ADDITIONAL DOCUMENT PACK (Additional Agenda and Report) (Bookmarked) ESC 08 03 23

West Dunbartonshire Council · 8 March 2023
Back to Educational Services Committee — 8 March 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Additional
Agenda 
Educational Services Committee 
Date:  Wednesday, 8 March 2023
___________________________________________________________________ 
Time:  10:00
___________________________________________________________________ 
Format:  Hybrid Meeting
___________________________________________________________________ 
Contact:    Scott Kelly, Committee Officer  
Tel: 01389 737220.  Email: scott.kelly@west-dunbarton.gov.uk 
Dear Member 
ITEM TO FOLLOW 
I refer to the agenda for the above Meeting of the Educational Services Committee
which was issued on 15 February 2023 and now enclose a copy of the undernoted
report which was not available for issue at that time.   
Yours faithfully 
PETER HESSETT 
Chief Executive 
Note referred to:-/ 
14 EDUCATIONAL SERVICES BUDGETARY CONTROL        101 – 118
REPORT TO 31 JANUARY 2023 (PERIOD 10) 
Submit report by the Chief Officer – Resources providing an update on the 
financial performance of Education Services to 31 January 2023 (Period 10). 
Page 99

Page 2

Distribution: 
Councillor Clare Steel (Chair)   Councillor Gordon Scanlan
Councillor Karen Conaghan    Councillor Hazel Sorrell
Councillor Gurpreet Singh Johal   Mrs Barbara Barnes
Councillor Daniel Lennie    Ms Kirsty Connolly 
Councillor David McBride    Mr Gavin Corrigan
Councillor Jonathan McColl   Miss Cara Cusick MSYP
Councillor Michelle McGinty   Miss Ellen McBride 
Councillor June McKay    Ms Hannah Redford
Councillor John Millar (Vice Chair)  Ms Julia Strang
Councillor Lawrence O’Neill   Miss Tian Qi Yu MSYP
Councillor Lauren Oxley    Vacancy
Councillor Martin Rooney 
All other Councillors for information
Chief Education Officer 
Date of Issue: 2 March 2023
Page 100

Page 3

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer (Resources)
Educational Services Committee: 8 March 2023
___________________________________________________________________
Subject: Educational Services Budgetary Control Report to
31 January 2023 (Period 10).
1. Purpose
1.1 The purpose of the report is to provide Committee with an update on the
financial performance of Educational Services to 31 January 2023 (Period
10).
2. Recommendations
2.1  Committee is asked to:
(a) note that the revenue account currently shows a projected annual adverse
revenue variance of £1.284m (1.16% of the total budget) which declines to
£0.839m (0.76% of the total budget) after application of COVID funds ;
and
(b) note that the capital account shows a projected in-year favourable
variance of £2.110m which is budget being re-profiled to 2023/24.
3. Background
Revenue
3.1 At the meeting of West Dunbartonshire Council on 9 March 2022, Members
agreed the revenue estimates for 2022/2023, including a total net Educational
Services Committee budget of £107.788m. Since then the following budget
adjustments have taken place revising the budget to £110.329m.
Budget Agreed by Council 9 March 2022   £107.788m
Easter Study Support Provision  £0.101m
Utilities Provision (reallocation from sundry
services) 
£0.397m
Mobile and adobe licenses realignment  (£0.001m)
Education Utilities (Gas & Electricity)
Pay Award
ISDN Budget savings 
National Insurance reduction 
£0.103m 
£2.340m
(£0.059m)
(£0.340m)
Revised Budget  £110.329m
ITEM 14
Page 101

