Item 09 Appendix 1

West Dunbartonshire Council · 6 November 2024
Back to Corporate Services Committee — 6 November 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

1
Appendix 1: People and Technology Delivery Plan 2024/25 - Mid Year Progress
4. Our Council
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Q1 2024/25 Q2 2024/25
Performance Indicator
Status Value Target Short
Trend
Long
Trend Status Value Target Short
Trend
Long
Trend
Notes Owner
Percentage of ICT helpdesk
incidents fixed with half day
of being logged.
75% 65% 77.9% 65%
Performance exceeded target.
Total Number of Incidents:
Opened 3918. This is a decrease
of 990 Incidents from Q1, due to
implementation of new
technologies and removal of
Citrix. Incidents closed and
resolved in under 3 hrs 35 mins
was 3683.
James
Gallacher
% employee attendance
improvement rate (teachers
& local govt.)
-15% 1% 10.6% 1%
Whilst Q1 missed target, Q2
exceeded target. Across the
Council workforce attendance
has improved by 10.6% when
compared to Q1.  Whilst this can
partly be attributed to lower
levels of absence during the
summer months when
employees are typically on leave,
it is encouraging and will
continue to be closely monitored
into Q3.
Alison
McBride

Page 2

2
Action Status Progress Due Date Note Owner
Progress assurance and test plan for Service Plans 31-Mar-2025
Action progressing as planned with Emergency Plans having been
reviewed, issued for consultation, updated and now live. 4 plans
remain outstanding.
Civil contingencies facilitated training for both Council and HSCP
Council Incident Officers (CIOs) and Support Centre Managers
(CSMs).
Scott
McFarlane
Progress and manage the Council`s & HSCPs Business
Continuity Process 31-Mar-2025
Action progressing as planned. Business Continuity Plans (BCPs)
being updated from 2023, and will require an annual review
(rolling programme).
Scott
McFarlane
Develop a framework for the Council’s Power Resilience
arrangements 31-Mar-2025
Action progressing as planned. The Essential Services Power
Resilience document and Assurance Checklists were updated by
the Strategic Resilience Group (SRG) this includes Council and
HSCP Strategic Leads.
A Power Resilience Workshop was facilitated by Civil Contingency
Officer (CCO) and Chief Officer, People & Technology in April. An
Action list will support work towards reducing the impact of a
National Power Outage or a Significant Cyber Attack. Once all
actions are completed, a “real time” exercise will be arranged.
Scott
McFarlane
Further secure the Council’s Technology Infrastructure 31-Mar-2025 Action progressing as planned, ongoing review, investigation and
testing to inform enhanced security and protection.
James
Gallacher
Deliver fit for purpose Bandwidth capacity to all Council
locations 31-Mar-2025
Action progressing as planned. 5 sites have now migrated to the
new SWAN2 network with schools reporting immediate
improvements. 28 sites will be completed by Dec 24 and 82 in
total by summer of 2025.
James
Gallacher
Enable an improved digital workplace experience for
council employees 31-Mar-2025
Action progressing as planned. Technology improvements
continue to progress well and are enhancing the digital workplace
experience for employees. This is due to improvements such as a
new remote access solution and decommission of legacy
technology resulting in 900 fewer ICT incidents being reported in
Q2.
James
Gallacher
Review and implement MS SharePoint and One Drive 31-Mar-2025 Action progressing as planned. SharePoint and One Drive is now
live for Health & Safety with ICT to migrate during October 24.
James
Gallacher
Coordinate ICT device replacement programme. 31-Mar-2025
Action progressing as planned. Device replacements are
progressing well across corporate and education estate with a low
volume of devices remaining to be replaced from 24/25 budget.
James
Gallacher
Enhance/ expand digital skills champion roles 31-Mar-2025
Action progressing as planned. Digital Champions (DigiChamps)
receive periodic newsletters to share with their services, and
advance notification of all the Digital Themes activities. DigiChamp
Alison McBride

