West Dunbartonshire Council · 22 May 2024
Back to Corporate Services Committee — 22 May 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

1
2024/25
CITIZEN, CULTURE
AND FACILITIES
Appendix 2

Page 2

2 
Contents 
1. Introduction .................................................................................................................................................................................................... 3
2. Performance Review ...................................................................................................................................................................................... 3
3. Strategic Assessment .................................................................................................................................................................................... 6
4. Resources .................................................................................................................................................................................................... 14
Appendix 1: Action Plan .......................................................................................................................................................................................... 16

Page 3

3 
1. Introduction 
Citizen, Culture and Facilities comprises a wide range of services covering Citizen Services, Communications, Community Empowerment, Youth
Learning, Community Planning, Facilities Management & Town Hall, Libraries and Cultural Services and Performance and Strategy. It is one of
seven strategic areas responsible for delivering the Council’s Strategic Plan. Key actions to help achieve this are set out in this Delivery Plan,
together with actions to address any performance challenges and service priorities identified in the planning process. 
The progress of this Plan will be monitored and managed by the management team and reported to Corporate Services Committee twice yearly,
at mid-year and year-end. 
2. Performance Review 
The CCF management team completed a detailed review of 2023/24 performance, focusing on the following: 
• 2023/24 Delivery Plan year-end progress
• Local Government Benchmarking Framework (LGBF) comparative data
• Citizens’ Panel feedback;
• Telephone Survey feedback;
• Complaints; and 
• Continuous Improvement 
This review highlighted our key achievements and challenges in 2023/24. These are summarised below. 
Key Achievements in 2023/24 
Listed below are some of the major achievements in each service area. All services achieve many other key outcomes for the Council and its
residents throughout the year which are not recorded here but are as important. 
Citizen, Libraries and Digital Services 
• Refresh and relaunch of Customer Service Standards detailing how we will interact and respond to our citizens
• Contact Centre answered over 150,000 calls. This includes enquires across all Council service areas

Page 4

4 
• Launch of online chat bot to enhance response to missed bin collections.
• Shortlisted for a national Project Excellence award for the SLIC funded “New Pathways” project within libraries to encourage disengaged
learners back into education.
• Delivered “Towards a Sustainable Future” project which saw a number of environmentally-responsible initiatives, including the transformation
of Alexandria Library Garden, launch of community eco-groups, and introduction of more sustainable policies and practices. 
Communities Team  
• Concluded a record year for Member of the Scottish Youth Parliament (MSYP) elections with 14 candidates in the programme and 13
standing for election.
• Delivered an extensive programme of awareness raising on Participatory Budgeting across the organisation and Community Planning
Partnership to help embed the process and support delivery towards the Council’s annual target. 
• Supported the establishment of the Scottish Government funded Cash-First Fund. Addressed the wider poverty agenda including the
establishment of the food pantry network.
• Initiated a programme of empowerment surgeries supporting over 50 vulnerable residents in the first 6 months. 
Strategic Communications, Culture & Performance 
• Delivered strategic communications support and advice, providing 24-7 media management to protect the Council’s reputation and continued
to expand the reach of the Council’s social media channels increasing the audience to over 43,000 and growing engagement 
• Provided comprehensive communications support for the budget process and implementation phase of service delivery changes as a result
of savings.
• Established a community gallery in Clydebank Town Hall. 
• Secured ongoing funding from Creative Scotland to support the Visual Artist and Craft Makers Awards in West Dunbartonshire with 10
bursaries awarded in 2023 -24. 
• Generated additional income for the Council through Performance, Strategic Planning and Equalities support to external organisations. 
• Supported a positive Best Value Audit, noting the development of key priorities and performance framework and joined up working for wider
strategic planning.