Page 4

3.2 The current APT&C pay award for staff from 1 April 2022 has been agreed.
Any cost beyond the increase assumed in the budget requires to be funded. 
The teachers’ pay award has yet to be agreed and this report assumes a pay
award of 5%.There is a risk that the 2022/23 teachers’ pay award is materially
different from the pay offer for the rest of local government. Whilst the Scottish
Government have committed additional funds to contribute towards the pay
offer to teachers of 6% in 2022/23 and 5.5% in 2023/24 this offer has not
been accepted and industrial action continues. 
Capital
3.3 At the meeting of Council on 22 March 2021 Members also agreed the
updated 10 year General Services Capital Plan for 2021/22 to 2030/31.  The
three years from 2021/22 to 2023/24 have been approved in detail with the
remaining seven years from 2024/25 to 2030/31 being indicative at this stage.
After adjusting for anticipated slippage from 2021/22 into 2022/23,
acceleration of £0.241m, and Free School Meals Expansion funding of
£0.495m the budget for 2022/23 is £5.7m. 
4. Main Issues   
Revenue Budget
4.1 The current departmental budgetary position is summarised in Appendix 1,
with detailed analysis by service in Appendix 2. 
4.2 The overall projected full year variance is £1.284m adverse. Information and
all individual variances of over £50,000 are detailed in Appendix 3. 
4.3      The uncertainty surrounding the split in residential placements costs between                          
WDC Education and HSCP has now been resolved. At its meeting held on 26
October 2022, Council agreed that the allocation of Residential Care Costs
should change from that of a 77.3% HSCP/22.7% Education split to a
72%/28% split in 2022/23 and on a recurring basis.  Furthermore, on 21
December 2022, Members agreed that the proportionate share of the 2022/23
budget to support this change, be transferred from West Dunbartonshire
Council to the HSCP budget. This has now been captured in the period 10 
Budgetary Control Report in the retention of an additional £1.419m within the
revised probable outturn for residential placements. 
4.4      These period 10 figures do not capture any further reduction in costs arising           
from the two additional strike days (28th February and 1st March). This, when
factored into future budgetary control reports, will reduce the projected
overspend by approximately £0.400m to £0.884m. After the application of
COVID funds the projected overspend would fall further to £0.439m. 
Page 102

Page 5

Capital
4.5 The overall Educational Services programme summary report at Appendix 5
shows that the expected spend on the project life is anticipated to be equal to
the original budget, and there is currently £2.110m reprofiling of current year
budget to 2023/24.  Appendix 6 highlights 2 projects which will have budget
reprofiled into 2023/24 and  Appendix 7 highlights all projects at green status,
of which none have an in-year variance of over £0.050m.
5. People Implications
5.1 There are no direct people implications.
6. Financial and Procurement Implications
6.1 Other than the financial position noted above and within the appendices, there
are no financial or procurement implications of the budgetary control report.
7. Risk Analysis
7.1 The main financial risks to the ongoing financial position relate to unforeseen
costs and/or reduced income streams being identified between now and the
end of the financial year. This is particularly sensitive with the ongoing ,
though diminishing, impact of Covid-19.  Finance staff are in regular
discussion with budget holders to ensure potential issues are identified as
early as possible in order to mitigate this risk.
7.2  A more specific uncertainty surrounds the outcome of the teachers’ pay award
for 2022/23. The figures in the attached appendices have assumed that the
teachers’ pay award replicates that accepted by APT&C staff and the table
below shows the consequences of such an award for APT&C and teachers.
Cost of pay award 2022/23   £4.446m 
Pay award assumption already in budget  £1.657m
Estimated Scottish Govt. Funding  £2.340m 
Shortfall to be funded by WDC      £0.449m
8. Equalities Impact Assessment (EIA)
8.1 The report is for noting and therefore, no Equalities Impact Assessment was
completed for this report.
9. Consultation
9.1 The views of Education, Finance and Legal services were requested in the
preparation of this report and they have advised there are neither any
additional issues nor concerns with the proposal. As the report is for noting no
further consultation is envisaged.
Page 103

Page 6

10. Strategic Assessment
10.1 Proper budgetary control and sound financial practice are cornerstones of
good governance and support Council and officers to pursue the 5 strategic
priorities of the Council’s Strategic Plan. This report forms part of the financial
governance of the Council. 
Laurence Slavin
Chief Officer - Resources
Date: 28 February 2023
Person to Contact: Joe Reilly - Business Unit Finance Partner (Education),
Church St, Dumbarton, G82 1QL, telephone: 01389
737707, e-mail joe.reilly@west-dunbarton.gov.uk 
Appendices: Appendix 1 - Revenue Budgetary Control 2022/23
- Summary Report
Appendix 2 - Revenue Budgetary Control 2022/23
- Service Reports
-
Appendix 3 - Analysis of Revenue Variances over  
£50,000
Appendix 4 – Analysis of Revenue Efficiencies
Appendix 5 - Capital Programme Summary
Appendix 6 – Capital Projects at Red Status
Appendix 7 – Capital Projects at Green Status
Background Papers: Ledger output – period 10
General Services Revenue Estimates 2022/23
Wards Affected: ,All
Page 104

