West Dunbartonshire Council - Education Appendix 2
General Services Capital 2026/27
Projects that are Off Track at Period 3
Service Project
Approved Project Life
Cost
Revised Project
Life Cost
Project Life
Variance
Initial Completion
Date
Revised
Completion Date
£000 £000 £000
Education EDUC 5 - Free School Meals Expansion                                  1,265                      1,265                  -   31/03/2027 31/03/2028
Project Name: Free School Meals Expansion Project Manager: Michelle Lynn
Initial Completion End Date: 31/03/2027 Revised End Date: 31/03/2028
How was this project initially funded: Please Detail any additional funding:
Prudential Borrowing
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
There is no requirement to take any action
What are the implications on the actions proposed?
Revenue Implications:-
Virement Implications:- no implications
This budget is proposed to be rephased to 2027/28. Planning permission has been secured and the project is progressing through detailed design, building warrant approvals and site investigations. Due to the
complexity of delivering works within an operational school environment, including the need to minimise disruption to pupils and staff, the construction programme and associated expenditure are now expected to fall
predominantly within 2027/28. The rephasing aligns the budget with the revised delivery programme and anticipated expenditure profile.
Source of Funding:
no implications