WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
1
Project Life Financials 30 7 25% 30 0 0%
Current Year Financials 23 1 3% 23 0 0%
Project Description
Project Manager Adrian Gray
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-27 31-Mar-27
2
Project Life Financials 1,000 250 25% 1,000 0 0%
Current Year Financials 250 11 4% 250 0 0%
Project Description
Project Manager Adrian Gray
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-26 31-Mar-26
3
Project Life Financials 1,590 0 0% 1,590 0 0%
Current Year Financials 1,590 0 0% 1,590 0 0%
Project Description
Project Manager Michelle Lynn
Chief Officer Laurence Slavin
Project Lifecycle 31-Mar-24 31-Mar-25
31 August 2023
Budget Details
Project Life Financials
Spend to Date Variance
Main Issues / Reason for Variance
Work planned for September to significantly reduce size of database in preparation for upgrade commencing.
Mitigating Action
None required
Anticipated Outcome
Anticipate completion of upgrade during 23-24 financial year.
Agresso development
The purpose of this project is to carry out an upgrade of the Agresso Finance System which was last upgraded in 2015. The
requirement to upgrade is to maintain a level of support available from Unit 4 who have advised that support for older
versions of the system is being reduced.
Planned End Date Forecast End Date
Cost of Living
To support Council and community organisations with capital costs for cost of living initiatives.
Anticipated Outcome
Project will be delivered on time and on budget
Strathleven Place
Re-development of Strathleven.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
No variances currently anticipated.
Mitigating Action
None required at this time.
Main Issues / Reason for Variance
This project is linked to Glencairn House and Depot Rationalisation and will free up the current museum store and office space in Poplar Road. Opportunities exist to
attract external funding. Detailed design work ongoing for Glencairn House.
Mitigating Action
None available at this time
Anticipated Outcome
Project delivered on budget
Appendix 7

Page 2

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2023
Budget Details
Project Life Financials
Spend to Date Variance
4
Project Life Financials 53 41 77% 48 (5) -10%
Current Year Financials 7 0 0% 7 0 0%
Project Description
Project Manager Alan Douglas
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
5
Project Life Financials 30 10 33% 30 0 0%
Current Year Financials 10 0 0% 10 0 0%
Project Description
Project Manager Pamela Clifford
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
6
Project Life Financials 155 145 93% 155 (0) 0%
Current Year Financials 10 0 0% 10 (0) 0%
Project Description
Project Manager Pamela Clifford
Chief Officer Alan Douglas
Project Lifecycle 31-Mar-24 31-Mar-24
7
Project Life Financials 421 305 72% 421 (0) 0%
Current Year Financials 116 0 0% 116 0 0%
Project Description
Project Manager David Main
Chief Officer Amanda Graham
Project Lifecycle 31-Mar-24 31-Mar-24
Solicitor Project Support for Capital Projects
Solicitor costs to directly support capital projects
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Trainee solicitor in place. Budget will be fully spent.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
This goes into the overall Antonine Project budget.
Mitigating Action
No action required
Mitigating Action
None required at this time.
Anticipated Outcome
Solicitor support for Capital Projects, with full budget spend anticipated.
Re -imagine Antonine Wall 
Council's capital contribution towards the multi-partner (five local authorities and Historic Environment Scotland)
Rediscovering the Antonine Wall project which is also funded by the Heritage Lottery Fund.
Main Issues / Reason for Variance
This outstanding money is being sought through the recharging order and through debtors.
Mitigating Action
No action required at this time in the hands of Legal
Anticipated Outcome
Continue to pursue repayment
Anticipated Outcome
Anticipate full budget spend.
Demolition 215 Main Street Alexandria
Demolition of 215 Main Street Alexandria.
Planned End Date Forecast End Date
Mitigating Action
None required.
Anticipated Outcome
Projects delivered on budget
Transformation of Infrastructure Libraries and Museums
To improve performance and efficiency of Council's Libraries and Cultural Services.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Project progressing well, due to be complete be end of financial year.

Page 3

WEST DUNBARTONSHIRE COUNCIL
GENERAL SERVICES CAPITAL PROGRAMME
ANALYSIS OF GREEN PROJECTS
PERIOD END DATE
PERIOD 5
Budget Forecast
Spend
£000 £000 % £000 £000 %
31 August 2023
Budget Details
Project Life Financials
Spend to Date Variance
8
Project Life Financials 1,457 56 4% 1,457 0 0%
Current Year Financials 892 56 6% 892 0 0%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-24 31-Mar-24
9
Project Life Financials 873 164 19% 873 0 0%
Current Year Financials 873 164 19% 873 0 0%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-24 31-Mar-24
10
Project Life Financials 503 318 63% 503 0 0%
Current Year Financials 185 (1) 0% 185 (0) 0%
Project Description
Project Manager James Gallacher
Chief Officer Victoria Rogers
Project Lifecycle 30-Sep-23 30-Sep-23
11
Project Life Financials 379 42 11% 379 (0) 0%
Current Year Financials 46 0 0% 46 0 0%
Project Description
Project Manager Arun Menon
Chief Officer Victoria Rogers
Project Lifecycle 31-Mar-30 31-Mar-30
Main Issues / Reason for Variance
Device replacement budget - planning replacement 2500 devices across budget period with an anticipated spend of £670k. Project Resourcing - capital posts,
consultancy (off payroll/suppliers) anticipated £123k spend.
Mitigating Action
none required
Anticipated Outcome
projects delivered on time and on budget
ICT Modernisation
This budget is to facilitate ICT infrastructure and modernise working practices.
Planned End Date Forecast End Date
ICT Security & DR
The project is for the enhancement of security systems, server replacement and the update of corporate applications to
ensure compliance with 15/16 PSN requirements, to enhance the disaster recovery capabilities of WDC.
Anticipated Outcome
projects delivered on time and on budget
365 Implementation
Project services to delivery Microsoft 365 Implementation including 3rd party supplier, training, technical consultancy etc.
Planned End Date Forecast End Date
Planned End Date Forecast End Date
Main Issues / Reason for Variance
£205k spent to-date. Due to delays on SWAN2 contract some of this capital budget may be required to carry to 24/25 budget and will be clarified further at contract sign
off. Wireless access project installation continues across the council with estimated installation costs of £75k. Technology replacement project ongoing with pilots in
progress. Infrastructure hardware replacement estimated £100k spend and  Security & Compliance remediation estimated £70k
Mitigating Action
none required
Development of Workforce Management System
Project to develop the Workforce Management System.
Planned End Date Forecast End Date
Main Issues / Reason for Variance
Work continues on developments resulting in some spend in the current year.
Main Issues / Reason for Variance
Budget spend for plannedSharepoint discovery and implementation alongside One Drive for Business.  Further external consultancy required for 365 Tenancy
configuration and to ensure Security of 365 environment.
Mitigating Action
none required
Anticipated Outcome
projects delivered on time and on budget
Mitigating Action
none required
Anticipated Outcome
Work continues on developments resulting in some spend in the current year.