WEST DUNBARTONSHIRE COUNCIL
Report by Chief Education Officer 
Educational Services Committee – 8 March 2023
Subject: Response on the Consultation Proposal to open an additional
support needs school at former Riverside Early Learning and
Childcare Centre (ELCC)
1. Purpose
1.1 The purpose of the report is to inform the Educational Services Committee of the
outcome and findings of the statutory consultation exercise undertaken in respect
of the formal consultation on the proposal to open a new additional support needs
school in the site of the former Riverside ELCC on the St. Martin’s Primary site.
2. Recommendations
2.1 It is recommended that the Committee:
(i) Agrees the findings from the statutory consultation exercise and
notes the content of the associated Education Scotland report.
3. Background
3.1 At the meeting on 28 September 2022, Educational Services Committee
agreed to commence formal consultation on a proposal to establish a new
additional support needs school to be located in the former Riverside ELCC
site within the campus of the current St. Martin’s Primary School.
3.2 The consultation has been undertaken in accordance with the Schools
(Consultation) (Scotland) Act 2010 and copies of the proposal document were
made available to all stakeholders as prescribed by the Act.  The consultation ran
from 3 October 2022 to 11 November 2022, a total of 33 days when schools were
open for pupils (reflecting the October holiday week).
3.3 Committee further agreed that a report outlining the results of the consultation
and appropriate recommendations be presented to the meeting of the
Educational Services Committee to be held on 8 March 2023.
4. Consultation Process / Considerations
4.1 The statutory consultation process was undertaken with a Proposal Paper
setting out the proposal on which the Council was consulting being
published on the Council’s website and stakeholders invited to participate in
the consultation exercise. An electronic link to the consultation page and
Proposal Paper, was issued by email to the consultees listed within the
document and was also published on the Council’s website and publicised
via the Council’s social media channels.
ITEM 8

Page 2

4.2 As part of the Council’s consultation process we undertook the following
activities: 
• Publicising the consultation and dates of public meetings through the
Council’s website, through public notices in local newspapers and on
social media.
• Advising relevant stakeholders by email of the consultation and
providing an electronic link to the website.
• Holding an online virtual public consultation meeting, and a public
consultation meeting at St. Martin’s Primary School on 25 October
2022.
• Utilising the Council’s consultation web page to make documentation on
the proposal, link to the online survey, background information and
details on how to participate in the survey available.
• Setting up a direct telephone line and email address to deal with queries 
4.3 Two public consultations meetings were held on 25 October 2022 to allow
Officers to explain the proposal and enable interested parties to ask
questions regarding the proposal. 
4.4 No interested parties attended the online virtual public meeting which took
place at 4.00 p.m. A total of 15 people attended the public meeting held in
the evening, and this included parents, staff and members of the local
community and a representative from Education Scotland was also in
attendance, as part of their role in the statutory consultation process.
Minutes were taken at both meetings (Appendix 1) and these minutes were
made available on the consultation pages of the Council’s website. 
4.5  An online survey was available during the consultation period, with 7
respondents registering. In answer to the question “Are you in favour of the
proposal to redevelop the former Riverside Early Learning and Childcare
Centre (ELCC) to form a new school, supporting ASN needs, on St. Martin’s
Campus”?  6 respondents were in favour of the proposal and 1 respondent
was not. 
4.6 The majority of the respondents were in favour of the proposal and a number
of positive comments were received. Details of comments submitted and the
Council’s response is outlined within the Consultation Response Report
(Appendix 2). 
4.7 One written response was made to the public consultation. The written
response supported the proposal. 
4.8  The Schools (Consultation) (Scotland) Act 2010 requires HM Inspectors
from Education Scotland to be involved in the formal consultation proposal.
As part of this process HM Inspectors undertook the following activities in
considering the educational aspect of the proposal: 
• attendance at the public consultation meetings held on 25 October 2022
in connection with the Council’s proposal;

