WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 869 659 76% 869 (0) 0%
Current Year Financials 397 0 0% 397 0 0%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-29 31-Mar-29
2
Project Life Financials 376 261 0% 376 (0) 0%
Current Year Financials 41 0 0% 41 0 0%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
3
Project Life Financials 20,621 19,766 96% 20,308 (313) -2%
Current Year Financials 4,222 169 4% 4,222 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
None available at this time
Mitigating Action
Anticipated Outcome
Project delivered within budget and to required specification.
Phase 1 of the project was handed over on Monday 18 October 2021, with pupils returning to the new school campus on Wednesday 20 October
2021.  Phase 2  handed over on 25th July 2022.  Ongoing work to conclude Final Defects and release final retention  Note to Sarah.  Forecast is
required for retention plus any other money to be spent.  Also Financial End date needs to be amended to the rention payment date.  Thereafter
no further payments will be made.
Main Issues / Reason for Variance
Although there is slippage caused mainly by the academic year starting several months after the financial year the project is still on track to be
completed by the planned end date.
Mitigating Action
None required at this time.
Anticipated Outcome
Increase the Chromebook ratio for most disadvantaged children.
None required at this time.
Anticipated Outcome
Purchase of AV Equipment for Education.
Digital Inclusion
Increase the ratio of chrome book devices for most disadvantaged children and families and support for
families with remote access.
Planned End Date Forecast End Date
Purchase of AV Equipment for Education.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Although there is slippage caused mainly by the academic year starting several months after the financial year the project is still on track to be
completed by the planned end date.
Mitigating Action
31 July 2023
Budget Details
Project Life Financials
Spend to Date Variance
AV Equipment - Education
Schools Estate Improvement Plan
Improvement of Schools Estate.
Planned End Date Forecast End Date
Main Issues / Reason for Variance

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2023
Budget Details
Project Life Financials
Spend to Date Variance
4
Project Life Financials 2,011 2,011 100% 2,011 0 0%
Current Year Financials 1,439 12 1% 1,439 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
5
Project Life Financials 750 750 100% 750 0 0%
Current Year Financials 112 0 0% 112 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
Project delivered on time and within budget
Choices Programme - to assist young people who require additional support
Bringing together Central Support Services which will include relocation of Choices Programme.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works progressing and budget spend anticipated in 2023/24
Main Issues / Reason for Variance
Project is complete other than snagging works which can only be completed when school is closed however project end date is still on target.
Additional budget required in relation to electrical phasing which was unknown at the time of project inception.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within amended timescales.
Provision of Capital Funding from Scottish Government to implement free school meal initiative.
Planned End Date Forecast End Date
Mitigating Action
None available at this time.
Anticipated Outcome
Free School Meals

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 3
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 July 2023
Budget Details
Project Life Financials
Spend to Date Variance
6
Project Life Financials 5,508 5,508 100% 5,508 0 0%
Current Year Financials 0 0 0% 0 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Laura Mason
Project Lifecycle 31-Mar-22 30-Apr-22
7
Project Life Financials 8,628 8,820 102% 8,820 192 2%
Current Year Financials 287 (11) -4% 287 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
Works progressing and budget spend anticipated in 2023/24
Mitigating Action
None required.
Schools Estate Refurbishment Plan
Completion of condition surveys has been carried out to identify works required to bring various schools from
Condition C to Condition B.
Main Issues / Reason for Variance
Works progressing and budget spend anticipated in 2023/234
Mitigating Action
None required at this time.
Anticipated Outcome
The project will be completed to deliver the requirements of the Early Years expansion plans.
Anticipated Outcome
Project delivered on time and within budget
Early Years Early Learning and Childcare Funding
Early learning and childcare funding awarded to West Dunbartonshire Council to facilitate the expansion in
entitlement to funded ELCC to 1140 hours from August 2020.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance