our peers during 2023/24 and mid-year progress in terms of
meeting the outcomes of the Scottish Social Housing Charter.
(ii) Notes that following the approval of our Annual Assurance Statement by
the Committee on 21 August 2024 that this has now been submitted to the
Scottish Housing Regulator as per our regulatory requirement.
(iii) Notes that our annual Charter Performance Report for 2023/24 has now
been published and a summary will be provided to all tenants with the
winter edition of the Housing News; and
(iv) Agrees that a full annual progress report on the Scottish Social Housing
Charter and Regulatory Framework will be submitted to the August 2025
meeting of the Housing and Communities Committee.
3. Background
3.1 The Scottish Government’s first Scottish Social Housing Charter came into force in
April 2012. This was reviewed during 2016 and again in 2021 and the resulting
revised Charter was approved by the Scottish Parliament and has effect from 1
November 2022.
3.2 The purpose of the Charter is to help improve the quality and value of the
services that social landlords provide by:
 Stating clearly what tenants and other customers can expect from social
landlords and helping them to hold landlords to account.
ITEM 14
Page 215

Page 216

 Focusing the efforts of social landlords on achieving outcomes that matter to
their customers, and
 Providing the basis for the Scottish Housing Regulator to assess and report
on how well landlords are performing.
3.3 The Scottish Housing Regulator published a revised Regulatory Framework and
associated statutory guidance for social landlords in February 2024 which has
effect from 1 April 2024 and the reporting timetable is outlined below:
When Who What
Throughout year
Housing Improvement
Board/Tenant
Representatives
Assess performance against the Charter
Outcomes
May each year Housing Development Submission of Annual Return on the Charter
(ARC) to the Scottish Housing Regulator
August each
year
Scottish Housing
Regulator
Publish a report about each social landlord with
key data from its ARC on their website
October each
year
Convener of Housing
and Communities
Committee
Submission of Annual Assurance Statement
(AAS) to the Scottish Housing Regulator
October each
year Housing Development Publication of annual Charter Performance
Report for tenants and other customers
by April each
year
Scottish Housing
Regulator 
Publish an Engagement Plan for each landlord,
highlighting areas where they are seeking
further assurance, based on performance
against Charter Indicators and outcomes and
compliance with statutory obligations
by April each
year
Scottish Housing
Regulator 
Publish a report on the analysis of the sectors’
performance in achieving the Charter Outcomes
3.4 On the 6 August 2014, Members of the Housing and Communities Committee
agreed that twice yearly reports be provided as follows:
 August Committee - Scottish Social Housing Charter Annual Update Report, and
 November Committee - Scottish Social Housing Charter Annual Benchmarking
Report and Mid-Year Progress Report – (April-September).
4. Main Issues
4.1 A report to the August 2024 meeting of the Housing and Communities
Committee outlined the content of our current Engagement Plan published by the
Regulator in April 2024, detailed 2023/24 performance compared to the previous
year and against annual targets set and highlighted key areas of concern that
would be monitored closely by the Housing Improvement Board, within the
context of the Housing Emergency declared by the Council in May 2024.
4.2 This report also sought approval for our Annual Assurance Statement which was
approved by the Committee and has subsequently been submitted to the
Scottish Housing Regulator within the timescale outlined in the Regulatory
Framework.
Page 216

Page 217

4.3 The key areas of focus in relation to the Scottish Social Housing Charter and
Regulatory Framework highlighted in this report are as follows: 
 Annual benchmarking data based on data published by the Scottish Housing
Regulator at the end of August 2024;
 Mid-year progress against key measures of performance in relation to
achieving the Charter Outcomes;
 The production and publication of our annual Charter Performance Report for
tenants and other customers;
 The continued development of effective tenant scrutiny arrangements in
conjunction with tenants and other customers. 
Benchmarking of key performance indicators 
4.4 The Scottish Housing Regulator now uses 32 Charter Performance Indicators to
monitor the performance of all social landlords against the Charter outcomes and
standards.   
4.5 Both our Annual Return on the Charter and annual performance information
submitted to Scotland’s Housing Network provide opportunities to compare our
performance against other landlords and to identify areas for improvement. This
process is known as “benchmarking”. 
4.6 The Regulator publishes a Landlord Report for every social landlord in Scotland on
their website by the end of August each year. This report contains key data from
the Annual Return on the Charter (18 key indicators) and compares our
performance with a Scottish average figure inclusive of all housing providers. Our
most recent Landlord Report is provided as a background paper to this report. 
4.7 Key findings from the benchmarking data available are outlined below: 
Status Key
Peer group compared to is all other
local authority landlords, as well as
Wheatley Homes Glasgow 
Top
quartile 
2nd
quartile 
3rd
quartile 
4th
quartile
Homeless People 2021/22
Value
2022/23
Value
2023/24
Value
2021/22
Rank
2022/23
Rank
2023/24
Rank
% of applications where household 
has experienced rough sleeping the 
night before presentation
2.9% 3.3% 3%   
Households assessed as homeless 
per 10,000 of households*  238 235   
% of all homeless cases re-assessed 
within 12 months (repeat homeless) 5.3% 4.4% 4.3%   
Average time in days from
application to assessment 14 13 12   
Households in temporary 
accommodation per 10,000 of 
households* 
68 62   
Page 217

Page 218

*Denotes new indicator and data not available for 2021/22 
Homeless People 2021/22
Value
2022/23
Value
2023/24
Value
2021/22
Rank
2022/23
Rank
2023/24
Rank
Average total time (days) spent in
temporary accommodation for cases
that closed
190 172 177   
Average time in days from homeless
assessment to case closure 207 189 175   
% of homeless households referred
to RSLs via section 5 referrals 31% 40% 25%   
Value for Money 2021/22
Value
2022/23
Value
2023/24
Value
2021/22
Rank
2022/23
Rank
2023/24
Rank
Average time to re-let properties 45.8
days
33.6
days
34.99
days   
Void rent loss expressed as a % of
the total amount of rent due 1.29% 1.28% 1.01%   
Rent collected as a % of total rent
due 98.39% 98.50% 99.09%   
Gross rent arrears as % of total rent
due 9.24% 10.00% 9.44%   
Neighbourhood and Community 2021/22
Value
2022/23
Value
2023/24
Value
2021/22
Rank
2022/23
Rank
2023/24
Rank
% of anti-social behaviour cases
resolved 98.1% 97.1% 98.1%   
% housed who maintained their
tenancy for at least 12 months 94.6% 94.1% 93.0%   
The average time to complete
applications for medical adaptations
107.8
days
73.0
days
45.4
days   
Quality of Housing 2021/22
Value
2022/23
Value
2023/24
Value
2021/22
Rank
2022/23
Rank
2023/24
Rank
% of properties meeting the
Scottish Housing Quality Standard 18.2% 32.2% 51.2%   
Repairs, Maintenance and
Improvements
2021/22
Value
2022/23
Value
2023/24
Value
2021/22
Rank
2022/23
Rank
2023/24
Rank
Average length of time taken to
complete emergency repairs
5.81
hours
4.5
hours
5.1
hours   
Average length of time taken to
complete non-emergency repairs
10.16
days
9.31
days
10.94
days   
% of reactive repairs carried out
completed right first time 86.5% 85.7% 85.6%   
How many times in the reporting
period did you not complete a gas
safety check within 12 months
0 0 0   
% of tenants satisfied with the
repairs and maintenance service 87.7% 83.7% 94.8%   
Page 218

Page 219

4.8 The tenant satisfaction levels reported for 2023/24 as part of the Scottish Social
Housing Charter Return are omitted from the table above as they are the same as
those for 2022/23 based on the last comprehensive survey carried out in 2022.  At
this time, the Council are conducting a new survey.  A report will be provided to
the Housing and Communities Committee in February 2025, fully outlining the
results of this latest survey
.
4.9 The table below provides a more local analysis comparing West Dunbartonshire
Council’s performance against comparable neighbouring housing organisations (3
neighbouring local authorities Renfrewshire, East Dunbartonshire and Stirling and
River Clyde Homes operating in Inverclyde). 
West
Dunbartonshire
Council
East
Dunbartonshire
Council
Renfrewshire
Council
Stirling
Council
River Clyde
Homes
HOMES AND RENT
Total Number of Homes
10,444 3,835 12,305 6,059 6,141
Rent increase
6.7% 4.8% 6.0% 6.0% 6.7%
West
Dunbartonshire
Council
East
Dunbartonshire
Council
Renfrewshire
Council
Stirling
Council
River Clyde
Homes
QUALITY AND MAINTENANCE OF HOMES
% of homes meeting the SHQS
51.2% 61.6% 68.6% 84.3% 84.2%
Average length of time taken to complete emergency repairs
5.1 hours 3.7 hours 5.6 hours 5.8 hours  4.1 hours
Average length of time taken to complete non-emergency repairs
10.9 days 13.1 days 7.9 days 6.9 days  22.1 days
% of reactive repairs carried out completed right first time
85.6% 81.1% 87.3% 92.5% 87.0%
% of tenants who have had repairs carried out on the last 12 months who were
satisfied with repairs and maintenance service
94.8% 89.7% 76.7% 84.1% 92.2%
NEIGHBOURHOODS
% of anti-social behaviour cases resolved
98.1% 100% 99.3% 81.5% 94.9%
VALUE FOR MONEY
Rent collected as % of total rent due
99.1% 100.7% 100.4% 99.7% 99.8%
Void rent loss expressed as a % of the total amount of rent due
1.0% 1.1% 1.5% 1.5% 6.1%
Average length of time taken to re-let homes
35.0 days 75.0 days 50.4 days 74.1 days 263.2 days
Page 219

Page 220

4.10 Performance improvement targets for 2023/24 for all the Charter Indicators have
been agreed based on robust benchmarking information and previous
performance. These targets challenge the housing service to meet our ambition
to be one of Scotland’s top performing landlord organisations. 
Mid-year progress achieving the Charter Outcomes  
4.11 Of the 32 Charter Indicators, 11 are reported on a six-monthly basis to the
Housing and Communities Committee, alongside 3 indicators relating to
homelessness (which are not part of the Charter return). 
4.12 A summary of performance for the period April 2024 – September 2024 for these
indicators is outlined in the table below: 
Status Key 
Target Met or exceeded  Target narrowly missed (within
agreed range)  Target missed
Quality of housing Mid-year
Target
Mid-year
Value Status
% of properties meeting the Scottish Housing
Quality Standard 62.2% 70.7% 
Repairs, Maintenance and Improvements Mid-year
Target
Mid-year
Value Status
Average length of time taken to complete
emergency repairs 4 hours  4.85 hours 
Average length of time taken to complete non-
emergency repairs 10 days 13.08 days 
% of reactive repairs carried out completed right
first time 91% 86.4 % 
How many times in the reporting period did you not
complete a gas safety check within 12 months 0 0 
% of tenants satisfied with the repairs and
maintenance service 87.5% 88.6 % 
Estate Management, Anti-Social Behaviour,
Neighbour Nuisance and Tenancy Disputes
Mid-year
Target
Mid-year
Value Status
% of anti-social behaviour cases resolved 93% 93.9% 
Tenancy Sustainability Mid-year
Target
Mid-year
Value Status
% of new tenants who maintained their tenancy for
at least 12 months 93.3% 91.3% 
Homeless People Mid-year
Target
Mid-year
Value Status
% of all homeless cases who received a decision
within 28-day target 95% 98.8% 
% of households requiring temporary
accommodation, to whom an offer was made 100% 100% 
Breeches of the Unsuitable Accommodation Order 0 17 
Value for Money Mid-year
Target
Mid-year
Value Status
Average length of time to re-let homes 30 days 28.2 days 
Void rent loss expressed as a % of the total amount
of rent due 1.0% 0.71 % 
Gross rent arrears as a % of total rent due 9.3% 9.9% 
Page 220

Page 221

4.13 Of these 14 key indicators, 8 are meeting the targets set, with another 3 narrowly
missing this target. Overall, this translates to 79% of these key indicators either
meeting or almost achieving target. 
Production and publication of Annual Charter Performance Report 
4.14 The Scottish Housing Regulator requires all social landlords to produce an Annual
Charter Performance Report for their tenants and other customers no later than 31
October each year. 
4.15 The Regulator states that the report should include: 
 An assessment of performance in delivering the Charter Outcomes.
 Relevant comparisons with previous years, other landlords and national
performance, and,
 How and when the landlord intends to address areas for improvement. 
4.16 In preparation for our first report, a working group of tenants and officers was
established and successfully: 
 Agreed how tenants wished to be involved.
 Agreed which indicators should feature in the report, and
 Agreed the best style and format to ensure that the report is user friendly and
easy to understand. 
4.17 Further engagement was conducted with tenant representatives during August
and September 2020 to review and update this report, in preparation for the
revised Charter coming into effect. This consultation again influenced the style,
content, and format the report and the update of the Service Standards that are
in place across housing services, and which are reported regularly to tenants and
other service users (via website and insert with Housing News). 
4.18 Our Annual Charter Performance Report for 2023/24 was published online within
the required timescale. The narrative in the report is based on the annual self-
assessment exercise of our performance and a summary of the report will be sent
to every tenant with the winter edition of the Housing News. The full report will be
sent to tenant groups, members of the WDTRO, members of the Scrutiny Panel
and the Scottish Housing Regulator. 
Tenant Scrutiny Arrangements 
4.19 The statutory regulatory framework for housing and homelessness services
demands that tenants participate in scrutinising landlords’ performance against
the Charter and requires that: 
 The form of involvement has been agreed with tenants.
 Involvement is effective and meaningful and that tenants have a real say in
assessment of performance.
 The approach is publicised to tenants; and
 Landlords’ can demonstrate the agreed approach was implemented.
Page 221

Page 222

4.20 Developing effective tenant scrutiny is therefore a challenging process, however
following support from the Scottish Government’s “Stepping Up to Scrutiny”
training programme in which elected members took part, these requirements
were successfully met and in November 2014 the Housing and Communities
Committee approved the establishment of our Tenant Scrutiny Panel with clear
terms of reference.
4.21 The Scrutiny Panel has subsequently carried out the following scrutiny exercises:
 2014/15 looking at our Anti-Social Behaviour Service.
 2015/16 looking at our Repairs Service.
 2016/17 looking at tenancy sustainment, specifically the new tenant visit
process.
 2017/18 looking at SHQS compliance, specifically the number and reasons
that properties that are held in abeyance.
 2018/19 looking at the timescales taken to complete medical adaptations.
 2020/21 looking at the complaints process and time taken to respond to
complaints, and,
 2022/23 looking at new tenant visits.
4.22 All of the recommendations made in the Panel’s first 7 reports were approved by
the HIB and progress in terms of implementing these are monitored by the HIB
and feedback provided to the Scrutiny Panel.
4.23 The Panel are currently looking at the service received by tenants in terms of
reporting and carrying out repairs and are due to submit their latest report to the
Housing Improvement Board on 25th November 2024.
4.24 The Scrutiny Panel were successful in being shortlisted for a prestigious
Chartered Institute of Housing excellence award in 2021 and though narrowly
missing out, this was national acknowledgement of the work that they do to
ensure that tenant scrutiny is a valued part of the Councils approach to
performance management.
4.25 The West Dunbartonshire Tenants and Residents Organisation (WDTRO) also
continue to be heavily involved in the scrutiny of the Housing Service and the
continuing work of the Joint Rent Group comprising tenants, Council officers and
the Convener of the Housing and Communities Committee, looking at the rent
setting process and the guidance in relation to the Housing Revenue Account,
remains important in ensuring Housing and Homelessness Services provide best
value for current and future tenants.
4.26 In September 2024 the WDTRO were announced as finalists in the Tenants
Information Service (TIS) National Excellence Awards for the Tenant Group of
the Year category. This recognises a tenant, resident, or community group who
have made an outstanding contribution and achieved great practice that others
can learn from in the future. The award winners will be announced as part of the
TIS National Housing Conference on 7th November 2024.
Page 222

Page 223

5. People Implications
5.1 There are no people implications because of this report. Delivery on the
requirements of the Scottish Social Housing Charter and compliance with the
Regulatory Framework is managed from within existing staffing resources.
6. Financial and Procurement Implications
6.1 There are no direct financial or procurement implications in relation to this report.
The improvement plan informed by the Charter self-assessment exercise is being
delivered from within existing budgets.
7. Risk Analysis
7.1 There is a significant risk that failure to respond appropriately to the
requirements of the Scottish Social Housing Charter and the Regulatory
Framework would attract an adverse reaction from the Scottish Housing
Regulator and may have wider consequences for the Council in the context of
Best Value.
7.2 At the time of writing we expect out next Engagement Plan to be published in
April 2025.
8 Environmental Sustainability
8.1 The delivery of the council’s housing investment programmes is within the
approved More Homes zero carbon approach. Our current and future approach
to strategic housing asset management will continue to prioritise a ‘zero carbon’
approach to decision making and deliverability and this will be done the aims of
the Housing Asset Management Strategy and the Council’s Climate Change
Strategy.
9. Equalities Impact Assessment (EIA)
9.1 Equalities legislation requires that new or significantly changing policies or
services and financial decisions should be subject to an assessment of their
impact on the wellbeing of certain groups of people. The recommendations
within this report do not alter any existing policy or pattern of service delivery and
so is not considered to require an equalities impact assessment.
10. Consultation
10.1 The Council has in place a well-established and proactive tenant and resident’s
organisational structure. The WDTRO meet with the Council (co-chaired by the
Convener of the Housing and Communities Committee) on a bi-monthly basis to
discuss all issues relating to the Housing Service.
10.2 There remains a strong appetite among tenants and customers to continue to
participate actively to improve housing services in West Dunbartonshire. This is
reflected in the successful partnership approach adopted to develop the Charter
Performance Report and the on-going activities of the WDTRO, the Joint Rent
Group the West Dunbartonshire Scrutiny Panel.
Page 223

Page 224

10.3 The Council is committed to ensure consultation continues and will support
arrangements to increase tenant scrutiny activities and assess our performance
in line with the requirements under the Scottish Social Housing Charter and the
SHR’s Regulatory Framework.  Our approach was commended via an external
validation exercise by the Tenant Participation Advisory Service (TPAS)
Scotland, who in 2023 again awarded West Dunbartonshire Council, a Gold
Accreditation for excellence in tenant participation.
11. Strategic Assessment
11.1 Having considered the Council's strategic priorities, this report contributes
significantly to all five strategic priorities and specifically to improve local housing
and environmentally sustainable infrastructure.
Peter Barry
Chief Officer, Housing & Employability
Date: 4 November 2024
___________________________________________________________________
Person to Contact:  John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness Team,
Housing and Employability, telephone: 07793717981, email:
john.kerr@west-dunbarton.gov.uk 
Stefan Kristmanns, Senior Housing Development Officer,
Housing Development and Homelessness Team, Housing and
Employability, email: stefan.kristamanns@west-
dunbarton.gov.uk
Appendices: None
Background Papers:     Annual Charter Performance Report 2023/24
Scottish Social Housing Charter/Regulation of Social Housing
in Scotland Annual Update,
Report by Chief Officer, Housing and Employability,
Housing and Communities Committee, 21 August 2024
West Dunbartonshire Council’s Engagement Plan, Scottish
Housing Regulator, 31 March 2024
Engagement plan from 1 April 2024 to 31 March 2025 |
Scottish Housing Regulator
Scottish Housing Regulator WDC Landlord Report 2023-24,
August 2023
West Dunbartonshire Council | Scottish Housing Regulator
The Scottish Social Housing Charter: Indicators and Context
Information, Scottish Housing Regulator
Page 224

