WEST DUNBARTONSHIRE COUNCIL APPENDIX 7 GENERAL SERVICES CAPITAL PROGRAMME ANALYSIS OF GREEN PROJECTS PERIOD END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 1 Project Life Financials 30 30 100% 30 0 0% Current Year Financials 23 3 15% 23 0 0% Project Description Project Manager Adrian Gray Chief Officer Laurence Slavin Project Lifecycle 31-Mar-27 31-Mar-27 2 Project Life Financials 1,000 500 50% 1,000 0 0% Current Year Financials 250 55 22% 250 0 0% Project Description Project Manager Adrian Gray Chief Officer Laurence Slavin Project Lifecycle 31-Mar-26 31-Mar-26 3 Project Life Financials 53 48 90% 48 (5) -10% Current Year Financials 7 0 0% 7 0 0% Project Description Project Manager Alan Douglas Chief Officer Alan Douglas Project Lifecycle 31-Mar-24 31-Mar-24 4 Project Life Financials 30 20 67% 30 0 0% Current Year Financials 10 0 0% 10 0 0% Project Description Project Manager Pamela Clifford Chief Officer Alan Douglas Project Lifecycle 31-Mar-24 31-Mar-24 5 Project Life Financials 155 155 100% 155 0 0% Current Year Financials 10 0 0% 10 0 0% Project Description Project Manager Pamela Clifford Chief Officer Alan Douglas Project Lifecycle 31-Mar-24 31-Mar-24 31 October 2023 Budget Details Project Life Financials Spend to Date Variance Agresso development The purpose of this project is to carry out an upgrade of the Agresso Finance System which was last upgraded in 2015. The requirement to upgrade is to maintain a level of support available from Unit 4 who have advised that support for older versions of the system is being reduced. Planned End Date Forecast End Date Main Issues / Reason for Variance Work to significantly reduce the database size to facilitate a system upgrade has now been completed. Upgrade work can now commence, ICT currently building required servers in preparation for new version to be installed, configured and tested. Mitigating Action None required Anticipated Outcome Anticipate completion of upgrade during 23-24 financial year. Planned End Date Forecast End Date Main Issues / Reason for Variance No variances currently anticipated. Mitigating Action None required at this time. Cost of Living To support Council and community organisations with capital costs for cost of living initiatives. Anticipated Outcome Project will be delivered on time and on budget Mitigating Action None required at this time. Anticipated Outcome Solicitor support for Capital Projects, with full budget spend anticipated. Re -imagine Antonine Wall Council's capital contribution towards the multi-partner (five local authorities and Historic Environment Scotland) Rediscovering the Antonine Wall project which is also funded by the Heritage Lottery Fund. Solicitor Project Support for Capital Projects Solicitor costs to directly support capital projects Planned End Date Forecast End Date Main Issues / Reason for Variance Trainee solicitor in place. Budget will be fully spent. Anticipated Outcome Anticipate full budget spend. Demolition 215 Main Street Alexandria Demolition of 215 Main Street Alexandria. Planned End Date Forecast End Date Planned End Date Forecast End Date Main Issues / Reason for Variance This goes into the overall Antonine Project budget - 5 Councils and Historic Environment Scotland - Expected spent by March 2024 Mitigating Action No action required Main Issues / Reason for Variance This outstanding money is being sought through the recharging order and through debtors. Mitigating Action No action required at this time in the hands of Legal Anticipated Outcome Continue to pursue repayment
Page 2
WEST DUNBARTONSHIRE COUNCIL APPENDIX 7 GENERAL SERVICES CAPITAL PROGRAMME ANALYSIS OF GREEN PROJECTS PERIOD END DATE PERIOD 7 Budget Forecast Spend £000 £000 % £000 £000 % 31 October 2023 Budget Details Project Life Financials Spend to Date Variance Agresso development6 Project Life Financials 421 421 100% 421 (0) 0% Current Year Financials 116 0 0% 116 0 0% Project Description Project Manager David Main Chief Officer Amanda Graham Project Lifecycle 31-Mar-24 31-Mar-24 7 Project Life Financials 892 205 23% 892 0 0% Current Year Financials 892 205 23% 892 0 0% Project Description Project Manager James Gallacher Chief Officer Victoria Rogers Project Lifecycle 31-Mar-24 31-Mar-24 8 Project Life Financials 873 202 23% 873 0 0% Current Year Financials 873 202 23% 873 0 0% Project Description Project Manager James Gallacher Chief Officer Victoria Rogers Project Lifecycle 31-Mar-24 31-Mar-24 9 Project Life Financials 503 503 100% 503 0 0% Current Year Financials 185 24 13% 185 (0) 0% Project Description Project Manager James Gallacher Chief Officer Victoria Rogers Project Lifecycle 30-Sep-23 30-Sep-23 10 Project Life Financials 379 88 23% 379 (0) 0% Current Year Financials 46 0 0% 46 0 0% Project Description Project Manager Arun Menon Chief Officer Victoria Rogers Project Lifecycle 31-Mar-30 31-Mar-30 Transformation of Infrastructure Libraries and Museums To improve performance and efficiency of Council's Libraries and Cultural Services. Planned End Date Forecast End Date Main Issues / Reason for Variance Awaiting outcome of Council decisions on library colocations before commencing with final spend of capital investment. Mitigating Action None required. Anticipated Outcome Projects delivered on budget ICT Modernisation This budget is to facilitate ICT infrastructure and modernise working practices. Anticipated Outcome projects delivered on time and on budget Planned End Date Forecast End Date Main Issues / Reason for Variance All PC's and laptops have now been replaced across Corporate/Education estate. Chromebook replacements are at checking/inventory stage and scoping requirements. Mobile phone replacement under review. Anticipating full budget spend. Mitigating Action none required ICT Security & DR The project is for the enhancement of security systems, server replacement and the update of corporate applications to ensure compliance with 15/16 PSN requirements, to enhance the disaster recovery capabilities of WDC. Planned End Date Forecast End Date Main Issues / Reason for Variance Due to delays on SWAN2 contract some of this capital budget is required for installations costs and is to be carried to 24/25 budget, will be clarified further at contract sign off. Wireless access project installation complete and awaiting final installation costs from DLO. Technology replacement project ongoing with proof of concepts nearing completion and procurement strategy at committee stage, In addition indentyifng volume and costs to replace WYSE terminals. Infrastructure hardware replacement estimated £100k spend and Security & Compliance remediation estimated £70k Planned End Date Forecast End Date Main Issues / Reason for Variance Budget spend for planned Sharepoint discovery and implementation alongside One Drive for Business. Further external consultancy required for 365 Tenancy configuration and to ensure Security of 365 environment. Mitigating Action none required Mitigating Action none required Anticipated Outcome projects delivered on time and on budget 365 Implementation Project services to delivery Microsoft 365 Implementation including 3rd party supplier, training, technical consultancy etc. Main Issues / Reason for Variance Work continues on developments resulting in some spend in the current year. Mitigating Action none required Anticipated Outcome Work continues on developments resulting in some spend in the current year. Anticipated Outcome projects delivered on time and on budget Development of Workforce Management System Project to develop the Workforce Management System. Planned End Date Forecast End Date