Page 5

5 
Facilities Management 
• Fully established new management structure and service model. Introduced service improvements including digital processes and new stock
control measures. 
• The service provided approx. 772,908 school meals through 2023/24, and received four positive Health and Nutrition inspections (Clydebank
High School, St Ronans Primary, Knoxland Primary and Linnvale Primary). 
• Our Food & Nutrition Coordinator was recognised as Scottish Chef of the Year at the Scottish School Food Awards 2023.
• Increased income and bookings at Clydebank Town Hall hosting a variety of successful events including civic, awards, dance and theatre
shows and celebrations in particular weddings. 
Key Challenges in 2023/24 
Cross Service
• Resilience / Capacity Challenges. The ongoing rationalisation of resources, development of service efficiencies and savings has resulted in
a range of challenges linked to a continuing and increased reduction to frontline services, both employee reductions and service delivery
rationalisation. This has resulted in a number of initiatives taking longer than anticipated, increased demand on staff, and increased demand
for support from services. This will require strict prioritisation, delivering services in a different way including service delivery redesign where
required.    
• Delays in the capital programme. Increasing market issues has caused delays in carrying out capital works on time and within budget.
Delays in the Library and Culture estate programmes have impacted on our service delivery and service satisfaction. This requires
reprioritisation within the service as the programme timelines are pushed out.   
Citizen, Libraries and Digital Services 
• There is continued increase in demand to the Housing Repairs Contact Centre. 
• Changes to ways of working within services increased the volume of calls to Contact Centre and placed additional demand on the service. 
• Some of the co-location proposals generated unexpected challenges and additional workload 
Facilities Management.
• High levels of sickness continue to have an impact on available resource resulting in reduced workforce numbers and increased demands on
existing teams.
• The turnover coupled with the time taken to replace, recruit and train employees continued to be a challenge.

Page 6

6 
Strategic Communications, Culture & Performance 
• The Communications and Arts & Heritage teams continued to operate without a full complement of staff for most of the year resulting in
increased demand on staff and alternative service models being introduced. 
3. Strategic Assessment 
The CCF management team completed a strategic assessment to determine the major influences on service delivery and priorities in 2024/25.
The key factors are summarised below. 
Key Factors 
Financial Challenges - 
The entire public sector is continuing to face significant financial challenges due to a range of factors including inflationary cost increases, pay
awards not being fully funded by the Scottish Government and insufficient overall funding to support the delivery of front line and back office
services. The Council are currently faced with an estimated cumulative funding gap in 2025/26 of £9.8m rising to £40.4m by 2028/29.  We will
continue to monitor the overall financial position of the Council and updates on estimated future budget gaps will be reported to Elected
Members throughout 2024/25. 
These challenges mean further action is required to balance our budget and protect services for residents. This will mean that within Citizen
Culture and Facilities available funding will be reduced over time and we will need to reconfigure how we work, what we do, where we work, and
potentially reduce the number of people employed. In this context, we will aim to continue to provide a sustainable, quality service to internal
clients and the public. 
Budget Sensitivity Analysis 
In reviewing the service budget projections, consideration has been given to sensitivity of these budgets, in particular for higher risk/ higher value
budgets which may have a significant impact on budgetary control and future budget projections. The analysis has considered sensitivity around
demand, costs and charges, and income levels. 
In CCF income budgets are more susceptible to fluctuations given the uncertainties surrounding demand

Page 7

7 
Citizen, Libraries and Digital Services 
Telephony Enhancements 
The telephony system was upgraded in December 2019 and again throughout 2021/22. ICT are investigating an upgrade to the Corporate
Telephone Network which placed voice project is on hold in 2023/24 as there is a risk technology purchased to record could become surplus to
requirement as ICT replace the voice hardware. Over 2024/25 we will explore further improvements with our ICT colleagues including
enhancements to expand self-serve options. 
Complaints Management Improvements - audit actions 
The coordination of the corporate complaints process requires review ensuring adequate communication channels with responsible managers in
each service. This will further support timely responses and adherence to regulatory timelines. A new complaints management system has been
developed in 2023/24. The testing of the pilot system will be complete in Q1 2024/25. Audit outcomes have been implemented. 
Child Friendly Complaints 
The Scottish Public Sector Ombudsman (SPSO) is launching a new Child Friendly Complaint procedure in 2024. A new procedure will be rolled
out that sets out how to handle and investigate complaints from children, making sure that all complaints are handled in a manner that respects
and promotes children's rights under the United Nations Convention on the Rights of the Child (the UNCRC). This will not be a standalone
procedure it will be an addition to our existing complaints procedure. 
Progress Library co-location proposals
Following the 2023/24 savings options, co-location opportunities were agreed for Balloch, Parkhall, Dalmuir and Duntocher libraries.  Work to
relocate Balloch and Dalmuir libraries now nears completion. In 2024/25 we will complete the co-location of Parkhall and focus on embedding
the new co-located branches as part of our network.   
Develop a Libraries Strategy 
There is a need to create a Libraries Strategy document outlining a renewed vision and future operating model which aligns with local and
national initiatives and ambitions.
.
Undertake a Library Management System Migration