Page 225

https://www.housingregulator.gov.scot/landlord-
performance/national-reports/national-reports-on-the-scottish-
social-housing-charter/about-the-scottish-social-housing-
charter 
Wards Affected:  All
Page 225

Page 226

Page 226

Page 227

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer, Housing and Employability
Housing and Communities Committee:   20 November 2024
___________________________________________________________________
Subject: “Involving You to Improve Housing Services,” West Dunbartonshire
Council’s Tenant Participation Strategy 2025- 2028
1. Purpose
1.1 The purpose of this report is to highlight to the Housing and Communities
Committee the Council’s statutory obligations in relation to tenant participation
and to seek approval for our new Tenant Participation Strategy entitled Involving
You to Improve Housing Services which will cover the period 2025-2028.
2. Recommendations
2.1 It is recommended that the Housing and Communities Committee:
(i) note the progress and achievements made in relation to the
implementation of the previous Tenant Participation Strategy 2021-
2024; and
(ii) approve the draft West Dunbartonshire Tenant Participation Strategy
2025-2028 and associated action plan
3. Background
3.1 The Council has a statutory obligation under the Housing (Scotland) Acts
2001 and 2010, to produce and adequately resource a Tenant Participation
Strategy. We also need to be able to evidence our commitment to involving
tenants in shaping and improving housing services.
3.2 In addition to being a legislative requirement, involving tenants and other
service users in decisions about their homes is now accepted as best
practice for all social housing providers and key to improving housing
services. The Tenant Participation Strategy supports the Council’s
commitment to deliver positive outcomes for our tenants and wider
communities.
3.3 Involving You to Improve Housing Services, West Dunbartonshire Council’s
Tenant Participation Strategy 2025-2028 replaces our previous strategy
covering the period 2021-2024 and builds on the many positive
developments of previous strategies successfully implemented since 2001.
3.4 Annual progress reports have been provided to Committee, with progress
also reported to the West Dunbartonshire Tenants and Residents
Organisation (WDTRO – the umbrella organisation for tenant groups in
WD) at bi-monthly Liaison meetings. An annual Tenant Participation
ITEM 15
Page 227

Page 228

Performance Report is also produced to publicly demonstrate the impact
tenant participation can have.
3.5 Some of the key achievements and improvements in tenant participation
delivered over the period of our previous strategies include:
• Re-awarded a Gold Accreditation for Excellence in Tenant Participation by
The Tenant Participation Advisory Service (TPAS) in 2023 (this is the
highest accreditation level that can be achieved);
• Communication is a key Social Housing Charter indicator for the Housing
Regulator, and we have continued to use our quarterly newsletter,
‘Housing News’ as a vehicle for updating and involving our tenants. The
WDTRO have a regular column in the newsletter, and it promotes local
Tenant & Resident Association activities, consultations, housing
developments and events. In line with the Charter, we also use it to share
our performance information with tenants.
• The Charter gives tenants the right and a range of measures to use, to
hold their landlord to account. That is an important part of tenant
participation, and it ensures that we can improve services for all tenants.
Tenants were involved in the review and design of the Annual Tenant
Report that we must produce on our performance against the Charter
outcomes;
• Bi-monthly WDC/WDTRO Liaison meetings allow Housing Services and
the WDTRO to work in partnership and improve Housing Services. The
WDTRO can raise concerns with Managers directly and has resulted in
improvements that all tenants can benefit from;
• Our active Scrutiny Panel play a key role in our performance monitoring
framework. The Panel is made up of tenants and factored owners who
independently scrutinise performance across the Housing Services and
make recommendations on how they could be improved for tenants. The
Panel are finalising their 8th scrutiny exercise and have been reviewing the
repair journey tenants experience and how that can be improved;
• Our Joint Rent Group (JRG) is made up of tenant volunteers, Housing and
Finance staff as well as the Housing Convenor to jointly scrutinise the
Housing Revenue Account (HRA) and it now fully complies with the
Scottish Government’s HRA Guidance. The group continues to meet
regularly and have contributed significantly to improving transparency
around how the Housing Revenue Account is spent;
• The work of the JRG has also helped improve the transparency of our rent
setting consultation and helped involve tenants earlier in the consultation
discussions;
• We have increased tenant involvement in rent setting. Tenant involvement
has consistently grown over the years and promoting voting options has
helped make tenants aware that they can influence the outcome of this
vital decision. In the rent setting consultation for 24/25, 1724 tenants voted
Page 228

Page 229

for their preferred option which equates to a healthy response rate of
17.3%; 
• Tenant Participation updates are distributed to Tenants and Residents
Associations (TRAs), tenants on the Interested Tenants Register,
Sheltered Housing Forum members, Scrutiny Panel members as well as
housing staff and elected members to share information and raise
awareness of tenant participation activities. 
4. Main Issues   
4.1 West Dunbartonshire Council can evidence a strong commitment to involving
tenants in shaping and improving housing services. However, the Charter
indicators that reflect tenant’s wider satisfaction with participation and
communication have declined so it is essential to reverse that change and use
effective tenant participation as a way of increasing tenant satisfaction. 
4.2 Involving You to Improve Housing Services– West Dunbartonshire Council’s
Tenant Participation Strategy 2025-2028 (attached as Appendix 1) sets out:  
• West Dunbartonshire Council’s approach to involving our tenants in the
development of Housing Services;
• The range of participation opportunities available to suit different
circumstances and interests;
• The benefits to tenants, Housing Services, and the wider community of
effective participation;
• The resources available and the support required for effective tenant
participation; and
• How the Strategy will be delivered, monitored, and reported. 
4.3 The aims of the Strategy are to: 
1. Improve the culture and practice of involving tenants across housing
services;
2. Improve our feedback to tenants so that we can evidence where our
tenants and other service users have influenced or shaped housing
services;
3. Continue to promote and provide a wide range of options for tenants to
get involved with us in a way that suits them;
4. Make sure that tenants are aware of the opportunities available to them to
get involved;
5.   Continue to encourage involvement of under- represented groups such as   
young people, homeless people, people with disabilities and minority ethnic
groups;
6.   Promote the difference tenants can make and the positive benefits of
participation to them personally as well to their community;
Page 229

Page 230

7.   Continue to develop tenants’ involvement in monitoring and improving
performance through our Scrutiny Panel as well as individual tenants
holding us to account;
8.   Ensure that the resources we put in place and practices we carry out are
adequate to support and develop tenant involvement; and
9.   Ensure that we communicate effectively with tenants and provide good
quality, accessible information that tenants want.  
4.4 The Strategy also addresses the Council’s tenant scrutiny requirements under
the Scottish Social Housing Charter, monitored by the Scottish Housing
Regulator. In terms of the Scottish Social Housing Charter a separate section
outlining how we measure and report performance to tenants and how we use
tenant scrutiny activities to inform service development and improve
performance is included within the strategy document. 
5. People Implications 
5.1 There are no people implications from this report. There are two fully
dedicated staff members funded from the Housing Revenue Account, focused
on the development and delivery of tenant participation. In addition,
supporting tenant participation is part of the remit of all officers across housing
services. The Strategy will therefore be delivered by input from staff across all
of Housing and Homelessness services. 
6. Financial and Procurement implications 
6.1 Actions required to take the Strategy forward in 2025/28 will be aligned to
current budgetary provision. There is a specific tenant participation budget
and for 2024/25 has been set at £102k which includes an additional budget
specifically to develop digital engagement including through the tenant self-
serve portal. 
6.2 There are no procurement implications in respect of this report. 
7. Risk Analysis 
7.1  The Council has a statutory responsibility to develop, publish and implement a
Tenant Participation Strategy. Our “Involving You to Improve Housing
Services” Strategy reflects the priorities and aspirations of tenants and tenant
representatives, therefore there is a risk that if its key aims are not be
achieved, then this would produce an adverse reaction from tenants, tenant
representatives and from the Scottish Housing Regulator. 
7.2 Our Tenant Participation Strategy builds on the achievements made in
developing good working relationships with tenants over the years, improving
transparency and a joint working approach to involving tenants. The continued
delivery of a new Tenant Participation Strategy is therefore essential in
demonstrating the Council’s on-going commitment to continuous improvement
across Housing Services and putting tenants at the centre of our activities. 
8 Environmental Sustainability 
Page 230

Page 231

8.1  The delivery of our housing investment programme is within the approved
More Homes zero carbon approach. Our current and future approach to
strategic housing asset management will continue to prioritise a ‘zero carbon’
approach to decision making and deliverability and this will be done the aims
of the Housing Asset Management Strategy and the Council’s Climate
Change Strategy. 
9.    Equalities Impact Assessment 
9.1     An Equality, Health and Human Rights Impact Assessment has been carried
out on the draft TP Strategy and found no substantive negative impacts. A
copy of the assessment is included in appendix 2. 
10.    Consultation 
10.1   The development of the new strategy started with a critical review of what had
been achieved from the previous strategy and what needed further
development. TPAS reviewed our 2017-2020 TP Strategy as part of their
accreditation process and highly commended the style and use of clear
language in the Strategy so that has been continued in this Strategy. 
10.2 Workshops were carried out with staff and tenants to review how tenant
participation was currently working and what needed to change and be
improved. 
10.3 A public consultation was carried out with a survey to all tenants to gauge
awareness of tenant participation, satisfaction with opportunities to get
involved, what information tenants use and how they rate it, and awareness of
consultations and feedback. 
10.4 The consultation highlighted that better communication was a critical element
needed to improve tenant participation and several actions are included to
improve communication with tenants but also to improve internal
communication to help housing staff be able to effectively deliver tenant
participation in their daily work. 
10.5 Improving the culture and practice of involving tenants across Housing
Services also needs to continue to improve to build trust and consistency and
ensure a positive experience for tenants. This is one of the key aims of the
strategy and several actions are included to increase local engagement,
walkabouts and promote the benefits of tenant participation to staff and to
tenants. 
10.6 The emphasis of tenant participation being about improving performance was
also identified in the consultation as needing more promotion, so we have
amended the name to ‘Involving You to Improve Housing Services ‘to help
emphasise the purpose of the Strategy. 
10.7 Actions are also included in the action plan to support existing tenants,
tenants’ groups, develop more digital options and increase engagement with
under-represented groups so that all tenants can have their say.
Page 231

Page 232

10.8 A fuller breakdown of the consultation outcomes are included in strategy
document attached as appendix 1. 
11.  Strategic Assessment   
11.1   Having considered the Council's strategic priorities, this report contributes
significantly to all strategic priorities. 
Peter Barry
Chief Officer, Housing and Employability
Date: 7 November 2024 
Person/s to Contact: John Kerr – Housing Development and Homelessness
Manager, Housing Development and Homelessness
Team, Housing and Employability, telephone:
07793717981, email: john.kerr@west-dunbarton.gov.uk 
Stefan Kristmanns, Housing Development Co-ordinator,
Housing Development and Homelessness Team,
Housing and Employability, email:
stefan.kristamanns@west-dunbarton.gov.uk 
Jane Mack, Senior Housing Development Officer,
Housing Development and Homelessness Team,
Housing and Employability, email: jane.mack@west-
dunbarton.gov.uk   
Appendices:                     1. Draft West Dunbartonshire Council Tenant Participation
Strategy 2024-2028 
2. Health and Inequalities Impact Assessment   
Wards Affected: All 
Page 232

Page 233

1
Involving You
To Improve Housing Services
West Dunbartonshire Council’s Draft Tenant Participation Strategy
2025-28
ITEM 15 -
APPENDIX 1
Page 233

Page 234

2
This document is also available in other languages, large print and audio format on
request.
Arabic
British Sign Language users can contact us via contactSCOTLAND-
BSL, the on-line British Sign Language interpreting service on 01389737198
Chinese (Cantonese)
Gaelic
Tha an sgrìobhainn seo cuideachd ri fhaighinn ann an cànanan eile, ann an clò mòr, agus
ann an cruth claisneachd ma thèid iarraidh
Hindi
Polish
Punjabi
Ukrainian
Цей документ також доступний іншими мовами, великим шрифтом та в аудіоформаті
за запитом.
Urdu
West Dunbartonshire Council, 16 Church Street, Dumbarton, G82 1QL
equalities@west-dunbarton.gov.uk 01389 737198
Page 234

Page 235

3
Contents
Foreword Councillor Gurpreet Singh Johal, Housing Convener and
Frances McGonagle, Chairperson of the WDTRO
Section 1 - Introduction – what is tenant participation?
Section 2 - Background and key principles
Section 3 - How can you get involved in West Dunbartonshire?
Section 4 - Benefits of tenant participation – for you, your neighbourhood and
for Housing Services
Section 5 - Achievements
Section 6 - How we developed the Strategy
Section 7 - Aims of the Strategy
Section 8 - Scottish Social Housing Charter and tenant scrutiny of performance
Section 9 - Measuring Tenant Participation
Section 10 - Consultation and feedback- seeking your views and influencing
decisions
Section 11 - Keeping you informed
Section 12 - Resourcing and supporting tenant participation activity
Section 13 - The Action Plan – what we will do to achieve the aims of this
Strategy
Appendices
Appendix 1 - Who’s who in Housing Services
Appendix 2 - List of current Tenants and Residents’ Associations
Appendix 3 - Tenant Participation Strategy Consultation Summary
Page 235

Page 236

4
Foreword
Councillor Gurpreet Singh Johal, Convener of the Housing and Communities
Committee.
Welcome to Involving You to Improve Housing Services, our new Tenant
Participation Strategy for the period 2025 to 2028.
(to be included)
Cllr Gurpreet Johal
Convener, Housing and Communities Committee
Frances McGonagle, WDTRO Chairperson
Tenants have a stronger voice when they work together, and we welcome this
Strategy as it sets out how we can continue to develop tenant participation in
decision making and improving the housing services we receive. The WDTRO is the
umbrella group for all Tenant & Resident Associations and tenants and we work to
make our neighbourhoods better places to live.
We appreciate that not everyone has the time or interest in getting involved and we
work hard to be a representative organisation so that we can do that on peoples’
behalf.  We want more tenants to get involved and this Strategy encourages that
involvement and sets out the resources and support available for tenants getting
involved, which can be very rewarding, either for yourself or in a group.
One of the key things for us is that tenants need to be able to make a difference and
be listened to. Through the Liaison meetings we have made sure that walkabouts
are more effective, repair performance is improved and its good we have the
opportunity to raise issues but we want all tenants to see improvements in their
areas and know how to raise issues. Every tenant should know who their Housing
officer is and they are key people to listen to tenants. The goal for tenant
participation is to improve Housing Services so that is our focus. We also want to
make sure that our rents are affordable and we get value for our rent money so there
is still a long way to go but I’m grateful to all the tenants who do get involved as
together we do make a difference.  
Page 236

Page 237

5
[Section One]
Introduction – What is tenant participation?
Welcome to our Tenant Participation Strategy 2025-28 which was produced in
partnership with tenant representatives, tenants, staff and Councillors. This Strategy
tells you how we will achieve effective tenant participation in housing services.  You
can find out about the range of ways you can get involved, how we are going to
provide you with information, how we are going to consult with you and use your
views and how we are going to work with you so that you can influence what we do
and hold us to account. The aim is to improve housing services and tenant
satisfaction.
What is tenant participation?
‘It’s about tenants and tenants and residents groups taking part in decision making
processes and influencing decisions about housing policies, conditions and related
services.  It is a two-way process, which involves the sharing of information, ideas
and power. Its aim is to improve housing conditions and services’.
(‘Partners in Participation, A National Strategy for Tenant Participation’ produced by
the Scottish Executive in 1999.)
This definition is useful because it tells us what tenant participation is, what needs
to happen to make it work and what the outcome should be.  Tenant
representatives agreed that it is a good definition and emphasises the 2-way process
- it doesn’t however emphasise the importance of local walkabouts as a way of
participating which tenants value and although in a definition all aspects can’t be
captured, the importance of walkabouts is emphasised in section 3.
Being able to demonstrate outcomes achieved by tenant involvement is one of the
best ways of encouraging more people to get involved and the main feedback from
tenants is that they want to make a difference so it’s vital that we can make that
happen.  ‘Involving You’ is the name we have used for this Strategy and that is
exactly what we want and need to do.
For more information on this Strategy or if you are interested in getting involved,
please contact our Tenant Participation Officers,
Jane Mack, 0798 354 2993 or jane.mack@west-dunbarton.gov.uk
Jennifer McKechnie 0782 366 247 or  Jennifer.McKechnie@west-dunbarton.gov.uk
Page 237

Page 238

6
[Section Two]
Background and key principles
At West Dunbartonshire we are committed to continually improving and the best way
to do that is to listen and involve tenants in decision-making.  We have a legal duty
to involve tenants and service users, but more importantly we have a long history of
active tenant involvement and are committed to ensuring that this continues.
The Housing (Scotland) Act 2001 introduced the first legal framework for tenant
participation by giving tenants the rights to participate and be consulted.  The Act
also put new duties on all Local Authorities and Registered Social Landlords (RSLs)
in Scotland which all still apply.
Your rights:
 to form independent representative organisations and apply for registration and
funding;
 to access information about housing policies and related services;
 be consulted on issues that affect your homes; and
 participate in decisions that affect the services you receive and have enough
time to consider draft proposals and put forward views
The Council’s duties:
 to comply with equal opportunity legislation and involve often forgotten groups
such as Gypsy Travellers and disabled tenants
 consult individual tenants as well as tenants and residents groups before making
any decision that would change,
- how we manage our housing properties
- the standard of service we provide
- any proposals to sell, transfer or demolish housing stock
 take on board tenants’ views before decisions are taken
 develop a Tenant Participation Strategy and put it into practice, ensuring that it
complies with equality requirements
 put the Tenant Participation Strategy into practice and measure performance
against the agreed action plan
 provide resources and support to make sure tenant participation is effective
 regularly review how well tenant participation is working
 set up arrangements for registering tenants groups
Page 238

