WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
GENERAL SERVICES CAPITAL PROGRAMME - EDUCATION
OVERALL PROGRAMME SUMMARY
MONTH END DATE
PERIOD 10
Spend to
Date
Spend to
Date
£000 £000
Red
2 25% 1,296 4% 2 25% 564 31%
Amber
0 0% 0 0% 0 0% 0 0%
Green
6 75% 30,330 96% 6 75% 1,270 69%
8 100% 31,626 100% 8 100% 1,834 100%
Budget Spend to
Date
Forecast
Spend
Forecast
Variance Budget Spend to
Date
Forecast
Spend
Forecast
Variance Slippage Over/
(Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
PL CY
30,200 1,296 30,200 (0) 2,910 564 800 (2,110) (2,110) 0 0% -73%
0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0!
36,677 30,330 36,750 74 2,790 1,270 2,790 0 0 0 0% 0%
66,877 31,626 66,950 74 5,700 1,834 3,590 (2,110) (2,110) 0
Projects are on target both in relation to overall budget and the forecast stages in the project life cycle and
no issues are anticipated at this time
31 January 2023
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of
Projects at
RAG Status
% Projects
at RAG
Status
% Project
Spend at
RAG Status
Number of
Projects at
RAG Status
% Projects
at RAG
Status
% Project
Spend at
RAG Status
Red
Projects are forecast to be overspent and/or experience material delay to completion
Amber
Projects are either at risk of being overspent and/or delay in completion (although this is unquantifiable at
present) or the project has any issues that require to be reported at this time
Green
TOTAL EXPENDITURE
Project Life Financials Current Year Financials
Red
Projects are on target both in relation to overall budget and the forecast stages in the project life cycle and
no issues are anticipated at this time
TOTAL EXPENDITURE
Projects are forecast to be overspent and/or significant delay to completion
Amber
Projects are either at risk of being overspent and/or delay in completion (although this is unquantifiable at
present) or the project has any issues that require to be reported at this time
Green