Appendix 1 - CCF Delivery Plan Year-end Progress 22/23
1. Our Communities
Objective 2. Our residents health and wellbeing remains a priority
Performance Indicator
2021/22 2022/23
Owner
Value Status Value Target Short Trend Long Trend Note
Number of attendances per 1,000 population for
indoor sports and leisure facilities 3,810 4,979 5,949
The figures are below the target set
but above the previous year for the
same period.  Gym usage at all three
leisure centres performed well over
the period in what is normally the
busiest quarter of the year.
Clydebank Leisure Centre gym usage
was up by 39% over the same period
last year, Meadow Centre up by 18%
and the Vale of Leven Swimming Pool
up by 48%.  Sports usage within the
Community Centres was below target
by almost 50% as the centres
continue to recover from the Covid
pandemic.  Sports Development usage
was above the target set for the
period.
Bobby Kerr
% of pupil medical dietary requests met 100% 100% 100% Target met. Sharon Jump
Action Status Progress Due Date Note Owner
Progress plans for launch of Free school meal
rollout (final phase) 31-Mar-2023
The action has been completed. The final works within the school kitchens
require to be carried out when the school is non-operational and are
scheduled in to be completed during summer recess 2023.
Michelle Lynn
APPENDIX 1

Page 2

Objective 3. Our residents are supported to increase life and learning skills 
Performance Indicator
2021/22 2022/23
Owner
Value Status Value Target Short Trend Long Trend Note
Total number of visits to funded and part funded
museums and heritage centres (in person & virtual)
per 1,000 population
909  1175 1024  
Target exceeded. Visits increased
since previous year. Total number
increased from 79,824 to 103,108.
Sarah Christie
Total number of library visits (physical and virtual)
per 1000 population 4042  4209 2824  
Target exceeded. Visits increased
since previous year. Total number
increased from 354,811 to 369,520.
David Main 
% Residents satisfied with Libraries 95%  94% 94%   Target met. David Main
% Satisfaction with museums & galleries 90%  90% 88%   Target met. Sarah Christie 
Action Status Progress Due Date Note Owner
Progress the development of Glencairn House as
an inspiring cultural hub Phase 3   31-Mar-2023
Action has been successfully completed to RIBA Stage 3 with planning
application submitted. The next phase of the programme will progress in
2023/24 with the planning decision due in April 2023, and progression to
RIBA Stage 4 thereafter.
Sarah Christie
Develop and launch an innovative heritage
strategy, reflecting the investment in the cultural
offering for the area  
31-Mar-2023
Action completed successfully. The heritage strategy has now been
submitted for internal approval. It will be rolled out during 2023/24 and
will inform the Arts and Heritage work plan going forward.
Sarah Christie
Progress digitalision of materials from Councils
historic archive and history collections   31-Mar-2023
Action successfully completed. Ancestry contract in place and digitisation
team due on site spring 2023. Digitisation and indexing process to follow
2023/24, with launch of digitised materials planned for 2024.
Sarah Christie
Progress investment projects in Alexandria
library, Clydebank museum and Dalmuir gallery   31-Mar-2023
The new museum space in Alexandria Library has successfully launched as
the Vale of Leven Heritage Hub. Following some delays associated with the
installation of necessary pipework in the library building, the new museum
space in Clydebank Library is designed to RIBA Stage 4 and will progress
to fit out during 23/24 as Clydebank Heritage Hub. Investment in the
Dalmuir Gallery was halted in line with Council budgetary decisions taken
in March 2023.  
Sarah Christie
Progress Libraries Investment and Enhancement
Programme   31-Mar-2023
Most elements of this action have been completed satisfactorily, including
the SLIC funded Pass IT on project, the creation of an externally-funded
fixed term Sustainability Co-ordinator post with associated sustainability
action plan for libraries, and the delivery of a winter Wellbeing programme. 
Actions looking at the service structure and frontline customer service
David Main