Page 239

7
We must also ensure we meet the standards set out in the Scottish Social Housing
Charter which was introduced by the Housing (Scotland) Act 2010 and last reviewed
in 2022.  The Charter sets out the standards and outcomes that all tenants can
expect from social landlords, in terms of the quality and value for money of the
services they receive, the standard of their homes, and opportunities for
communication and participation in the decisions that affect them.
There are currently 16 outcomes and standards that all landlords need to achieve
and publicise their performance against, every year. This means tenants can review
their landlords performance and it is a useful tool for helping tenants hold their
landlord to account. A full list of the Charter indicators are in Appendix 5.
Of the 16 Charter outcomes there are four main ones that are particularly relevant to
tenant participation:
Outcome 2 – Communication   Social landlords manage their businesses so that:
 Tenants and other customers (i.e. residents) find it easy to communicate with
their landlord and get the information they need about their landlord, how and
why it makes decisions and the services the landlord provides.
Outcome 3 – Participation   Social landlords manage their businesses so that:
 Tenants and other customers find it easy to participate in and influence their
landlords’ decisions at a level they feel comfortable with.
Outcome 14 & 15 - Rents and Service Charges   Social landlords set rents and
service charges in consultation with their tenants and other customers so that:
 A balance is struck between level of service provided, the costs of the services,
and how far current and prospective tenants and service users can afford them.
 Tenants get clear information on how rents and other money is spent, including
any details of individual items of expenditure above thresholds agreed between
landlords and tenants.
Equality and Inclusion
We are committed to being inclusive, free from discrimination and prejudice and
treating everyone equally.
We will comply with all Equality and Human Right legislation and fulfil the three key
elements of the general equality duty as defined in the Equality Act 2010:
 We want to get rid of discrimination, harassment and victimisation
 We want to encourage equal opportunities between people who share a
protected characteristic and those who do not
 We want to encourage good relations between all people. This includes
challenging prejudice and building understanding.
We will promote inclusive approaches and work in ways that are appropriate to
different people and differing needs within our communities. We have also carried
out an equality impact assessment on this Strategy to minimise any barriers that
Page 239

Page 240

8
tenants may experience and identify opportunities for improving our approach that
we have built into the Strategy.
Our Tenants and Residents Associations also must show their commitment to equal
opportunities to meet our registration conditions to become registered tenant
organisations.
We will continue to use a range of ways to give all tenants the opportunity to get
involved and influence decisions about housing services, policies and standards. We
will provide information in a range of formats (e.g. large print, BSL video and
interpreting) and various languages to suit our tenants and prospective tenants’
needs on request.  We also use “WDC Communicating Effectively”, the Council
guide to inclusive communication.
Public meetings and events will always be held in accessible buildings with hearing
Loop system facilities. We will also provide transport or cover transport costs and
cover reasonable care costs to support people attending meetings or to get involved.
[Section 3]
How you can get involved
We want to encourage more tenants to get involved in shaping housing services and
provide you with as many opportunities as possible to do this so you can pick
something that suits your circumstances and interest. 
We have a long history of active tenant involvement through Tenants and Residents
Associations (TRAs).  While our Associations have an important part to play and we
continue to support them, we recognise that not all tenants want to or have the time
to get involved in this way.
If you want to find out more about any of these options then please get in touch –
phone or text 0798 354 2993 or email tenant.participation@west-dunbarton.gov.uk
Walkabouts were identified in our consultation as an important way for tenants to
get involved locally. A walkabout is a planned and publicised walk around your
neighbourhood, street or block of flats. It is a good way to highlight what could be
improved and can be done with housing staff so that issues are recorded and then
actioned. The walkabout process has been improved to ensure actions are
completed as quickly as possible or updates are given, and progress is now
monitored at WDC/WDTRO Liaison meetings to ensure they get done well
consistently. They are also a good way to identify proposals for the Tenant Priority
Budget.
Make a proposal for the Tenant Priority Budget
The Tenant Priority Budget is an annual budget that tenants decide how it’s spent.
Any tenant can put in a proposal and there are criteria for how it can be used,
 must benefit tenants.
Page 240

Page 241

9
 be on land owned by the Housing Revenue Account (we can help confirm
that)
 the idea should be something that the Council, as the landlord, would not be
responsible to carry out but it improves the area. (ie not repairs that the
Council should already be doing).
If you have an idea to improve your area, then the Tenant Priority Budget can help
bring these ideas to life. Proposals are costed up and at a public meeting, tenants
decide if it’s value for money (i.e. consider cost against how many tenants it will
benefit) and if it should proceed. Successful proposals are varied from planters in
Faifley to planned laundry facilities for multi-storey flats at Littleholm and Kilbowie
Court.
Read the Housing News
We use the Housing News to provide you with information on what is happening in
housing services, how to get involved in consultations and report the outcomes of
consultations and Council decisions. We also promote community activities and
showcase what impacts tenants are having in their area. It also includes regular
performance information so all tenants can see how we are performing and question
performance levels.
It gets posted to all WDC tenants 4 times a year and also available online. We try to
make the Housing News as interactive as possible, include a quiz and tenants can
write or email Housing News (housing.news@west-dunbarton.gov.uk)  if you have a
question about Housing Services or if you would like to comment on the Housing
News.
Completing surveys or questionnaires
We use a number of satisfaction surveys for your view about specific areas of
housing services, for example you will be sent a survey from Building Services when
they complete a repair or a survey from Housing Operations when you move into a
new tenancy. These are used to gauge satisfaction and resolve any issues identified.
The Council will also carry out a bi-annual tenant satisfaction survey to capture
tenants’ views which are used to develop an action plan for improvements.
Consultation surveys will also be carried out from time to time and we will promote
them through the Housing News, our website and Facebook page
https://www.facebook.com/West-Dunbartonshire-Council-Tenant-Participation  to
make them available to individual tenants as well as TRA members. Most surveys
are done online but paper copies of surveys are also available.
New tenants
Housing Officers advise new tenants on their rights to participate as part of the
process of signing a tenancy agreement.  They will use this, and the new tenant visit
to explain the opportunities available for tenants to get involved in their particular
area as well as an individual tenant.
Tenant Participation Officers also send out a follow-up post card to encourage new
tenants to get involved and provide their contact details.
Page 241

Page 242

10
Interested Tenant Register
Many tenants don’t want to be involved in a group or don’t have a group in their area
but still want to get more involved, so we have an ‘Interested Tenant Register’.
Tenants on the Register are given the same information shared with our Tenants
and Residents Associations and receive direct invites to get involved in consultations
and other events. They don’t have to attend regular meetings but can still keep up to
date with what’s happening in Housing Services and get involved in topics that they
are interested in.  Any tenant can join our Interested Tenant Register by contacting
the Tenant Participation Officers or through their Housing Officer.
Attending conferences and events
We host annual tenant events designed to encourage individual tenants to engage
with Housing Services and to develop existing groups.  These events aim to raise
awareness about tenant participation activities, ask for views on different areas of
the housing service and provide an opportunity for tenants to get together and share
their ideas. Representatives from our registered tenant organisations are invited to
be involved in planning these events with us.
We also provide funding for tenants to attend conferences and events run by TIS,
CIH or any other relevant organisation.
Attending focus groups and public meetings
From time to time, we will set up focus groups or public meetings to look at a
particular part of the housing service, for example if we review our Allocations Policy
or the Joint Rent Group which was set up to scrutinise the Housing Revenue Account
(HRA).  These will be open to all tenants and we will promote them widely.
Sheltered Housing Forum
Housing Services and the Health and Social Care Partnership (HSCP) have
developed a joint approach to supporting the Sheltered Housing Forum.  The Forum
gives representatives from all nine sheltered complexes an opportunity to get
together with Housing and HSCP staff to discuss the Sheltered Housing Service
Standards, raise issues directly with staff and monitor developments.
The Forum meets every 3 months and each complex takes a turn in hosting the
meeting. Tenant Participation staff work with the Care at Home staff to provide
minutes, agenda and transport for all Forum members.
Scrutiny Panel
Our Scrutiny Panel is open to all tenants or owners who receive a factoring service
from the Council and they take an independent look at Housing performance.  They
choose what area they want to scrutinise and once they have reviewed performance
and the processes involved, they make recommendations for improvements which
Housing Services have committed to implementing. Thus, the Panel can directly
influence improvements. Depending on what topic they look at, their work can be
quite in-depth but they are supported by tenant participation staff, training, by each
other and their work can be very rewarding.
Page 242

Page 243

11
Tenants and Residents’ Associations
Tenants and Residents’ Associations are made up of local tenants and residents who
represent their area to bring about improvements in housing and other related services.
We recognise the independence of these Associations and the contribution they make
in improving services for all tenants and in representing the area they live in. 
A full list of all Tenants and Residents Associations is in Appendix three.
Groups can apply for a Tenant Participation Grant if at least half of the elected
committee (50%) are West Dunbartonshire Council tenants.  This is because the
grants are funded from the Housing Revenue Account (HRA) so needs to benefit
tenants. The Tenant Participation Grant can be used to cover all the administration
costs of running a TRA e.g. hall hire and printing costs etc.  Groups that do not wish
to apply for funding can still become a registered tenant organisation (RTO) with
West Dunbartonshire Council. 
Registered Tenant Organisations
Tenants and Residents’ Associations that meet the criteria set out by the Scottish
Government can register with West Dunbartonshire Council as a registered tenant
organisation.  Registration is easy and doesn’t require the Associations to do much
more than they are already required to do under their constitution.  The key
difference between an Association and a registered group is that by registering with
the Council, Associations have a recognised role in decision-making processes.
West Dunbartonshire Tenants and Tenants and Residents Organisation
West Dunbartonshire Tenants and Residents Organisation (WDTRO) is an umbrella
organisation which acts to co-ordinate the activities of all registered tenant
organisations (RTOs). Their aim is to make sure that the RTOs work together to
improve housing services and standards and raise issues that affect all tenants.
You can contact the WDTRO by email (harrymccormack.wdtro@gmail.com) or by
Facebook www.facebook.com/WestDunbartonshireTRO
WDC/WDTRO Liaison Meetings
The Council and the WDTRO have regular bi-monthly meetings so that tenant
representatives, Councillors and senior housing staff can work together to improve
the delivery of housing services.  This ensures that our tenant representatives have
direct access to those with decision making authority. Objectives are agreed and
driven jointly by tenants and Council representatives with both being able to put
items on the agenda. Minutes of these meetings are distributed to all RTOs and
available on the Council’s website. The meetings are chaired alternatively by the
Housing Convenor and the WDTRO chairperson, or their deputies, to reflect this key
partnership approach.
Page 243

Page 244

12
Pre-HACC Tenants Forum
The Housing and Communities Committee (HACC) sets the policies and strategies
for all services provided by Housing Services. It meets every 3 months and decisions
are taken by the committee after Councillors consider and discuss reports by the
Council’s officers.
Prior to each of the quarterly HACC meetings, tenant representatives from tenant
groups and individual tenants have an opportunity to meet with the Housing
Convener and officers who wrote the reports.  The purpose of the meeting is to
exchange views on the reports going before the HACC and to allow tenants direct
access to the Housing Convener. The Housing Convener then presents these views
as part of the Committee’s discussion which forms part of the decision-making
process, so this Forum gives real power to tenants to influence the HACC’s
decisions.
Representing all Tenants
We are aware that there are groups of tenants that are often under-represented in
tenant participation.  For example, young people, travelling people, homeless service
users, people with disabilities, black and minority ethnic groups and lesbian, gay,
bisexual and transgender groups.
We will look to develop different ways to involve tenants so that groups of people are
not excluded and our action plans sets out more detail on what we will do to achieve
inclusive participation.
Local engagement
Since 2016 Housing Services have been organised into 3 operational teams to focus
housing management resources at a local area level. Housing Officers have a set area
to manage and are involved in all aspects of tenancy management.  This model allows
them to build up relationships with the tenants within their patch. Our consultation has
highlighted that more local engagement is needed to increase tenant satisfaction and
involvement and several actions are included in our action plan to develop that
positively.
Complaints and compliments
West Dunbartonshire Council is committed to providing the best quality services it
can afford and aims to continually improve services.  Our complaints procedure lets
you tell us what you feel has gone wrong and helps us improve our services for
everyone.  Our complaints procedure is set out in Appendix Four.
It is also good to hear when things work well and any compliments are passed onto
the staff involved so they are aware of the difference they are making.
Page 244

Page 245

13
[Section four]
Benefits of tenant participation – for you, your neighbourhood and for
Housing Services
Ultimately, we want to improve Housing services but there is much to be gained
personally and for your neighbourhood from tenant participation.
Benefits for you:
Tenant Participation has many benefits, both for you as an individual and for tenants
in general:
 Improve the services you and all tenants receive
 Improve your home and neighbourhood
 Ensures tenants get good information about the Council’s Housing Services
 Gives tenants better knowledge and understanding of Housing processes
 Empowers tenants to influence decision-making on changes to Housing Services
 Gives tenants the opportunity to scrutinise performance and processes
 Helps people build confidence
 Develop new skills and knowledge
 Add volunteering experience to your CV
 Reduce social isolation and improve mental health
 Can give people a purpose and help them make a positive contribution to their
community
 Make new friends and can even be fun!
Benefits to Housing Services
 Improves performance through tenant insight, scrutiny and suggestions
 Helps ensure Housing Services are responsive to tenants’ needs and aspirations
 Tenants provide knowledge to officers about how things are working on the
ground and helps them understand the problems tenants are facing
 Builds relationships between tenants and Council officers
 Can increase tenant satisfaction
 Tenant volunteers bring with them a lifetime of skills and experience, and can
make a positive contribution to the work of the Council
 Allows for communications, policies and procedures to be considered and
reviewed by tenants to ensure they meet tenants’ needs and are effective
Page 245

Page 246

14
Benefits to the wider community
 Better neighbourhoods through improved services
 Offers a stronger voice to the wider community
 Provide the Council with an insight into how services work in the community
 Ensures the community is better informed about housing services
 Makes sure that tenants and other customers’ views are heard
Valuing your time
Without tenants who volunteer their time to get involved, we can’t have tenant
participation and we value the time that tenants give to get involved with us.  We
hope that any involvement will be personally rewarding but we also provide transport
or cover travelling expenses for any tenant attending a meeting arranged by Housing
Services and our TP Grants cover out of pocket expenses for tenant and resident
group members as well as the running costs of the group. 
We will provide support and training to help tenants get involved. Volunteering in any
tenant participation activity can be a good way to help people get into or back into
employment and we will provide references for any tenant who has been actively
involved.
[Section five]
Achievements
Since the last TP Strategy was agreed in 2022, we have made some key
improvements in tenant participation, for example:
 TPAS accreditation is a national mark of excellence for participation activities
and we were re-awarded a gold accreditation in 2023.
 We’ve increased tenant involvement in rent setting. Tenant involvement has
consistently grown over the years - information provided has been made easier
to understand and voting options promoted which has helped make tenants
aware that they can influence the outcome of this vital decision. In the rent
setting consultation for 24/25, 1724 tenants voted for their preferred option which
equates to a healthy response rate of 17.3%.
 We’ve developed an annual performance report on TP activities to help evidence
the positive impact tenant participation can have.
 The WDC/WDTRO Liaison meetings regularly resolve a range of issues brought
up by tenants from improving communications when lifts are out of action to
improving the consistency of walkabouts to ensure they were more effective and
that updates are regularly provided. The regularity of the Liaison meetings also
helps develop positive working partnerships to improve effectiveness.
 Our Joint Rent Group, made up of tenant volunteers, Housing and Finance staff
as well as the Housing Convenor, jointly scrutinises the Housing Revenue
Account (HRA) and the Council is now fully compliant with HRA Guidance. Their
Page 246

Page 247

15
work has also helped increase transparency around the HRA, monitor how rent
money is spent and help ensure tenants get value for money.
 The Tenant Priority Budget is an effective participatory budget that gives tenants
the opportunity to decide how this annual budget is spent.  Any tenant can make
a proposal and tenants publicly decide which proposals are value for money and
should go ahead.  The Budget is promoted in the Housing News and gives
tenants a great opportunity to see improvements happen in their neighbourhood.
 Our quarterly newsletter called ‘Housing News’ is an important way to
communicate with all WDC tenants. In the tenant satisfaction survey carried out
in October 2022, 85% said they read the Housing News to keep up to date. As
well as housing updates, we include community news and the WDTRO have a
regular column to help give a tenants’ point of view.
 We have developed clear, understandable performance information which we
regularly include along with Housing News to increase tenant awareness around
Housing Services’ performance and to help tenants scrutinise our performance.
 Our Scrutiny Panel independently scrutinise performance across the Housing
Services and focus on areas that are most important to tenants or where
improvements are most needed. For each of their scrutiny exercises, they make
recommendations and then monitor action plans to ensure they are happy that
their recommendations are implemented. All Scrutiny Panel recommendations
have been implemented to date.
 TP Updates are distributed to Tenants and Residents Associations (TRAs),
tenants on the Interested Tenants Register, Sheltered Housing Forum members,
Scrutiny Panel members as well as housing staff and elected members to share
information and raise awareness about tenant participation activities.
 We continue to support local TRAs and helped establish new TRAs where there
was demand.
 We continually review the content of our TP webpages and update with meeting
notes from the Joint Rent Group, WDC/WDTRO Liaison meetings, Sheltered
Housing Forum and Pre-HACC Forum so that all tenants can get access to this
information.
 Our number of followers on Facebook continue to increase and we post regularly
with community information as well as housing and TP information.
[Section Six]
How we developed the Strategy
This Strategy builds on previous TP Strategies and action plans. It has been
developed in line with current housing legislation, the National Standards for
Community Engagement and in consultation with staff, tenants and tenant groups.
The following key stages formed our review process:
 We reviewed the previous Tenant Participation Strategy, what had been
achieved, and what areas were still relevant and needed further development
Page 247

Page 248

16
 We reviewed other landlords’ strategies to learn from their objectives and
achievements
 TPAS reviewed our 2017-2020 TP Strategy as part of our Accreditation and
highly commended the style and use of clear language in the Strategy so that
has been continued into this Strategy.
 In May and June 2024, we carried out workshops with staff and then tenants to
review how TP was currently working and what needed to change and be
improved.
 From 1 August to 24 September, we carried out a public consultation with a
survey to all tenants to gauge awareness of tenant participation, satisfaction with
opportunities to get involved, what information tenants use and how they rate it
and awareness of consultations and feedback.
A summary of the consultation and consultation results are included in Appendix 6.
[Section seven]
Aims of the strategy
Our main aim is to improve Housing Services by working in partnership with tenants
to develop and influence how these services are provided. We have amended the
name of the strategy to ‘Involving You to improve Housing Services’ to help reinforce
this key aim of tenant participation.
Our aims reflect important legislative and regulatory requirements but also reflect the
views of tenants collected during our consultation and the aims are listed in the order
of importance that tenants gave them.
We will:
 make sure that the resources and practices we put in place are sufficient to
support and develop tenant involvement
 continue to promote a wide range of options for tenants to get involved in. This
will include more interactive online networks and virtual meetings to help people
be involved from home.
 Make sure tenants are aware of the opportunities and their rights to get involved.
 improve our feedback to tenants so that we can evidence where tenants and
other service users have influenced or shaped housing services
 promote the difference tenants can make and the positive benefits of
participation to them personally as well to their community
 continue to encourage involvement of under-represented groups such as young
people, homeless people, people with disabilities and minority ethnic groups
 improve the culture and practice of involving tenants across housing services
 make sure that we communicate effectively with tenants and provide good
quality, accessible information that tenants want
Page 248