Page 8

8 
Libraries will undertake a significant Library Management System migration project to support service delivery and ensure the most efficient
ways of working. 
Review Library Materials and Staffing
Following the 2024/25 savings options the budget for library materials by will reduce by £50,000 and a review of staffing out with the branch
libraries will be undertaken to consider existing and possible alternatives.   
Upgrade Content Management System 
The version of the Content Management System (CMS) used for the Website and Intranet is coming to end of life in February 2025 .Over
2024/25 We will work with our external developers to upgrade to a later version of the CMS, this will also require development work as the code
it is written on has also been upgraded by Microsoft. 
Security reviews of the external and internal website (cloud based)
Content Security Policies (CSPs) which details the rules, expectations, and overall approach that an organization uses to maintain the
confidentiality, integrity, and availability of its data are crucial for strengthening security. CSP’s help to detect and mitigate certain types of
attacks by essentially creating a whitelist of permitted content. Over 2024/25 we will progress security reviews of the websites. 
Accessibility
The most recent Web Content Accessibility Guidelines (WCAG 2.2 standard) was published on the 5th of October 2023, as an extension to
WCAG 2.1. We have had the external site audited by the Cabinet Office in Aug 21 and achieved a pass rate. Over 2024/25 we will put actions in
place to make sure the website are still complaint with the new standards and build a plan to address issues with the intranet that is not
accessible.   
Community Facilities
The savings options agreed to deliver the 2023/24 budget resulted in a review of community facility provision across West Dunbartonshire.  Up
to seven community facilities were to be transferred to community ownership, lease or where no alternative exists, closed and five completed
during 23/24. Finalisation of arrangements for the final two centres will be progressed in 2024/25. 
Commercialisation Opportunities

Page 9

9 
Following the saving option agreed to deliver the 2024/25 budget we continue to progress a plan to generate additional income through the sale
of advertising space on waste vehicles, lease of sites for billboard advertising and commercialisation opportunities at Church Street, Bruce Street
Baths and Aurora House including letting available space to third parties. Due to capacity this work will continue into 24/25. 
Communities Team 
Statement of provision for period products 
The Period Products (Free Provision) (Scotland) Act 2021 requires local authorities to ensure period products (like pads and tampons) can easily
be picked up free of charge for anyone who needs to use them. This service ensures that no one in West Dunbartonshire should struggle with
the cost of essential period products and supports the council’s anti-poverty agenda. 
In 2024-25 the Communities Team will respond to the most recent survey of local residents to develop and improve the delivery of this important
community-based service and will ensure it is promoted across the Community Planning Partnership and associated networks. 
Community Empowerment (Scotland) Act 2015
The Act sets out clear requirements for public bodies in promoting a greater level of local decision-making and empowerment of citizens. This
includes, for example, Asset Transfers, Participation Requests and Community Planning. Empowered communities can deliver a range of results
that include improved health and mental health, increased confidence and social networks, reduced sense of isolation and can reduce demand
on public sector resources. 
During 2024/25 the team’s approach to community empowerment will be shaped by UK Shared Prosperity Funding and will focus on delivering
specific projects to increase levels of participation and support people in our most disadvantaged communities. Progress will be driven and
monitored by a Project Board that will report to CPWD via the Empowered DIG. 
Locality planning was introduced, under Part 2 of the act: Community Planning. Locality planning has two main functions:
• to tackle inequalities
• to enable community bodies to participate in decision-making at a neighbourhood level 
Community Planning Partnerships are required to develop at least one Locality Plan to support communities to identify their local priorities. In
2024/25 the team will support Community Planning Partners to deliver an approach aimed at increasing participation through community
planning, including the delivery of two community planning events through the year.

