WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 1,110 232 21% 1,110 (0) 0%
Current Year Financials 441 43 10% 441 0 0%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-29 31-Mar-29
2
Project Life Financials 376 335 89% 376 (0) 0%
Current Year Financials 41 0 0% 41 0 0%
Project Description
Project Manager David Jones/ Julie McGrogan
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
3
Project Life Financials 20,241 15,299 76% 20,241 0 0%
Current Year Financials 1,005 482 48% 1,005 0 0%
Project Description
Project Manager Sharon Jump/ Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Project delivered within budget and to the revised programme, following COVID-19.
31 October 2022
Budget Details
Project Life Financials
Spend to Date Variance
Digital Inclusion
Increase the ratio of chrome book devices for most disadvantaged children and families and support for
families with remote access.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Additional devices have been ordered to increase the ratio of devices to pupils as part of a commitment towards a 1:1 device ratio. The project is
on track to be fully spent in 2022/2023.
Main Issues / Reason for Variance
Although there is re-profiling of budget caused mainly by the academic year starting several months after the financial year the project is still on
track to be completed by the planned end date.
Mitigating Action
None available at this time.
Anticipated Outcome
Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Renton Campus: The overall construction is programmed to complete by 25 July 2022. (Previously April 2022 but re-programmed due to 13
week COVID-19 site closure).  Phase 1 of the project was handed over on Monday 18 October 2021, with pupils returning to the new school
campus on Wednesday 20 October 2021.  Phase 2 on schedule to be handed over 25th July 2022. There is an acceleration of spend due to part
retention being paid 2022/2023.   St Mary's:  anticipated commencement of MUGA is September 2022 which means new build kitchen will slip to
June 2023.  Pitch onsite September and dining hall will be July 2023 as cannot be onsite at the same time as pitch works.   Additional ASN
Provision: temporary accommodation for Choices will be in place by September and plans for rebuild extension ongoing. Additional scoping in
respect of vacant space at Choices and former Riverside ELC ongoing.  Skills School: scoping ongoing.  Balloch Campus, Lomond Base,
artificial grass installation is complete.
Mitigating Action
None required
Mitigating Action
None required at this time.
Anticipated Outcome
Increase the Chromebook ratio for most disadvantaged children.
Schools Estate Improvement Plan
Improvement of Schools Estate.
AV Equipment - Education
Purchase of AV Equipment for Education.
Planned End Date
Purchase of AV Equipment for Education.

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 October 2022
Budget Details
Project Life Financials
Spend to Date Variance
4
Project Life Financials 694 251 36% 694 0 0%
Current Year Financials 504 62 12% 504 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-24 31-Mar-24
5
Project Life Financials 750 638 85% 750 0 0%
Current Year Financials 113 1 1% 113 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
6
Project Life Financials 5,508 5,505 100% 5,508 (0) 0%
Current Year Financials 3 0 0% 3 0 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-22 30-Apr-22
Main Issues / Reason for Variance
Project complete and await final charges.
Mitigating Action
None required.
Anticipated Outcome
Project delivered on time and within budget
Anticipated Outcome
Project delivered on budget.
Schools Estate Refurbishment Plan
Completion of condition surveys has been carried out to identify works required to bring various schools from
Condition C to Condition B.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
A new contractor has been appointed and looking at the programme of works.
Mitigating Action
None available at this time.
Mitigating Action
None available at this time.
Anticipated Outcome
Project delivered within amended timescales.
Choices Programme - to assist young people who require additional support
Provision of Capital Funding from Scottish Government to implement free school meal initiative.
Planned End Date Forecast End Date
Main Issues / Reason for Variance Project is complete other than snagging works which can only be completed when school is closed however project end date is still on target.
Additional budget required in relation to electrical phasing which was unknown at the time of project inception. Additional funding granted for Free
School Meals Expansion.
Bringing together Central Support Services which will include relocation of Choices Programme.
Free School Meals

Page 3

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF PROJECTS AT GREEN ALERT STATUS
PERIOD END DATE
PERIOD 7
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 October 2022
Budget Details
Project Life Financials
Spend to Date Variance
7
Project Life Financials 8,748 7,990 91% 8,748 (0) 0%
Current Year Financials 795 37 5% 795 (0) 0%
Project Description
Project Manager Michelle Lynn/ Craig Jardine
Chief Officer Laura Mason
Project Lifecycle 31-Mar-23 31-Mar-23
The project will be completed to deliver the requirements of the Early Years expansion plans.
Mitigating Action
None required at this time.
Anticipated Outcome
Early Years Early Learning and Childcare Funding
Early learning and childcare funding awarded to West Dunbartonshire Council to facilitate the expansion in
entitlement to funded ELCC to 1140 hours from August 2020.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Works progressing and budget spend anticipated in 2022/2023.