Projects that are Off Track as at Period 3 - 30 June 2024 Appendix 2
Service Project
Approved
Project Life Cost
Revised
Project Life
Cost Project Life Variance
Initial
Completion
Date
Revised
Completion
Date
£'000 £'000 £'000
1 Resources Agresso Development (Res4)                        62 102 40 30/04/2024 30/09/2024
1 Citizen, Cultural and Facilities Transformation of Infrastructure Libraries and Museums (CCF2) 421 421 0 31/03/2024 31/03/2025
1 Regulatory and Regeneration Legal Case Management System (RR1) 33 33 0 31/03/2024 31/03/2026
Project Name: Agresso Development - Res 4
Initial End Date: 30/04/2024 Revised End Date: 30/9/24
How was this project initially funded: Please Detail any additional funding
Prudential Borrowing £40k
Why is the project classified as off track and what has caused the issues identified?
Notification from the supplier of a policy change towards supporting only cloud based installations necessitated further expenditure to ready the system for cloud migration.
What action will be taken to rectify the position?
Additional Funding Requested:  £40k
New Completion Date: 30/9/24
What are the implications on the actions proposed?
Revenue Implications £6k over 5 years.
Virement Implications
Project Name: Transformation of Infrastructure Libraries and Museums - CCF2
Initial End Date: 31/3/24 Revised End Date: 31/3/25
How was this project initially funded: Please Detail any additional funding
Prudential Borrowing N/A
Why is the project classified as off track and what has caused the issues identified?
to accommodate the new decisions for colocations.
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date: 31/3/25
What are the implications on the actions proposed?
Revenue Implications N/A
Virement Implications N/A
Chief Officer Resources
Source of Funding
Prudential Borrowing
Chief Officer CCF
Project delayed due to savings options taken at Council which had an impact on sites and previous spend profile was then refocused
Source of Funding

Page 2

Project Name: Legal Case Management System (RR1)
Initial End Date: 31/3/24 Revised End Date: 31/3/26
How was this project initially funded: Prudential Borrowing Please Detail any additional funding
Why is the project classified as off track and what has caused the issues identified?
This project is delayed as waiting to explore the functionality of Sharepoint to see if a new standalone system is required for this.
What action will be taken to rectify the position?
Additional Funding Requested:  £0
New Completion Date:31/3/26
What are the implications on the actions proposed?
Revenue Implications
Virement Implications
Chief Officer Regulatory and Regeneration
Source of Funding