2023/24
RESOURCES
Appendix 2: Resources Delivery Plan 2023/24
APPENDIX 2

Page 2

Contents
1. Introduction ........................................................................................................................................................................... 2
2. Performance Review ............................................................................................................................................................. 2
3. Strategic Assessment ........................................................................................................................................................... 4
4. Resources ............................................................................................................................................................................. 8
Appendix 1: Action Plan ................................................................................................................................................................. 10

Page 3

1. Introduction
Resources comprises Finance, Business Support and Internal Audit & Fraud. It provides accountancy, treasury management, internal audit and
fraud, and business support services to the Council and external clients including the West Dunbartonshire Leisure Trust, the Valuation Joint
Board, Clydebank Property Company, charities and trusts, and West Dunbartonshire Energy Ltd. Company. In addition, it provides direct
services to residents of West Dunbartonshire. It is one of eight strategic areas responsible for delivering the Council’s Strategic Plan. Key actions
to help achieve that are set out in this Delivery Plan, together with actions to address any performance issues and service priorities identified in
the planning process.
Progress against this plan will be monitored and managed by the management team and reported to Corporate Services Committee twice
yearly, at mid-year and year-end.
2. Performance Review
The Resources management team completed a detailed review of 2022/23 performance, focusing on:
• 2022/23 Delivery Plan year-end progress
• Local Government Benchmarking Framework (LGBF) comparative data
• Complaints
• Benchmarking within the Audit service.
This review highlighted our key achievements and challenges in 2022/23. These are summarised below.
Key Achievements in 2022/23
Finance
• Completed a number of audited Financial Statements within statutory deadlines, with no qualifications.
• Further progressed financial support to the District Heating Network.
• Continued to deliver service and financial returns to public sector bodies.
• Supported transformation projects within the Council, including the District Heating Network, ongoing development of revised costing models
and financial reporting within Housing Maintenance Trading Account.

Page 4

• Supported the roll out of the Council’s Cost of Living Capital Fund.
Business Support
• Processed £2.5m in Free School Meals and hardship payments to families in need.
• Processed £1.3m in clothing grants to parents and carers of 4,497 school pupils.
• Processed £5.5m in cost of living payment to 36,768 residents providing assistance with rising energy costs.
• Processed £2.5m in discretionary housing payments to assist 3,316 vulnerable tenants with housing costs.
• Improved the rent arrears process working in partnership with Housing.
• Increased efficiency by developing and improving automation solutions to process Employee New Start, Sickness Absence, Teachers
Pension Notification, Free School Meals, Clothing Grants and Discretionary Housing payments.
Internal Audit & Fraud
• Finalised the 2021/22 annual audit plan and progressed the 2022/23 audit plan.
• Delivered actual savings and re-billings of £255,563 against an annual target of £250,000 through the Corporate Fraud Team.
Key Challenges in 2022/23
Finance
• Reconciling and managing a significant number funding streams mainly due to Scottish Government priorities.
• Worked closely with all services to develop an extensive range of savings options to help deliver a balanced 2023/24 budget.
• The service operated without a Finance Manager for three months due to the resignation of the existing post holder and the need for the new
post holder to serve their notice period in their previous role. This created significant pressure at a critical time as it coincided with the
announcement of the Council’s 2023/24 Local Government Settlement and preparation of the draft 2023/24 budget.
• Providing personal development for staff by allocating new roles to officers resulting in a significant learning curve whilst continuing to provide
a quality service to customers.
Business Support
• Level of rent arrears was aggravated by the cost of living crisis.
• Collection of sundry debt was greatly impacted by cost of living crisis which is being managed in line with the Corporate Debt policy and a
range of flexible measures.
• Managing levels of service delivery with the levels of budget cuts.

