Item 7 Appendix 3 - Budgetary Control Report Capital Period 3 2024-25

West Dunbartonshire Council · 14 August 2024
Back to Corporate Services Committee — 14 August 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Changes to Capital Plan and Implications Appendix 3
CITIZENS CULTURE AND FACILITIES
CCF 1
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28
Future
Years  Total Capital Plan
£'000 £'000 £'000 £'000 £'000 £'000 £'000
Heritage Capital Fund (132) 389               -        -        -        -                                       257
Heritage Capital Fund 257               -        -        -        -                                       257
Explanation
Acceleration of works
CCF 2
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28
Future
Years  Total Capital Plan
£'000 £'000 £'000 £'000 £'000 £'000 £'000
Transformation of Infrastructure Libraries and Museums - Original 95              -                -        -        -        -                                         95
Transformation of Infrastructure Libraries and Museums - Revised 95                 -        -        -        -             95                          
Explanation
Earmarked for future works within retained libraries
RR1
Legal Case Management System - original 33 0 0 0 0 0 33
Legal Case Management System - Revised 33 33
Explanation
Waiting to explore the functionality of Sharepoint to see if a new standalone system is required for this.
RR2
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28
Future
Years  Total Capital Plan 
£'000  £'000  £'000  £'000  £'000  £'000  £'000
Re -imagine Antonine Wall - Original 5                10                 -        -        0 -                                         15
Re -imagine Antonine Wall - Revised 15                 -        -        -        -                                         15
Explanation
Multi year project
PEOPLE & TECHNOLOGY
Project P&T 1
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28
Future
Years  Total Capital Plan
£'000 £'000 £'000 £'000 £'000 £'000 £'000
ICT Modernisation - Original (69) 551               696       554       806       2,180                                4,718
ICT Modernisation - Revised 482               696       554       806       2,180                                4,718
Explanation
Acceleration of projects
Project P&T 2
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28
Future
Years  Total Capital Plan
£'000 £'000 £'000 £'000 £'000 £'000 £'000
ICT Security & DR - Original 138            504               792       387       387       1,935                                4,143
ICT Security & DR - Revised 642               792       387       387       1,935                                4,143
Explanation
We were still researching suitable infrastructure upgrade options for end of life equipment, this has now been complete and will be spent this year.
Project P&T 3
2023/24
Reprofiling
Current Year
2024/25 2025/26 2026/27 2027/28
Future
Years  Total Capital Plan
£'000 £'000 £'000 £'000 £'000 £'000
365 Implementation - Original 85              240 240 0 -                                       565
365 Implementation - Revised 325 240 0                          565
Explanation
Reprofiled to ensure that we continue the deployment of sharepoint and one drive through 2025/26.