WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME CSC
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 24 6 23% 24 0 0%
Current Year Financials 2 2 119% 2 0 19%
Project Description
Project Manager Russell Hewton
Chief Officer Russell Hewton
Project Lifecycle 31-Mar-23 31-Mar-24
2
Project Life Financials 20 10 50% 20 0 0%
Current Year Financials 10 0 0% 10 (0) -1%
Project Description
Project Manager Karen Shannon
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-24
3
Project Life Financials 1,000 500 50% 1,000 0 0%
Current Year Financials 250 180 72% 250 0 0%
Project Description
Project Manager Adrian Gray
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-26 31-Mar-26
4
Project Life Financials 53 48 90% 53 0 0%
Current Year Financials 7 0 0% 7 0 0%
Project Description
Project Manager Alan Douglas
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
5
Project Life Financials 30 20 67% 30 0 0%
Current Year Financials 10 1 10% 10 0 0%
Project Description
Project Manager Pamela Clifford
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
Anticipated Outcome
Anticipate full budget spend.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This goes into the overall Antonine Project budget - 5 Councils and Historic Environment Scotland - Expected spent by March 2024
Mitigating Action
No action required
Mitigating Action
None required at this time.
Anticipated Outcome
Solicitor support for Capital Projects, with full budget spend anticipated.
Re -imagine Antonine Wall  
Council's capital contribution towards the multi-partner (five local authorities and Historic Environment Scotland)
Rediscovering the Antonine Wall project which is also funded by the Heritage Lottery Fund.
Solicitor Project Support for Capital Projects
Solicitor costs to directly support capital projects
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Trainee solicitor in place. Budget will be fully spent.
Anticipated Outcome
Project will be delivered on time and on budget
Planned End Date Forecast End Date
Main Issues / Reason for Variance
No variances currently anticipated.
Mitigating Action
None required at this time.
Cost of Living
To support Council and community organisations with capital costs for cost of living initiatives.
Main Issues / Reason for Variance
The module is live
Mitigating Action
None required at this time.
Anticipated Outcome
Upgraded version with PCI compliant telephone payment system.
None available at this time.
Anticipated Outcome
Requisition of ICT Equipment.
Payment Card Industry Data Security Standard (PCIDSS)
Module would ensure that WDC were compliant with the current requirements of PCIDSS for card payments without the need
for numerous costly workarounds
Planned End Date Forecast End Date
Requisition ICT Equipment.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Replacement of laptops, monitors and other ICT equipment. No further spend anticipated.
Mitigating Action
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 7
GENERAL SERVICES CAPITAL PROGRAMME CSC
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 10
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 January 2024
Budget Details
Project Life Financials
Spend to Date Variance
Valuation Joint Board - Requisition of ICT Equipment6
Project Life Financials 421 421 100% 421 0 0%
Current Year Financials 116 0 0% 116 0 0%
Project Description
Project Manager David Main
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-25
7
Project Life Financials 892 290 32% 892 0 0%
Current Year Financials 892 290 32% 892 0 0%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-24 31-Mar-24
8
Project Life Financials 873 296 34% 873 0 0%
Current Year Financials 873 296 34% 873 0 0%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-24 31-Mar-24
9
Project Life Financials 983 503 51% 983 0 0%
Current Year Financials 185 53 29% 185 0 0%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 30-Sep-23 30-Sep-23
10
Project Life Financials 337 88 26% 337 0 0%
Current Year Financials 46 0 0% 46 0 0%
Project Description
Project Manager Arun Menon
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-30 31-Mar-30
Mitigating Action
none required
Anticipated Outcome
Work continues on developments resulting in some spend in the current year.
Development of Workforce Management System
Project to develop the Workforce Management System.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Work continues on developments resulting in some spend in the current year.
Main Issues / Reason for Variance
Delay to Sharepoint implementation project. External resourcing requirements less than expected and small underspend being carried to next year.
Mitigating Action
none required
Anticipated Outcome
projects delivered on time and on budget
Anticipated Outcome
projects delivered on time and on budget
365 Implementation
Project services to delivery Microsoft 365 Implementation including 3rd party supplier, training, technical consultancy etc.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Various projects in progress and orders raised for Cyber Security technology, Citrix replacement devices, SAN storage, server hardware, system security remediation and
upgrades,  Anticipate full budget spend subject to delivery timescales.
Mitigating Action
none required
ICT Security & DR
The project is for the enhancement of security systems, server replacement and the update of corporate applications to
ensure compliance with 15/16 PSN requirements, to enhance the disaster recovery capabilities of WDC.
Main Issues / Reason for Variance
Device replacement project in progress and orders raised totally £480k awaiting delivery.
Mitigating Action
none required
Anticipated Outcome
projects delivered on time and on budget
ICT Modernisation
This budget is to facilitate ICT infrastructure and modernise working practices.
Planned End Date Forecast End Date
Mitigating Action
None required.
Anticipated Outcome
Projects delivered on budget
Transformation of Infrastructure Libraries and Museums
To improve performance and efficiency of Council's Libraries and Cultural Services.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Library colocations of Dalmuir and Balloch being fitted out by Asset Management.  Awaiting outcome for Duntocher and Parkhall libraries.  Remaining Libraries capital to
be spent in 24/25 once colocation plans completed.