Page 3

3
Action Status Progress Due Date Note Owner
role in supporting rollout of Microsoft 365 will continue to be
developed as pilot evolves.
Develop a plan to further mainstream digital
transformation across the Council 31-Mar-2025
Action progressing as planned. Digital themes have been designed
and introduced focussing on Putting People First using Intranet
based trickle learning tools for all staff.  The third theme -
Maximising Technology is being delivered and will complete before
the end of November.
Support for pilot project for roll-out of Microsoft 365 collaboration
tools (MS Teams, SharePoint, OneDrive) is underway and will be
completed before end of 2024.
Alison McBride
Workforce Planning: Develop and implement wellbeing,
employee engagement, equality and learning and
development plans to enable capabilities, improve
resilience and promotion of a diverse workforce
31-Mar-2025
Action progressing as planned. Of the workforce planning sub
actions agreed within each service area progress includes;
Knowledge sharing and development is taking place across the
service. Focused resource on Voluntary Severance/ Voluntary
Early Retirement (VS/VER) and savings exercise, Staff Working in
Transition and Change (SWITCH) and equalities.
A number of employee benefit initiatives have been launched
including a new Cycle to Work scheme, counselling and My Money
Matters financial advice.  Further developments in the workforce
planning console to support the management of intermittent
absence and stress risk assessment process.
Trickle use continues to be promoted for engagement and there
has been a realignment of the employee recognition awards with
the Council’s ACHIEVE values and this will launch in November
2024.
The ICT customer satisfaction survey was issued in early October
24 and will aid improvements.
Victoria Rogers
Workforce Planning: Develop and implement employee
life cycle plans in line with the People First Strategy to
attract and retain the workforce.
31-Mar-2025
Action progressing as planned. Of the workforce planning sub
actions agreed within each service area, progress includes;
A review of the succession planning guidance is underway and is
expected to be rolled out in phases with Phase 1 concentrating on
Chief Office and senior management levels by the end of this year.
Development of career pathway roles and talent pools and
considering different Social Media platforms to reach a wider
audience and diversify the workforce.
Victoria Rogers

Page 4

4
Action Status Progress Due Date Note Owner
The HR Graduate post development into a temp HR Adviser post
with buddying and mentoring taking place across the teams to
ensure resilience.
Year 2 of the recruitment work plan (onboarding) has commenced
with user research for new employees and recruiting managers.
Workforce Planning: Implement service review process
including role design, use of new technology and new
ways of working to add resilience, address gaps, and
establish opportunities for efficiencies
31-Mar-2025
Action progressing as planned. Of the workforce planning sub
actions agreed within each service area, progress includes;
Review of structures, roles and requirements in line with SOM
compliance and phases. 
Job evaluation revised policy and processes now embedding,
strengthening the Council’s position on equal pay and
considerations around role design.
Development of the workforce planning console in terms of trends
and red flags around employee data. Management information
sessions on use of the console by Strategic HR has led to around a
250% increase on average console use.
Review of Data Management provision during Sharepoint
implementation.
Victoria Rogers
Workforce Planning: Develop and implement learning
and development opportunities to improve capabilities
and resilience within the workforce.
31-Mar-2025
Action progressing as planned. Of the workforce planning sub
actions agreed within each service area, progress includes;
Digital themes to support pilot project roll-out of M365
collaboration tools (MS Teams, SharePoint, OneDrive) are
underway.
Various development initiatives focused on new technologies,
M365 and Remote Access, and Cyber. We continue to progress job
evaluation/analysis, management development and leadership
training.
Victoria Rogers