Page 10

10 
Community Learning and Development 
The Community Learning and Development (Scotland) Regulations 2013 place a statutory requirement on local authorities to publish a plan
every three years. The plan should outline how the local authority will co-ordinate and secure ‘adequate and efficient’ Community Learning and
Development (CLD) provision with other sector partners. Delivery against the CLD plan 2021-24 to provide community-based learning
opportunities throughout West Dunbartonshire continues. For 2024-25 we will work in collaboration with Working 4U colleagues and partners to
develop new three-year plan for 2024-27. 
Participatory Budgeting
Community Choices 1% Framework agreement / Local Democracy. This joint agreement between COSLA and Scottish Government sets out a
framework for at least 1% of local government budgets to be decided by local residents through a participatory budgeting (PB) approach.  The
framework includes the need for greater deliberative and participatory processes that contribute to ensuring equality, inclusion and social
renewal. The key mechanism for meeting this target is the mainstreaming of Participatory Budgeting. This requires service areas across the
Council to consider and agree on how a percentage of their annual budgets can be decided/directed by local people. The Community
Empowerment Project Board monitors performance, promotes a corporate PB approach and ensures accurate reporting to the Scottish
Government on an annual basis. Following the budget decision for 2024/25 the Community Budgeting fund will be reduced by 50%. In 2024/25
we will develop an approach for the future provisioning of community budgeting.   
Food Insecurity and Cash First Project 
Cash First is a Scottish Government funded initiative to ensure those in need get help to gain a grant of £200, this will be available until March
2025. In addition, as part of “test of change” those in receipt of a grant will be referred on to the Citizens Advice Bureau (CAB) to ensure they get
addition support to prevent further need for grants. 
Communities Team Service Delivery Review 
The savings options agreed to deliver the 2024/25 budget have resulted in a reduction in the Community budget fund, community engagement
budget and the Communities Team core budget. This will result in a reduction of FTE and the delivery of reduced community services. 
A review and redesign of the delivery model across all aspects of the service will be undertaken. 
Facilities Management 
Facilities Management Improvement Plan – Next phase 
A review of the FM management structure was undertaken in 2022/23 to respond to Scottish Government policy changes and resultant service
expansion, provide additional support for frontline employees and ultimately deliver a more efficient and sustainable service aligned to delivering

Page 11

11 
the requirements of FM. In 23/24 with the new management structure in place we implemented new policies and procedure to support frontline
staff. Focused on staff engagement and roll out of training programme for staff at all levels. In 2024/25 we will progress training further, review
design and develop new operating models for catering, cleaning and janitorial services. 
Menu and Food Purchase
The savings options agreed to deliver the 2024/25 budget have resulted in a review of all menus and food purchases. The Council spends over
£1.7million a year on food to provide healthy and nutritious meals across education establishments. Food costs for school meals have continued
to rise over the last year and increased food waste is an issue which the service continues to work to reduce. In 2024/25 a, a review would be
undertaken across the menus in line with (Health Promotion and Nutrition) (Scotland) Act 2007 guidance to minimise waste and reduce costs. 
Good Food Nation Plan
The Good Food Nation (Scotland) Act 2022 provides a framework to progress toward Scotland being a Good Food Nation where people take
pride, pleasure and benefit from the food they produce, buy, cook and serve and eat each day. A consultation on proposals for the plan in is
progress. The outputs will inform the next steps in developing national and local plans.  In 2024/25 Facilities Management will work alongside
Education and other service areas within the authority to review the outputs and understand any obligations as a result of the consultation
process.   
Strategic Communications, Culture & Performance 
Communications Strategy  
Following delay in preparing a new Communications Strategy 2023/24, it will be developed in early 2024/25 and presented to align with the
Strategic Plan for period 2022-27. A communication strategy enables effective communication with and between employees and meet core
organisational objectives. It sets out how we will engage with colleagues, citizens and partners. It ensures that everyone involved has adequate
information to communicate the Council’s key messages, maintaining consistency in the workplace and preventing any ambiguity. This will
supersede the current 2017-22 Communications Strategy. 
Communication Plan to Support Budget Savings Initiatives
Following the budget meeting on March 6 2024, a number of savings options to balance the budget were agreed. There are a number of these
which will result in changes to the operation of frontline services and will require formal communications planning to ensure objectives are met,
target audiences are reached and key messages are provided effectively. Bespoke communications plans will be developed to support this
activity in each service area.