Page 7

WEST DUNBARTONSHIRE COUNCIL APPENDIX 1
REVENUE BUDGETARY CONTROL 2022/23REVENUE BUDGETARY CONTROL 2022/23
EDUCATION SUMMARY
Total Budget
2022/23
YTD Spend
2022/23
Forecast Spend
2022/23
Annual
RAG
Status
Net Variance
attributable
to covid
Underlying
Variance
excluding
covid
£000 £000 £000 £000 % £000 £000
31,914 25,300 31,025 (889) -3%  (889)
31,675 25,179 31,300 (374) -1%  (374)
17,290 14,219 19,935 2,645 15%  445 2,200
583 428 573 (10) -2%  (10)
627 550 627 0 0%  0
8,864 4,055 8,837 (27) 0%  (27)
15,420 14,981 15,536 116 1%  116
Creative Arts 642 470 637 (5) -1%  (5)
191 41 191 0 0%  0
854 802 852 (2) 0%  (2)
357 267 323 (34) -10%  (34)
Performance & Improvement 467 281 366 (101) -22%  (101)
Education Development 1,447 853 1,410 (36) -3%  (36)
Raising Attainment - Primary 0 0 0 0 0%  0
Raising Attainment - Secondary 0 0 0 0 0%  0
Pupil Equity Fund LAC 0 0 0 0 0%  0
110,329 87,426 111,612 1,284 1.16%  445 839
Central Admin
Workforce CPD
Total Net Expenditure
Psychological Services
Sport Development / Active Schools
Early Education
PPP
Curriculum for Excellence
31 January 2023
Specialist Educational Provision
Service / Subjective Summary Annual Variance
2022/23
Primary Schools
Secondary Schools
Page 105

