WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Educational Services Committee 16 September 2026
___________________________________________________________________ 
Subject:      Educational Services Capital Budgetary Control Report 2026/27 to
30 June 2026 (Period 3) 
1. Purpose 
1.1 This report provides an update on the Educational Services capital
programme to 30 June 2026 (period 3). 
2. Recommendations 
2.1 Committee is asked to: 
i) Note the current position of the 2026/27 Educational Services capital
budget. 
ii) Note the revised completion date in respect of one project detailed in
appendix 2. 
3. Background 
3.1 On 4 March 2026 the Council approved the updated General Services Capital
Plan for 2025/26 to 2034/35. The three years from 2026/27 to 2028/29 were
approved in detail with the remaining years being indicative. The budget
agreed for Educational Services was £4.847m for 2026/27 and £67.905m for
the project life budget 
3.2 Since then budget adjustments have taken place which result in a revised
Education capital budget as set out in Exhibit 1. 
Exhibit 1: Revised Capital Budget as at 30 June 2026   
2025/26
(£m)
Project
Life (£m)
Capital Budget Agreed 4 March 2026 4.847 67.905
Changes to capital budget reported on P12
Capital BCR to council on 17 June 2026 
0.267 
Adjustment to project life - Remove Faifley
costs and matching income (see 3.3 below) 
(7.362)
Revised Approved Budget Period 3 (subject
to Council approval August 2026)
5.114 60.543 
ITEM 15

Page 2

3.3      There is an adjustment to the project life income and expenditure for Faifley
Campus of £7.362m as the income and associated expenditure is being
accounted for on a revenue basis as per the funding agreement from Scottish
Government. 
4. Main Issues 
4.1 Progress against the 2026/27 capital plan is detailed in: 
Appendix 1 – Project Life Summary by Chief Officer 
Appendix 2 – Off Track Projects 
Appendix 3 – Changes to Capital Plan 
Appendix 4 – All Approved Projects 
4.2  Appendix 4 shows all projects with approval in year and project life budgets as
well as anticipated expenditure. It highlights that the 2026/27 budget is
£5.114m with current forecast spend of £4.114m. The spend as at period 3 is
£0.392m (9.5%) of the current forecast spend of £4.114m. 
5. Option Appraisal 
5.1 No option appraisal was required for this report. 
6. People Implications 
6.1 There are no people implications. 
7. Financial and Procurement Implications 
7.1 The report notes the projected in-year financial position for capital budgets. 
8. Risk Analysis 
8.1 The main risks are as follows: 
(a) The reported variances should be viewed in the knowledge that there
are a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets. 
(b) As a consequence of current market conditions, inflation is high and
interest rates continue to be volatile. To forecast for the full year costs
budget assumptions have been required. These assumptions continue to
change regularly and therefore it is likely the projected year end
budgetary position will change from that reported. 
9. Equalities Impact Assessment (EIA) 
9.1 No equalities impact assessment was required in relation to this report. 
10. Environmental Sustainability

Page 3

10.1 No assessment of environmental sustainability was required in relation to this
report. 
11. Consultation 
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report. 
12. Strategic Assessment 
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council. 
________________
Laurence Slavin
Chief Officer – Resources
Date:  20 July 2026 
Person to Contact: Joe Reilly/Jackie Nicol-Thomson 
Council Offices, Church Street, Dumbarton  
E-mail: joe.reilly@west-dunbarton.gov.uk                                                  
jackie.nicolthomson@west-dunbarton.gov.uk 
Appendices: Appendix 1 : Project Life Summary 
Appendix 2 : Off Track Projects 
Appendix 3 : Reprofiling and Acceleration of Projects 
Appendix 4 : Details of all Projects. 
Background Papers:  General Services Capital Plan Update - Council 4 March 
2026.       
Wards Affected :          All Wards