WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Annual Spend RAG Status
£000 £000 £000 %
Finance 1,291 1,374 83 6% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Rent Rebates & Allowances (341) (256) 85 -25% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Planning 687 428 (259) -38% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Information Services 4,631 4,529 (102) -2% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Clydebank Town Hall 340 273 (67) -20% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
The service provided by this area deals with Accountancy, Capital, Treasury, Reconciliations,
Cash Office and Municipal Bank
Main reason for adverse variance is full turnover savings are not being achieved.
None available at this time.
Adverse variance is anticipated
31 October 2023
Budget Details
Variance Analysis
Variance
Payment of Rent Rebates and other Allowances
Reduction in overpayment (OP) recoveries is due to DWP recovering some HB OP’s against
Universal Credit, subject to the OP reason. Previously the Council would have received 40%
subsidy in OP’s with the ability to recover 100% of the OP, therefore a potential to receive up
to 140% of the OP value.  This change means we receive 100% subsidy of the OP therefore
a reduction from the potential 140% that could have been recovered.
None available at this time.
Adverse variance is anticipated
This service area provides general ICT support to the Council and also supports
transformational change and modernisation of working practices through technology
Main reason for the favourable variance is additional telephone costs are being offset by
recharge income to recover these from other services. In addition centralised printing and
leasing costs for copiers are anticipated to overspend during the year.
None at this moment
Favourable variance overall is anticipated
The service provides civic accommodation and facilities within Clydebank
The main reason for the favourable variance is reduced expenditure on property costs
(principally gas and non-domestic rates). There has also been an increase in projected
income.
None necessary.
Favourable variable anticipated.
The main reason for the favourable variance is that income is higher than budgeted. The
additional income predicted is an in-year benefit only as a result of one-off additional fees.
None required
A favourable variance is anticipated.
This Service provides Building & Planning services

Page 2

WEST DUNBARTONSHIRE COUNCIL APPENDIX 3
REVENUE BUDGETARY CONTROL 2023/24
ANALYSIS FOR VARIANCES OVER £50,000
PERIOD END DATE
Total Budget Annual Spend RAG Status
£000 £000 £000 %
31 October 2023
Budget Details
Variance Analysis
Variance
Leisure Management 3,459 3,534 75 2% 
Service Description
Main Issues / Reason for Variance
Mitigating Action
Anticipated Outcome
Payment to West Dunbartonshire Leisure Trust for leisure services
The management fee to WDLT has been higher because of delays in the reduction in
community facilities provision. In addition budgeted contribution from Education towards
overall management fee overstated.
None at the moment.
Adverse variance is anticipated.