Page 8

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2022/23
EDUCATION DETAIL
MONTH END DATE31 January 2023
Total Budget
2022/23
YTD Spend
2022/23
Forecast Spend
2022/23 RAG Status
£000 £000 £000 £000 %
Employee 91,529                  71,852         90,764                  (765) -0.01 
Property 8,167                    6,453           8,315                    148 0.02 
Transport and Plant 2,495                    1,499           2,498                    3 0.00 
Supplies, Services and Admin 3,038                    1,842           3,131                    93 0.03 
Payments to Other Bodies 22,064                  20,900         24,755                  2,690 0.12 
Other 2,219                    4,501           4,658                    2,439 1.10 
Gross Expenditure 129,513 107,047 134,121 4,608 0.04 
Income (19,184) (19,621) (22,509) (3,325) -0.17 
Net Expenditure 110,329 87,426 111,612 1,284 0.01 
£000 £000 £000 £000 %
Employee 27,686 21,854 27,020 (666) -0.02 
Property 3,062 2,310 3,098 36 0.01 
Transport and Plant 333 295 347 14 0.04 
Supplies, Services and Admin 386 255 355 (31) -0.08 
Payments to Other Bodies 15 3 15 0 0.00 
Other 766 786 788 22 0.03 
Gross Expenditure 32,248 25,503 31,623 (625) -0.02 
Income (334) (203) (598) (264) -0.79 
Net Expenditure 31,914 25,300 31,025 (889) -0.03 
£000 £000 £000 £000 %
Employee 29,233 22,788 28,569 (664) -0.02 
Property 1,173 922 1,208 35 0.03 
Transport and Plant 614 566 618 4 0.01 
Supplies, Services and Admin 418 202 418 0 0.00 
Payments to Other Bodies 472 446 472 (0) 0.00 
Other 929 798 941 12 0.01 
Gross Expenditure 32,840 25,722 32,226 (613) -0.02 
Income (1,165) (543) (926) 239 0.21 
Net Expenditure 31,675 25,179 31,300 (374) -0.01 
£000 £000 £000 £000 %
Employee 12,102 9,643 12,208 106 0.01 
Property 145 94 123 (22) -0.15 
Transport and Plant 1,391 538 1,382 (9) -0.01 
Supplies, Services and Admin 113 81 113 0 0.00 
Payments to Other Bodies 3,805 3,868 6,370 2,565 0.67 
Other 38 26 38 0 0.00 
Gross Expenditure 17,595 14,250 20,235 2,640 0.15 
Income (305) (31) (300) 5 0.02 
Net Expenditure 17,290 14,219 19,935 2,645 0.15 
£000 £000 £000 £000 %
Employee 648 499 638 (10) -0.02 
Property 0 0 0 0 0.00 
Transport and Plant 1 1 2 1 1.00 
Supplies, Services and Admin 6 1 6 (0) -0.05 
Payments to Other Bodies 0 0 0 0 0.00 
Other 0 0 0 0 0.00 
Gross Expenditure 656 501 646 (10) -0.01 
Income (73) (73) (73) 0 0.00 
Net Expenditure 583 428 573 (10) -0.02 
Sports Development / Active Schools £000 £000 £000 £000 %
Employee 0 0 0 0 0.00 
Property 0 0 0 0 0.00 
Transport and Plant 0 0 0 0 0.00 
Supplies, Services and Admin 0 0 0 0 0.00 
Payments to Other Bodies 893 744 893 0 0.00 
Other 0 0 0 0 0.00 
Gross Expenditure 893 744 893 0 0.00 
Income (266) (194) (266) 0 0.00 
Net Expenditure 627 550 627 0 0.00 
Secondary Schools
Service Summary Annual Variance 2022/23
All Services
Primary Schools
Specialist Educational Provision
Psychological Services
Page 106

Page 9

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2022/23
EDUCATION DETAIL
MONTH END DATE31 January 2023
Total Budget
2022/23
YTD Spend
2022/23
Forecast Spend
2022/23 RAG Status Service Summary Annual Variance 2022/23
£000 £000 £000 £000 %
Employee 15,041 11,426 15,112 71 0.00 
Property 286 170 286 0 0.00 
Transport and Plant 10 4 6 (4) -0.40 
Supplies, Services and Admin 1,069 387 1,069 0 0.00 
Payments to Other Bodies 3,218 2,491 3,229 11 0.00 
Other 0 0 0 0 0.00 
Gross Expenditure 19,624 14,478 19,702 78 0.00 
Income (10,760) (10,423) (10,865) (105) -0.01 
Net Expenditure 8,864 4,055 8,837 (27) 0.00 
£000 £000 £000 £000 %
Employee 0 0 0 0 0.00 
Property 3,486 2,945 3,585 99 0.03 
Transport and Plant 0 0 0 0 0.00 
Supplies, Services and Admin 0 0 0 0 0.00 
Payments to Other Bodies 12,692 12,794 12,709 17 0.00 
Other 0 0 0 0 0.00 
Gross Expenditure 16,178 15,739 16,294 116 0.01 
Income (758) (758) (758) 0 0.00 
Net Expenditure 15,420 14,981 15,536 116 0.01 
£000 £000 £000 £000 %
Employee 0 0 0 0 0.00 
Property 0 0 0 0 0.00 
Transport and Plant 0 0 0 0 0.00 
Supplies, Services and Admin 171 41 171 0 0.00 
Payments to Other Bodies 20 0 20 0 0.00 
Other 0 0 0 0 0.00 
Gross Expenditure 191 41 191 0 0.00 
Income 0 0 0 0 0.00 
Net Expenditure 191 41 191 0 0.00 
£000 £000 £000 £000 %
Employee 117 447 486 369 3.15 
Property 8 6 8 0 0.00 
Transport and Plant 0 4 4 4 0.00 
Supplies, Services and Admin 53 78 91 38 0.72 
Payments to Other Bodies 248 348 441 193 0.78 
Other 486 2,891 2,891 2,405 4.95 
Gross Expenditure 912 3,774 3,921 3,009 3.30 
Income (58) (2,972) (3,069) (3,011) -51.91 
Net Expenditure 854 802 852 (2) 0.00 
£000 £000 £000 £000 %
Employee 321 224 278 (43) -0.13 
Property 0 0 0 0 0.00 
Transport and Plant 1 0 0 (1) -1.00 
Supplies, Services and Admin 22 32 32 10 0.45 
Payments to Other Bodies 13 11 13 0 0.00 
Other 0 0 0 0 0.00 
Gross Expenditure 357 267 323 (34) -0.10 
Income 0 0 0 0 0.00 
Net Expenditure 357 267 323 (34) -0.10 
£000 £000 £000 £000 %
Employee 515 312 402 (114) -0.22 
Property 0 0 0 0 0.00 
Transport and Plant 2 0 0 (2) -1.00 
Supplies, Services and Admin 0 0 0 0 0.00 
Payments to Other Bodies 0 0 0 0 0.00 
Other 0 0 0 0 0.00 
Gross Expenditure 518 312 402 (116) -0.22 
Income (51) (31) (36) 15 0.29 
Net Expenditure 467 281 366 (101) -0.22 
Curriculum for Excellence
Central Admin
PPP
Workforce CPD
Early Education
Performance & Improvement
Page 107