Page 12

12 
Arts & Heritage 
Glencairn House  
Work will continue to progress detailed exhibition design and content for the redevelopment of Glencairn House into a combined museum/library
facility via WDC’s successful Levelling Up Fund bid. Following design workshops and feedback, content will be developed in 2024 for an external
funding application to support an ambitious heritage activity programme for Glencairn House. External funding will be sought in 2024/25 to
support a programme of heritage engagement for Glencairn House. 
Strathleven Place
In tandem with the Glencairn House redevelopment, planning will commence on the current Dumbarton Library building on Strathleven Place to
be converted into a publically accessible archive and collections store for the Council’s most important heritage objects and documents. In
2024/25 A&H will progress plans to review the storage areas and collections to prepare for the future decant to Strathleven House in 2025.
Clydebank Heritage Hub
Detailed designs have been agreed and activity is underway to deliver an engaging and informative new museum experience that highlights the
rich history of Clydebank to both local residents and visitors alike. Having been further impacted by delays associated with remedial works this
project is now expected to complete by end 2024. In 2024/25 A&H will support the opening of the Heritage Hub and submit a Museums Galleries
Scotland Museum Development Fund application to support activity and engagement by October 2024 with view to securing funding.   
Implementation of MODES CMS
A&H will progress the plans to Install MODES computer management system to manage and maintain collections information for the benefit of
the service and service users. This system enables access to museum, fine art, local history and archival records for research purposes and for
management and maintenance of collection records. The current Collections Management Software (CMS), ADLIB contract expired in
December 2023. MODES will offer an updated system for A & H officers. Following install in conjunction with ICT and web team A&H will
investigate funding to implement the front end build to enable access by the public. 
Performance & Strategy Team 
Strategic Engagement 
In line with the Council’s Strategic Plan, to ensure our residents are engaged and empowered we will continue to review and strengthen our
approach towards strategic engagement with a particular focus on increasing participation from seldom heard voices, improving how we

Page 13

13 
feedback results to the community and partners, and exploring best practice with engagement tools. We will support the Council with budget
consultations and continue to gather resident’s views through the Citizens Panel. 
Equalities Review
The rights set out in the United Nations Children’s Rights Convention (UNCRC) Bill was passed unanimously by the Scottish Parliament on 16
March 2021, and work continues nationally to have this incorporated as law. The UNCRC sets out the rights to which children under 18 are
entitled in all areas of their lives and recognises that especially vulnerable children, including care experienced children, migrant children and
children with disabilities, require particular protection. To meet new legislative requirements, we will continue to review our Equalities Strategy to
ensure the inclusion of UNCRC is considered in all areas of policy and practice and undertake a review of our approach towards Equality Impact
Assessments to reflect any changes. In addition, the British Sign Language (Scotland) Act 2015 came into force in October 2015. It promotes the
use of BSL in Scotland, primarily by requiring local authorities to develop BSL plans that outline how they will promote and raise awareness of
the language; in 2024/25 we will develop our new six year plan 2024-30. 
Continuous Improvement 
Continuous improvement is central to all that we do. The actions set out in this section, as well as those at an operational level not included in
this Delivery Plan, demonstrate our commitment to continuous improvement and take account of the wider Best Value focus on vision and
leadership; governance and accountability; effective use of resources; partnerships and collaborative working; working with communities;
sustainability; and fairness and equality. 
Action Plan 
The challenges identified in Section 2 and the key factors identified in Section 3 have informed CCF priorities for 2024/25. Appendix 1 sets out
the action plan to address them. It also includes:
• performance indicators and targets that will enable progress to be monitored and reported to stakeholders
• strategic workforce actions to address workforce issues identified in the planning process; and 
• strategic and/or service risks. 
In relation to the latter, strategic risks represent the potential for the Council to take advantage of opportunities or fail to meet stated strategic
objectives and those that require strategic leadership. Service risks relate to service delivery and represent the potential for impact on individual
services, or the experience of those who work within the services, i.e. employees, partners, contractors and volunteers or service users and