Page 5

5
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Workforce Management
System not fit for purpose
There is a risk that the WMS system is
not fit-for-purpose thereby requiring
manual workarounds restricting the level
of automation impacting on efficiencies
25-Sep-2024
This risk remains current due to the
manner in which Frontier deploy
improvements and support the system
development in line with operational
requirement. Officers continue to monitor
and manage this risk.
No change to risk matrix
Arun Menon
Challenges in protecting the
Health and Safety of
Employees and Others
Failure to meet the Council’s duty to
protect the health, safety and welfare of
its employees and other people who
might be affected by its business
02-Aug-2024
Corporate H&S are actively reviewing and
optimising key service areas, including
Safety Management Standards and
training. Changes are underway to the
H&S / Insurance management system to
improve efficiency and reduce turnaround
times for enhancements to the system.
Work is also being carried out to refine
and simplify the health surveillance
process in collaboration with OH and line
managers.
Recent activities include management
workplace inspections, noise monitoring,
H&S auditing, a review of the Corporate
Warning Marker System and significant
work on the management of Hand Arm
Vibration Syndrome (HAVS).
Fire safety management includes, the fire
risk assessment programme, fire safety
training and support to services to ensure
compliance with regulatory requirements.
No change to risk matrix
Alison McBride
Complexities in ensuring an
appropriately resourced and
resilient workforce
Failure to ensure that there is an
appropriately resourced and resilient
workforce in place to meet future
organisational needs, in effectively
executing the Council’s 2022-27
Strategic Plan.
02-Aug-2024
Workforce Planning Strategy in place for
2022-2027. People First Strategy is in
place covering 2022-2027 and this is a
consolidation of a number of areas: well-
being, employee engagement, workforce
planning, learning and development and
digital.
A robust package of wellbeing resources
continue to be available, absence levels
are closely monitored, with personal
stress and minor ailments absences
prevalent.
Alison McBride

Page 6

6
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Trickle relaunch is ongoing across the
whole of the organisation to ensure this
tool is better used for employee feedback
and engagement with the recent issue of a
Chief Officers pack.
Digital Skills approach has been refreshed
with a matrix cascade planned across the
organisation to support 365 Share point
rollout utilising digital leads and
champions. To further support this the
digital transformation board has been
restructured to focus more on innovation
and with a view to achieving more
pragmatic outcomes such as
understanding service skills gaps, better
use of data and dashboards and more use
of digital tools to improve processes.
Services are currently working on
structures and service delivery whilst
considering the difficult financial funding
position and the impact of this will be
closely supported and monitored.
No change to risk matrix
Threat of Cyber-attack
Data, systems and/or infrastructure are
impacted as result of security attacks
which are increasing in number at a time
when this threat is already placing
demands on resources to deliver
increased levels of security controls.
02-Aug-2024
Cyber strategy, policies and technologies
are continually being improved, reviewed
and monitored; ICT continues to follow
NCSC guidance where applicable.
A new Cyber Security team and lead is
now in place with the focus on promoting
employee awareness to cyber risk from
both a professional and personal
perspective. This is including development
of a dedicated security intranet page to
provide guidance and advice to
employees.
Recent focus has strengthened email mail
security with posture scoring
improvements.
Progress continues to further improve our
M365 security posture in addition to a
review of our disaster recovery planning
and incident management procedures.
James
Gallacher

Page 7

7
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Incident response readiness, security gap
analysis and M365 security review has
been completed by our 3rd party security
partner. Results are currently being
reviewed with the aim to agree an
improvement action plan. Cyber Incidents
response plans have been updated and
will be completed during October 24. ICT
are also planning to simulate a Cyber-
attack with assistance from Scottish
Government Digital Office.
Enhanced online email security training is
in progress with continuous phishing
campaigns to raise employee awareness.
There is a continual review of the process
to apply security updates, patches, and
software deployments. Recent
improvements and investment have been
implemented to automate the update
processes where possible.
Geo-blocking to GB remains in place and
the geo-political situation continues to be
monitored. We have now implemented
additional 365 security policies to align
with these security restrictions. This will
be further extended to our new remote
access solution.
No change to risk matrix
Objective 11. Our Council is adaptable and focused on delivering best value for our residents
Action Status Progress Due Date Note Owner
Undertake annual Payroll Audit 12-Jan-2025
Action progressing as planned. Audit has been issued to all Chief
Officers and HSCP Heads of Service for completion by 8th
November 2024.
Arun Menon