Page 5

3. Strategic Assessment
The Resources management team completed a strategic assessment to determine the major influences on service delivery and priorities in
2023/24. The key factors are summarised below.
Key Factors
Financial Challenges
The entire public sector is continuing to face significant financial challenges due to a range of factors including inflationary cost increases, rising
utility costs and insufficient funding to support the delivery of front line and back office services. The Council are currently faced with an
estimated cumulative funding gap in 2024/25 of £9.7m rising to £29.5m by 2027/28.  We will continue to monitor the overall financial position of
the Council and updates on estimated future budget gaps will be reported to Elected Members throughout 2023/24.
These challenges mean further action is required to balance our budget and protect services for residents. This will mean that within Resources
available funding will be reduced over time and we will need to reconfigure how we work, what we do, where we work, and potentially reduce the
number of people employed. In this context, we will aim to continue to provide a sustainable, quality service to internal clients and the public.
Budget Sensitivity Analysis
In reviewing the service budget projections, consideration has been given to the sensitivity of these budgets, in particular for higher risk/ higher
value budgets which may have a significant impact on budgetary control and future budget projections. The analysis has considered sensitivity
around demand, costs and charges, and income levels.
Specifically within Resources there were no budgets identified as being more susceptible to fluctuations. However, on a more Council-wide
basis, the Council’s cost of borrowing is susceptible to fluctuations in the bank interest rate due to the level of the Council’s short-term borrowing.
Reduction in Workforce
The savings options agreed to deliver the 2023/24 budget have resulted in a reduction in resources within the Accountancy, Business Support
and Audit & Fraud teams. This will require a review of workloads and prioritisation of tasks and responsibilities to ensure quality services are still
delivered without placing undue pressures on staff.

Page 6

In 2023/24, we will review and prioritise workload within Accountancy, Business Support and Audit & Fraud. This will be carried out as part of the
wider workforce planning action: Implement service review process including role design, use of new technology and new ways of working to
add resilience, address gaps, and establish opportunities for efficiencies
Accounting Code of Practice – Change Regarding Leasing
There has been a change to the Code of Practice on Local Authority Accounting issued by CIPFA (the Chartered Institute of Public Finance &
Accountancy) in relation to leasing, which was due to be in place for 1 April 2022 but has subsequently been delayed.
Going forward, this results in a significant change in the way leasing costs are presented within the Financial Statements and within the Treasury
Management Strategy. This will require us to gather and analyse a significant amount of corporate-wide information, ensure awareness of the
changes for both members and officers and change disclosures in the Financial Statements and Treasury Management Strategy.
In 2023/24, we will continue to gather and analyse information received to ensure we are prepared for the inclusion in the Financial Statements
2024/25.
West Dunbartonshire Energy Limited
The district heating network provides low carbon heating and cooling solutions to the Queens Quay regeneration site. It aims to significantly
reduce fuel poverty and deprivation within some of the poorer neighbourhoods of West Dunbartonshire and, crucially, contribute to key climate
change targets. West Dunbartonshire Energy Limited, established in 2021, will progress the district heating network at Queens Quay.
There are plans to extend the network across commercial and residential sites over the next few years and there are ongoing discussions with
prospective customers and the Scottish Government about funding arrangements for the extensions (both capital and revenue). 
In 2023/24, we will continue to support the development of the business case for a further extension of the district heating network across
commercial and residential sites and we will strengthen financial processes and controls. This will include creating new financial, banking and
VAT processes for West Dunbartonshire Energy Limited within the Council’s financial management systems.

Page 7

Review of Capital Monitoring and Reporting
The Council receives a general capital grant from the Scottish Government each year (approximately £6m). Any spend above this level not
funded from other grants, is funded from borrowing. There is extensive monitoring and reporting of the Capital Programme to Council and
Service Committees. Whilst it is important that robust monitoring is in place, it needs to be delivered in a way which finds a balance between
transparent and effective reporting and not being excessively resource intensive. During 2023/24, we will review the approach to capital
programme reporting to ensure it is efficient and effective.
Increased Corporate Debt
Wider economic factors, in particular the cost of living crisis, have impacted on the collection of rent, Council Tax and sundry debt. The Council
is finding it more difficult to collect all the money it is owed resulting in increased levels of debt across a range of debt types. In 2023/24, we will:
• continue to review ways of decreasing corporate debt through continued improvements to debt collection processes in relation to sundry,
NDR, Council Tax and rent
• continue to review ways to improve rent collection rates in conjunction with Housing and W4U.
Automation of Processes and Information Provision
Staff across the Council are employed in manual processes and information provision, such as processing invoices and updating transactional
spreadsheets. Many such processes can be automated, providing benefits such as faster service delivery, improved quality and greater
flexibility, as well as enabling staff to refocus on more complex tasks rather than repetitive tasks. In 2023/24, we will continue to pursue
automation opportunities across the Council to improve efficiency.
Review of Council’s Support Services Model
The Council has a support services recharge model which is designed to ensure the cost of support services is appropriately allocated to
services based on usage. This model has not been reviewed for a number of years and requires to be updated to ensure services, including the
Health & Social Care Partnership and Housing Revenue Account, are being charged appropriately for the services they make use of.
In 2023/24, we will review the Support Services Model.