Page 10

WEST DUNBARTONSHIRE COUNCIL APPENDIX 2
REVENUE BUDGETARY CONTROL 2022/23
EDUCATION DETAIL
MONTH END DATE31 January 2023
Total Budget
2022/23
YTD Spend
2022/23
Forecast Spend
2022/23 RAG Status Service Summary Annual Variance 2022/23
£000 £000 £000 £000 %
Employee 987 887 1,208 221 0.22 
Property 0 0 0 0 0.00 
Transport and Plant 124 75 123 (1) -0.01 
Supplies, Services and Admin 21 32 88 67 3.19 
Payments to Other Bodies 472 130 347 (125) -0.26 
Other 0 0 0 0 0.00 
Gross Expenditure 1,605 1,124 1,767 162 0.10 
Income (158) (271) (357) (199) -1.26 
Net Expenditure 1,447 853 1,410 (36) -0.03 
£000 £000 £000 £000 %
Employee 817 566 817 0 0.00 
Property 0 0 0 0 0.00 
Transport and Plant 0 0 0 0 0.00 
Supplies, Services and Admin 89 89 89 0 0.00 
Payments to Other Bodies 5 5 5 0 0.00 
Other 0 0 0 0 0.00 
Gross Expenditure 911 660 911 0 0.00 
Income (911) (660) (911) 0 0.00 
Net Expenditure 0 0 0 0 0.00 
£000 £000 £000 £000 %
Employee 675 563 675 0 0.00 
Property 0 0 0 0 0.00 
Transport and Plant 0 1 0 0 0.00 
Supplies, Services and Admin 3 3 3 0 0.00 
Payments to Other Bodies 157 0 157 0 0.00 
Other 0 0 0 0 0.00 
Gross Expenditure 835 567 835 0 0.00 
Income (835) (567) (835) 0 0.00 
Net Expenditure 0 0 0 0 0.00 
£000 £000 £000 £000 %
Employee 2,641 2,074 2,641 0 0.00 
Property 7 6 7 0 0.00 
Transport and Plant 15 14 15 0 0.00 
Supplies, Services and Admin 664 635 664 0 0.00 
Payments to Other Bodies 54 52 54 0 0.00 
Other 0 0 0 0 0.00 
Gross Expenditure 3,381 2,781 3,381 0 0.00 
Income (3,381) (2,781) (3,381) 0 0.00 
Net Expenditure 0 0 0 0 0.00 
£000 £000 £000 £000 %
Employee 744 569 709 (35) -0.05 
Property 0 0 0 0 0.00 
Transport and Plant 4 1 1 (3) -0.75 
Supplies, Services and Admin 23 6 32 9 0.39 
Payments to Other Bodies 0 8 29 29 0.00 
Other 0 0 0 0 0.00 
Gross Expenditure 771 584 771 0 0.00 
Income (129) (114) (134) (5) -0.04 
Net Expenditure 642 470 637 (5) -0.01 
Raising Attainment - Primary
Raising Attainment - Secondary
Pupil Equity Fund
Education Development
Creative Services
Page 108