Page 249

17
 continue to develop tenants’ involvement in monitoring and improving
performance through our Scrutiny Panel as well as individual tenants holding us
to account
Our Action Plan in Section 13 sets out more detail of how we will meet these aims.
[Section eight]
Scottish Social Housing Charter and tenant scrutiny of performance
The Scottish Social Housing Charter came into effect on 1st April 2012.  Tenants
across Scotland were involved in its creation and in its review every 5 years to
ensure it is still focuses on performance that tenants are most interested in.  The
Charter aims to improve the quality and value of services provided by social
landlords and sets out 16 outcomes and standards that all social landlords should
aim to achieve. You can see the full list of Charter Outcomes in Appendix five.
The Scottish Housing Regulator is an independent body responsible for monitoring,
reporting and assessing how well social landlords, like West Dunbartonshire Council,
are achieving the Charter’s outcomes and standards.  Each year the Council must
gather evidence to demonstrate to the Regulator and to tenants and service users
how it is meeting the outcomes of the Charter.  Tenants can also use the Regulator‘s
website to compare how well the Council is performing against other social
landlords.  This helps tenants understand if their landlord is performing well or not. 
https://www.scottishhousingregulator.gov.uk/ 
How we monitor performance
We monitor performance to make sure we are improving the services we provide
and to identify where we can make improvements, for example we measure how
long it takes to allocate a house when a tenant leaves and the number of repairs
done right first time.  We have a performance monitoring framework which makes
sure that all the necessary performance information is being recorded and that
authorised officers are monitoring and accountable for that performance.
How tenants are involved in monitoring performance
We have developed clear, understandable performance information which we
include with each edition of the Housing News to increase tenant awareness around
Housing Services’ performance and to help tenants scrutinise our performance.
Tenants can raise any questions on the performance information and contact details
are given on the reports.  There is also a performance section on the Council’s
website which all tenants can look at.
How tenants are involved in Scrutiny
Involving tenants in scrutinising our performance is essential for improvements to be
made and to ensure we focus on tenants’ priorities.  Tenant scrutiny is the name
given to the activities that offer tenants an opportunity to get involved in assessing
our performance. 
Page 249

Page 250

18
WD Scrutiny Panel
Our Scrutiny Panel was set up in 2014. The Panel is open to all tenants or owners
who receive a factoring service from the Council and training and out of pocket
expenses are provided.  The Panel developed their own terms of agreement and
aims and are independent from the Council although supported by the Housing
Development team to access information and assist with their meetings.
A training tool called ‘Stepping up for Scrutiny’ was developed nationally and is used
to introduce volunteers to scrutiny.  On-going training and support is also available
for Panel members as their involvement in tenant scrutiny activity develops.  The
Scrutiny Panel form part of the Council’s formal performance monitoring framework
and there is a commitment to action all reasonable recommendations from the
Panel’s scrutiny exercises.  The Panel’s  reports and recommendations are reported
through the Housing News and made public on the TP webpages.– https://www.west
-dunbarton.gov.uk/housing/council-housing/tenant-participation/west-dunbartonshire-
scrutiny-panel/
They have carried out 7 scrutiny exercises so far:
 New tenant visit 2023
 WDC Complaints Handling 2021
 Medical adaptation process 2020
 Scottish Social Housing Quality Standard (SHQS) Compliance 2019
 New tenant visit process 2017
 ‘Right First time’ repairs 2016
 Anti-social behaviour complaint process 2015
The Panel monitor the implementation of their recommendations so they are assured
that they are put in place.  It is the Panel who decide what performance area they
want to look at and focus on ensuring processes are improved from the tenants point
of view.
If you’d like to join the Scrutiny Panel or find out more, please contact them as they
welcome new members. Email scrutinypanel2014@gmail.com or give the TP team a
call or text on 0798 354 2993.
How performance is reported to tenants
In addition to submitting annual performance information to the Regulator, the
Council is also required to produce a Tenants Report to show progress in meeting
the Charter outcomes. Tenants played a key role in creating the look and content of
our report to ensure that the performance information included is what they are
interested in.  Each year the report is reviewed involving tenants to ensure it
continues to reflect tenant’s priorities.  The tenants report also gives us an
opportunity to encourage tenants to get involved in performance monitoring and ask
questions about performance.
We also have a regular performance insert that gets delivered to all tenants along
with the Housing News and contact details are included to encourage contact.
Page 250

Page 251

19
[Section nine]
Measuring Tenant Participation
We have created a range of actions to ensure that the aims of ‘Involving You to
Improve Housing Services’ can be put into practice and tenant impact can be
measured. Being able to demonstrate outcomes achieved by tenant involvement is
one of the best ways of encouraging more people to get involved and to ensure that
we are continually improving housing services.
We will continue to provide regular progress reports to the WDTRO via the Liaison
meetings as well as the Sheltered Housing Forum, through the Housing News and
our TP webpages.
We will also produce an annual tenant participation performance report and share it
widely to help emphasise the outcomes achieved.
Of the 16 Charter outcomes there are four main ones that are particularly relevant to
tenant participation:
Outcome 2 – Communication   Social landlords manage their businesses so that:
 Tenants and other customers (i.e. residents) find it easy to communicate with
their landlord and get the information they need about their landlord, how and
why it makes decisions and the services the landlord provides.
Outcome 3 – Participation   Social landlords manage their businesses so that:
 Tenants and other customers find it easy to participate in and influence their
landlords’ decisions at a level they feel comfortable with.
Outcome 14 & 15 - Rents and Service Charges   Social landlords set rents and
service charges in consultation with their tenants and other customers so that:
 A balance is struck between level of service provided, the costs of the services,
and how far current and prospective tenants and service users can afford them.
 Tenants get clear information on how rents and other money is spent, including
any details of individual items of expenditure above thresholds agreed between
landlords and tenants.
We will report how well we are achieving these outcomes as well as measuring what
we spend the TP Budget on, what we produce as a result and the outcomes for
tenants.  This will be reported to both the WDTRO and to the Housing and
Communities Committee on an annual basis in the format of an annual committee
report.
Page 251

Page 252

20
[Section ten]
Consultation and feedback- seeking your views and influencing
decisions
Consultation must be meaningful and the outcome of consultations must direct
changes in policy or service delivery as a result.  This distinguishes consultation from
asking your views. We will always follow good practice and a consultation toolkit for
staff has been developed to ensure all consultations conducted are meaningful and
effectively deliver change.
 We will bring tenants and tenant organisations into the consultation process from
the start
 We will use a number of approaches to consulting, for example, the Housing
News, leaflets / posters, public meetings, open days, focus groups, surveys and
through our website and social media to collect views from as wide a range of
tenants possible
 The method of consultation will depend on the scale and significance of the issue
or topic
 We will give detailed information on any proposals we are consulting on,
including:
- how the proposal will affect tenants,
- how and within what timescales tenants can make their views known to us,
- how and when the final decision will be taken,
- the contact officer dealing with the consultation and,
- information on how and where to complain.
 Where possible, individual tenants and tenant organisations will be given a
minimum of 8 weeks to respond to any consultation
 If we want to do this in less than eight weeks, Council officers must seek
permission from the Housing Development and Homelessness Manager. If
permission is granted, we will explain why the consultation must be carried out
within a shorter timescale.
We will consult you on:
1. Annual Rent levels
2. Any changes to housing policies or housing services e.g. Allocation policy,
relet standard for empty properties, repairs and maintenance services and
standards.
Feedback
We use the views of tenants and service users to shape and improve the housing
services you receive.  It is important that we provide feedback so that you know we
have listened to and acted on your feedback. Providing feedback is also important as
it encourages others to get involved. 
Page 252

Page 253

21
[Section eleven]
Keeping you informed
We know how important it is that we provide you with good quality, up to date
information which is accessible to everyone and free of jargon.  Some of the
methods we use include:
 Letters, phone, text and email
 surveys and questionnaires
 briefing notes and TP Updates
 face to face meetings
 home visits where a need is identified
 updates to Tenants and Residents Associations and registered tenant organisations
 through our Interested Tenants Register
 focus groups
 public meetings
 tenant handbook
 tenant events or other public events
 Housing News
 notice boards in our multi-storey blocks or tenement flats
 Council website  https://www.west-dunbarton.gov.uk/housing/council-
housing/tenant-participation/  and
 Social media
https://www.facebook.com/WestDunbartonshireCouncilTenantParticipation
We produce 4 editions of our tenant newsletter ‘Housing News’ each year and send
it to all our Council tenants and those staying in temporary accommodation.
Electronic copies are also sent to all housing staff and local Councillors and an
accessible version is available on our webpage.
We encourage tenants groups as well as staff to use Housing News as a way of
communicating with all our tenants.
To ensure we are as inclusive as possible, we provide all written information in a
clear, accessible and easy to understand format, using plain language and where
necessary in community languages.  This includes making information available on
request in other formats such as Braille, large print and audio format.
Page 253

Page 254

22
Tenants Handbook
Our tenant handbook provides essential information for tenants. An electronic
version is available on the Council’s website and tenants can request a paper copy
from their Housing Officer. We regularly review the handbook with the help of
tenants to make sure that it is in a style and format which is useful, clear and easy to
use. https://www.west-dunbarton.gov.uk/housing/council-housing/tenancy-and-
allocations/tenant-handbook/
The Sheltered Housing Tenant Handbook
Tenants in Sheltered Housing accommodation have a specific tenant handbook
which set out their tenancy rights and responsibilities as well as support
arrangements.  The Sheltered Housing Forum members helped produce their tenant
handbook and will be involved in its review. https://www.west-
dunbarton.gov.uk/media/4318309/sheltered-housing-booklet.pdf
Tenants and Residents Associations Handbook
A Basic Guide designed to support new and existing TRAs has been developed to
cover all aspects of running and managing a group. It also includes how to register
with the Council as a registered tenant organisation. The TRA Handbook is available
on our TP webpages along with useful forms to help TRAs be independent while still
having the support of TP staff when needed.
http://www.west-dunbarton.gov.uk/media/4307905/basic-guide-website-
version.pdf
TP Updates
Tenant Participation Officers produce a quarterly TP Update for TRA members, and
tenants in our Scrutiny Panel, Sheltered Housing Forum or on the Interested Tenants
Register. The updates are also shared with staff and Councillors to help keep people
informed on TP activities and developments.
Digital Communication
The Council invested in an Integrated Housing Management System (IHMS) in 2019
to help develop how we provide services to tenants. The Tenant Portal side of the
system gives tenants greater access to check on their rent account, report repairs
and monitor the progress of repairs. The system also provides options to send text
reminders to tenants about appointments, consultations or to carry out short surveys.
The reminders about consultations have already proven useful and helped increase
response rates. There is more scope to develop this system further and could help
improve communication with tenants so a specific action is included in the action
plan to prioritise this.
The Tenant Participation section on the Council’s website is kept up to date with
information and minutes from meetings so they are available to any tenant at a time
that suits them and to encourage involvement. https://www.west-
dunbarton.gov.uk/housing/council-housing/tenant-participation/
The Council also has a Facebook page and X account which tenants can use to
obtain information and provide comment.  There is also a TP Facebook page which
we use to promote consultations and share information about local events and group
activities. Facebook
Page 254

Page 255

23
[Section twelve]
How we will resource and support tenant participation activity
To make the process of involving tenants as effective as possible, we provide a
range of resources which both individual tenants and TRAs can access. 
Housing Staff
All housing staff are responsible for encouraging and supporting tenants to get
involved.  This can include practical support such as providing information about
Council services, attendance at meetings, providing training or information sessions
and delivering consultation events. Tenants should be advised of the opportunities to
get involved when they sign up for a WDC tenancy but also at other times during
their tenancy as people’s circumstances and interests change.
Tenant Participation Officers
Within the Housing Development Team there is a Senior Housing Development
Officer (Tenant Participation) and a Housing Development Officer (Tenant
Participation) who are responsible for supporting and developing tenant participation
activity across West Dunbartonshire.
The Senior Housing Development Officer is specifically responsible for developing,
implementing and reporting on the aims of this Strategy. They also support the
WDTRO, Scrutiny Panel, Joint Rent Group and Sheltered Housing Forum.
The Housing Development Officer is responsible for promoting the Tenant Priority
Budget, developing new ways to get involved, supporting existing TRA’s and help
create and support new groups where there is a demand.
They both also provide encouragement, training and support to individual tenants
and tenants on our Interested Tenant Register to participate and develop.
Funding Tenants and Residents Associations
TRAs play a vital part in making sure our services reflect the needs of local
communities.  We are committed to providing support and resources to make sure
Associations can function effectively and be representative.
Start-up grants are available for new Associations and annual grants are available to
existing Associations to cover their administration and running costs – e.g.to pay for
photocopying, room hire for meetings or travelling expenses.  One-off expenses to
provide equipment to groups, such as laptops, printers are also made available to
groups which are well established. Public Liability Insurance is also paid for each TRA.
There are currently 5 Associations who have a community flat to base their activities
from. The rent, insurance and utility charges are met by TP Grants given to groups.
Their use of premises varies, but is primarily used as office and meeting space,
Housing Officer and local Councillor Surgeries and can be used to provide meeting
space for other community activities. We encourage these TRA’s to maximise the
use of their community flat so that it is a valuable community asset e.g.
Page 255

Page 256

24
Westbridgend TRA host a clothing bank in theirs and Tullichewan TRA host a regular
Knit and Natter group and art classes. 
Information, training and support
All TRAs are offered support and training from the Housing Development Team. 
Tenant Participation Officers usually attend meetings to support the committee until
they are happy to proceed on their own. Formal training covering all aspects of
running and managing an Association and guidance to become registered tenant
organisations is offered.  Our Associations will also be offered help to
carry out action planning to assist them to achieve their goals and demonstrate their
achievements.
Tenant Participation training is also made available to all housing staff to ensure that
we can put our tenant participation strategy into practice effectively. An ilearn course
called ‘What is Tenant Participation?’ is available and should be part of all new staff’s
induction training as well as a regular refresher for existing staff.
Information sessions are arranged as and when required in response to
developments, in support of consultation events or to discuss housing topics
requested by TRAs.
The Housing News is distributed to all tenants and TRAs four times a year and used
as our main way of sharing information with all tenants.  We also use regular TP
Updates and briefing notes to share good practice and information.
Training and encouragement are made available to all tenants to help them get
involved.  As an additional incentive to encourage more involvement, we also
provide references for anyone who has volunteered to help them get into or back
into, employment.
Financial support is available to ensure that no one is out of pocket by getting
involved and we can cover travelling expenses and reasonable care costs. We can
arrange taxis to assist people getting to and from meetings.
Conferences and events
Tenants who are represented by a Tenants and Residents Association or who are on
the Council’s list of interested tenants can attend annual conferences and events
carried out by the Council, the Chartered Institute of Housing, the Tenants
Information Service or the Tenant Participation Advisory Service. Costs for attending,
transport and any other expenses are met through the tenant participation budget.
Including everyone
Our resources and support services are there for everyone to get involved.  We use
the principles set out in the National Standards for Community Engagement to
ensure that where possible there are no practical barriers to any tenant being fully
involved.  This includes:
 suitable transport to attend meetings
 general assistance
 access to premises
Page 256

Page 257

25
 communication aids (such as loop systems, advocacy and interpreting services)
 opportunities to meet at a time and a place that suits
Access to other sources of information, support and advice
Scottish Government Social Housing Team
Contact: 0300 244 4000 or email: ceu@gov.scot
Tenants Information Service (TIS) - www.tis.org.uk
Contact:  0141 248 1242 or email info@tis.org.uk
Tenant Participation Advisory Service Scotland (TPAS Scotland) -TPAS - Your
Friendly Engagement Experts (tpasscotland.org.uk)
Contact: 0141 552 3633 or email enquiries@tpasscotland.org.uk
www.tpasscotland.org.uk
Equality Advisory and Support Service
Contact: 0808 800 0082 or via FREEPOST EASS HELPLINE FPN6521
www.equalityadvisoryservice.com
The Tenant Participation Budget
All direct funding to support tenant participation activity comes from the rent and
benefits tenants pay into the Housing Revenue Account. Therefore, we need to
ensure that we spend our Budget effectively and for the benefit of tenants.
In 2023/24 we spent £82,158.44 on tenant participation activities. Our Budget enables
us to financially support 12 TRAs, the WDTRO, Sheltered Housing Forum, Pre-HACC
Forum and Scrutiny Panel to help them function effectively and as independently as
possible. The cost of producing the Housing News also comes out of our Tenant
Participation Budget and this takes up most of our communication costs.
We also have 5 TRAs who have community flats that they operate from and the running
costs for these are included in the costs for supporting TRA’s, along with annual and top
up grants to cover their running costs. Public liability insurance is also paid for each
active TRA.
Transport costs to and from meetings are also covered to ensure no-one is put off
attending meetings by costs and that no tenant volunteer is out of pocket. Our postage
costs are from providing pre-paid postage envelopes to encourage people to return
surveys, vote in the rent setting consultation, return tenant priority budget proposal
forms etc. if not doing so on-line. It also includes posting out meeting information so
people have paper copies of information to be discussed.
We report each year how the Tenant Participation Budget is spent in our annual TP
performance report and make the details publicly available. The chart below splits up
how the 23/24 Budget was spent.
Page 257

Page 258

26
Page 258

Page 259

27
The action plan [Section thirteen]
This action plan sets out how we will meet the aims of this Strategy.
What we will do How we will do it When we
will do it
Who is responsible
1. We will
improve the
culture and
practice of
tenant
participation
across
housing
services
 Ensure all new
staff complete
the TP ilearn
course as well
as existing staff
completing
course every 3
years
 Promote the
benefits of
involving tenants
to staff and it’s
direct link to
improving
housing services
and tenant
satisfaction
 produce
quarterly TP
updates for
elected
members,
housing and
related services
staff to raise
awareness of TP
activities
 Improve inter
team
communication
and provide TP
updates for all
housing and
homelessness
services.
 record outcomes
from involving
tenants and
publicise them
through the
Housing News
and other TP
On-going
August
2025
quarterly
March
2025
ongoing
annually
November
2025
Service Managers
TP Team (Housing
Development)
TP Team (Housing
Development)
TP Team (Housing
Development)
TP Team (Housing
Development)
TP Team (Housing
Development)
TP Team (Housing
Development)
TP Team (Housing
Development) and Service
Managers
Page 259

