Page 1

Projects that are Off Track as at Period 5 - 31 August 2024 Appendix 2
Service Project
Approved
Project Life
Cost
Revised
Project Life
Cost
Project Life
Variance
Initial
Completion Date
Revised
Completion
Date
£'000 £'000 £'000
EDUC 3 Schools Estate Improvement Plan - next Phase - Faifley Campus            35,620              36,515 (895) 31/03/2027 31/03/2027
Project Name: Schools Estate Improvement Plan - next Phase - Faifley Campus EDUC 3 Project Manager: Michelle Lynn
Initial Completion End Date: 31/03/2027 Revised End Date: 31/03/2027
How was this project initially funded: Please Detail any additional funding
Council Capital Funding/ Prudential Borrowing n/a
Why is the project classified as off track and what has caused the issues identified?
What action will be taken to rectify the position?
New Completion Date: 31/03/2027
What are the implications on the actions proposed?
Revenue Implications n/a
Virement Implications n/a
Given ongoing volatile market conditions there is an increase in the expected labour and materials  costs.  It is anticipated that the increase can be accommodates within the overall school
improvement capital budget which is currently unallocated. 
Source of Funding
Schools Estate Improvement Plan
Project EDUC 4
Virement from Schools Estate Improvement Plan Project EDUC 4