Page 11

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2022/23
ANALYSIS FOR VARIANCES OVER £50,000
YEAR END DATE
Total Budget Annual Spend Variance RAG Status
£000 £000 £000 %
Primary Schools (Laura Mason) 31,914 31,025 (889) -3% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Secondary Schools (Laura Mason) 31,675 31,300 (374) -1% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
31 January 2023
Budget Details
Variance Analysis
This service area includes all Primary Schools.
The budget was set before the delay to free school meal expansion was confirmed. As primaries 6 & 7 will now not be covered by
universal free school meal provision from August 2022 income from school meals will be significantly above the budgeted target income
(£225k).  This offsets the reduction in school lets income (£15k) . There is also a favourable variance (£665k) against employee costs as
the budget was set higher than expenditure would suggest and reduced expenditure from 3 days strike action has been recognised
None necessary
Favourable variance anticipated
This service area includes all Secondary Schools.
Income from sale of school meals is currently projected to be less than budgeted (£177k) while income from lets is also lower than
expected (£104k). There is a favourable variance against employee costs caused in part by reduced expenditure from 3 days strike
action.
None necessary
Favourable variance anticipated
Page 109

Page 12

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2022/23
ANALYSIS FOR VARIANCES OVER £50,000
YEAR END DATE
Total Budget Annual Spend Variance RAG Status
£000 £000 £000 %
31 January 2023
Budget Details
Variance Analysis
Additional Support Needs (Claire Cusick) 17,290 19,935 2,645 15% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
PPP (Laura Mason) 15,420 15,536 116 1% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
This service area covers all ASN Services.
The adverse variance within employee costs (£107k) is due to a combination of turnover targets not being achieved , a greater than
expected pay award and greater staffing as part of our efforts to minimise external placements , all reduced partly by reduced
expenditure from 3 days strike action. Payments to Other Bodies adverse variance is primarily due to Council's decision regarding the
division of residential costs between WDC and HSCP exacerbated by the ongoing high demands on the Residential Placements Budget
(£2.367m) - the number of residential placements is 6% higher (about 2 placements)  than the average for 2021/22.  Day placements
are also over budget (£199k) as placements are on average about 6 greater than last year.
The requirement for Residential Placements is demand-led  and decisions are taken jointly with HSCP following an assessment of the
best option for all concerned. However, the actual usage throughout the year will be reviewed regularly to identify where there is scope
to reduce the number of placements.
adverse variance anticipated
This service area includes Vale of Leven, Clydebank High and St Peter the Apostle High Schools and St Eunan's Primary School. The
costs charged to this service are Property costs and the Unitary charge.
There is an overspend because of the increased pressure over the year on gas costs (£57k) ,contract cleaning costs (£41k) and
possible payments to BAM for banked hours/change notices (£16k).
None possible
An overspend is anticipated
Page 110

Page 13

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2022/23
ANALYSIS FOR VARIANCES OVER £50,000
YEAR END DATE
Total Budget Annual Spend Variance RAG Status
£000 £000 £000 %
31 January 2023
Budget Details
Variance Analysis
Performance & Improvement (Andrew
Brown) 467 366 (101) -22% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
This service covers the monitoring of policies and improvement on curriculum within Education.
The reason for the favourable variance is the number of vacancies throughout the year
none necessary
A favourable variance is anticipated
Page 111

Page 14

WEST DUNBARTONSHIRE COUNCIL
MONITORING OF EFFICIENCIES AND MANAGEMENT ADJUSTMENTS 2022/23 APPENDIX 4
Efficiency
reference
Efficiency Detail budgeted
Amount £
Projection of
Total Saved £
Projection of Total
Not Saved £
Comment
Reduce Teacher costs - 0.6 Consortium
Secondary Schools
35,467            35,467           -                                        
35,467                  35,467                                 -  
Page 112