Page 3

Action Status Progress Due Date Note Owner
training were halted pending the outcome of the Council budget setting in
March 2022 and will now proceed in 2023/24.
Successfully deliver the £421k capital investment
across the branch network and finalise the
branding improvements at all branches.  
31-Mar-2023
Most elements of this action have been completed successfully including
designs and new furniture installation for Alexandria, Clydebank and
Dumbarton libraries.  Work to progress a new interior design for Dalmuir
library was halted pending the outcome of the Council budget setting
meeting in March 2023.  As a result of Council decisions, Dalmuir library
will now co-locate with the CE Centre.  An action to design and install
furniture at the new location will now be undertaken in 2023.
David Main 
4. Our Council 
Objective 10. Our workforce is resilient and skilled where digital technology supports service delivery for our residents 
Action Status Progress Due Date Note Owner
Develop and implement wellbeing, employee
engagement, equality and training plans to
enable capabilities, improved resilience and
promotion of a diverse workforce.  
31-Mar-2023
Action successfully completed. In excess of 93 CCF employee registered as
Trickle Users, 3 Trickle Champions identified and 5 Wellbeing Advocates
who represent the service. Across the service team meetings are carried out
as well as Be the Best 1-2-1 meetings to ensure employees feel supported.
Amanda Graham
Develop and implement employee life cycle plans
in line with the People First Strategy to attract
and retain the workforce.  
31-Mar-2023
Action successfully completed. Review of the working patterns of hard to fill
vacancies within Facilities Management, including hours offered and flexible
working is progressing to identify changes that will improve recruitment and
retention. Changes required will be progressed in 2023/24. 
Amanda Graham
Implement service review process including role
design, use of new technology and new ways of
working  to add resilience, address gaps,  and
establish opportunities for efficiencies  
31-Mar-2023
Action successfully completed. Review of Management structure in Facilities
Management complete and implementation complete. Across the service
reviews of processes are regularly carried out to identify efficiencies.
Amanda Graham
Develop and implement training plans and
development opportunities to improve
capabilities and resilience within the workforce.  
31-Mar-2023
Action successfully completed. Digital Lead identified and 3 Digital champs
also identified and taking part in support sessions.  Additionally 3 Trickle
Champions represent the service. 
Amanda Graham 
Objective 11. Our Council is adaptable and focused on delivering best value for our residents

Page 4

Performance Indicator
2021/22 2022/23
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of complaints received by the Council
that are resolved/ closed at Stage 1 91.33% 85.02% 90%
Target marginally missed. Overall
621 complaints were received of
these 528 were closed or resolved at
Stage 1. This represents a slight
deterioration on the previous year.
Increased workload and complexity
has meant more complaints being
dealt with at Stage 2 or escalated
from Stage 1.
Stephen Daly
Percentage of complaints received by the Council
that are resolved at Stage 2
New PI
22/23 1.93% 10% Target exceeded. Stephen Daly
% of telephone calls answered within 2 minutes by
Contact Centre as a proportion of all calls
answered.
62% 74% 90%
Whilst target has not been met
performance shows an improvement
from previous year, with
improvement in each quarter this
year. However resource issues
meant overall only 74% of calls
could be answered within the
desired 2 minute time frame.
Stephen Daly
% of telephone calls answered within 2 minutes by
Repairs Contact Centre as a proportion of all calls
answered.
New PI
22/23 60% 90%
Target not met. Increased call
volumes and some resource issues
meant that only 60% of calls to the
Repairs contact centre could be
answered within the desired 2
minute time frame. An increased
volume in calls in year has been
discussed with the Building Services
Management Team with work
underway to understand and
address.
Stephen Daly
Action Status Progress Due Date Note Owner
Implement required complaints management
process enhancements 31-Mar-2023
Action has not progressed as planned. The testing of the pilot system has
been delayed due to competing priorities. This will be further progressed in
2023/24. This action will be carried forward.
Stephen Daly
Explore enhanced telephony technology solutions 31-Mar-2023
Action complete. Options considered on voice recording and call
announcement positioning. Exploring costs and implementation detail with
ICT for 2023/24.
Stephen Daly

Page 5

Action Status Progress Due Date Note Owner
Implement the Fit for Future Actions for Contact
Centre and Online from Housing Repairs Report –
Phase 1  
31-Mar-2023
All actions deliverable by Citizen Services completed. Process
improvements required both in IHMS and by Building Services to deliver
further improvements identified in Fit for Future process
Stephen Daly
Further Review Town Hall arrangements   31-Mar-2023
Action progressed as planned. The Town Hall structure is integrated with
the Facilities Management restructure and recruitment to Town Hall
Facilities Officer post now concluded.
Amanda Graham
Review structure of Facilities Management
Service   31-Mar-2023
Action complete.  Implementation of the agreed new structure will take
place in 2023/24 once recruitment of final Team Leader positions have
been concluded.
Sharon Jump
Support progress of integration of payment and
cashless software  31-Mar-2023 Education leading this programme, and action was cancelled for 22/23.  Sharon Jump
Undertake planning and preparation of new
Council  Strategic Plan  2022-2027   31-Mar-2023 Action complete. New Strategic plan agreed and in place. Nicola Docherty 
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Risk of Failure to meet
citizen expectation and
service standards
Risk of citizen dissatisfaction due to us
not doing what we say we will when we
say we will. 
31-Mar-2023
There are a number of actions and
strategies in place to monitor service
standards and customer satisfaction in
partnership with services across the
Council. 
No change to risk matrix.
Stephen Daly
Failure to effectively
manage and learn from
complaints
There is a risk of damage to the Council's
reputation. If complaints are not handled
effectively, there can be an adverse
effect on the public perception of the
Council which can lead to a lack of trust
in the services provided.   
31-Mar-2023
Risk reconsidered as part of the yearly
planning process. 
No change to risk matrix.
Stephen Daly 
Objective 12. Our residents are engaged and empowered 
Performance Indicator
2021/22 2022/23
Owner
Value Status Value Target Short Trend Long Trend Note
Percentage of residents who are satisfied with the
Council website 89%  85% 85%   Target met. Marginal downturn on
previous year. Jonathan Muir

