WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Annual Spend RAG Status
£000 £000 £000 %
Finance 1,329 1,404 75 6% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Rent Rebates & Allowances (341) (226) 115 -34% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Licensing (143) (220) (77) 54% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Planning 715 231 (484) -68% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Strategic People and Change 2,074 2,041 (33) -2% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
The service provided by this area deals with Accountancy, Capital, Treasury, Reconciliations,
Cash Office and Municipal Bank
Main reason for adverse variance is full turnover savings are not being achieved.
None available at this time.
Adverse variance is anticipated
31 January 2024
Budget Details
Variance Analysis
Variance
Payment of Rent Rebates and other Allowances
Reduction in overpayment (OP) recoveries is due to DWP recovering some HB OP’s against
Universal Credit, subject to the OP reason. Previously the Council would have received 40%
subsidy in OP’s with the ability to recover 100% of the OP, therefore a potential to receive up
to 140% of the OP value.  This change means we receive 100% subsidy of the OP therefore a
reduction from the potential 140% that could have been recovered.
None available at this time.
Adverse variance is anticipated
This service provides all licensing on behalf of the Council
The main reason for the variance is an increase in expected income.
None required
Favourable variance is anticipated
This service area provides strategic and operational HR advice, H&S advice and guidance
There are two main variances, staffing costs are adverse due to additional posts being added
and full turnover savings not being fully met.  This adverse position is being offset by a
favourable variance in income due to recharges being completed for these posts.
None required
Favourable variance overall is anticipated
There are two main favourable variances  income is higher than budgeted. The additional
income predicted is an in-year benefit only as a result of one-off additional fees. Staffing is
favourable due to vacancies
None required
A favourable variance is anticipated.
This Service provides Building & Planning services

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Annual Spend RAG Status
£000 £000 £000 %
31 January 2024
Budget Details
Variance Analysis
Variance
Information Services 4,682 4,452 (230) -5% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Communications & Marketing 267 221 (47) -17% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Clydebank Town Hall 345 284 (61) -18% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Office Accommodation 1,231 1,293 62 5% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Leisure Management 3,701 3,880 180 5% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
This service area provides general ICT support to the Council and also supports
transformational change and modernisation of working practices through technology
There are three main reasons for the favourable variance. Staffing is favourable due to
vacancies. Additional telephone costs are being offset by recharge income to recover these
from other services. In addition centralised printing and leasing costs for copiers are
anticipated to overspend during the year.
None possible at this time.
Favourable variance overall is anticipated
This service provides communication and marketing for the Council.
Employee costs are favourable due to vacancies.
None at the moment.
Favourable variance overall is anticipated.
The service provides civic accommodation and facilities within Clydebank
The main reason for the favourable variance is reduced expenditure on property costs
None necessary.
Favourable variable anticipated.
This service provides the office buildings for the Council.
The overspend is mainly due to higher rates and energy costs than anticipated when the
None available. Officers will continue to monitor and review budgets
Overspend anticipated
Payment to West Dunbartonshire Leisure Trust for leisure services
The management fee to WDLT has been higher because of delays in the reduction in
community facilities provision. In addition budgeted contribution from Education towards
overall management fee overstated.The unachieved saving will be considered for funding
from the smoothing fund for 2023/24
None at the moment.
Adverse variance is anticipated.