Page 8

Action Plan
The challenges identified in Section 2 and the key factors identified in Section 3 have informed Resources priorities for 2023/24. Appendix 1 sets
out the action plan to address them. It also includes:
• performance indicators and targets that will enable progress to be monitored and reported to stakeholders
• strategic workforce actions to address workforce issues identified in the planning process
• strategic and/or service risks.
Strategic risks represent the potential for the Council to take advantage of opportunities or fail to meet stated strategic objectives and those that
require strategic leadership. Service risks relate to service delivery and represent the potential for impact on individual services, or the
experience of those who work within the services, i.e. employees, partners, contractors and volunteers or service users and clients in receipt of
the services provided. In identifying the relevant risks for 2023/24 and actions to mitigate them, the aim is to improve or maintain the current
position (i.e. the current risk score) set out in the appendix.

Page 9

4. Resources
Finance
Resources has a net revenue budget of £5.603m and a capital budget of £0.002m in 2023/24. A breakdown by service area is set out below. We
will make the best use of the resources available to deliver on key priority areas and secure external/match funding where this is possible.
Service Area 
(Figures subject to ongoing
verification)
Gross
Expenditure
2023/24 (£m)
Gross Income
2023/24 (£m)
Net
Expenditure
2023/24 (£m)
Capital Budget
2023/24 (£m)
Finance 1.568 0.281 1.287 0.002
Audit & Fraud 0.380 0.303 0.077 0.000
Business Support 40.188 38.701 1.487 0.000
CAS 2.773 0.021 2.752 0.000
Total 44.909 39.306 5.603 0.002
Employees
Employee Numbers
The headcount and full time equivalent staff in each service area (as of 31st March 2023) are as follows:
Function Headcount FTE
Audit & Fraud 9 7.10
Business Support 184 161.15
Finance 45 35.25
TOTAL 234 203.40

Page 10

Absence
The 2022/23 quarterly absence figures for Resources are shown below, together with the Council average for the same periods for comparison.
The figures for Resources have been significantly lower than the Council average throughout 2022/23:
Absence in 2022/23 Quarter 1 Quarter 2 Quarter 3 Quarter 4 Annual FTE days lost
per FTE employee
Resources 2.05 2.00 2.63 1.72 6.83
COUNCIL WIDE TOTAL 3.86 3.28 4.42 4.02 14.00

Page 11

Appendix 1: Action Plan
Please Note: All PI targets for 2023/24 are indicative until 2022/23 year-end data becomes available.
Our Economy
Our area has the infrastructure for sustainable and inclusive growth where businesses can flourish
Performance Indicator 2023/24 Owner Target
Number of invoices paid within 30 calendar days of receipt as a percentage of all invoices paid 90% Stella Kinloch
Our partnerships support economic development to deliver increased prosperity for our area
Performance Indicator 2023/24 Owner Target
Time for processing applications for new Housing Benefits claims from application receipt date to the day the
claim is decided 23 Ryan Chalmers
Time for processing applications for notifications of changes of circumstances for Housing Benefits from the
application receipt date to the day the claim is decided 5 Ryan Chalmers

Page 12

Our Council
Our workforce is resilient and skilled where digital technology supports service delivery for our residents
Action Due Date Owner
Develop and implement wellbeing, employee engagement, equality and training plans to enable capabilities,
improved resilience and promotion of a diverse workforce. 31-Mar-2024 Management
Team
Develop and implement employee life cycle plans in line with the People First Strategy to attract and retain the
workforce. 31-Mar-2024 Management
Team
Implement service review process including role design, use of new technology and new ways of working to
add resilience, address gaps, and establish opportunities for efficiencies 31-Mar-2024 Management
Team
Develop and implement training plans and development opportunities to improve capabilities and resilience
within the workforce. 31-Mar-2024 Management
Team
Our Council is adaptable and focused on delivering best value for our residents
Performance Indicator 2023/24 Owner Target
Value of outstanding sundry debt as a percentage of total that is more than 90 days old from date of invoice 75% Ryan Chalmers
Rent collected as a % of total rent due 98% Ryan Chalmers
Percentage of corporate fraud savings target achieved 100% Andi Priestman
Cost of collecting council tax per dwelling £5.00 Ryan Chalmers
Percentage of income due from council tax received by the end of the year 94.9% Ryan Chalmers
Current tenants' arrears as a percentage of total rent due 11.4% Ryan Chalmers
Gross rent arrears (all tenants) as at 31 March each year as a percentage of rent due for the reporting year 10% Ryan Chalmers