Page 8

8
Action Status Progress Due Date Note Owner
Implement statutory Payroll changes 31-May-2024 Action complete. All statutory changes such as Tax and NI have
been implemented for 2024/25. Arun Menon
Implement revised team structure and service
provision 30-Sep-2024 Action complete. This was achieved through removal of tasks
which have been actioned and communicated. Arun Menon
Review and update Fit For Future approach 31-Mar-2025
Action complete. Following review, the approach this year will
concentrating on digital champions, skills and improvements
alongside supporting SharePoint rollout which will ensure services
are efficient and that we make the best use of our resources. 
Alison McBride
Continue to embed sound H&S practice 31-Mar-2025 Action progressing as planned. Corporate H&S are continuing to
meet targets set out in the Operational Plan. Alison McBride
Implement improvements in recruitment life cycle
processes 31-Mar-2025
Action progressing. Review of project plan has taken place and
prioritised actions to progress over 2024/25. Progress has been
made in reviewing succession planning guidance for future talent
resources. Progress has been limited due to limited resources and
conflicting priorities.
Alison McBride
Maintain and monitor employee wellbeing, engagement
and workforce planning 31-Mar-2025
Action progressing as planned. Employee awards have now been
refreshed in line with the Achieve values framework and launch is
planned. The first ceremony will take place in May 2025. The
intranet page is currently being updated to prepare for the launch
and Senior Management Network session was held to introduce
the new employee award framework. Further work is required
around the console development and job profiles.
Alison McBride
Review and enhance employee skills and learning
programme 31-Mar-2025
Action progressing as planned. Mandatory training information for
teams has now been made available to Managers on the console.
Access to the national M365 skills hub has been granted and
joining instructions are being developed. The Pilot M365 is
underway and additional training resources and opportunities will
be available to employees as M365 is rolled out.
Alison McBride
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Keeping abreast of
developments in the
innovative use of
Information Technologies
Failure to keep pace with changing
technology environment 02-Aug-2024
WDC is continuing to implement several
technology transformation projects with a
focus on delivering an improved and
secure digital workplace experience for
council employees. Delivery of a new
secure remote access solution is now
complete for employees and additional
James
Gallacher

Page 9

9
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
tasks are ongoing to provide separate
access for suppliers and 3rd party users
such as NHS employees.
Modern Desktop projects are progressing
well with end-of-life storefront technology
being replaced with improved and
consistent local access to the latest
desktop applications for users. Laptop
devices are now secured and controlled
via the Microsoft cloud and are also
imaged offsite by our supplier. A project
to redesign the process to updates devices
with windows updates and security
patching is ongoing with the aim to reduce
disruption to employees.
ICT continue to embrace and research
new technologies and maximise our
existing investments. MS SharePoint is
now live for H&S team with ICT to migrate
during October 24. Phase 2 of the project
will deploy SharePoint to remaining
council services from January 25 onwards.
All corporate email mailboxes have now
migrated to the cloud with Education
being scheduled for completion during
October 24.
ICT in conjunction with NHS are
progressing cross organisation projects
with access to WDC Wi-Fi now available in
3 NHS buildings. NHS employees are now
accessing NHS Wi-Fi in Church Street with
additional file access to follow.
New firewall technology has been ordered
and installation being planned, this project
will increase data capacity throughput at
our data centre and provide enhanced
security. This new technology will ensure
we are secure and allow increased
bandwidth speeds to be delivered as part

Page 10

10
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
of our Scottish Wide Area Network project
to improve bandwidth at all council sites.
No change to Risk matrix.
Action Status
Overdue
Not on track
In Progress and on track
Completed
PI Status
Target significantly missed
Target narrowly missed
Target met or exceeded
Risk Status
Alert
High risk
Warning
OK
Long Term Trends
Improving
No change
Declining
Short Term Trends
Improving
No change
Declining