WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer – Resources
Corporate Services Committee – 14 August 2024
___________________________________________________________________
Subject: Corporate Services Capital Budgetary Control Report to 30 June 2024
(Period 3)
1. Purpose
1.1 This report provides an update on the Corporate Services capital programme
to 30 June 2024.
2. Recommendations
2.1 Committee is asked to:
i) Note the current position of the 2024/25 capital budget for Corporate
Services
ii) Note a projected adverse project life variance of £0.040m (0.14% of the
overall revised budget)
iii) Note an in-year variance of £0.162m due to reprofiling of projects.
iv) Approve additional prudential borrowing of £0.040m to fund the
adverse variance noted in 2.1 ii) above for the Agresso Development
Project.
3. Background
3.1 On 6 March 2024 the Council approved the updated General Services Capital
Plan for 2024/2025 to 2032/33.  The three years from 2024/25 to 2026/27
were approved in detail with the remaining years being indicative.
3.2 Since then budget adjustments have taken place which result in a revised
Corporate Services capital budget as set out in Exhibit 1.
Exhibit 1: Revised Corporate Services Capital Budget
2024/25
(£m)
Project Life
(£m)
Corporate Services Capital Budget Agreed 6 March 2024 3.624 28.560
Remove Electronic Insurance System, Project ended. (0.007) (0.050)
RES 7 Community Success Capital Fund 0.150 0.150
RES 8 Community Sports Success Capital Fund 0.250 0.250
Revised Capital Budget as at Period 3 4.017 28.910

Page 2

4. Main Issues
4.1 Progress against the 2024/25 capital plan is detailed in:
Appendix 1 – Project Life Summary by Chief Officer
Appendix 2 – Off Track Projects
Appendix 3 – Changes to Capital Plan for Noting
Appendix 4 – All Approved Projects
4.2 The overall programme summary report at Appendix 1 shows that planned
expenditure is higher than the budget agreed 6 March 2024 by £0.040m
(0.14% of budget) due to an anticipated overspend on the Agresso
Development Plan.
4.3 Appendix 2 highlights three projects currently showing as off-track.
• Agresso Development due to necessary £0.04m further expenditure to
ready the system for cloud migration.
• Transformation of Infrastructure Libraries and Museums - CCF2 due to
savings options taken at Council which had an impact on sites and
previous spend profile was then refocused to accommodate the new
decisions for colocations.
• Legal Case Management System (RR1) - waiting to explore the
functionality of Sharepoint to see if a new standalone system is
required for this.
4.4 Appendix 3 highlights seven projects where the project expenditure requires
to be reprofiled but there is no need for additional budget.
4.5 Appendix 4 shows all projects with approved in year and project life budgets
as well as anticipated expenditure. It highlights that the 2024/25 budget is
£4.017m with current forecast spend of £4.179m, a variance of £0.162m,
(4.03%).  The spend as at period 3 is £0.167m (4.0%) of the current forecast
spend of £4.179m.  
4.6 Other minor changes to the capital plan already included in the summarised
plan in appendix 4 are:
• Removal of Electronic Insurance System budget of £0.007m in 2024/25.
This project is now complete.
• Addition of Community Success Fund budget of £0.250m in 2024/25
• Addition of Community Sports Success Fund budget of £0.150m in
2024/25
5. Option Appraisal
5.1 No option appraisal was required for this report.
6. People Implications
6.1 There are no people implications.
7. Financial and Procurement Implications

Page 3

7.1 The report notes the projected in-year financial position for capital budgets.
8. Risk Analysis
8.1 The main risks are as follows:
(a) The reported variances should be viewed in the knowledge that there
are a number of variable factors which could arise between now and 31
March which could affect the year end results for capital budgets.
(b) As a consequence of current market conditions, inflation is at an all-time
high and interest rates continue to be volatile. To forecast for the full
year costs budget assumptions have been required. These assumptions
continue to change regularly and therefore it is likely the projected year
end budgetary position will change from that reported.
9. Equalities Impact Assessment (EIA)
9.1 No equalities impact assessment was required in relation to this report.
10. Environmental Sustainability
10.1 No assessment of environmental sustainability was required in relation to this
report.
11. Consultation
11.1 All services involved in delivering the capital budgets have been consulted in
the compilation of this report.
12. Strategic Assessment
12.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the
strategic priorities of the Council’s current Strategic Plan. This report
forms part of the financial governance of the Council.
Laurence Slavin
Chief Officer – Resources
Date: 26 July 2024
________________
Person to Contact: Adrian Gray
Council Offices, Church Street, Dumbarton
E-mail: adrian.gray@west-dunbarton.gov.uk
Appendices: Project Life Summary
Off Track Projects
Reprofiling and Acceleration of Projects
Appendix 1 -
Appendix 2 - 
Appendix 3 -
Appendix 4 -  Details of all Projects.
Background Papers:  General Services Capital Plan Update - Council 6 March 2024.
Wards Affected           All Wards