Page 260

28
What we will do How we will do it When we
will do it
Who is responsible
communication
channels
 publish an
Involving You
annual report
 Develop better
links between
Housing Officers
and local TRA’s
and help
develop positive
relationships
with TRA
members.
 Promote to staff
that walkabouts
are a good way
to identify issues
and build
relationships
with tenants.
November
2025
2. We will
improve
feedback to
tenants so
that we can
demonstrate
where our
tenants and
other service
users have
influenced or
shaped the
housing
services
 Review the
Consultation
Toolkit with staff
to ensure it is
effective and
easy to use
 outcomes from
consultations
will be
communicated
to participants
and will be
publicised via
the Housing
News,
webpages and
social media to
ensure that
tenants can see
where they are
November
2025
on-going
on-going
Housing Development
Housing Development
TP Team (Housing
Development)
TP Team (Housing
Development)
Page 260

Page 261

29
What we will do How we will do it When we
will do it
Who is responsible
making a
difference.
 support TRAs to
demonstrate
their
achievements
locally
 Promote the
benefits of
having a TRA
and include
practical
examples.
 publish annual
tenant
involvement
outcomes as
part of TP
performance
report
 demonstrate the
outcome(s) of
tenant
involvement in
tenant scrutiny
activities
 support tenants
and TRA
representatives
to review papers
going to the
HAC Committee
and encourage
them to
participate in the
Pre-HACC
Forum
November
2025
annually
on-going
quarterly
TP Team (Housing
Development)
TP Team (Housing
Development)
TP Team (Housing
Development)
3. We will
promote and
provide a
wide range of
options for
 promote the
range of options
and support in
place to
encourage
on-going
June 2025
TP Team (Housing
Development)
Page 261

Page 262

30
What we will do How we will do it When we
will do it
Who is responsible
tenants to get
involved with
us. 
tenants to get
involved
 explore easy
read option to
produce a leaflet
version of the
TP Strategy
2025-2028 to
make the TP
Strategy more
accessible and
user-friendly
 Encourage
more
individual
tenants to
become
involved in
tenant
participation
.
 support TRAs to
produce flyers,
posters  and
create social
media or
websites
promoting the
work that they
do and how to
get involved
 continue to
deliver an
annual tenant
conference or
event
 explore new
methods to
provide
information and
obtain tenants’
views (e.g.
social media,
Tenant Portal)
on-going
on-going
annual
November
2025
ongoing
ongoing
TP Team (Housing
Development)
TP Team (Housing
Development)
TP Team (Housing
Development)
TP Team (Housing
Development)
TP Team (Housing
Development)
TP Team (Housing
Development)
TP Team (Housing
Development)
Housing Ops
Building Services
Page 262

Page 263

31
What we will do How we will do it When we
will do it
Who is responsible
 continue use of
virtual meetings
as option for
people with
limited time as
well as for those
with mobility
issues as an
attractive option
to get involved
from the comfort
of own home.
 promote
walkabouts to
encourage
tenants to get
involved in their
own
neighbourhood.
4. We will
encourage
involvement
of under-
represented
groups such
as young
people,
homeless
people,
people with
disabilities
and minority
ethnic
groups.
 explore
opportunities to
develop
Mightynetworks,
a digital
platform, as a
more interactive
and accessible
option to
increase tenant
participation
from young
people
 Continue links
with local youth
groups like
YSORTIT, Youth
Council to raise
awareness of
participation
opportunities
and tenant rights
 explore
opportunities to
November
2025
ongoing
November
2025
TP Team (Housing
Development)
TP Team (Housing
Development)
TP Team (Housing
Development / Homelessness
Team
TP Team (Housing
Development)
Page 263

Page 264

32
What we will do How we will do it When we
will do it
Who is responsible
develop a forum
for people in or
previously lived
in
temporary/supp
orted 
accommodation
 Continue to
support tenants
at Dennystoun
Forge to work
with Housing
Services and
focus on their
priorities.
 Continue
membership of
West
Dunbartonshire
Equality Forum
and promote
tenant
participation to
wider groups
 develop links
with other
agencies and
projects that
work with
tenants who
have disabilities
and identify
ways to improve
involvement in
TP
Monthly
quarterly
ongoing
TP Team (Housing
Development)
TP Team (Housing
Development)
5. Ensure
tenants are
aware of the
options
available to
them to
shape
housing
 produce and
promote an
annual
consultation
calendar so
tenants know in
advance
opportunities
they have to
annually TP Team (Housing
Development)
Page 264

Page 265

33
What we will do How we will do it When we
will do it
Who is responsible
service plans
and budgets
influence
housing services
and policies.
 carry out an
annual
consultation on
rent setting and
provide clear
information for
tenants to be
able to make
informed
choices
 Continue to
facilitate the
Joint Rent
Group to
scrutinise the
Housing
Revenue
Account to
increase
transparency
and value for
money.
 Support the
Joint Rent
Group to
develop tenant
involvement in
the HRA budget
decision making
process
 Ensure new
tenants are told
at sign ups and
new tenant visits
about their rights
to get involved
and the
opportunities
available.
 Explore new
opportunities to
promote the
annually
on-going
ongoing
March
2025
ongoing
Chief Officer, Housing and
Employability/Housing
Development
TP Team (Housing
Development)/Tenant
representatives
TP Team (Housing
Development)/Finance/Tenant
representatives
Housing Operations Manager
TP Team (Housing
Development)
Page 265

Page 266

34
What we will do How we will do it When we
will do it
Who is responsible
range of options
available to
tenants to get
involved.
6. Assess our
performance
in line with
the Scottish
Social
Housing
Charter and
involve
tenants in our
annual
Tenant
Report.
 agree with
tenants what
Charter
indicators they
want included in
the Tenant
Report.
 review the best
style to use to
ensure the
report is
accessible and
easy to
understand
 Assist WD
Scrutiny Panel
to review and
scrutinise
performance
data
 support scrutiny
activity by
offering formal
training for staff
and tenants
taking part
 recruit new
members onto
the WD Scrutiny
Panel
June 2025
June 2025
on-going
on-going
on-going
Housing Development
Housing Development
Housing Development
TP Team (Housing
Development)
TP Team (Housing
Development)
7. Ensure that
the resources
we put in
place and
practices we
carry out are
 Assess training
requirements of
TRA members
and create
training plans for
each group
Annually
ongoing
TP Team (Housing
Development)
Page 266

Page 267

35
What we will do How we will do it When we
will do it
Who is responsible
adequate to
support and
develop
tenant
participation
activity
 Monitor TP
Budget
spending
Housing Development Co-
ordinator
8. We will
ensure we
communicate
effectively
with tenants
and provide
good quality,
accessible
information
that tenants
want
 review and
improve the
content on the
TP web pages
and use of
social media.
 Ensure all
Housing web
pages remain up
to date with
relevant
information
 Create a
webpage to
promote
walkabouts and
share updates
on action plans
 continue to
produce
quarterly
editions of the
Housing News
to keep all
tenants up to
date with
housing
investment,
service
developments,
outcomes from
consultations
and local tenant
activities.
 Share digital
skills and
access, to assist
housing teams
annually
quarterly
March
2025
quarterly
ongoing
June 2025
TP Team (Housing
Development)
All Housing Service Managers
TP Team (Housing
Development)
TP Team (Housing
Development)
Housing Development
TP Team (Housing
Development)
Page 267

Page 268

36
What we will do How we will do it When we
will do it
Who is responsible
produce and
promote
improved
information for
tenants
 assess interest
in creating an
editorial group
with tenants to
develop content
of the Housing
News
 Ensure TP
information is
circulated
directly to
relevant staff
November
2025
TP Team (Housing
Development)
Page 268

Page 269

37
Appendix One - Who’s Who in Housing Services
Chief Officer
Housing and
Employability
Peter Barry
Housing Development
and Homelessness
Manager
John Kerr
Homelessness
Co-ordinator
Joanne Sutherland
Housing Development
Co-ordinator
Stefan Kristmanns
IHMS Project
Co-ordinator
Graham Watters
Housing Development
Co-ordinator
Claire McKay
Housing Operations
Manager
Nicola Pettigrew
Area Co-ordinator
Suzanne Marshall
Area Co-ordinator
Scott McLelland
Area Co-ordinator
David Lynch
Area Co-ordinator
Kevin McCrossan
Page 269

Page 270

38
Appendix Two
List of current registered tenant organisations (RTOs) and tenants and
residents associations and federations
Contact details are available on Council website or by contacting TP team
Registered Tenant Organisations
 Central Alexandria Tenants and Residents Association
 Central Radnor Park Tenants and Residents Association
 Dalmuir Multi-Storey Flats Tenants and Residents Association
 Haldane
 Littleholm Tenants and Residents Association
 Old Whitecrook Tenants and Residents Association
 North & South Drumry Tenants and Residents Association
 Risk Street Tenants and Residents Association
 Tullichewan Tenants and Residents Association
 Westbridgend Tenants and Residents Association
 Willox Park Tenants Association
Federation
 WDTRO- West Dunbartonshire Tenants and Residents Organisation
(representing all groups across West Dunbartonshire)
Contact details of all Tenants and Residents Associations can be obtained from the
Tenant Participation Team by calling 07823 664247 or by email to
tenant.participation@west-dunbarton.gov.uk
Page 270

Page 271

39
Appendix Three
Housing Services - Consultation Recording Sheet
Housing Service …Housing Development
Person responsible:  Jane Mack, Snr Housing Development Officer (Tenant
Participation)
Consultation Start date:……28/5/24…….End Date……24/9/24…………………...
1. Title of consultation /
participation exercise
Review of Tenant Participation Strategy.
2. Aims and objectives Review current Strategy and develop a new strategy and
action plan for 2025-28.
3. Invited to get involved:
(e.g. all tenants, tenant
from the interested
tenants register,
RTOs, staff)
All tenants and members of the WDTRO, Tenant &
Residents Associations, Scrutiny Panel, Sheltered Housing
Forum, Interested Tenant Register, housing staff and
TPAS.
4. Methods used to
promote/invite
stakeholders to get
involved? (e.g. letters,
posters, website)
The Council’s website was used to advertise the
consultation as well as social media, text and emails.
The online survey was directly promoted to all TRA
members, tenants on our Interested Tenant Register,
through the WDTRO and TP Facebook page.
We also sent text and emails to all tenants that we had
contact details of through QL to promote the survey.
Paper copies of the survey were made available, and
tenants given a name and contact number to make this as
easy as possible.
5. Who took part
(Actual number of
individuals and or
number of tenant
organisations
represented)
5 members of staff took part in the workshop on 28/5/24 to
give their views and those of their colleagues.
14 tenants attended the workshop on 1/6/24.
411 tenants responded to the tenant survey and 35 staff
members responded to the staff survey.
6. Method(s) used to
obtain views? (e.g.
focus/working group,
newsletter, survey)
Staff and tenant workshops were used to get initial views
on how TP was currently working and to identify key
priorities.
Page 271

Page 272

40
Why ? 2 surveys were used to collect further views and
comments. Separate surveys were used for staff and
tenants so that more specific questions could be used in
each survey.
These methods were chosen to gather a range of views
and to develop effective actions to be included in the new
Strategy.
7. What good practice or
minimum standards
can you evidence as
part of your
consultation?
The tenant workshop took place at our annual tenant event
which is well publicised and takes place in an accessible
building.
The survey was also well publicised and paper copies of
the survey and free post envelopes were available and a
contact name and number provided so they could be easily
obtained.
8. Outcome of
consultation?
The views and comments collected have been included in
the new Strategy and action plan.
Staff identified that remote working has resulted in less
collaboration within teams and between teams and so we
need to do more to counter that. Information about issues
that are raised at Liaison meetings don’t always get fed
down to front-line staff and this was also reflected in the
staff survey, where 40% of staff respondents didn’t think
they received enough information about tenant
participation activities. Actions have been included to
improve communication and make sure that the
information that is already shared, gets circulated to the
right staff.
When asked if the culture and practice of involving tenants
across Housing Services had improved compared to 3
years ago, most staff said it was about the same (43%),
24% said it was better and 14% said it had got worse. Staff
also identified that we need to do more to focus staff on
their accountability to tenants so that all staff can play their
role in tenant participation. 
This is key to the strategy being effective and linked to
ensuring that there is a strong tenant participation culture
throughout Housing services and there are a number of
actions to tackle this in the action plan. The emphasis of
tenant participation being about improving performance
was also identified as needing more promotion through the
workshop and also in the staff survey and is one of the key
aims that unite tenants and staff so the name of the
Strategy has been amended to recognise this, been put as
the main aim of the Strategy and emphasised throughout
the document.
The tenants workshop identified that tenants get involved
for a range of reasons so having a range of participation
Page 272

Page 273

41
options was really important and also needs to be flexible
as people’s circumstances can change. Actions are
included in the action plan to support existing tenants and
tenants groups and develop more digital options and
increase engagement with under-represented groups so
that all tenants can have their say.
Tenants said they also wanted more face-to-face contact
with housing staff and more commitment from officers so
actions to improve the culture within Housing services and
improving communication are included to address these
issues.
From the tenant survey in terms of awareness of tenant
participation, the majority of respondents were aware of
TRAs and getting involved through completing satisfaction
surveys but less so of the rest of the range of options, so
actions included to increase awareness and more
promotion of the range of options available. Positive
suggestions made include having an online forum and
making it easier for people with disabilities to get involved
so they have been included in action plan.
The majority of respondents were satisfied with the
opportunities to get involved. If dissatisfied, respondents
were given opportunity to say what they thought needed to
change and many comments made were negative about
the Council in general and needing to improve service
delivery, particularly repairs. Comments also referred to
needing to listen to tenants more and this is key if tenants
don’t think we do. Many comments were also about not
knowing about the options mentioned so need to improve
how we get information out to tenants and in a range of
ways. Actions also been included to increase local
engagement to help turnaround dissatisfaction.
When asked what sources of information they used, the
majority said it was the Housing News (71%) and did rate
the content as good or very good. The website was also
another important source. Other sources of information
were rated indifferently so improving communication
identified as a key priority in the action plan.
Only 48% of respondents were aware of consultations and
feedback provided so again improving communication is
needed.
9. How did the
consultation influence
decision making?
The views and comments collected have been used to
create the new strategy and the action plan being put
forward for committee approval.
Tenants will also have an opportunity at the Pre- HACC
Forum to add any final comments on the draft Strategy and
they will be conveyed to the committee by the Housing
Convenor.
Page 273

Page 274

42
10. Are you able to demonstrate this?     Yes - through the survey results, workshop
notes and references in the TP Strategy and action plan.      
11. How was feedback
about the consultation
and final decision
given?
An article will be included in the winter edition of the
Housing News to feedback to all tenants on the
consultation and the new strategy developed. We will also
promote the new Strategy through our TP channels and
update the Council’s website with a summary of the
consultation and the new Strategy.
12. Was the eight week timescale observed?  Yes
If no please say why?
13. Was equal opportunities information collected?  Yes
14. Did you check with
participants that they
were happy with the
opportunities given to
make their views
known and that they
felt that they were
listened to and acted
upon?
The outcomes of the workshops and the survey were 
discussed with the WDTRO and their chairperson wrote an
introduction in the Strategy document supporting it.
The survey is anonymous to encourage people to
participate and give their views but downside is that then
can’t directly contact them to check their experience but no
complaints about the consultation have been received.
15. What worked well,
what didn’t work well –
or any other
comments.
Using QL to send emails and text to those tenants we have
up to date contact details helped promote the consultation
and resulted in an increased response rate which is very
welcome.
It also meant we have been able to reach out further to
tenants not already involved in participation and their views
were really important in identifying that communication,
local engagement and improving service delivery were key
priorities.
Page 274

Page 275

Assessment No 1084 Owner JMACK
Resource Regeneration, Environment and
Growth
Service Housing and Employment
FirstName Surname Job Title
Head Officer Jane Mack Snr Housing Development
Officer (Tenant Participation)
Members Stefan Kristmanns, Housing Development Co-Ordinator
(Please note: the word 'policy' is used as shorthand for strategy policy
function or financial decision)
Policy Title Involving You - Tenant Participation Strategy 2025-28
The aim, objective, purpose and intended out come of policy
The Strategy sets out the Council's commitment to developing effective consultation
and participation to improve and develop its housing services. It sets out how the
Council will provide information, consult with tenants, future tenants and other service
users, use their views and work with tenants so that they can influence and hold the
Council to account. An action plan to support the Strategy is included along with
information on how the Strategy will be monitored and reviewed. 
The Strategy includes a commitment to equal opportunities and to comply with all
Equality and Human Right legislation.
With regard to tenant consultation and participation, we promote inclusive approaches
and work in ways that are appropriate to different people and differing needs within our
communities to minimise any barriers that tenants may experience and empower all
tenants to have their say.
Service/Partners/Stakeholders/service users involved in the development
and/or implementation of policy.
All tenants and members of the following group - the West Dunbartonshire Tenants &
Residents Organisations, Tenant & Residents Associations, Scrutiny Panel, Sheltered
Housing Forum and Interested Tenant Register, as well as housing staff and TPAS.
Does the proposals involve the procurement of any goods or services? No
If yes please confirm that you have contacted our procurement services to
discuss your requirements.
No
SCREENING
You must indicate if there is any relevance to the four areas
Duty to eliminate discrimination (E), advance equal opportunities (A) or
foster good relations (F)
Yes
Relevance to Human Rights (HR) Yes
Relevance to Health Impacts (H) Yes
Relevance to Social Economic Impacts (SE) No
Who will be affected by this policy?
All current WDC tenants, future tenants (e.g. homeless clients, housing waiting list applicants) and
residents in areas where there is an active Tenant & Resident Association (TRA).
Who will be/has been involved in the consultation process?
All tenants and members of the WDTRO, Tenant & Residents  Associations, Scrutiny Panel, Sheltered
Housing Forum, Interested Tenant Register, housing staff and TPAS.
ITEM 15 -
APPENDIX 2
Page 275

