Item 16 - Educational Services Capital Budgetary Control Report 2025-26 to 31 January 2026 (Period 10)

West Dunbartonshire Council · 18 March 2026
Back to Educational Services Committee — 18 March 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Some pages contain no extractable text. They may be blank, graphics or scanned pages. OCR has not been applied.

Page 1

WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Educational Services Committee 18 March 2026
___________________________________________________________________
Subject: Educational Services Capital Budgetary Control Report 2025/26 to
31 January 2026 (Period 10)
1. Purpose
1.1 This report provides an update on the Educational Services capital
programme to 31 January 2026 (period 10).
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2025/26 Educational Services capital
budget.
ii) Note the revised completion date in respect of one project detailed in
appendix 2.
3. Background
3.1 On 5 March 2025 the Council approved the updated General Services Capital
Plan for 2025/26 to 2033/34. The three years from 2025/26 to 2027/28 were
approved in detail with the remaining years being indicative. The budget
agreed for Educational Services was £11.664m for 2025/26 and £60.220m for
the project life budget
3.2 Since then budget adjustments have taken place which result in a revised
Education capital budget as set out in Exhibit 1.
Exhibit 1: Revised Capital Budget as at 31 January 2026
2025/26
(£m)
Project
Life (£m)
Capital Budget Agreed 5 March 2025 11.664 60.220
Reprofiling Reported from 2024/25 0.679 0.679
Removal of completed project (Education 2
Digital Inclusion)
(0.028) (0.356)
Reprofiling Education 5 Free School Meals (1.239)
Revised Approved Budget Period 10 11.076 60.543
4. Main Issues
4.1 Progress against the 2025/26 capital plan is detailed in:
ITEM 16

Page 2

Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan
Appendix 4 – All Approved Projects
4.2 Appendix 4 shows all projects with approval in year and project life budgets as
well as anticipated expenditure. It highlights that the 2025/26 budget is
£11.076m with current forecast spend of £10.332m. The spend as at period
10 is £7.653m (74%) of the current forecast spend of £10.332m.
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications
7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there are
a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.
(b) As a consequence of current market conditions, inflation is high and
interest rates continue to be volatile. To forecast for the full year costs
budget assumptions have been required. These assumptions continue to
change regularly and therefore it is likely the projected year end
budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.

Page 3

12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
________________
Laurence Slavin
Chief Officer – Resources
Date:  26 February 2026
Person to Contact: Joe Reilly
Council Offices, Church Street, Dumbarton
E-mail: joe.reilly@west-dunbarton.gov.uk
Appendices: Appendix 1 : Project Life Summary
Appendix 2 : Off Track Projects
Appendix 3 : Reprofiling and Acceleration of Projects
Appendix 4 : Details of all Projects.
Background Papers:  General Services Capital Plan Update - Council 5 March     
2025.