Page 13

Performance Indicator 2023/24 Owner Target
Income generated as a % of total revenue budget 11% Carol Alderson
Action Due Date Owner
Review ways of decreasing corporate debt through continued improvements to debt collection processes in
relation to sundry, NDR, Council Tax and rent 31-Mar-2024 Ryan Chalmers
Review ways to improve rent collection rates in conjunction with Housing and W4U 31-Mar-2024 Ryan Chalmers
Maximise automation opportunities across the Council 31-Mar-2024 Arun Menon
Risk Description Current
Assessment
Target
Assessment Owner
Debt is not recovered
efficiently or effectively,
with inherent risk of
financial loss
The processes deployed in collection of monies owed to the
Council are inefficient and ineffective resulting in money not
collected on time or having to be written off.
Ryan Chalmers
Increase in the level of
rent arrears due to the
level of Welfare Reform
changes and general
state of economy
The Council sees an increase in its level of rent arrears due to
lower disposable income and national changes to the national
benefits regime and the ongoing economic position
Ryan Chalmers

Page 14

Our residents are engaged and empowered
Performance Indicator 2023/24 Owner Target
Percentage of council resources directed by communities 1%
Carol Alderson;
Clare English;
Elaine Troup
Strong financial governance and sustainable budget management (Service Objective)
Performance Indicator 2023/24 Owner Target
Amount of free reserves as a percentage of the prudential reserve target - HRA 100% Carol Alderson
Amount of free reserves as a percentage of the prudential reserve target - General services 100% Carol Alderson
Percentage variance to budget projected (General Services budget) 0% Carol Alderson
Percentage of Audit Plan completed 85% Andi Priestman
Action Due Date Owner
Implement the change to the Accounting Code of Practice in relation to leasing 31-Mar-2024 Carol Alderson
Support the development of the business case to extend the district heating network and strengthen the
financial processes and controls of West Dunbartonshire Energy Limited 31-Mar-2024 Carol Alderson
Review the current capital programme reporting procedures 31-Mar-2024 Carol Alderson
Review the Council's Support Services Model and implement any changes 31-Mar-2024 Carol Alderson
Revise the Code of Good Governance 31-Mar-2024 Andi Priestman
Ensure continued compliance with the Code of Good Governance during 2023/24 31-Mar-2024 Andi Priestman

Page 15

Action Due Date Owner
Prepare and submit draft Annual Governance Statement for 2022/23 to the Audit Committee 30-Jun-2023 Andi Priestman
Continue to improve and deliver the Assurance Statement for 2022/23 to support the Annual Governance
Statement 30-Jun-2023 Andi Priestman
Complete the Internal Audit & Corporate Fraud Plan 2022/23 and report to Audit Committee as part of the
Annual Assurance Statement 31-Aug-2023 Andi Priestman
Risk Description Current
Assessment
Target
Assessment Owner
Failure to provide
assurance of the system
of financial controls
Either Internal Audit or External Audit is unable to provide
assurances on the Council's financial control environment Andi Priestman
Failure to meet statutory
deadlines for external
returns (including
HMRC) and financial
statements
Finance Services failing to meet statutory deadlines resulting
in lost revenue or penalty costs Carol Alderson
Financial projections are
significantly incorrect
Financial projections for both capital and revenue are
significantly incorrect resulting in insufficient reserves being
held.
Laurence Slavin
Significant financial
funding reductions /
limitations from Scottish
Government
It is expected that the Council will be faced with significant
ongoing funding reductions/limited increases from the Scottish
Government settlement. This is based on recent settlements,
the March 2022 Resource Spending Review which states that
Council funding will remain as ‘flat cash’ (at current 2022/23
Laurence Slavin

Page 16

Risk Description Current
Assessment
Target
Assessment Owner
levels) until 2025/26 with a £100m added in 2026/27 – the real
term impact of this (taking inflation into account) for the next
four years is a 7% reduction between 2022/23 and 2026/27.
This coincides with a period where costs are expected to rise
in relation to social care due to an aging population;
inflationary increases with RPI at a level not seen since 1991;
post-COVID-19 ongoing costs; increases in the cost of
borrowing as interest rates increase and pay award pressures
linked to inflation. The ongoing population decline of West
Dunbartonshire versus the average population for the whole of
Scotland leads directly to funding reductions with marginal
impact on service delivery cost/need.