Page 15

WEST DUNBARTONSHIRE COUNCIL APPENDIX 5
GENERAL SERVICES CAPITAL PROGRAMME - EDUCATION
OVERALL PROGRAMME SUMMARY
MONTH END DATE
PERIOD 10
Spend to
Date
Spend to
Date
£000 £000
Red
2 25% 1,296 4% 2 25% 564 31%
Amber
0 0% 0 0% 0 0% 0 0%
Green
6 75% 30,330 96% 6 75% 1,270 69%
8 100% 31,626 100% 8 100% 1,834 100%
Budget Spend to
Date
Forecast
Spend
Forecast
Variance Budget Spend to
Date
Forecast
Spend
Forecast
Variance Slippage Over/
(Under)
£000 £000 £000 £000 £000 £000 £000 £000 £000 £000
PL CY
30,200 1,296 30,200 (0) 2,910 564 800 (2,110) (2,110) 0 0% -73%
0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0!
36,677 30,330 36,750 74 2,790 1,270 2,790 0 0 0 0% 0%
66,877 31,626 66,950 74 5,700 1,834 3,590 (2,110) (2,110) 0
Projects are on target both in relation to overall budget and the forecast stages in the project life cycle and
no issues are anticipated at this time
31 January 2023
Project Status Analysis
Project Life Status Analysis Current Year Project Status Analysis
Number of
Projects at
RAG Status
% Projects
at RAG
Status
% Project
Spend at
RAG Status
Number of
Projects at
RAG Status
% Projects
at RAG
Status
% Project
Spend at
RAG Status
Red
Projects are forecast to be overspent and/or experience material delay to completion
Amber
Projects are either at risk of being overspent and/or delay in completion (although this is unquantifiable at
present) or the project has any issues that require to be reported at this time
Green
TOTAL EXPENDITURE
Project Life Financials Current Year Financials
Red
Projects are on target both in relation to overall budget and the forecast stages in the project life cycle and
no issues are anticipated at this time
TOTAL EXPENDITURE
Projects are forecast to be overspent and/or significant delay to completion
Amber
Projects are either at risk of being overspent and/or delay in completion (although this is unquantifiable at
present) or the project has any issues that require to be reported at this time
Green
Page 113

Page 16

WEST DUNBARTONSHIRE COUNCIL APPENDIX 6
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT RED ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
Project Life Financials 29,450 659 2% 29,450 (0) 0%
Current Year Financials 2,797 563 20% 800 (1,997) -71%
Project Description
Project Manager Sharon Jump/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-26 31-Mar-26
Project Life Financials 750 638 85% 750 0 0%
Current Year Financials 113 1 1% 0 (113) -100%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
Project delivered on budget.
None available at this time.
Anticipated Outcome
Delivery of the project will be on time.
Choices Programme - to assist young people who require additional support
Bringing together Central Support Services which will include relocation
Planned End Forecast End Date
Main Issues / Reason for Variance
A new contractor has been appointed and looking at the programme of works.
Mitigating Action
None available at this time.
Anticipated Outcome
Mitigating Action
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Schools Estate Improvement Plan - next Phase - Faifley Campus
Improvement of Schools Estate.
Planned End Forecast End Date
Main Issues / Reason for Variance
The next phase of the Schools Estate Improvement Plan involves the development of a new Campus provision in the Faifley area.
WDC has been successful in securing funding from the Scottish Government Learning Estate Improvement Programme. SFT
confirmed the indicative funding allocation for this project at £18.416m on the 4 May 2021, this will be received as a revenue stream
over the 25 years of the Scottish Government financial support (subject to the Council adhering to the funding criteria). Site Options
Appraisal has taken place and Members approved the recommendation to proceed with the new Faifley Campus on the St Joseph's
site at Education Committee on 9th June 2021.  The design team and main contractor have been appointed and the next phase will
see the design development for the new Campus taking place. The statutory consultation process was launched in September 2021
and a report was brought back to the Educational Services committee in March 2022 concluding the process. RIBA Stage 2 Design
development slightly behind programme but this will not have an impact on the overall Phase 1 completion date for the project.
Page 114