Page 3

• consideration of all relevant documentation provided by the Council in
relation to the proposal, specifically the educational benefits statement,
related consultation documents, and written and oral submissions from
parents and others; and 
• visits to the site of St. Martin’s Primary School, including discussions with
relevant consultees; and engagement with the Archbishop of Glasgow’s
representative. 
4.9  Education Scotland produced a report on the consultation undertaken by the
Council on the proposal for the establishment of a new school to support
additional support needs at the former Riverside ELCC. The full report from
Education Scotland (Appendix 3) was published on their website and also
published as part of the Consultation Report. 
4.10  Within the report, Education Scotland has expressed the following opinion
on the education benefit arising if this proposal is implemented. “HM
Inspectors agree that the proposal has the potential to bring clear
educational benefits for young people with additional support needs
attending the new school. A shared campus will create joint learning
opportunities for both the new school and the existing primary school”. 
4.11 Education Scotland also stated, “HM Inspectors agree that the new facility
will enhance the current provision for children and young people with
additional support needs across West Dunbartonshire.  The shared campus
will ensure that the building that is currently empty, is put to good use.” 
4.12 The report also commented that “In order to alleviate any concerns that
stakeholders may have about the layout of the building, the council should
share proposed plans as soon as is practicable. Should the proposal go
ahead, the council should ensure that all stakeholders are kept fully up to
date with developments”  If the proposal goes ahead education services is
committed to including all stakeholders in the planning and design stage,
and will continue to use effective communication strategies to ensure
continued engagement with all stakeholders throughout the development 
4.13  Almost all stakeholders who spoke with HM Inspectors or who responded in
writing are supportive of the proposals and recognise that it will enhance the
current provision and provides an option for children to be educated locally. 
Staff and children from St. Martin’s Primary School also welcomed the
development and recognized the educational benefits of working
collaboratively and sharing resources. 
4.14 A few stakeholders expressed some reservations in terms of safety
regarding car parking and access at the school at busy times.  The Council
is aware of known problems at the site with car parking, and drop off points
and the turning area.  Response to this issue is contained within the
Consultation Report.

Page 4

4.15  Education Scotland recognised that the Archdiocese of Glasgow welcomes
the fact that the co-location of the two schools will be in accordance with the
Catholic Church’s protocols for co-located establishments.  Response to the
issues raised in relation to separate entrances and connecting doors within
the school, and shared use of facilities are contained within the Consultation
Report. 
4.16  The Council is required to prepare and publish its final Consultation Report
when the consultation exercise has been concluded. In preparing the report,
the Council must consider the report from Education Scotland and other
responses to the consultation. The consultation report must explain how the
Council has reviewed the proposal, a summary of the points raised during
the consultation and the Council’s response to them. Responses to
comments received from the consultation were published as part of the
Consultation Report.
4.17  The Council is required to publish the Consultation Report and Educational
Services Committee cannot take a decision on whether to formally
implement a proposal until 3 weeks have elapsed from the date it publishes
the Consultation Report. The Consultation Report was published on the
website on Monday 14 February 2023 
5. People Implications 
5.1 If the proposal is accepted there will be some effect on staffing levels within the
new campus, particularly within cleaning and facilities management services as
there will be two establishments on the premises to be supported.  There is
potential to create a number of teaching and support staff posts.  Any changes
would be managed via the Council’s policies for managing such changes.  The
timescales involved mean that any additions or recruitment of staff will be
managed in a planned way.   
6. Financial and Procurement Implications 
6.1 The additional staffing costs will be met from the agreed budget for approved
expansion of the school learning estate to meet projected needs of the
Additional Support Needs (ASN) sector. 
7. Risk Analysis 
7.1 There are no risks in adopting the recommendations contained in this
paper and HM Inspectors believe the proposal is of educational benefit. 
8. Equalities Impact Assessment (EIA) 
8.1 An Equalities Impact Assessment has been undertaken for the proposal and
was reported to Educational Services Committee on 22 September 2022. 
The project will improve the quality of the educational experience for young
people in West Dunbartonshire who have severe and complex learning
needs and there are therefore no negative impact relating to equality issues.

Page 5

9. Consultation 
9.1 Consultation on the proposed changes was undertaken in accordance with the
Schools (Consultation) (Scotland) Act 2010. 
9.2 Legal Services and the Section 95 Officer have been consulted on the
content of this report. 
10. Strategic Assessment 
10.1 The improvements in the learning environments in the adaptation of
the former ELCC promotes and encourages imaginative and
innovative learning and teaching thereby increasing attainment and
achievement.  This in turn leads to the strategic objective of a strong
local economy and increased employment opportunities. 
Laura Mason
Chief Education Officer 
Person to Contact: Claire Cusick, Senior Education Officer, 
claire.cusick@west-dunbarton.gov.uk  
Appendices: Appendix 1 – Minutes from Public Meetings on 25.10.22
Appendix 2 – Consultation Report
Appendix 3 – Education Scotland Report 
Background Papers: Education Services Committee Report 28 September
2022   
Wards Affected: All council Wards