Page 276

Please outline any particular need/barriers which equality groups may have in relation to
this policy list evidence you are using to support this and whether there is any negative
impact on particular groups.
Specific group to
consider
Needs Evidence Impact
Age                           To make sure all ages are
represented in tenant
participation activities
The Council has an Equality
Outcome on increasing
participation of younger
people.
Actions included to help
encourage younger people to
get involved by improving
digital options. Transport, use
of accessible buildings for
meetings, LOOP facilities,
crèche  are provided to help all
tenants get involved.
Positive and will reduce
any barriers due to age
preventing someone
getting involved.
Disability                    Council services need to be
accessible to disabled
people including in terms of
information and
communication.
To make sure disabled
tenants are represented in
tenant participation activities
The Council has an Equality
Outcome on increasing
participation of disabled
people.
We provide a range of options
to get involved to suit different
individual needs and
circumstances. Transport
provision, use of accessible
buildings for meetings, LOOP
facilities are all provided to
help tenants get involved.
Actions are also included to
link in with local disability
groups to raise awareness of
tenant rights to participate and
development of digital options
to assist involvement from
home.
Approximately 50% of those of
responded to the online survey
identified as disabled.
Positive and will reduce
any barriers due to
disability preventing
someone getting
involved.
Gender Reassign               To make sure all tenants
are represented in tenant
participation activities.
We provide a range of
participation options and
promote inclusive participation.
Positive and will
increase representation
in participation.
Marriage & Civil
Partnership 
To make sure all tenants
are represented in tenant
participation activities.
We provide a range of
participation options and
promote inclusive participation.
Positive and will
increase representation
in participation.
Pregnancy &
Maternity        
To make sure all tenants
are represented in tenant
participation activities.
We provide crèche facilities at
public events. Timing of
meeting are set to avoid school
pick-up and drop off times as
well as avoiding school
holidays.
Positive and will reduce
any barriers due to child
care preventing
someone getting
involved.
Race                          To enable access to
housing information and
tenant participation activities
particularly where English is
not the first language
The Council has an equality
outcome on ‘better meet the
accommodation needs of
Gypsy/Travellers’
The Council has an Equality
Outcome on increasing
participation of BME people.
We ensure that relevant
information about translation is
on all public documents and
consultation information  to suit
tenants . Use of interpreters
provided when necessary for
public meetings. TRAs can
also use translation services
when required.
Positive and will reduce
any barriers due to race
preventing someone
getting involved.
Page 276

Page 277

Religion and Belief           As individuals of some
beliefs/faiths  require to
worship on particular days
they may not be able to
attend
meetings/appointments.
We ensure that due
consideration is given to those
with religious requirements
when arranging meetings and
offer dietary options.
Positive and will reduce
any barriers due to
religion or belief
preventing someone
getting involved.
Sex                           To make sure all tenants
are represented in tenant
participation activities.
Women are more likely to have
care responsibilities for
children and others than men.
We provide a range of
participation options and
promote inclusive participation.
Options to dip in and out are
available and development of
digital options will also give
more flexibility to fit in with any
care responsibilities.
Positive and will
increase representation
in participation.
Sexual Orientation  To make sure all tenants
are represented in tenant
participation activities.
Provide a range of participation
options and promote inclusive
participation.
Positive and will
increase representation
in participation.
Human Rights                  The Human Rights Act
recognises the right to have
people's housing needs
met. Housing is particularly
relevant in terms of Article 8
private and family life and
home.
The UNCRC is relevant in
terms of participation for 16
and 17 year old tenants.
Provide a range of 
participation options and
promote tenant rights.
Positive and will
increase representation
in participation.
Health                      To make sure all tenants
are represented in tenant
participation activities.
The Strategy promotes the
positive impact on personal
health and wellbeing that can
be gained from participation.
Options to dip in and out are
available to accommodate ill
health and development of
digital options will also give
more flexibility to fit in with any
health issues.
Positive and will reduce
any barriers due to
health preventing
someone getting
involved.
Social & Economic
Impact     
To make sure all tenants
are represented in tenant
participation activities.
The Strategy is designed to be
inclusive and promotes the
personal as well as community
benefits of volunteering and
getting involved.
Positive and social and
economic impact will be
increased by tenant
empowerment.
Cross Cutting          The TP Strategy applies to
all tenants so may cross cut
all the associated needs of
the EIA.
The Strategy is designed to be
inclusive and to increase all
tenant participation in decision
making.
Positive and will
increase representation
in decision-making.
Page 277

Page 278

Actions
Page 278

Page 279

Policy has a negative impact on an equality group,but is still to be implemented, please
provide justification for this.
No negative impacts identified.
Will the impact of the policy be monitored and reported on an ongoing bases?
Yes the Strategy will be subject to continuous review through regular monitoring of the action plan on
Pentana  as well as being reported bi-monthly at the WDC/WDTRO Liaison meetings and an annual
update presented to Housing & Communities Committee.
Q7 What is you recommendation for this policy?
Intoduce
Please provide a meaningful summary of how you have reached the recommendation
EIA 1084: The updated Tenant Participation Strategy aim is to develop and improve tenant
participation and ensure that participation is meaningful  and inclusive for all tenants. This will
particularly benefit some protected groups, for example women, disabled people, younger people
and people from minority ethnic groups, with a range of participation activities provided to meet a
range of needs and circumstances. The Strategy also focuses on ensuring  good clear
communication practices and empowering all tenants to challenge and be involved in improving
services for all tenants. There will be an overall benefit to all tenants, future tenants and residents
of West Dunbartonshire and the implementation of the TP Strategy will continue to support all of
the Council’s key strategic priorities.
Page 279

Page 280

Page 280

Page 281

ITEM 16
WEST DUNBARTONSHIRE COUNCIL
Report by the Chief officer Housing and Employability
Housing and Communities Committee: 20 November 2024
Subject: Building Services Update
1. Purpose
1.1 The Purpose of this report is to advise Committee of changes to
Building Services establishment and delivery model and seek approval
to continue with procurement and tender processes.
2. Recommendations
2.1 It is recommended that Members:
i. note the contents of this report.
ii. approve the procurement processes to tender the requirements
listed within the table in section 4.6 of this report; and
iii. delegate authority to the Chief Officer of  Regulatory and
Regeneration to award contracts to successful bidders
3. Background
3.1 Changes to the structure and delivery model of Building Services have
been implemented over the last two years and we are now in a position
to implement further improvements.
3.2 A report was presented to the Strategic Review and Renewal Group on
17 October 2024 seeking approval to implement the phase 3 of the
Review of Building Services. This included the externalisation of the
reroofing programme and the resizing of the painter establishment
resource both of which were approved.
3.3 Good progress continues to be made in contracting to ensure full
compliance with Council Standing Orders, Council Financial
Regulations and all Procurement Regulation.
4. Main Issues
4.1 Over the last two years, significant and unprecedented pressure on the
HRA budget has emerged, and HRA costs in both revenue and capital
budgets must be reviewed for Best Value.
Page 281

Page 282

4.2 Building Services has delivered the Council’s capital funded reroofing
programme for over 15 years. Despite improvements in efficiencies and
productivity, continuing to deliver the programme in-house is not
economically viable when compared to costs of external contractors,
which are substantially cheaper.
4.3 Very few tenants only blocks requiring new roofs remain and owners in
mixed tenure blocks seek the cheapest option possible. Obtaining
owner buy-in is proving difficult given these cost issues, which in turn
delays improvements in living conditions for our tenants in these
blocks.
4.4 Officers are progressing with arrangements to externalise the Housing
Capital funded reroofing programme.
4.5 Changes in the way empty homes are repaired to the Council’s relet
standard have also resulted in a significant reduction in the amount of
painter work which is carried out in void properties. This has resulted
in having more painters than there is work for, and consequently there
is a requirement to reduce the size of the painter establishment by 6.
4.6 For Supply and Delivery of Building Materials, the following contracts
will be required to deliver a comprehensive repairs and maintenance
service for a period of up to four years from the date of let. They will be
of sufficient size, scope and duration to cover the estimated volume of
work for the period in question and will be awarded to suitably qualified
and competent suppliers and contractors. A review of the historic
spend on the previous versions of these contracts and estimated
volumes of known and expected works has taken place, costs identified
are expected to have increased over the intervening period and
projected costs are set out in the table below
Requirement Total
Estimated
Annual
Value
Funded By
HRA
Revenue /
Capital and
CRA
Priority
Supply and delivery of Building
materials and building
sundries including:
• Timber
• Paint
• Plumbing and heating
Materials
• Electrical Materials
• Trade Materials
• Building and roofing
• Ironmongery
• Tools
£4.5m
Revenue /
Capital High
Page 282

Page 283

4.7 All procurement activity carried out by the Council in excess of £50,000
is subject to a contract strategy. The strategy for the contracts as
listed in the table at 4.2 will include but may not be limited to; contract
scope, service forward plan, the market, procurement model and
routes – including existing delivery vehicles, roles and responsibilities,
risks, issues and opportunities and on-going contract management.
4.8 This procurement exercise will be conducted in accordance with the
Corporate Procurement Unit in close consultation with Building
Services officers and the provisions of Contract Standing Orders, the
Financial Regulations and relevant Public Procurement Regulations.
4.9 The route to market will be to conduct a number of tenders calling off
from the Scotland Excel Construction Materials (1422) The use of an e-
Auction maximises commercial advantages and increases the
opportunities for savings. The use of E-Auctions will provide
transparency to all parties and allows the suppliers multiple
opportunities to bid.
5. People Implications
5.1 18 craft team members work on the reroofing programme and at this
stage we are estimating a transfer of 10 with the remainder
accommodated within other workstreams in the service.
5.2 As noted in 4.5, we are estimating a reduction of 6 posts from the
painter establishment of 20.
5.2 The Transfer of Undertakings (Protection of Employment) Regulations
2006 (TUPE) implications are applicable in terms of the externalisation
of the Councils’ capital funded reroofing programme.
5.3 Further communication and consultation will be carried out with
Building Services workforce and Trade Unions.
5.4 Progressing these changes to Building Services establishment and
delivery models and procurement processes will require significant
Officer time resource from Building Services, Consultancy Services,
Housing Operations, Legal and Corporate Procurement teams.
6. Financial Implications
6.1 It is too early to provide exact financial information as a result of
changes to the structure and delivery model of Building Services at this
stage. However, these will result in lower staff costs, lower reroofing
programme costs and less housing capital expenditure resulting in
marginally lower interest payments in future.
6.2 Costs of the support contracts will be funded by both Capital and
Revenue budgets through the Housing Revenue Account, Central
Page 283

Page 284

Repairs Account and Housing Maintenance Trading Account.
6.2   Costs of contracts listed under 4.6 are included within existing budgets.
7. Risk Analysis
7.1 There are significant financial, operational and reputational risks facing
Housing and Building Services, and to the HRA in the coming period if
changes to Building Services establishment and delivery model are not
implemented.
7.2 These changes will form part of actions in addressing the financial
challenges in the HRA budget in future years.
7.3 On-going investment, in-line with business plans, will allow the Council
to meet its landlord duties, health and safety obligations and quality
standards, whilst providing appropriate asset management.
7.2 Procurement related risks and mitigation/management measures will
be identified as part of the development of tendering strategies for the
individual requirements.
8. Equalities Impact Assessment (EIA)
8.1 An Equalities Impact Assessment or screening as appropriate will be
carried out.
9. Strategic Assessment
9.1 This report forms part of the financial governance of the HRA and
contributes to the Council’s Strategic Priorities and in particular
towards:
i. improving local housing and environmentally sustainable
infrastructure; and
ii. improving the wellbeing of communities.
10. Consultation
10.1 Finance and Legal and Chiel Legal Officer have been consulted
regarding the changes to Building Services establishment and delivery
model and the setup of the contracts referred to in this report.
10.2 The Corporate Procurement team have been consulted in the
P
Bdevelopment of this report. They will provide assistance and
professional guidance with the administration or exercises.
Chief Officer Housing & Employability
Date: 30 October 2024
Page 284

Page 285

Persons to Contact: Martin Feeney – Building Services Manager,
Cochno Street, Clydebank, Telephone: 01389
738200, e-mail: mfeeney@west-dunbarton.gov.uk
Appendices: Nil
Background Papers: Nil
Wards Affected: All
Page 285

Page 286

Page 286

Page 287

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources 
Housing and Communities Committee: 20 November 2024
___________________________________________________________________
Subject: Housing Revenue Account Budgetary Control Report
to 31 August 24 (Period 05) 
1. Purpose
1.1 The purpose of this report is to advise members of the 2024/2025 HRA revenue
budget position on 31 August 2024 and the forecast HRA reserves position as
of 31 March 2025.
2. Recommendations
2.1 Members are asked to:
i. note the HRA revenue account is currently forecasting an adverse variance
of £2.174m. If required, the adverse variance will be offset by using HRA
reserves of £0.968m and a General Fund reserve contribution of £1.205m.
ii. note that the HRA will be expected to develop a repayment plan to reimburse
the General Fund for any contribution that the General Fund makes towards
a HRA deficit and note that the HRA will also need to develop a plan to
replenish HRA reserves to the HRA prudential target.
iii. note that work will continue to identify efficiencies across all areas of the
HRA revenue account budget to minimise the adverse variance including
reviewing loan charges as highlighted in 4.5 of this report.
iv. note that there is limited scope to further reduce spend in 2024/2025 beyond
the significant actions set out in this report.
3. Background
Revenue
3.1 The Council approved a £53.218m HRA revenue budget for 2024/2025 on the
6th of March 2024
4. Main Issues
4.1 This report advises members of the key issues that are contributing to the
Housing Revenue Account (HRA) currently forecasting a deficit of £1.205m in
2024/2025 after applying all available HRA reserves. Members have
previously been advised that the Housing (Scotland) Act 1987 specifies that if
an HRA deficit arises in any one year, the local authority must make a
General Fund contribution to make good the deficit. In this event, the HRA
ITEM 17
Page 287

Page 288

would then be expected to repay that General Fund contribution from any
future HRA surpluses. Council was advised on the 30 October that the
Housing Senior Management Team are continuing to identify efficiencies
across all areas of the HRA revenue account budget to minimise the in-year
deficit and that an update on progress in this matter will be reported to Council
in December when the BCRs for period 7 are reported.
Budgetary Control BCR05
4.2 The budgetary position for HRA revenue account is provided in Appendix 1
with information on projected variances valued at more than £0.050m being
provided at Appendix 2.
Adverse Variances
Loan Charges - £3.949m Adverse Variance 
4.3 The main pressure on the HRA revenue account is elevated borrowing costs
leading to higher interest and expense payments on new borrowing and debt
refinancing. When the Council went to rent consultation in the last quarter of
2023 and drafted the 2024/2025 HRA budget, a HRA loan charge budget of
£22.092m was set with the assumption that council borrowing costs would fall
during 2024/2025. Unfortunately, local authority borrowing costs have
remained at elevated levels during the first 6 months of this financial year, with
the current expectation that they will remain elevated during the remainder of
this year. HRA outstanding debt on 31 March 2024 was £301m, with the HRA
debt expected to increase to £356m on 31 March 2025. Interest and expense
payments are forecast to be £3.531m more than the 2024/2025 budget. 
4.4 A further pressure on the HRA loan charge budget is higher than planned debt
repayments. The HRA repays capital borrowing over the expected economic
life of the asset invested in. (E.g. heating systems – 20 years, new build
properties – 60 years). The HRA debt repayment period has decreased
(leading to higher annual debt repayment) as the Council has recently
reprofiled capital expenditure on housing stock to improve the condition of the
asset to allow a quicker turnaround of void properties – more information is
provided at paragraph 4.13. Debt repayments are forecast to be £0.418m
more than the 2024/2025 budget.
4.5 Officers continue to review the Council’s HRA loan charge accounting
arrangements to explore options to improve loan charges and to reprofile
expenditure in the short term to alleviate some of the financial pressures on
the HRA account. 
Void Loss (Council Tax / Lost Rents) - £0.173m Adverse Variance
4.6 Council tax payments for longer term void houses are forecast to exceed
budget. The main factor behind HRA properties incurring a council tax liability
are delays resolving issues with debt on meters and with meter reconnections.
The poor performance of the utility companies is adversely impacting on the
length of time properties are void and leading to more empty properties
incurring a council tax liability. Officers continue to work with utility companies
Page 288

Page 289

to drive sustainable improvement in this challenging area and to minimise the
number of longer-term voids and the attendant council tax liability. Council tax
payments are forecast to be £0.099m more than budget.
4.7 Regarding void losses, there has been considerable progress in reducing void
levels and there is a consistent decrease in the number of vacant properties
through 24/25. This reduction is being achieved whilst the HRA reduces the
cost to bring a void property back to the Councils' relet standard, including a
reduced reliance on overtime working and the support of sub-contractors.
However, void time and void loss continue to be impacted by meter
challenges with energy suppliers resulting in time delays in returning several
of our void properties to the letting pool. Reducing the void loss remains an
operational priority area and the Council’s Void Working Group and Building
Services Improvement Plan will drive ongoing improvement in this key area.
Void losses are forecast to be £0.074m more than budget.
Other Expenditure - £0.180m Adverse Variance
4.8 The key adverse variance is a forecast rent abatement overspend of £0.100m.
Demand is exceeding the new reduced abatement budget. There has been
considerable progress in reducing this area of spend with the 2024/2025 rent
abatement spend forecast to be more than £250,000 less than the 2023/2024
spend. Officer will continue to tightly control this budget to minimise spend.
4.9 A further variance is a forecast spend of £0.063m to Womens Aid. The HRA
budget for payments to Womens Aid was removed during the setting of the
2024/2025 HRA Budget, however through discussions with the Womens Aid
organisations it was agreed to retain an element of that spend for a proportion
of the 2024/25 year.
Favourable Variances
4.10 The HRA cost pressures detailed present unprecedented financial challenges
for the council’s Housing Revenue Account. Officers have reviewed the HRA
spend to explore any efficiencies and to identify the scope to reduce spend.
Two key areas have been identified that are forecast to deliver an offsetting
budget underspend of £2.193m  
Employee Costs - £0.378m Favourable Variance
4.11 The HRA employee cost budget is £7.661m. The spend against this budget is
influenced by staff turnover, staff overtime spend and the success in recruiting
to posts as they become vacant. Management is targeting additional staffing
efficiencies to deliver a significant underspend against budget in 2024/2025,
including tighter controls on staff recruitment and overtime together with a
review of the HRA staff recharge to the HRA capital account and the General
Fund account.
Page 289

Page 290

Repair & Maintenance – £1.815m Favourable Variance
4.12 The HRA repair and maintenance budget is £15.208m. This budget primarily
funds reactive repairs, void repairs, planned maintenance, compliance works,
and environmental works.
4.13 The repairs spend was reviewed and a potential £1.7m saving was identified
against the 2024/2025 repair and maintenance budget through revenue spend
that qualifies for capitalisation. A review of specific workstreams assessed
that some works extend the lifespan of assets, specifically work conducted in
void properties to bring properties back to relet standard are significant and
include component renewals. Furthermore, the completion of an Electrical
Installation Condition Report (EICR) is complementary to the environmental
sensor installation programme. 
4.14 Discussion is ongoing with Greenspace colleagues to deliver a minimum
£0.1m saving by revising work specifications and streamlining processes.
5. People Implications
5.1 There are no people implications.
6. Financial and Procurement Implications
6.1 Other than the financial position noted above, there are no financial
implications of the budgetary control report. There are no procurement
implications arising from this report.
7. Risk Analysis
7.1 The main financial risks to the ongoing financial position relate to unforeseen
cost being identified between now and the end of the financial year. This can
affect all service areas.
8. Equalities Impact Assessment (EIA)
8.1 The report is for noting and therefore no Equalities Impact Assessment was
completed for this report.
9. Consultation
9.1 All services involved in delivering the HRA revenue budget have been
consulted during the compilation of this report.
10. Strategic Assessment
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. This report is for noting and, therefore, does not
directly affect any of the strategic priorities.
Page 290

