All Approved Projects at Period 5 - 31 August 2024 Appendix 4
Service Project
Initial End
Date
Revised End
Date
Project Life
Budget
Spend to
31 /3/24 Spend to
Date
Projected
Future
Spend
Total
Projected
Spend
Project
Variance
Approved
Budget
2024/25 
Actual to
date
2024/25 
Revised
Forecast
2024/25 
In Year
Variance 
£'000 £'000 £'000 £'000 £'000 £'000 £'000  £'000  £'000  £'000
RES 1 Valuation Joint Board - Requisition of ICT Equipment 31/03/2025 31/03/2025 25                6                              12 13                                 25                -   11              6               11              -           
RES 2 Cash Receipting system enhancements 30/09/2023 31/03/2025 30                5                                5 25                                 30                -   25              -            25              -           
RES 4 Agresso Development 30/04/2024 30/09/2024 102              62                            82 20                               102                -   40              20             40              -           
RES 5 Cost of Living 31/03/2026 31/03/2026 1,002           502                        583 419                          1,002                -   250            81             250            -           
RES 6 IFRS 16 Database 31/03/2023 31/03/2025 5                  -                          -   5                                     5                -   5                -            5                -           
RES 7 Community Success Capital Fund 31/03/2025 150              -                          -   150                             150                -   150            -            150            -           
RES 8 Community Sports Success 31/03/2025 250              -                          10 240                             250                -   250            10             250            -           
RES 12 Direct Project Support 31/03/2025 31/03/2025         14,274               -                  52 14,222                   14,274                -   1,586                       52 1,586         -           
Total Resources 15,838         575           744            15,094       15,838           -             2,317         169           2,317         -           
CCF 1 Heritage Capital Fund 31/03/2024 31/03/2026 2,491           2,234                  2,288 203                          2,491                -   257            54             257            -           
CCF 2 Transformation of Infrastructure Libraries and Museums 31/03/2024 31/03/2025 421              326                        366 55                               421                -   95              40             95              -           
Total CCCF 2,912           2,560        2,654         259            2,912             -             353            94             353            -           
-                
RR 1 Legal Case Management System 31/03/2024 31/03/2026 33                -                          -   33                                 33                -   -             -            -             -           
RR 2 Re -imagine Antonine Wall   31/03/2024 31/03/2025 25                15                            15 10                                 25                -   15              -            15              -           
Total Regulatory and Regeneration 58                15             15              43              58                  -             15              -            15              -           
P&T 1 ICT Modernisation 31/03/2025 31/03/2025 4,718           -                        125 4,593                       4,718                -   482            125           482            -           
P&T 2 ICT Security & DR 31/03/2025 31/03/2025 4,143           -                        104 4,039                       4,143                -   642            104           642            -           
P&T 3 365 Implementation 30/09/2023 31/03/2026 983              418                        466 517                             983                -   325            48             325            -           
P&T 4 Development of Workforce Management System 31/03/2030 31/03/2030 298              -                          -   298                             298                -   46              -            46              -           
Total P&T 10,142         418           695            9,447         10,142           -             1,495         277           1,495         -           
Overall Total 28,950         3,568        4,108         24,842       28,950           -             4,180         540           4,180         -           
Full Project Life In Year