Page 6

Performance Indicator
2021/22 2022/23
Owner
Value Status Value Target Short Trend Long Trend Note
% of stage 2 complaints responded to within 20
working days.
New PI
22/23  33.33% 100%  
Target missed. Complexity of
complaints together with increased
response times from other Council
services has impacted on resolving
complaints and in meeting the 20 day
timescale. Citizen Relations are
working with services to look at
complaints management and how we
can work together to improve
responses and timescales
Stephen Daly
% of press enquiries responded to within deadline
as a proportion of all press enquiries 100%  100% 99%   Target met. Lauren Crooks
Percentage of citizens who agree the Council listen
to community views when designing and delivering
services
66%  63% 70%  
Target not met. Overall performance
is marginally lower than previous
year. However there have been in
excess of 18 consultations carried out
remotely including consultations on
Council Strategic Plan, local
improvement schemes and service
delivery. We will continue to focus on
ensuring communities are aware of
the opportunities to provide feedback
and inform service design
Amanda
Graham
Residents satisfaction with Council services overall 88%  87% 88%   Target narrowly missed with a general
increasing trend over the year. 
Amanda
Graham
% of residents who feel the Council communicates
well with them 74%  71% 75%  
Marginally missed target with
performance marginally down on last
year. Communication continues to be
a key priority. Over the last year
communications have been issued
across a range of channels including
social media, the Council website,
media releases and Housing News as
well as specific tailored
communications.
Amanda
Graham
No. of transactions undertaken online 57,543  54,563 50,500  
Performance has exceeded target.
Work continues to improve and
develop online transactions.
Stephen Daly
% of stage 1 complaints responded to within 5 45.39%  64.19% 100%   Whilst target has not been met Stephen Daly

Page 7

Performance Indicator
2021/22 2022/23
Owner
Value Status Value Target Short Trend Long Trend Note
working days. performance shows improvement from
previous year. Some resource issues
caused a backlog of complaints
together with increased response
times from other Council services has
impacted on resolving complaints and
in meeting the 5 day timescale. 
Citizen Relations are working with
services to look at complaints
management and how we can work
together to improve responses and
timescales 
Action Status Progress Due Date Note Owner
Enhance intranet content and ensure compliance
with accessibility   31-Mar-2023
Action complete. Process in place to identify issues and address them.
Guidance and feedback is given regularly across the council to reduce the
instances of noncompliance.
Stephen Daly
Develop Strategic Communications Strategy   31-Mar-2023
This Action was not progressed in 2022/23, due to vacancy of
Communications Manager. The action will be carried forward and
progressed in 2023/24. 
Amanda Graham
Prepare and implement a communications
campaign road map   31-Mar-2023
Action incomplete. Due to other competing priorities this action has been
delayed. Following review of work plans and forecasted campaigns there is
no need to prepare a formal road map for 23/24. Action no longer
required.
Amanda Graham
Undertake review and design of strategic
performance reporting ensuring compliance with
statutory obligations.  
31-Mar-2023
This action has been successfully completed. We have carried out a peer
review of Public Performance Reporting and have updated pages
accordingly, work continuing to ensure they meet the statutory
requirements and enhance the user experience of accessing Council
Strategic performance information. The Strategic Planning & Performance
Framework 2022-27 was presented and accepted at PMRG in October. A
review of strategic reporting has been carried out and a new format agreed
to present all of our strategic performance into one comprehensive report,
this will provide a holistic overview of how we perform internally and
nationally. 
Nicola Docherty 
Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner

Page 8

Risk Description Current
Assessment Target Assessment Date Reviewed Note Owner
Risk of Ineffective
Communications /
Reputation Risk
Ineffective use of corporate
communication channels may result in
messages that are inconsistent with
authorised responsibilities or established
performance measures. Employees
without intranet access or email access
may not receive communications. Not
effectively managing corporate responses
to adverse events may lead to an erosion
of the Council's reputation.  
31-Mar-2023
There are a number of processes and
strategies in place to ensure
communications are effective both
internal and external to the Council. 
No change to risk matrix.
Amanda Graham 
Action Status 
Cancelled 
Overdue 
Not on track 
In Progress and on track 
Completed 
PI Status 
Target significantly missed 
Target narrowly missed 
Target met or exceeded 
Risk Status 
Alert
Long Term Trends 
Improving 
No change 
Getting worse 
Short Term Trends 
Improving 
No change 
Getting worse

Page 9

High risk
Warning
OK
Unknown
Risk Status
Alert
High Risk
Warning
OK
Unknown