Page 291

Laurence Slavin
Chief Officer – Resources
Date: 20 November 24 
___________________________________________________________________ 
Person to Contact:  Jim McCarron - Business Unit Finance Partner 
Telephone: 07772 322055   
e-mail james.mccarron@west-dunbarton.gov.uk 
Appendices:  Appendix 1 - Budgetary Position (Revenue)    
Appendix 2 - Variance analysis (Revenue)
Background Papers: None 
Wards Affected:  All 
Page 291

Page 292

WEST DUNBARTONSHIRE COUNCIL
HRA REVENUE BUDGETARY CONTROL 2024/25
PERIOD END DATE
Budget
2024/25
Spend to Date
2024/25
Forecast Spend
2024/25 Annual RAG Status
£000 £000 £000 £000 %
Employee Costs 7,661 3,108 7,283 (378) -5% 
Property Costs 2,600 1,083 2,600 0 0% 
Transport Costs 148 66 158 10 0% 
Supplies, Services And Admin 406 171 411 5 1% 
Support Services 2,788 1,160 2,785 (3) 0% 
Other Expenditure 330 267 560 230 70% 
Repairs & Maintenance 15,208 5,261 13,393 (1,815) -12% 
Bad Debt Provision 876 366 879 3 0% 
Void Loss (Council Tax / Lost Rents) 1,109 576 1,282 173 16% 
Loan Charges 22,092 10,850 26,041 3,949 18% 
Total Expenditure 53,218 22,908 55,392 2,174 4% 
House Rents (51,049) (21,270) (51,049) 0 0% 
Lockup Rents (215) (90) (215) 0 0% 
Factoring/Insurance Charges (1,555) (648) (1,555) 0 0% 
Other rents (130) (54) (130) 0 0% 
Interest on Revenue Balance (146) (61) (146) 0 0% 
Miscellaneous income (123) (51) (123) 0 0% 
Transfer from Reserves 0 0 0 0 0% 
Total Income (53,218) (22,174) (53,218) 0 0% 
Net Expenditure 0 734 2,174 2,174 
31 August 2024
Subjective Summary Forecast Variance
2024/25
ITEM 17 - APPENDIX 1
Page 292

Page 293

WEST DUNBARTONSHIRE COUNCIL
HRA REVENUE BUDGETARY CONTROL 2024/25
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31 August 2023
PERIOD 5
Budget
2024/25
Forecast
Spend
2024/25
£000 £000 £000 %
Employee Costs 7,661 7,283 (378) -5% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget
2024/25
Forecast
Spend
2024/25
£000 £000 £000 %
Other Expenditure 330 560 230 70% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget
2024/25
Forecast
Spend
2024/25
£000 £000 £000 %
Repairs & Maintenance 15,208 13,393 (1,815) -12% 
Main Issues
Mitigating Action
Anticipated Outcome
Variance Analysis
Subjective Analysis Forecast Variance
2024/25
RAG
Status
Officers have reviewed the repairs spend and identified a potential saving against the
2024/2025 repair and maintenance budget by transferring spend charged to revenue to the
capital programme. A review of specific workstreams identified revenue funded works that
extend the lifespan of the assets. Specifically work carried out in void properties to bring these
back to relet standard are significant and include component renewals.
Furthermore, the completion of an Electrical Installation Condition Report (EICR) is
complementary to the environmental sensor installation programme.
Subjective Description
Responsive and planned repair and maintenance services to houses and lockups and income recovered from tenant rechargeable and owner
occupier repairs.
Variance Narrative
A high  volume of repair orders and ongoing inflationary pressures are driving up costs, with the
most significant pressures across responsive repair and void repair budgets.
A year end underspend
A rent abatement overspend of £100k is forecast because demand is exceeding the new
reduced abatement budget. It is worth noting that the 2024/2025 rent abatement spend is
forecast to be circa £250,000 less than the 2023/2024 spend.
A year end overspend.
Forecast Variance
2024/25
Subjective Description
Rent abatements, support for young tenants, legal and banking expenses, and other sundry costs.
Variance Narrative
Subjective Analysis RAG
Status
Housing Operations and Building Service will continue to place the strictest controls over the
abatement process to minimise this spend.
Variance Analysis
Variance Analysis
Forecast Variance
2024/25
Subjective Description
Subjective Analysis RAG
Status
Cost of employees charged directly to the HRA.
Variance Narrative
An employee cost underspend is anticipated as management target staffing efficiencies,
including tighter controls on staff recruitment and overtime.
None required.
A year end underspend.
ITEM 17 -
APPENDIX 2
Page 293

Page 294

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
HRA REVENUE BUDGETARY CONTROL 2024/25
ANALYSIS FOR VARIANCES OVER £50,000
MONTH END DATE 31 August 2023
PERIOD 5
Budget
2024/25
Forecast
Spend
2024/25
£000 £000 £000 %
Void Loss (Council Tax / Lost Rents) 1,109 1,282 173 16% 
Main Issues
Mitigating Action
Anticipated Outcome
Budget
2024/25
Forecast
Spend
2024/25
£000 £000 £000 %
Loan Charges 22,092 26,041 3,949 18% 
Main Issues
Mitigating Action
Anticipated Outcome
Variance Analysis
Subjective Analysis Forecast Variance
2024/25
RAG
Status
The Council will continue to actively manage its external / internal borrowing to ensure that it
minimises borrowing costs.
Subjective Description
Loans Fund repayments and the payment of interest and expenses on outstanding HRA debt.
Local authority borrowing costs for medium / long term Public Works Loan Board (PWLB) debt
and short term debt have remained  high. The higher interest rates are driving up HRA debt
financing costs. The HRA budget assumed that borrowing rates would reduce in 2024/2025.
Whilst Interest rates were originally expected to fall over the course of this year, we now expect 
rates to remain high for the remainder of ths financial year.
A year end overspend.
Variance Analysis
Forecast Variance
2024/25
Variance Narrative
Subjective Analysis RAG
Status
Variance Narrative
Council tax payments for longer term void houses are forecast to exceed budget. There is
limited  progress being made with utility companies as council  staff try and resolve debt on
meters and meter reconnections. The poor performance of the utility companies adversely
impacts on the length of time properties are void and leads to more empty properties incurring a
council tax liability.
Housing staff will continue to engage with utility companies to highlight meter issues that are
preventing properties being available for let. Housing and Building Services staff will continue to
prioritise the repair and subsequent allocation of longer term void properties.
A year end overspend.
Subjective Description
Lost rental income for void houses and lockups and the cost of council tax on long term void properties
Page 294

Page 295

WEST DUNBARTONSHIRE COUNCIL
Report by Chief Officer – Resources
Housing and Communities Committee: 20 November 2024
___________________________________________________________________
Subject:  General Fund Housing and Communities Financial Report 2024/25
as at Period 5 (31 August 2024)
1. Purpose
1.1 The purpose of the report is to provide the Committee with an update on the
financial performance to 31 August 2024 (Period 5) of General Fund Revenue
services under the remit of the Housing and Communities Committee.
2. Recommendations
2.1.1 Members are asked to:
i) note the contents of this report which shows the revenue budget forecast
to underspend against budget by £0.029m (0.9 %) at the year-end.
ii) note the progress on efficiencies incorporated into budgets for 2024/25.
3. Background
3.1      Revenue Budget
Members agreed the revenue estimates for 2024/25 at the meeting of West
Dunbartonshire Council on 01 March 2024,
A total net budget of £3.772m was approved for services under the remit for
Housing and Communities services.
The budget has been reduced to reflect the decrease in Strathclyde pension
fund contributions. This budget has been vired to a central reserve to be used
to balance the budget over the next four years as agreed at the Council
meeting on 6 March 2024.
Budget adjustments are shown below: -
Service £m
Agreed budget 6 March 2024 3.772
Additional Funding:
Additional Rapid Rehousing Transition
Programme funding  Homeless 0.010
Base Budget Adjustment:
Remove excess superannuation budget All (0.469)
Revised budget as at Period 3 3.313
ITEM 18
Page 295

Page 296

4. Main Issues
Revenue Budget
4.2 Appendix 1 shows the probable outturn for the services at £3.645m. As the
revised annual budget is £3.313m there is a projected overspend on budget of
£0.332m. £0.361m of the overspend relates to approved additional spend
financed by specific reserves. The underlying variance is therefore a positive
variance of £0.029m. Details of the reserves applied in 2024/25 are below.
Reserve Service £m
Cost Of Living: -
Additional investment to the energy fund to cover
winter. 
W4U 0.125
Transitional Funding Support to Y-Sort-It over 4
years. £39,000 per year for 4 years.
W4U 0.039
Cost of Living 3: Additional Support for
Apprenticeships. £50,000 per year for 4 years.
W4U 0.050
Total Cost of Living Reserve Used 0.214
Earmarked reserves: -
CCTV Network Upgrade ASB 0.021
Modern Apprentice 23/24 underspend W4U 0.126
Total Earmarked Reserves used 0.147
Total Reserves Used 0.361
Appendix 2 provides a detailed analysis by service area.
Appendix 3 provides commentary of projected net annual variances greater
than £0.050m. 
Appendix 4 shows progress on the delivering 2024/2025 saving options.
5. People Implications
5.1 There are no people implications.
6. Financial Implications
6.1 Other than the financial position noted above, there are no financial
implications of the budgetary control report.
Page 296

Page 297

6.2   Agreed efficiencies for 2024/2025 are monitored with current indications being
that £0.202m of the savings budgeted of £0.222m will be achieved (see
Appendix 4). As noted in 4.2 above, the smoothing fund will be used to offset
this £0.020m shortfall.
7. Risk Analysis
7.1 The present variances should be viewed in the knowledge that there are a
number of variable factors which could arise between now and 31 March and
which could affect the year end results for both the revenue and capital
budgets.
7.2 Assumptions around service demand and timing of nationally agreed changes
through the phasing out of lockdown change regularly and therefore there is a
significant risk that the projected year end budgetary position will change from
that reported.
8. Equalities Impact Assessment (EIA)
8.1 The report is for noting and therefore no Equalities Impact Assessment was
completed for this report.
9. Consultation
9.1 All services involved in delivering the budgets have been consulted in the
compilation of this report
10. Strategic Assessment
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the five strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. This report is for noting and, therefore, does not
directly affect any of the strategic priorities.
Laurence Slavin
Chief Officer, Resources
Date: 20 November 2024
___________________________________________________________________
Person to Contact: Jim McCarron  - Business Unit Finance Partner,
16 Church Street, Dumbarton, G82 1QL, 
Telephone: 07772 322055
e-mail james.mccarron@west-dunbarton.gov.uk
Page 297

Page 298

Appendices: Appendix 1 - Summary Budgetary Position (Revenue)
Appendix 2 - Detailed Budgetary Position (Revenue)
Appendix 3 - Variance Analysis (Revenue)
Appendix 4 - Monitoring of Efficiencies/Savings Options
(Revenue)
Background Papers: None
Wards Affected: All
Page 298

Page 299

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2023/24
HOUSING & COMMUNITIES SUMMARY
MONTH END DATE 31 August 2024
Actual
Outturn
2023/24
Total Budget
2024/25
YTD
Spend
2024/25
Forecast
Spend
2024/25
Annual
RAG
Status
Net Variance
attributable to
earmarked
reserves
spend
Underlying
Variance
excluding
earmarked
reserves
spend
£000 £000 £000 £000 £000 % £000 £000
2,583 1,954 1,281 2,294 340 17%  340 0
0 Shared Prosperity Fund 0 411 0 0 0%  0 0
951 942 455 894 (48) -5%  0 (48)
828 620 455 639 19 3%  0 19
15 15 6 15 0 0%  0 0
0 Private Sector Housing Grant 41 17 41 0 0%  0 0
291 330 122 351 21 6%  21 0
(569) (589) (285) (589) 0 0%  0 0
4,099 3,313 2,462 3,645 332 10.02%  361 (29)
Service / Subjective Summary
Annual
Variance
2024/25
Communities
Homeless Persons
Private Sector Housing
Anti Social Behaviour
Housing Maintenance Trading A/c
Total Net Expenditure
Working 4 U
ITEM 18 -
APPENDIX 1
Page 299

Page 300

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2023/24
HOUSING AND COMMUNITIES COMMITTEE DETAIL
YEAR END DATE 31 August 2024
PERIOD 5
Actual
Outturn
2023/24
Service Summary
Total
Budget
2024/25
YTD
Spend
2024/25
Forecast
Spend
2024/25
RAG Status
£000 £000 £000 £000 £000 %
20,172 Employee 18,870 7,292 18,209 (661) 3% 
2,496 Property 2,668 450 2,657 (11) -75% 
1,320 Transport and Plant 1,221 502 1,217 (3) 33% 
6,335 Supplies, Services and Admin 5,929 2,500 6,000 71 17% 
3,437 Payments to Other Bodies 3,009 1,111 3,178 169 16% 
998 Other 884 454 1,009 125 0% 
34,759 Gross Expenditure 32,580 12,310 32,270 (310) -1% 
(30,660) Income (29,268) (10,259) (28,625) 643 -53% 
4,099 Net Expenditure 3,313 2,051 3,645 334 10% 
£000 £000  £000  £000  £000 %
2,718 Employee 2,460 956 2,469 9 0% 
0 Property 0 0 0 0 0% 
15 Transport and Plant 18 3 13 (5) -28% 
79 Supplies, Services and Admin 96 5 100 4 4% 
1,898 Payments to Other Bodies 1,484 586 1,691 207 14% 
29 Other 0 86 125 125 0% 
4,739 Gross Expenditure 4,058          1,636          4,398 340 8% 
(2,156) Income (2,104) (355) (2,104) 0 0% 
2,583 Net Expenditure 1,954          1,281          2,294 340 17% 
£000 £000  £000  £000  £000 %
638 Employee 691 225 669 (22) -3% 
3 Property 0 0 0 0 0% 
1 Transport and Plant 0 1 2 2 0% 
21 Supplies, Services and Admin 0 6 6 6 0% 
342 Payments to Other Bodies 2,233 179 2,246 13 1% 
0 Other 0 0 0 0 0% 
1,005 Gross Expenditure 2,924          411 2,923 (1) 0% 
(1,005) Income (2,924) 0 (2,923) 1 0% 
- Net Expenditure - 411 - 0 0% 
£000 £000  £000  £000  £000 %
888 Employee 655 290 670 15 2% 
0 Property 17 0 0 (17) -98% 
7 Transport and Plant 5 2 7 3 65% 
98 Supplies, Services and Admin 103 38 81 (22) -21% 
166 Payments to Other Bodies 233 139 237 4 2% 
0 Other 0 0 0 0 0% 
1,160 Gross Expenditure 1,012          470 995 (17) -2% 
(209) Income (71) (15) (101) (30) -43% 
951 Net Expenditure 942 455 894 (48) -5% 
£000 £000 £000 £000 £000 %
2,887 Employee 2,793 1,065 2,811 18 1% 
2,181 Property 2,165 330 2,150 (15) -1% 
25 Transport and Plant 25 8 24 (1) -4% 
146 Supplies, Services and Admin 76 55 101 25 33% 
1,010 Payments to Other Bodies 958 249 910 (48) -5% 
0 Other 0 0 0 0 0% 
6,249 Gross Expenditure 6,017 1,707 5,996 (21) 0% 
(5,421) Income (5,397) (1,252) (5,357) 40 1% 
828 Net Expenditure 620 455 639 19 3% 
Shared Prosperity Fund
Communities
Homeless Persons
Annual
Variance
2024/25
All Services
Working 4 U
ITEM 18 -
APPENDIX 2
Page 300

Page 301

WEST DUNBARTONSHIRE COUNCIL Appendix 2
REVENUE BUDGETARY CONTROL 2023/24
HOUSING AND COMMUNITIES COMMITTEE DETAIL
YEAR END DATE 31 August 2024
PERIOD 5
Actual
Outturn
2023/24
Service Summary
Total
Budget
2024/25
YTD
Spend
2024/25
Forecast
Spend
2024/25
RAG Status
Annual
Variance
2024/25
£000 £000 £000 £000 £000 %
0 Employee 0 0 0 0 0% 
0 Property 0 0 0 0 0% 
0 Transport and Plant 0 0 0 0 0% 
1 Supplies, Services and Admin 0 0 0 0 0% 
14 Payments to Other Bodies 15 6 15 0 0% 
0 Other 0 0 0 0 0% 
15 Gross Expenditure 15 6 15 0 0% 
0 Income 0 0 0 0 0% 
15 Net Expenditure 15 6 15 0 0% 
£000 £000 £000 £000 £000 %
44 Employee 41 17 41 0 0% 
121 Property 241 20 241 0 0% 
0 Transport and Plant 0 0 0 0 0% 
0 Supplies, Services and Admin 0 (1) (1) (1) 0% 
247 Payments to Other Bodies 205 81 205 0 0% 
0 Other 0 0 0 0 0% 
412 Gross Expenditure 487 117 486 (1) 0% 
(412) Income (446) (100) (445) 1 0% 
0 Net Expenditure 41 17 41 0 0% 
£000 £000 £000 £000 £000 %
278 Employee 279 109 293 14 5% 
78 Property 86 34 107 21 24% 
0 Transport and Plant 0 0 0 0 0% 
0 Supplies, Services and Admin 0 0 1 1 0% 
102 Payments to Other Bodies 114 50 120 6 5% 
0 Other 0 0 0 0 0% 
458 Gross Expenditure 479 193 521 42 9% 
(167) Income (149) (71) (170) (21) -14% 
291 Net Expenditure 330 122 351 21 6% 
………………………………………………………………………………………………………………………………………………………………………………………….
£000 £000 £000 £000 £000 %
13,357 Employee 12,642 4,855 11,925 (717) -6% 
116 Property 159 66 159 0 0% 
1,273 Transport and Plant 1,173 489 1,173 0 0% 
6,011 Supplies, Services and Admin 5,654 2,403 5,718 64 1% 
0 Payments to Other Bodies 0 0 0 0 0% 
969 Other 884 368 884 0 0% 
21,726 Gross Expenditure 20,512        8,181          19,859         (653) -3% 
(22,295) Income (21,101) (8,466) (20,448) 653 3% 
(569) Net Expenditure (589) (285) (589) 0 0% 
Housing Maintenance Trading A/c
Private Sector Housing Grant
Anti Social Behaviour
Private Sector Housing
Page 301