Page 14

14 
clients in receipt of the services provided. In identifying the relevant risks for 2024/25 and actions to mitigate them, the aim is to improve or
maintain the current position (i.e. the current risk score) set out in the appendix. 
4. Resources 
Finance 
The Finance team are currently creating the detailed service budgets to accurately reflect all savings, management  adjustments and other
budget adjustments agreed by Council on 6 March 2024. Once this is complete the service plans will be updated with each Service’s Gross
Expenditure, Gross Income and Net Revenue Expenditure Budgets. 
Employees 
Employee Numbers
The headcount and full time equivalent staff in each service area (as of 31st March 2024) are as follows: 
Absence in 2023/24 
Service Area Headcount FTE
Communications & Sales 5 5
Customer Services  47 41.98
Facilities Management (Including Town Hall) 583 318.99 
Libraries 58 46.67 
Arts & Heritage 8 8
Performance & Strategy  4 3.81 
Communities   22 17.71
TOTAL 727 442.16

Page 15

15 
The quarterly absence statistics for Citizen, Culture and Facilities are shown below together with the Council average for the same periods for
comparison. The figures have been higher than the Council average throughout 2023/24: 
Absence in 2023/24 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Annual FTE days lost per FTE employee
Citizen, Culture and
Facilities 
5.36  3.92  6.52  5.82  17.41 
COUNCIL WIDE TOTAL 3.64  3.36  4.67  5.01  13.74

Page 16

16 
Appendix 1: Action Plan   
1. Our Communities 
Objective 1. Our neighbourhoods are safe, resilient and inclusive 
Performance Indicator 2024/25
Target Owner
Number of adults and young people participating in engagement activity through Community Development
activity. 250 Elaine Troup 
Action Due Date Owner
Increase the number of locations offering access to free period products 31-Mar-25 Elaine Troup
Continue the development of Locality Planning approach  31-Mar-25 Elaine Troup
Support community planning partners to develop and deliver two CP events to support increased
participation
31-Mar-25 Elaine Troup 
Strategic Risk Description Current
Assessment
Target
Assessment Owner
Engaging positively
with Residents,
Communities &
Partnerships
The risk that the Council fails to adequately engage, establish
and maintain positive relationships with local residents and
communities in addition to partnership bodies.    
Elaine Troup   
Objective 2. Our residents health and wellbeing remains a priority

Page 17

17 
Performance Indicator Target 24-25 Owner
% of pupil medical dietary requests met  100% Sharon Jump
% of pupils who take up free school meals ( P1-7 ) 75% Sharon Jump 
Action Due Date Owner
Review menu and food purchase to minimise waste and reduce costs 31-Mar-2025 Sharon Jump
Review outputs from Good Food Nation consultation process. 31-Mar-2025 Sharon Jump 
Objective 3. Our residents are supported to increase life and learning skills 
Performance Indicator Target 24-25 Owner
Total number of visits to funded and part funded museums and heritage centres (in person & virtual)  106,500 Lauren Crooks
Total number of library visits (physical and virtual)  385,000 Stephen Daly
Total number of library issues ( physical and e-issues) 220,000 Stephen Daly
% of adults satisfied with libraries 90% Stephen Daly
% of adults satisfied with museums and galleries 88% Lauren Crooks 
Action Due Date Owner
Progress funding application to support heritage activity programme for Glencairn House 31-Mar-2025 Lauren Crooks
Progress storage review and planning for future decant of WDC collections to Strathleven  31-Mar-2025 Lauren Crooks
Support progress of plan for opening of Clydebank Heritage Hub   31-Mar-2025 Lauren Crooks
Support progress of MODES installation 31-Mar-2025 Lauren Crooks

Page 18

18 
Action Due Date Owner
Implement and embed a new delivery model for co-located libraries 31-Mar-2025 Stephen Daly
Create a strategy document for West Dunbartonshire Libraries 31-Mar-2025 Stephen Daly
Migrate the Libraries Management System (LMS) to a new software supplier 31-Mar-2025 Stephen Daly
Continue to delivery youth learning and community based learning and participation opportunities. 31-Mar-2025 Elaine Troup 
4. Our Council 
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Action Due Date Owner
Develop and implement wellbeing, employee engagement, equality and learning and development plans to
enable capabilities, improve resilience and promotion of a diverse workforce 31-Mar-2025 All Managers 
Develop and implement employee life cycle plans in line with the People First Strategy to attract and retain
the workforce. 31-Mar-2025 All Managers
Implement service review process including role design, use of new technology and new ways of working to
add resilience, address gaps, and establish opportunities for efficiencies 31-Mar-2025 All Managers
Develop and implement learning and development opportunities to improve capabilities and resilience within
the workforce. 31-Mar-2025 All Managers

