WEST DUNBARTONSHIRE COUNCIL
Report by the Chief Officer - Resources 
Corporate Services Committee – 07 February 2024
___________________________________________________________________
Subject: Corporate Services Budgetary Control Report to 31 October 2023 
(Period 07)
1. Purpose
1.1 The purpose of this report is to advise the Committee on the performance of
the Corporate Services budget for the period to 31 October 2024.
2. Recommendations
2.1 Members are asked to:
i) note that the revenue account currently shows a projected annual
favourable variance of £0.017m (0.05% of the total budget) and
ii) note that the capital account is showing a projected in-year underspend
of £2.097m (0.43% of in-year budget). Explanations for projected
variances to the 19 current projects are detailed in Appendices 6 and 7.
The project life projection is currently showing a projected overspend of
£0.002m (0.02% of project life budget).
3. Background
3.1 Revenue Budget
At the meeting of West Dunbartonshire Council on 1 March 2023, Members
agreed the revenue estimates for 2023/24.
A total net budget of £34.850m was approved for services under the remit for
Corporate Services at that time.
Since the budget changes to the value of -£0.782m have occurred, the details
of these are as follows:
Description £m
Budget Agreed March 2023 34.850
PAT Testing budget moved from P&T to Education -0.014
CCF - Allocation of Commercialisation saving target 0.056
Transfer of vacancy underspends to miscellaneous -0.828
Adjustment to SIP Trucking movements 0.004
34.068
ITEM 12

Page 2

3.2 Capital Budget 
At the meeting of Council on 1 March 2023, Members also agreed the
updated 10 year General Services Capital Plan for 2023/2024 to 2031/32. 
The three years from 2023/24 to 2025/26 have been approved in detail with
the remaining 7 years being indicative at this stage. The total project life
budget approved for projects that have either commenced or are due to
commence in that period total for Corporate Services is £7.299m. 
4. Main Issues 
Revenue Budget 
4.1 The summary report at Appendix 1 identifies a projected annual favourable
variance (underspend) of £0.017m (0.05% of the total budget). Detailed
service reports are attached as Appendix 2.          
4.2 There are six projected annual variances in excess of £0.050m. Notes on
these variances are highlighted and noted within Appendix 3, with additional
information on action being taken to minimise or mitigate overspends where
possible. 
4.3  Although the report indicates that expenditure is favourable in comparison to
that anticipated during the budget exercise, the present variance should be
viewed in the knowledge that there are a number of variable factors which
could arise between now and 31 March 2024 and which could affect the year
end results. 
Capital Budget
4.4 Appendices 5 to 7 highlight 8 projects showing an in-year variance and 10
projects on target. The overall Corporate Services programme summary
report at Appendix 5 shows that there is a projected £0.558m (7.6%) of the
total programmed budget) to be re-phased in future years. 
There is one significant variance within the Capital Budget, this is: 
Project Budget 23-24
(£m)
Forecast 23-24 Variance
Heritage Capital
Fund
0.814 0.256 0.558 
See Appendices 6 and 7 for more details. 
5. People Implications 
5.1 There are no people implications.

Page 3

6. Financial and Procurement Implications 
6.1 Other than the financial position noted above, there are no financial or
procurement implications from this budgetary control report. 
7. Risk Analysis
7.1 The main financial risks to the ongoing financial position relate to unforeseen
costs being identified between now and the end of the financial year. This can
affect all service areas 
8. Equalities Impact Assessment (EIA) 
8.1 No equalities impact assessment was required in relation to this report. 
9. Consultation 
9.1 All services involved in delivering the revenue and capital budgets have been
consulted in the compilation of this report. 
10. Strategic Assessment 
10.1 Proper budgetary control and sound financial practice are cornerstones
of good governance and support Council and officers to pursue the 5
strategic priorities of the Council’s Strategic Plan. This report forms part
of the financial governance of the Council.   
__________________
Laurence Slavin
Chief Officer Resources 
Date:  18 January 2024 
________________________________________________________________
Person to Contact: Adrian Gray, Finance Business Partner 
Council Offices, 16 Church Street, Dumbarton  
Telephone: (01389) 737838  
E-mail: adrian.gray@west-dunbarton.gov.uk 
Appendices: Appendix 1 - Revenue Budgetary Control 2023/24
– Summary Report 
Appendix 2 -  Revenue Budgetary Control 2023/24
– Service Reports
Appendix 3 - Analysis of Revenue Variances over 
£50,000

Page 4

Appendix 4 -  Monitoring of Savings Options 
Appendix 5 -  Overall Capital Programme Summary 
Financials 
Appendix 6 -  Capital Programme – Red Status
Appendix 7 - Capital Programme – Green Status 
Background Papers: 
Ledger output – Period 07  
General Services Revenue Estimates 2023/24 – Council 1
March 2023  
General Services Capital Strategy 2023/24 to 2032/33 -
Council 1 March 2023  
Wards Affected           All Wards