Page 302

WEST DUNBARTONSHIRE COUNCIL
REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
YEAR END DATE
Total Budget Forecast
Spend RAG Status
£000 £000 £000 %
Working 4 U 1,954 2,294 340 17% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Communities 942 894 (48) -5% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Housing Maintenance Trading A/c (589) (589) 0 0% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
This service provides support to communities
There have been delays in achieving the communities restructure savings though projected
recharges to PEF are greater than budgeted
Progression with restructure
favourable variance
This is the provision of Working 4u service
None Required
Net expenditure will be in line with budget.
31 August 2024
The adverse variances on payments to other bodies/ other expenditure reflects spend that that
will met by use of earmarked balances
Budget Details
Variance Analysis
Variance
The service will achieve its budgeted surplus
None available
Employee costs showing a positive variance due to vacant posts within the service. The
forecast overspend in supplies and services reflects building material inflationary pressures.
Income recovery is slightly less then budget due to the service undertaking less work than
originally anticipated.
This service delivers maintenance and investment services to the council's housing stock
ITEM 18 -
APPENDIX 3
Page 302

Page 303

WEST DUNBARTONSHIRE COUNCIL
MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2024/25 - BCR05
Efficiency Detail Reference
Budgeted
Amount £'000
Projection of
Total Saved
£'000
Projection of
Total Not
Saved £'000
Comment
1 Reduces the budget that funds furniture for temporary accommodation from £1,065
per property to £1,000 per property
HE07 16 16 0
2 Reduce funding provided to  YSortIt by 25% HE02 29 29 0
3 Reduce funding provided to  LCCR by £40k HE06 40 40 0
4 Review the Communities team reducing the delivery of community based services CCF26 87 67 20 Delay in implementation, in
year shortfall will be covered
by the smoothing fund. Full
year savings expected in
future years.
5 Removal of GF Contribution to Housing Asset & Investment Team HE05 50 50 0
222 202 20
STATUS: COMPLETE
ITEM 18 -
APPENDIX 4
Page 303

Page 304

Page 304

Page 305

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Housing and Communities Committee: 20 November 2024
___________________________________________________________________
Subject: Housing Revenue Account (HRA) Capital  
Budgetary Control Report to 31 August 24 (Period 5)
1. Purpose
1.1 This report provides an update on the HRA capital programme to 31 August
2024.
2. Recommendations
2.1 Members are asked to:
i) Note the current position of the 2024/2025 HRA capital budget and the
HRA capital plan.
ii) Note that in year financial performance is monitored against a
2024/2025 capital expenditure budget of £73.664m and a 2024/2025
capital income budget of £10.003m, a one-year borrowing requirement
of £63.661m.
iii) Note that project life performance is monitored against a five-year
project life expenditure budget of £319.738m and a project life income
budget of £54.577m, a five-year borrowing requirement of £265.161m.
iv) Note that there are six projects reporting off track with an anticipated
over / under spend against their 2024/2025 budgets, with a forecast net
overspend of £0.334m in 2024/2025.
v) Note that all projects are currently on track to achieve their planned
completion dates and to deliver within their respective five-year project
life budgets.
3. Background
3.1 On 6 March 2024 the Council approved the updated Housing Revenue
Account Capital Plan for 2024/2025 to 2028/2029.
3.2 Since then budget adjustments have taken place to bring forward in year
project under/over spends during 2023/2024, to reflect up to date information
on progress delivering the plan and any need for budget acceleration and
budget deceleration from / to future years, and to update the expenditure and
income budgets for Affordable Housing Supply projects to reflect the
2023/2024 outturn and to reflect that the most recent cost and income
forecasts  The budget adjustments result in revised capital budgets as set out
in Exhibit 1.
ITEM 19
Page 305

Page 306

Exhibit 1: Revised HRA Capital Budget 2024/2025 – 20278/2029
2024/25
BCR05 
(£m)
Project Life
BCR05 
(£m)
Project Life
March 24 
(£m)
Other Capital Expenditure 7.165 27.129 27.180
Major Component Replacement  19.795 92.604 92.604
Void Capital 4.902 19.212 20.712
Structural & Environmental  2.767 14.175 14.175
Support Costs 2.761 14.367 14.367
Affordable Housing Supply Programme  36.274 152.251 149.053
Total Expenditure 73.664 319.738 318.091
Total Income  10.003 54.577 47.029
Prudential Borrowing 63.661 265.161           271.062
4. Main Issues
4.1 Progress against the 2024/25 capital plan is detailed in:
Appendix 1 – HRA Capital Summary BCR05
Appendix 2 – HRA Capital Detail BCR05
4.2 The HRA capital summary report at Appendix 1 reports that planned
expenditure and planned income are both in line with the overall project
budgets. Appendix 1 reports that there are twenty-nine capital projects where
expenditure / income budget is tracked over the multi-year life of the project
and twenty-eight projects classified as rolling programme projects, which is
programmes of work where an annual budget is set each year that takes
account of demand, cost, and affordability.
4.3 Appendix 2 shows all projects with approved in year and project life budgets
as well as forecast expenditure / income. The appendix highlights a
2024/2025 expenditure budget of £73.664m and a forecast spend of
£73.998m, a net overspend of £0.334m (0.005% of the planned 2024/2025
spend) The 2024/2025 capital income budget is £10.003m, with a forecast
income of £10.003m.
4,4 Commentary on the 2024/2025 expenditure variances are set out in Exhibit 2
below.
Exhibit 2: Project Over / Underspends 2024/2025
Project 
2024/2025
BCR05 
Forecast 
(£m) 
2024/2025
BCR05 
Budget
(£m) 
2024/2025
Variance 
(£m)
Commentary
Special Need Adaptations 0.552 0.655 -0.103 • Reduced throughput of capital adaptations this
year
• Inhouse adaptations team is fully up to date
with its order books.
• Improved performance with average time of 46
days.
• Underspend will be available for reprofiling in
future years.
Page 306

Page 307

Project 
2024/2025
BCR05 
Forecast 
(£m) 
2024/2025
BCR05 
Budget
(£m) 
2024/2025
Variance 
(£m)
Commentary
Capitalised Minor Works 3.964 3.000 0.964 • Transfer of Electrical Installation Condition
Works `spend to minor works budget.
• Overspend will be re-profiled over future years.
• Officers are increasingly directing minor works
requests to the relevant planned capital
programme.
Environmental Sensors 1.365 2.000 -0.635 • Excellent progress with this programme with an
anticipated 2,000 sensors due to be installed
this year.
• Underspend reflects the mobilization period
and challenges in getting access to properties.
• Underspend will be available for reprofiling in
future years.
Roofing Works  2.033 2,500 -0.467 • Underspend reflects the changing mix of the
capital programme with an increased number of
mixed tenure blocks that require owner consent
before work can start. This necessary process
delay project start
• Underspend will be available for reprofiling in
future years.
Void House Works 5.733 4.902 0.831 • Transfer of increased void spend to HRA capital
account following a review.
• Void delivery costs, including overtime on voids
and contractor spend, have reduced as void
number have reduced.
• Overspend will be re-profiled over future years.
Environmental Works 0.910 1.068 -0.158 • Reduced throughput of environmental works
this year because operatives have also worked
across other HRA service areas.
• Underspend will be available for reprofiling in
future years.
Contingency - 0.100 -0.100 • Contingency released to offset cost pressures
across the HRA capital account.
0.334
4.5 Budget assumptions are required to forecast costs / income, especially where
projects span multi-year and project finances have yet to be finalised. It is
therefore likely that the projected year end budgetary position will change
during the year.
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
Page 307

Page 308

7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there
are several variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.
(b) Because of current market conditions, inflation is at an all-time high and
interest rates continue to be volatile. To forecast for the full year costs
budget assumptions have been required. These assumptions continue to
change regularly and therefore it is likely the projected year end
budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted
during the compilation of this report. 
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
________________
Laurence Slavin
Chief Officer – Resources
Date: 20 November 2024
Person to Contact: Jim McCarron
Business Partner, Finance 07772 322055
E-mail: james.mccarron@west-dunbarton.gov.uk
Appendices: Appendix 1 - HRA Capital Summary BCR05
Appendix 2- HRA Capital Details BCR05  
Background Papers:
Housing Revenue Account (HRA) Capital Investment Programme, Revenue Budget, and Rent
Levels for 2024/25 - Council 6 March 2024.
Wards Affected    All Wards
Page 308

Page 309

Period 5 - 31 August 2024
HRA Capital Summary
HRA Capital Expenditure Project Life
Budget
Project Life
Forecast Spend
Project Life
Variance
Rolling
Programmes
Projects Projects
On Track / Complete
Projects
Off Track
£000 £000 £000
Other Capital Expenditure 27,129 27,129 - 5 3 3 -
Major Component Replacement 92,604 92,604 - 10 1 1 -
Void Capital 19,212 19,212 - 1 - - -
Structural & Environmental 14,175 14,175 - 3 1 1 -
Support Costs 14,367 14,367 - 1 - - -
Affordable Housing Supply Programme 152,253 152,253 - 5 12 12 -
Total Expenditure 319,740 319,740 - 25 17 17 -
Total Income (54,576) (54,576) - 3 12 12 -
Total 265,164 265,164 - 28 29 29 -
ITEM 19 -
APPENDIX 1
Page 309

Page 310

Period 5 _  31 August 2024
HRA Capital Detail
Project Category Planned
End Date
Revised
End Date
Project Life
Budget
Expenditure
to 31 /3/24
Expenditure
to Date
Projected
Future Spend
Project Life
Forecast Spend
Project
Variance
Approved
Budget
2024/25
Expenditure
to Date
2024/25
Projected
Spend
2024/25
In Year
Variance
2024/25
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
OCE1 Special Needs Adaptations Rolling 31/03/2025 3,408 - 249 3,159 3,408 - 655 249 552 (103)
OCE2 Capitalised Minor Works Rolling 31/03/2025 10,945 - 1,113 9,832 10,945 - 3,000 1,113 3,964 964
OCE3 Better Homes Priority Budget Rolling 31/03/2025 1,680 - 196 1,484 1,680 - 705 196 705 -
OCE4 Environmental Sensors Programme Project 31/03/2029 10,000 103 645 9,355 10,000 - 2,000 542 1,365 (635)
OCE5 Housing CCTV Installation Programme Project 31/03/2025 750 - - 750 750 - 750 - 750 -
OCE6 QL Development Rolling 31/03/2025 109 - 9 100 109 - 21 9 21 -
OCE7 Gypsy Travellers Site Rolling 31/03/2025 141 - - 141 141 - 34 - 34 -
OCE8 Airport Noise Project 31/03/2026 96 - - 96 96 - - - - -
Other Capital Expenditure 27,129 103 2,212 24,917 27,129 - 7,165 2,109 7,391 226
MCR1 Targeted SHQS /EESSH compliance works Rolling 31/03/2025 32,632 - 2,173 30,459 32,632 -   6,537 2,173 6,537 -
MCR2 External Component Renewal - Roofs Rolling 31/03/2025 13,010 - 691                       12,319 13,010 -   2,500 691 2,033 (467)
MCR3 Doors/Windows Component Renewals Rolling 31/03/2025 14,599 - 1,888 12,711 14,599 -   5,011 1,888 5,011 -
MCR4 District Heating Project 31/03/2030 6,400 - - 6,400 6,400 -   - - - -
MCR5 External Stores / Garages / Bin Stores Rolling 31/03/2025 245 - - 245 245 -   47 - 47 -
MCR6 Secure entry component renewals Rolling 31/03/2025 245 - 7 238 245 -   47 7 47 -
MCR7 Statutory / Regulatory Compliance Works Rolling 31/03/2025 976 - - 976 976 -   294 - 294 -
MCR8 Heating Improvement Works Rolling 31/03/2025 8,800 - 693 8,107 8,800 -   1,900 693 1,901 1
MCR9 Energy Improvements / Energy Efficiency Works Rolling 31/03/2025 295 - - 295 295 -   57 - 57 -
MCR10 Kitchen Upgrade Rolling 31/03/2025 12,102 - 1,291 10,811 12,102 -   2,652 1,291 2,652 -
MCR11 Bathroom & Shower Replacement Rolling 31/03/2025 3,300 - 320                       2,980 3,300 -   750 320 750 -
Major Component Replacement 92,604 - 7,063 85,541 92,604 - 19,795 7,063 19,329 (466)
VOC1 Void House Strategy Programme Rolling 31/03/2025 19,212 - 2,325 16,887 19,212 -   4,902 2,325 5,734 832
Void Capital 19,212 - 2,325 16,887 19,212 - 4,902 2,325 5,734 832
STE1 Defective structures/component renewals Rolling 31/03/2025 2,210 - 306 1,904 2,210 - 712 306 712 -
STE2 Environmental Renewal - Paths & Environment Rolling 31/03/2025 5,559 - 296 5,263 5,559 - 1,068 296 910 (158)
STE3 Asbestos Management Works Rolling 31/03/2025 1,235 - 23 1,212 1,235 - 237 23 237 -
STE4 Multi Storey Flat Strategy Project 31/03/2029 5,171 65 70 5,101 5,171 - 750 5 750 -
Structural & Environmental 14,175 65 695 13,480 14,175 - 2,767 630 2,609 (158)
SUP1 Salaries / Central Support / Overhead Rolling 31/03/2025 14,367 - 1,150 13,217 14,367 -   2,761 1,150 2,761 -
Support Costs 14,367 - 1,150 13,217 14,367 - 2,761 1,150 2,761 -
AHP1 Buy Backs Rolling 31/03/2025 20,522 - 1,315 19,207 20,522 -   4,670 1,315 4,670 -
AHP2 Demolition Programme Rolling 31/03/2025 485 - 164 321 485 -   485 164 485 -
AHP3 Contingency Rolling 31/03/2025 520 - - 520 520 -   100 - - (100)
AHP4 Clydebank East Project 15/04/2025 32,894 22,334 27,852 5,042 32,894 -   9,700 5,518 9,700 -
AHP5 Pappert Project 22/05/2025 10,517 601 2,838 7,679 10,517 -   9,653 2,237 9,653 -
AHP6 Mount Pleasant Project 31/03/2025 6,005 555 1,712 4,293 6,005 -   4,396 1,157 4,396 -
AHP7 7-9 Gilmour Avenue Project 10/10/2024 574 40 85 489 574 -   534 45 534 -
AHP8 Willox Park Phase1 Project 01/10/2025 5,143 401 418 4,725 5,143 -   2,500 17 2,500 -
AHP9 Bank Street Project 01/01/2026 7,549 231 278 7,271 7,549 -   518 47 518 -
AHP10 Bonhill Gap Sites Project 01/03/2026 11,537 99 203 11,334 11,537 -   514 104 514 -
AHP11 Clydebank Health Centre Project 30/09/2026 10,595 705 773 9,822 10,595 -   390 68 390 -
AHP12 Silverton Project 01/12/2026 2,537 33 35 2,502 2,537 -   429 2 429 -
AHP13 Queen Mary Avenue Project 01/12/2026 4,556 32 36 4,520 4,556 -   120 4 120 -
AHP14 Queens Quay Site C Project 01/04/2029 8,231 31 31 8,200 8,231 -   1,000 - 1,000 -
AHP15 Dennystoun Forge – New Build Project 01/04/2026 4,000 - 30 3,970 4,000 -   250 30 250 -
AHP16 Future New Build & Related Regeneration Projects Rolling 31/03/2025 24,515 - - 24,515 24,515 -   515 - 515 -
AHP17 Fees, Staffing Costs, contingency Rolling 31/03/2025 2,073 - 125 1,948 2,073 -   500 125 500 -
Affordable Housing Supply Programme 152,253 25,062 35,895 116,358 152,253 - 36,274 10,833 36,174 (100)
Total Expenditure 319,740 25,230 49,340 270,400 319,740 - 73,664 24,110 73,998 334
Full Project Life In Year
ITEM 19 -
APPENDIX 2
Page 310

Page 311

Period 5 _  31 August 2024 Appendix 2
HRA Capital Detail
Full Project Life In Year
Project Category Planned
End Date
Revised
End Date
Project Life
Budget
Income
to 31 /3/24
Income
to Date
Projected
Future Income
Project Life
Forecast Income
Project
Variance
Approved
Budget
2024/25
Income
to Date
2024/25
Projected
Income
2024/25
In Year
Variance
2024/25
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
CAPI1 Scottish Govt Buyback Grant Rolling 31/03/2025 (9,451) - (748) (8,703) (9,451) - (2,858) (748) (2,858) -
CAPI2 Clydebank East Project 15/04/2025 (12,605) (12,605) (12,605) - (12,605) - - - - -
CAPi3 Pappert Site Project 22/05/2025 (3,725) (172) (672) (3,053) (3,725) - (3,303) (500) (3,303) -
CAPI4 Mount Pleasant Project 31/03/2025 (1,838) (467) (467) (1,371) (1,838) - (1,371) - (1,371) -
CAPI5 7-9 Gilmour Avenue Project 10/10/2024 (195) - - (195) (195) - (195) - (195) -
CAPI6 Willox Park Phase1 Project 01/10/2025 (1,489) (414) (489) (1,000) (1,489) - (1,075) (75) (1,075) -
CAPI7 Bank Street Project 01/01/2026 (2,108) (258) (258) (1,850) (2,108) - - - - -
CAPI8 Bonhill Gap Sites Project 01/03/2026 (4,789) (188) (188) (4,601) (4,789) - - - - -
CAPI9 Clydebank Health Centre Project 30/09/2026 (3,785) (585) (585) (3,200) (3,785) - (200) - (200) -
CAPI10 Silverton Project 01/12/2026 (1,000) - - (1,000) (1,000) - - - - -
CAPI11 Queen Mary Avenue Project 01/12/2026 (1,600) (140) (140) (1,460) (1,600) - - - - -
CAPI12 Queens Quay Site C Project 01/04/2029 (3,086) (2,086) (2,086) (1,000) (3,086) - (1,000) - (1,000) -
CAPI13 Dennystoun Forge – New Build Project 01/04/2026 (2,000) - - (2,000) (2,000) - - - - -
CAPI14 Future new build sites & related regeneration projects Rolling 31/03/2025 (6,900) - - (6,900) (6,900) - 0 - 0 -
CAPI15 HRA Loan Repayments Rolling 31/03/2025 (5) - - (5) (5) - (1) - (1) -
Total Income (54,576) (16,915) (18,238) (36,338) (54,576) - (10,003) (1,323) (10,003) -
Prudential Borrowing Requirement 265,164 8,315 31,102 234,062 265,164 - 63,661 22,787 63,995 334
Full Project Life In Year
Page 311