Page 17

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
Project Life Financials 1,110 244 22% 1,110 (0) 0%
Current Year Financials 441 56 13% 441 0 0%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-29 31-Mar-29
Project Life Financials 376 335 89% 376 (0) 0%
Current Year Financials 41 0 0% 41 0 0%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
Main Issues / Reason for Variance
Additional devices have been ordered to increase the ratio of devices to pupils as part of a commitment towards a 1:1 device ratio. The
project is on track to be fully spent in 2022/2023.
Mitigating Action
None required at this time.
Anticipated Outcome
Increase the Chromebook ratio for most disadvantaged children.
Planned End Forecast End Date
Purchase of AV Equipment for Education.
Planned End Forecast End Date
Main Issues / Reason for Variance
Although there is re-profiling of budget caused mainly by the academic year starting several months after the financial year the project is still
on track to be completed by the planned end date.
Mitigating Action
None available at this time.
Anticipated Outcome
Purchase of AV Equipment for Education.
Digital Inclusion
Increase the ratio of chrome book devices for most disadvantaged children
AV Equipment - Education
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Page 115

Page 18

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Project Life Financials 20,241 15,280 75% 20,241 0 0%
Current Year Financials 1,005 464 46% 1,005 0 0%
Project Description
Project Manager Sharon Jump/ Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
Mitigating Action
None required
Anticipated Outcome
Project delivered within budget and to the revised programme, following COVID-19.
Renton Campus: The overall construction is programmed to complete by 25 July 2022. (Previously April 2022 but re-programmed due to 13
week COVID-19 site closure).  Phase 1 of the project was handed over on Monday 18 October 2021, with pupils returning to the new school
campus on Wednesday 20 October 2021.  Phase 2 on schedule to be handed over 25th July 2022. There is an acceleration of spend due to
part retention being paid 2022/2023.   St Mary's:  anticipated commencement of MUGA is September 2022 which means new build kitchen
will slip to June 2023.  Pitch onsite September and dining hall will be July 2023 as cannot be onsite at the same time as pitch works.  
Additional ASN Provision: temporary accommodation for Choices will be in place by September and plans for rebuild extension ongoing.
Additional scoping in respect of vacant space at Choices and former Riverside ELC ongoing.  Skills School: scoping ongoing.  Balloch
Campus, Lomond Base, artificial grass installation is complete.
Schools Estate Improvement Plan
Improvement of Schools Estate.
Planned End Forecast End Date
Main Issues / Reason for Variance
Page 116

Page 19

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Project Life Financials 694 472 68% 694 0 0%
Current Year Financials 504 283 56% 504 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
Project Life Financials 5,508 5,508 100% 5,508 (0) 0%
Current Year Financials 3 3 98% 3 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-22 30-Apr-22
Project delivered on time and within budget
Anticipated Outcome
Project delivered within amended timescales.
Schools Estate Refurbishment Plan
Completion of condition surveys has been carried out to identify works
Planned End Forecast End Date
Main Issues / Reason for Variance
Project complete and await final charges.
Mitigating Action
None required.
Anticipated Outcome
None available at this time.
Free School Meals
Provision of Capital Funding from Scottish Government to implement free
Planned End
Date Forecast End Date
Main Issues / Reason for Variance
Project is complete other than snagging works which can only be completed when school is closed however project end date is still on
target. Additional budget required in relation to electrical phasing which was unknown at the time of project inception.
Mitigating Action
Page 117

Page 20

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2023
Budget Details
Project Life Financials
Spend to Date Variance
Project Life Financials 8,748 8,490 97% 8,822 74 1%
Current Year Financials 795 464 58% 795 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
Mitigating Action
None required at this time.
Anticipated Outcome
The project will be completed to deliver the requirements of the Early Years expansion plans.
Early Years Early Learning and Childcare Funding
Early learning and childcare funding awarded to West Dunbartonshire
Planned End Forecast End Date
Main Issues / Reason for Variance
Works progressing and budget spend anticipated in 2022/2023.
Page 118