Page 19

19 
Objective 11. Our Council is adaptable and focused on delivering best value for our residents 
Performance Indicator Target 24-25 Owner
% of complaints received by the Council that are resolved at Stage 1 90% Stephen Daly
% of complaints received by the Council that are resolved at Stage 2 10% Stephen Daly
% of telephone calls answered within 3 minutes by Contact Centre as a proportion of all calls answered. 90% Stephen Daly
% of telephone calls answered within 5 minutes by Repairs Contact Centre as a proportion of all calls
answered.
90% Stephen Daly
Residents satisfaction with Council services overall 85% Amanda Graham 
Action Due Date Owner
Implement complaints management process enhancements – next phase 31-Mar-2025 Stephen Daly
Explore telephony self-serve options 31-Mar-2025 Stephen Daly
Roll out child friendly complaint procedure.  31-Mar-2025 Stephen Daly
Review library materials and staffing 31-Mar-2025 Stephen Daly
Review and redesign of the Communities team service delivery  31-Mar-2025 Elaine Troup
Review operating model of Facilities Management service – Next Phase  31-Mar-2025 Sharon Jump
Progress commercialisation and income generation opportunities   31-Mar-2025 Amanda Graham
Progress community facilities plan 31-Mar-2025 Amanda Graham

Page 20

20 
Risk Description Current Assessment Target Assessment Owner
Risk of failure to meet
citizen expectation and
service standards
Risk of citizen dissatisfaction due to us not doing what
we say we will when we say we will.  Stephen Daly
Failure to effectively
manage and learn from
complaints
There is a risk of damage to the Council's reputation.
If complaints are not handled effectively, there can be
an adverse effect on the public perception of the
Council which can lead to a lack of trust in the
services provided.   
Stephen Daly 
Objective 12. Our residents are engaged and empowered 
Performance Indicator Target 24-25 Owner
% of residents who are satisfied with the Council website 85% Stephen Daly
% of stage 1 complaints responded to within 5 working days. 100% Stephen Daly
% of stage 2 complaints responded to within 20 working days. 100% Stephen Daly
% of residents who feel the Council communicates well with them 75% Lauren Crooks
No. of transactions undertaken online 54,500 Stephen Daly 
Action Due Date Owner
Progress upgrade online content management system – next phase 31-Mar-2025 Stephen Daly
Progress security reviews of websites 31-Mar-2025 Stephen Daly

Page 21

21 
Action Due Date Owner
Review accessibility of the website and intranet 31-Mar-2025 Stephen Daly
Develop strategic communications strategy 31-Mar-2025 Lauren Crooks
Develop a communication plan to support budget savings initiatives 31-Mar-2025 Lauren Crooks
Progress plans to strengthen approach to strategic engagement  31-Mar-2025 Lauren Crooks
Reflect legislative changes from Scottish Gov in WDC equalities framework, process and procedures 31-Mar-2025 Lauren Crooks
Develop WDC British Sign Language (BSL) plan 2024-30 31-Mar-2025 Lauren Crooks
Deliver the UK Shared Prosperity Funded projects. 31-Mar-2025 Elaine Troup
Develop an approach for the future provision of community budgeting 31-Mar-2025 Elaine Troup
Continue to Develop an approach to food insecurity  31-Mar-2025 Elaine Troup 
Risk Description Current Assessment Target Assessment Owner
Risk of Ineffective
Communications /
Reputation Risk
Ineffective use of corporate communication channels
may result in messages that are inconsistent with
authorised responsibilities or established performance
measures. Employees without intranet access or
email access may not receive communications. Not
effectively managing corporate responses to adverse
events may lead to an erosion of the Council's
reputation.  
Lauren Crooks
Failure to deliver on the
capacity building of the
Community
Empowerment
(Scotland) Act
As communities continue to recover from the impact of
Covid-19 there is an ever greater need to support and
develop communities. Community capacity building
and community development work continues within
existing resources.   
Elaine Troup

Page 22

22 
Risk Description Current Assessment Target Assessment Owner
Failure to secure
community and partner
buy-in for the approved
Community
Empowerment Strategy
and Action Plan.  
The risk level remains the same as work continues on
the Delivery Plan. The establishment of a Project
Board in 2021/22 has reduced this risk level in relation
to service area buy-in. 
Elaine Troup